ML24312A221
Letter Sequence Request | |
|---|---|
CAC:001029, (Approved, Closed) EPID:L-2024-NEW-0003, Initial Submittal of the Safety Analysis Report for Docket No. 71-9384 (Open) | |
Initiation Questions
Answers Results Other: ML18206A311, ML18317A353, ML18317A355, ML22005A350, ML22006A352, ML22006A353, ML22006A356, ML22278A001, ML23003A046, ML23137A441, ML24204A233, ML24275A093, ML24289A207, ML24305A054, ML24327A249, ML25055A139, ML25078A414, ML25078A416, ML25086A041, ML25086A055, ML25086A244, ML25086A284, ML25087A028, ML25090A330, ML25090A331, ML25112A337, ML25112A339, ML25142A158, ML25161A179, ML25161A181, ML25176A170, ML25178C673, ML25223A188, ML25230A135, ML25253A491, ML25272A064, ML25344A143 | |
MONTHYEARML18156A4282018-05-30030 May 2018
[Table View]Letter from J. Mccann/Columbiana Hi Tech to Document Control Desk Application for Revision of Certificate of Compliance No. 9291 for the Model No. Liqui-Rad (Lr) Transportation Unit Package, Docket No. 71-9291 Project stage: Request ML18206A3112018-07-25025 July 2018 Letter to Mccann Application for Amendment of Certificate of Compliance No. 9291 for the Model No. Liqui-Rad Transport Unit Package - Accepted for Review Project stage: Other ML18264A0022018-09-0707 September 2018 Columbiana Hi Tech, LLC - Certificate Holder Name and Address Change Project stage: Request ML18269A2732018-09-24024 September 2018 Package: Renewal of Certificate of Compliance No. 9291 for the Model No. Liqui-Rad Transport Unit Package Project stage: Request ML19015A3732019-01-10010 January 2019 Tn Americas, LLC - Application for Revision to Certificate of Compliance for USA/9291/B(U)F-96 for the Model No. Lr Transport Unit Project stage: Request ML18317A3552019-02-13013 February 2019 Letter to W. Edwards Amendment and Renewal of Certificate of Compliance No. 9291 for the Model No. LIQUI-RAD Transport Unit Package (W/Enclosure 2) Project stage: Other ML18317A3532019-02-13013 February 2019 Enclosure 1: Certificate of Compliance No. 9291, Rev No. 11 (Letter to W. Edwards Amendment and Renewal of Certificate of Compliance No. 9291 for the Model No. LIQUI-RAD Transport Unit Package) Project stage: Other ML18317A3522019-02-13013 February 2019 Package: Amendment and Renewal of Certificate of Compliance No. 9291 for the Model No. LIQUI-RAD (Lr) Transport Unit Package Project stage: Request ML20209A3722020-07-27027 July 2020 Notice of Partially Closed Third Pre-Application Meeting with Tn Ammericas LLC for Model No. TN-EAGLE Transportation Package Project stage: Meeting ML22005A3462021-12-14014 December 2021 Transmittal Letter from A. M. Al-Daouk to U.S. Nuclear Regulatory Commission, Renewal Request of the Certificate of Compliance No. 9329 for the Model No. S300 Package Project stage: Request ML22005A3502021-12-14014 December 2021 Email from D. Ortega (NNSA) to N. Garcia (U.S. NRC) Renewal of Certificate of Compliance (CoC) No. 9329 for the Model No. S300 Package Project stage: Other ML22006A3532021-12-27027 December 2021 Enclosure 2: Attachment to Email Dated 11-29-21, Responses to Follow Up Questions, Acceptance Tests for the Lead Ssield of the Shielded Canisters (Model Nos. TRUPACT-II and Halfpact Packages Project stage: Other ML22006A3562021-12-27027 December 2021 Enclosure 5: Clarification Regarding Testing Performed During the Shielded Container Prototype Testing (Drop Tests, Gamma Scans, Destructive Disassembly), Model Nos. TRUPACT-II and Halfpact Packages Project stage: Other ML22006A3522021-12-27027 December 2021 Enclosure 3: Email Dated 12/27/21 from S. Burns (Nwp) to N. Garcia Santos (Nrc), Comments on Telephone Call Summary Dated 12/1/21, Model Nos. TRUPACT-II and Halfpact Packages Project stage: Other ML22006A3552022-01-0606 January 2022 12/1/21-Conference Call Summary: Follow Up Questions Related to Shielding RAIs RAI-Sh-5 and -8 (Acceptance Tests, Shielded Canisters), Model Nos. TRUPACT-II and Halfpact Packages Project stage: RAI ML22020A1872022-01-25025 January 2022 Enclosure 2 - Safety Evaluation Report: Renewal for Certificate of Compliance, Revision 6, the Model No. S300 Package Project stage: Approval ML22278A0072022-09-0808 September 2022 Email from T.E. Sellmer (Nwp) to N. Garcia Santos (NRC) Acknowledgement of Application for CoC, Revision 27, Model No. TRUPACT-II and CoC, Revision 11, Model No. Halfpact Packages Project stage: Request ML25086A0552022-09-30030 September 2022 Redacted, Revised SAR, 435-B Transport Package, Safety Analysis Report, Revision 6 (CoC No. 9355, Rev. 4) (Docket No. 71-9355) Project stage: Other ML22278A0012022-10-0404 October 2022 Email from T. Sellmer (Nwp) to N. Garcia Santos (NRC) Et Al., Delay of RAI Response-CoC, Revision 27, Model No. TRUPACT-II and CoC, Revision 11, Model No. Halfpact CoCs Project stage: Other ML23046A4542023-02-15015 February 2023 Request for Authorization of One-Time Shipment of Model No. Halfpact Crediting the Outer Confinement Vessel as the Containment Boundary Project stage: Request ML23003A0462023-03-29029 March 2023 Response to Request for Reviewing a Position Paper from Nuclear Fuel Services, Inc. Related to Applicability of 10 CFR 71.15(C) to Shipment(S) Project stage: Other ML23089A2582023-03-29029 March 2023 Email Attachment, Staggered Request for Additional Information (Structural Evaluation and Operating Procedures), Model No. Halfpact - One-time Letter Authorization Project stage: RAI ML23333A0332023-05-30030 May 2023 Email Dated 5-30-23 from T Holly (NFS) to Ngarcia Santos (Nrc), Transmittal of Affidavit Related to Fissile Material Exemption (10 CFR 71.15 (C), Follow Up Questions and Additional Comments (Docket No. 70-143) Project stage: Request ML23137A4412023-06-0202 June 2023 Authorization for Shipment of the Model No. Halfpact Package - Inner Containment Vessel No. 506 Project stage: Other ML25087A0282023-07-0303 July 2023 Enclosure, Letter Dated 7/3/23 from NNSA to NRC, Roadmap, Revised SAR, 435-B Transport Package, Safety Analysis Report, Revision 6 (CoC No. 9355, Rev. 4) (Docket No. 71-9355) Project stage: Other ML23220A1572023-07-21021 July 2023 Transmittal Letter from Ahmad M. Al-Daouk (NNSA) to Ngarcia Santos (NRC) Related to the Application for Certificate of Compliance No. 9355, Revision 4, Model No. 435-B Project stage: Request ML23263A1022023-09-20020 September 2023 Email Dated 9-20-23 from N. Garcia Santos (NRC) to J. Mumma (Nnsa), Subject: Package Model No. 453-B--Need Clarification on Submittals Project stage: Approval ML24067A1282024-02-27027 February 2024 Initial Submittal of the Safety Analysis Report for Docket No. 71-9384 Project stage: Request ML24072A0022024-03-0505 March 2024 Revision of Model No. 435-B Package’S Certificate of Compliance (CoC) Number 9355 for the 435-B Package Project stage: Request ML24089A2562024-04-0101 April 2024 NRC Approval of Robatel Technologies, LLC Request for Withholding Information from Public Disclosure for the Initial Submittal of the Safety Analysis Report for Docket No. 71-9384 - Enterprise Project Identification Number L-2024-NEW-0003 Project stage: Withholding Request Acceptance ML24145A1342024-06-0505 June 2024 Cover Letter Application for Certificate of Compliance for the Model RT-200 Type B(U) Cask - Accepted for Review Project stage: Other ML24145A1362024-06-0505 June 2024 Enclosure 2 Observations Robatel RT-200 Type B(U) Cask - NON-PROPRIETARY Project stage: Other ML24295A1602024-06-30030 June 2024 Redacted, Industrial Nuclear Company - Application for Certificate of Compliance for the Inc IR1 00ST, Revision 0, Docket No. 71-9385 Project stage: Request ML24204A2332024-08-0808 August 2024 Acceptance Determination Letter with Observation, Certificate of Compliance No. 9355, Model No. 435-B Project stage: Other ML24222A7182024-08-30030 August 2024 Cover Letter - Requests for Additional Information Robatel RT-200 Type B(U) Cask, Docket No. 71-9384 Project stage: RAI ML24222A7192024-08-30030 August 2024 Enclosure 2 - Request for Additional Information Robatel RT-200 Type B(U) Cask - Non-Proprietary Project stage: RAI ML24248A2532024-09-20020 September 2024 Request for Additional Information, Certificate of Compliance No. 9355, Revision 4, Model No. 435-B Packaging, EPID L-2023-LLA-0102, CAC 001029 Project stage: RAI ML24281A1762024-09-25025 September 2024 9/25/2024 Conference Call Summary - Supplemental Information to Proposed RAI Responses Related to the Criticality Safety Review of the Model No. Castor geo69 Transport and Storage Systems (Docket Nos. 71-9383 and 72-1052, Respectively) Project stage: Supplement ML24312A2212024-10-0101 October 2024 Extension Request - Robatel Technologies’ Response to U.S. NRC Request for Additional Information for Review of the Robatel Technologies, LLC Model No. RT-200 Type B(U) Cask - Cac/Epid Numbers: 001029/L-2024-NEW-0003 Project stage: Request ML24275A0932024-10-11011 October 2024 Transmittal Letter - Certificate of Compliance No. 9310, Revision No. 8, for the Model No. F-431 Transport Package Project stage: Other ML25058A3612024-10-16016 October 2024 Email Dated 10/16/24 from Ngarcia Santos (NRC) to Mrose (Inc) Transmittal of Draft Requests for Supplemental Information and Observations, Thermal and Structural Evaluations, Model No. IR 100ST, CoC No. 9385, Rev. 0 Project stage: Draft Other ML25058A3592024-10-16016 October 2024 Enclosure to Email Dated 10/16/24, Draft Requests for Supplemental Information and Observations, Model No. IR-100ST, CoC No. 9385, Rev. 0 Project stage: Draft Other ML24289A2072024-10-28028 October 2024 Transmittal Letter and Enclosure, Requests for Supplemental Information and Observations for Revision 0 of CoC No. 9385 for the Model No. IR 100ST Project stage: Other ML24305A0542024-10-31031 October 2024 Email Dated 10-31-24 from Ngarcia Santos (NRC) to Mrose (Inc), Final Signed Letter with Requests for Supplemental Information for the Model No. IR 100ST Project stage: Other ML25058A3562024-11-0707 November 2024 Email Dated 11/7/24 from Ngarcia Santos (NRC) to Mrose (Inc)/Gclark (Orano), Follow Up to Requests for Supplemental Information (Rsis) and Observations Discussion on 11/7/24, Thermal and Structural Evaluations, Model No. IR-100ST, CoC No. 9 Project stage: Approval ML25058A3572024-11-21021 November 2024 Transmittal Email Dated 11/21/24 from Ngarcia Santos (NRC) to Mrose (Inc), Summary of Telephone Call Dated 11/7/24 with Inc, Acceptance Review Questions (Rsis and Observations), Thermal and Structural, Model No. IR-100ST, CoC No. 9385, Rev Project stage: Acceptance Review ML24327A2492024-12-0505 December 2024 Enclosure 1 - Certificate of Compliance No. 5086, Revision 17 (Renewal of Certificate of Compliance No. 5086, Model No. Unc 2600 (EPID L-2024-RNW-0024)) Project stage: Other ML24327A2472024-12-0505 December 2024 Enclosure 2 - Safety Evaluation Report, Renewal of Certificate of Compliance No. 5086, Model No. Unc 2600 Project stage: Approval ML25086A0322024-12-0606 December 2024, 9 January 2025, 4 February 2025, 21 February 2025 Responses to Requests for Additional Information for CoC No. 9355, Revision 4, Model No. 435-B (Docket No. 71-9355) Project stage: Request ML25086A0382024-12-0606 December 2024 Letter Dated 12/6/24 from Kschwendenman (NNSA) to Ngarcia Santos (Nrc), Response to Request for Additional Information on Preshipment Leakage Rate Test (Model No. 435-B, Docket No. 71-9355) Project stage: Response to RAI 2023-07-03 |
| ML24312A221 | |
| Person / Time | |
|---|---|
| Site: | 07109384 |
| Issue date: | 10/01/2024 |
| From: | Horin J Robatel Technologies |
| To: | Document Control Desk, Office of Nuclear Material Safety and Safeguards |
| References | |
| CAC 001029, EPID L-2024-NEW-0003 | |
| Download: ML24312A221 (1) | |
Similar Documents at 07109384 | |
|---|---|
Text
Page 1 of 1 Robatel Technologies 5115 Bernard Dr. Suite 304 Roanoke, VA 24018 October 1, 2024 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk One White Flint North 11555 Rockville Pike Rockville, MD 20852-2738
Subject:
Extension Request - Robatel Technologies Response to U.S. NRC Request for Additional Information for Review of the Robatel Technologies, LLC Model No. RT-200 Type B(U) Cask - Cost Activity Code/Enterprise Project Identification Numbers 001029/L-2024-NEW-0003, Dated August 30, 2024
Reference:
ADAMS Accession No. ML24222A718, dated August 30, 2024 Docket No. 71-9384 I am writing to request an extension of the submittal date of Robatels responses to the attached Requests for Additional Information (RAIs) which were originally due on October 15, 2024. Robatel is working diligently to provide the requested information on or before October 31, 2024. Our proposed submittal date should provide us with sufficient time to adequately address the RAIs.
Thank you for your understanding. Please do not hesitate to contact us if you have any questions.
Respectfully, Jay Horin Project Manager jhorin@robateltech.com CC: Daneira Meléndez Colón Attachments :