CAC:001029, (Approved, Closed) EPID:L-2022-LLA-0122, Transmittal Letter from A. M. Al-Daouk to U.S. Nuclear Regulatory Commission, Renewal Request of the Certificate of Compliance No. 9329 for the Model No. S300 Package (Approved, Closed) EPID:L-2022-LLA-0123, Transmittal Letter from A. M. Al-Daouk to U.S. Nuclear Regulatory Commission, Renewal Request of the Certificate of Compliance No. 9329 for the Model No. S300 Package (Approved, Closed) | |
Initiation Questions
Answers Results Other: ML18206A311, ML18317A353, ML18317A355, ML22005A350, ML22006A352, ML22006A353, ML22006A356, ML22278A001, ML23003A046, ML23137A441, ML24204A233, ML24275A093, ML24289A207, ML24305A054, ML24327A249, ML25055A139, ML25078A414, ML25078A416, ML25086A041, ML25086A055, ML25086A244, ML25086A284, ML25087A028, ML25090A330, ML25090A331, ML25112A337, ML25112A339, ML25142A158, ML25161A179, ML25161A181, ML25176A170, ML25178C673, ML25223A188, ML25230A135, ML25253A491, ML25272A064, ML25344A143 | |
MONTHYEARML18156A4282018-05-30030 May 2018
[Table View]Letter from J. Mccann/Columbiana Hi Tech to Document Control Desk Application for Revision of Certificate of Compliance No. 9291 for the Model No. Liqui-Rad (Lr) Transportation Unit Package, Docket No. 71-9291 Project stage: Request ML18206A3112018-07-25025 July 2018 Letter to Mccann Application for Amendment of Certificate of Compliance No. 9291 for the Model No. Liqui-Rad Transport Unit Package - Accepted for Review Project stage: Other ML18264A0022018-09-0707 September 2018 Columbiana Hi Tech, LLC - Certificate Holder Name and Address Change Project stage: Request ML18269A2732018-09-24024 September 2018 Package: Renewal of Certificate of Compliance No. 9291 for the Model No. Liqui-Rad Transport Unit Package Project stage: Request ML19015A3732019-01-10010 January 2019 Tn Americas, LLC - Application for Revision to Certificate of Compliance for USA/9291/B(U)F-96 for the Model No. Lr Transport Unit Project stage: Request ML18317A3532019-02-13013 February 2019 Enclosure 1: Certificate of Compliance No. 9291, Rev No. 11 (Letter to W. Edwards Amendment and Renewal of Certificate of Compliance No. 9291 for the Model No. LIQUI-RAD Transport Unit Package) Project stage: Other ML18317A3552019-02-13013 February 2019 Letter to W. Edwards Amendment and Renewal of Certificate of Compliance No. 9291 for the Model No. LIQUI-RAD Transport Unit Package (W/Enclosure 2) Project stage: Other ML18317A3522019-02-13013 February 2019 Package: Amendment and Renewal of Certificate of Compliance No. 9291 for the Model No. LIQUI-RAD (Lr) Transport Unit Package Project stage: Request ML20209A3722020-07-27027 July 2020 Notice of Partially Closed Third Pre-Application Meeting with Tn Ammericas LLC for Model No. TN-EAGLE Transportation Package Project stage: Meeting ML22005A3502021-12-14014 December 2021 Email from D. Ortega (NNSA) to N. Garcia (U.S. NRC) Renewal of Certificate of Compliance (CoC) No. 9329 for the Model No. S300 Package Project stage: Other ML22005A3462021-12-14014 December 2021 Transmittal Letter from A. M. Al-Daouk to U.S. Nuclear Regulatory Commission, Renewal Request of the Certificate of Compliance No. 9329 for the Model No. S300 Package Project stage: Request ML22006A3522021-12-27027 December 2021 Enclosure 3: Email Dated 12/27/21 from S. Burns (Nwp) to N. Garcia Santos (Nrc), Comments on Telephone Call Summary Dated 12/1/21, Model Nos. TRUPACT-II and Halfpact Packages Project stage: Other ML22006A3562021-12-27027 December 2021 Enclosure 5: Clarification Regarding Testing Performed During the Shielded Container Prototype Testing (Drop Tests, Gamma Scans, Destructive Disassembly), Model Nos. TRUPACT-II and Halfpact Packages Project stage: Other ML22006A3532021-12-27027 December 2021 Enclosure 2: Attachment to Email Dated 11-29-21, Responses to Follow Up Questions, Acceptance Tests for the Lead Ssield of the Shielded Canisters (Model Nos. TRUPACT-II and Halfpact Packages Project stage: Other ML22006A3552022-01-0606 January 2022 12/1/21-Conference Call Summary: Follow Up Questions Related to Shielding RAIs RAI-Sh-5 and -8 (Acceptance Tests, Shielded Canisters), Model Nos. TRUPACT-II and Halfpact Packages Project stage: RAI ML22020A1872022-01-25025 January 2022 Enclosure 2 - Safety Evaluation Report: Renewal for Certificate of Compliance, Revision 6, the Model No. S300 Package Project stage: Approval ML22319A2292022-08-18018 August 2022 Redacted - August 2022, Revision No. 9 of the Safety Analysis Report for the Model No. Halfpact Package (Docket No. 71-9279) Project stage: Other ML22319A2282022-08-18018 August 2022 Redacted - August 2022, Revision No. 26 of the Safety Analysis Report for the Model No. TRUPACT-II Package (Docket No. 71-9218) Project stage: Other ML22230C9202022-08-18018 August 2022 Nuclear Waste Partnership, LLC, Revision 26 of the Trupact-II Shipping Package Application, and Revision 9 of the Halfpact Shipping Package Application Project stage: Other ML22278A0072022-09-0808 September 2022 Email from T.E. Sellmer (Nwp) to N. Garcia Santos (NRC) Acknowledgement of Application for CoC, Revision 27, Model No. TRUPACT-II and CoC, Revision 11, Model No. Halfpact Packages Project stage: Request ML22256A3062022-09-19019 September 2022 Transmittal Letter- Request for Additional Information, Model Nos. TRUPACT-II and Halfpact Project stage: RAI ML22256A3052022-09-19019 September 2022 Enclosure- Request for Additional Information Model Nos. TRUPACT-II and Halfpact Project stage: RAI ML25086A0552022-09-30030 September 2022 Redacted, Revised SAR, 435-B Transport Package, Safety Analysis Report, Revision 6 (CoC No. 9355, Rev. 4) (Docket No. 71-9355) Project stage: Other ML22278A0012022-10-0404 October 2022 Email from T. Sellmer (Nwp) to N. Garcia Santos (NRC) Et Al., Delay of RAI Response-CoC, Revision 27, Model No. TRUPACT-II and CoC, Revision 11, Model No. Halfpact CoCs Project stage: Other ML22319A2302022-10-10010 October 2022 Redacted - October 2022, Revision No. 26 of the Safety Analysis Report for the Model No. TRUPACT-II Package (Docket No. 71-9218) Project stage: Other ML22283A0292022-10-10010 October 2022 Nuclear Waste Partnership, LLC, Response to Request for Additional Information on Revision 26 of the Trupact-II Shipping Package Project stage: Response to RAI ML22319A2312022-10-10010 October 2022 Redacted - October 2022, Revision No. 9 of the Safety Analysis Report for the Model No. Halfpact Package (Docket No. 71-9279) Project stage: Other ML22320A1042022-11-14014 November 2022 Nuclear Waste Partnership, LLC (Applicant), T Sellmer Comments on Draft Certificate of Compliance No. 9279, Revision 11 Project stage: Draft Other ML22320A1032022-11-15015 November 2022 Email from S. Burns (Nwp) to N. Garcia Santos (Nrc), Subject-IMPORTANT, Courtesy Review, Revised Draft CoCs for the TRUPACT-II and Halfpact Packages Project stage: Draft Other ML22312A4042022-11-21021 November 2022 Transmittal Letter-Revision No. 27 of Certificate of Compliance No. 9218, Model No. TRUPACT-II, and Revision No. 11 of Certificate of Compliance No. 9279, Model No. Halfpact, Transport Packages (EPIDs L-2022-LLA-0123 and L-2022-LLA-122) Project stage: Other ML22312A4052022-11-21021 November 2022 Enclosure 2 - Revision No. 11 of Certificate of Compliance No. 9279, Model No. Halfpact Project stage: Other ML22312A4062022-11-21021 November 2022 Enclosure 1 - Revision No. 27 of Certificate of Compliance No. 9218, Model No. TRUPACT-II Project stage: Other ML22312A4032022-11-21021 November 2022 Enclosure 3 - Safety Evaluation Report-Revision No. 27 of Certificate of Compliance No. 9218, Model No. TRUPACT-II, and Revision No. 11 of Certificate of Compliance No. 9279, Model No. Halfpact, Transport Packages Project stage: Approval ML23046A4542023-02-15015 February 2023 Request for Authorization of One-Time Shipment of Model No. Halfpact Crediting the Outer Confinement Vessel as the Containment Boundary Project stage: Request ML23067A4362023-03-16016 March 2023 Application for a Letter Authorization Related to Coc No. 9279, Model No. Halfpact - Accepted for Review - CAC No. 001029, EPID No. L-2023-LLA-0030 Project stage: Other ML23003A0462023-03-29029 March 2023 Response to Request for Reviewing a Position Paper from Nuclear Fuel Services, Inc. Related to Applicability of 10 CFR 71.15(C) to Shipment(S) Project stage: Other ML23089A2582023-03-29029 March 2023 Email Attachment, Staggered Request for Additional Information (Structural Evaluation and Operating Procedures), Model No. Halfpact - One-time Letter Authorization Project stage: RAI ML23333A0332023-05-30030 May 2023 Email Dated 5-30-23 from T Holly (NFS) to Ngarcia Santos (Nrc), Transmittal of Affidavit Related to Fissile Material Exemption (10 CFR 71.15 (C), Follow Up Questions and Additional Comments (Docket No. 70-143) Project stage: Request ML23137A4412023-06-0202 June 2023 Authorization for Shipment of the Model No. Halfpact Package - Inner Containment Vessel No. 506 Project stage: Other ML25087A0282023-07-0303 July 2023 Enclosure, Letter Dated 7/3/23 from NNSA to NRC, Roadmap, Revised SAR, 435-B Transport Package, Safety Analysis Report, Revision 6 (CoC No. 9355, Rev. 4) (Docket No. 71-9355) Project stage: Other ML23220A1572023-07-21021 July 2023 Transmittal Letter from Ahmad M. Al-Daouk (NNSA) to Ngarcia Santos (NRC) Related to the Application for Certificate of Compliance No. 9355, Revision 4, Model No. 435-B Project stage: Request ML23263A1022023-09-20020 September 2023 Email Dated 9-20-23 from N. Garcia Santos (NRC) to J. Mumma (Nnsa), Subject: Package Model No. 453-B--Need Clarification on Submittals Project stage: Approval ML24072A0022024-03-0505 March 2024 Revision of Model No. 435-B Package’S Certificate of Compliance (CoC) Number 9355 for the 435-B Package Project stage: Request ML24295A1602024-06-30030 June 2024 Redacted, Industrial Nuclear Company - Application for Certificate of Compliance for the Inc IR1 00ST, Revision 0, Docket No. 71-9385 Project stage: Request ML24204A2332024-08-0808 August 2024 Acceptance Determination Letter with Observation, Certificate of Compliance No. 9355, Model No. 435-B Project stage: Other ML24248A2532024-09-20020 September 2024 Request for Additional Information, Certificate of Compliance No. 9355, Revision 4, Model No. 435-B Packaging, EPID L-2023-LLA-0102, CAC 001029 Project stage: RAI ML24281A1762024-09-25025 September 2024 9/25/2024 Conference Call Summary - Supplemental Information to Proposed RAI Responses Related to the Criticality Safety Review of the Model No. Castor geo69 Transport and Storage Systems (Docket Nos. 71-9383 and 72-1052, Respectively) Project stage: Supplement ML24312A2212024-10-0101 October 2024 Extension Request - Robatel Technologies’ Response to U.S. NRC Request for Additional Information for Review of the Robatel Technologies, LLC Model No. RT-200 Type B(U) Cask - Cac/Epid Numbers: 001029/L-2024-NEW-0003 Project stage: Request ML24275A0932024-10-11011 October 2024 Transmittal Letter - Certificate of Compliance No. 9310, Revision No. 8, for the Model No. F-431 Transport Package Project stage: Other ML25058A3612024-10-16016 October 2024 Email Dated 10/16/24 from Ngarcia Santos (NRC) to Mrose (Inc) Transmittal of Draft Requests for Supplemental Information and Observations, Thermal and Structural Evaluations, Model No. IR 100ST, CoC No. 9385, Rev. 0 Project stage: Draft Other 2022-09-19 |
| ML22278A007 | |
| Person / Time | |
|---|---|
| Site: | 07109218, 07109279 |
| Issue date: | 09/08/2022 |
| From: | Sellmer T Nuclear Waste Partnership, US Dept of Energy (DOE) |
| To: | Garcia-Santos N Division of Fuel Management |
| Garcia-Santos N | |
| References | |
| CAC 001029, EPID L-2022-LLA-0122, EPID L-2022-LLA-0123 | |
| Download: ML22278A007 (2) | |
Text
1 Norma Garcia Santos From:
Sellmer, Todd - NWP <Todd.Sellmer@wipp.ws>
Sent:
Thursday, September 8, 2022 3:41 PM To:
Garcia Santos, Norma Cc:
White, Bernie
Subject:
[External_Sender] RE: TRUPACT-II and HalfPACT Application-Acknowledgement of your Application Thank you Norma.
- Regards, Todd Todd Sellmer NWP, Manager, Packaging & Information Systems ASNT Level III / ASNT Fellow Contractor for the U.S. Department of Energy Office Phone (575) 234-7396 Cell Phone (575) 302-7583 From: Garcia Santos, Norma <Norma.GarciaSantos@nrc.gov>
Sent: Wednesday, September 07, 2022 7:37 AM To: Sellmer, Todd - NWP <Todd.Sellmer@wipp.ws>
Cc: White, Bernie <Bernard.White@nrc.gov>
Subject:
TRUPACT-II and HalfPACT Application-Acknowledgement of you Application WARNING - EXTERNAL EMAIL This message does not originate from a known WIPP email system.
Use caution if this message contains attachments, links or requests for information.
Good morning, The purpose of this communication is to acknowledge the receipt of your application for Revision 27 of the CoC of the Model No. TRUPACT-II package and Revision 11 of the Model No. HalfPACT package.
Please contact me if you have questions about this review.
- Thanks, Norma Garcia Santos Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety
2 and Safeguards