ML20215K188
ML20215K188 | |
Person / Time | |
---|---|
Site: | Beaver Valley |
Issue date: | 06/16/1987 |
From: | Asars A, Gramm R, Gray H, Kaplan H, Kamal Manoly, Paulitz F, Strosnider J, Winters R NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I) |
To: | |
Shared Package | |
ML20215K131 | List: |
References | |
50-412-87-20, IEB-79-07, IEB-79-14, IEB-79-7, NUDOCS 8706250250 | |
Download: ML20215K188 (56) | |
See also: IR 05000412/1987020
Text
n , ,
, ,
- ..
. -
!s
,
U~S.LNUCLEAR REGULATORY COMMISSION.
.
REGION I-
Report:No, . 50-412/87-20
'
Docket'No. 50-412
-License No. CPPR-10b Category A' ;
Licensee: Duquesne Lignt Company
Robinson Plaza Building No. 2
p Suite No. 210, Pa. Route 60
-
Facility.Name: Beaver Valley Unit 2
Inspection At:- Shippingport, Pennsylvania
..I.
~. Inspection Conduct : . March 16 - 26, 1987
Inspectors: A "- '
4[3/87
.R./ Gram ,-Seni r Resident Inspector date
H. Gray, Lead Rea p Engineer
d /3/8 date
') -1
l
W. bstetm 6/7fr7
H. Kaplan,. Lead Reactor Engineer '
d~ ate
[H4ww
K. Manol - Lead Rea'ctor Engineer
db/87
date
l .
~ n& h 6 /h /3 7
F(faulitz, React'6rEngineep ( dat'e
kNint rs Reactor Engineer
R.
b is
date
O-
Y9/87
. Asars, Re ident Inspector '
date
f
Approved by: 8 f/r/#7
. Strosnider, Chief, Materials and 'date .<
Processes Section
- 1
J
$$06*IO$$0S A2 ,
G
'1
.
- 1
y
r
-
.
i 2
.
Inspection Summary: Announced As-Built Team Inspection Conductcd on
March 16 - 26, 1987 (Inspection Report No. 50-412/87-20).
Areas Inspected: A special team inspection was conducted of installed
Mechanical, Electrical, HVAC, Instrumentation and Controls, and structural
hardware. The purpose of the inspection was to verify that the "as-built"
systems and hardware were of acceptable quality and in compliance with NRC
regulations, licensee commitments, and design specifications.
Results: The inspectors concluded, based on the sample of systems and hardware
inspected, that the "as built" condition of the plant systems and hardware are
constructed substantially in accordance with NRC requirements and licensee i
commitments and are of acceptable quality. One violation and one deviation I
were identified. The violation involves multiple examples of failure of
licensee QC inspections to identify minor hardware deficiencies. It was i
determined that none of these deficiencies had the potential to significantly l
affect safe plant operation. However, the number of examples of QC deficiencies !
observed indicates that increased attention to detail is warranted during the l
completion of construction and during plant operation. The deviation involved j
failure to properly identify by color coding the assigned electrical chain or
channel of safety related electrical equipment. I
1
i
V
.
'
.
I
.
..
TABLE OF CONTENTS
i
Page
Inspection Summary . ..................... 2
1.0 Scope and Purpose of the Inspection . . . . . . . . . . . . . . 3
2.0 Persons Contacted . . . . . . . . . . . . . . . . . . . . . . . 3 ,
3.0 Piping System Inspections . . . . . . . . . . . . . . . . . .. . 4
3.1 Scope and Objective . . . . . . . . . .......... 4
3.2 Inspection Criteria . . . . . . . . . . . . . . . . . . . 'S
3.3 Inspection Activities . ................ 7
3.4 Findings . ,..................... 8 l
3.5 Conclusions . . . . . . . . . . . . . .... ... . 10
l
4.0 Piping As-Built Verification and Stress Reconciliation Program 11 1
4.1 Overview of Licensee Program . .... ......... 11
I
4.2 Review and Inspection Activities . . . . . . . . . . . . . 12
i
4.3 Findings . . . ......... ............. 13
4.4 Conclusions . . . . . . . . . . . . . . . . . . . . . . . 13
5.0 Heating, Ventilation, and Air Conditioning (HVAC) Systems . . . 14
5.1 Scope . .... . .................... 14
5.2 Inspection Criteria . . . . . . ............. 14
1
5.3 Control Room and Control Building HVAC . . . . . . . . . 15
5.3.1 Inspection Activities . . . .......... 15
5.3.2 Fi n di n g s . . . . . . . . . . . . . . . . . . . 15
5.4 Emergency Battery Room HVAC . . . . . . . . . . . . . . . 17
5.4.1 Inspection Activities . . . . . . . . . . . . . 17
5.4.2 Findings . . ................. 17
5.5 Diesel Generator Building HVAC , . . . . . . ..... 18
5.5.1 Inspection Activities . ............ 18
5.5.2 Findings . . . . ................. 18
- ,
'
.
i@.
.
. Table of Contents Cont'd Page
5.6 Conclusions . . . . . . . . . . . . . . . . . . . . . . . 19
6.0 Electrical Power Systems . . . . . . . . . . . . . . . . . . . 20 ,
6.1 Scope of Electrical Power System Inspections . . . . . . 20
6.2 Inspection Criteria . . .. . ... . , . . . .. .. . . 20
i
i
6.3 Inspection Activities . . . . . . .. . .. . .. .... 22
6.4 Findings . . . . . . . . ... . .. . ... . . .... 23
6.5 Conclusions . . . . . . . . . . . . . . . . . . . . . . . 27
7.0 Instrumentation and Control . . . . . . . . . . . . . . . . . 28
7.1 Scope . . . . . . . . . . . . . . . . . . . . . . . .. . 28
7.2 Inspection Criteria . . . . . . . . . . . . . .. . . .. 28 ,
l
7.3 Inspection Activities . . . . . . . . . . . . . . . . . . 29 -
7 .' 4 Findings . . . . . . . . . . . . . . .. . . . . . . .. 31
7.5 Conclusions . . . . . . . . . . . . . . . . . . . . . . . 33
8.0 Structures . . . .. . ... .. . . ... . . . . . . . . . . 35 l
!
8.1 Scope of Inspection . .. .. . . . . . . . . . . . . .. 35 .
1
<
8.2 Inspection Criteria . . . . . . . . . . . . . . . . . .. 35 :
i
a
8.3 Building Loads Verification Program . . .. . . . . . . . 35 J
i
!
8.4 Inspection Activities . . . . . . . . . . . . . . . . . . 38 i
l
8.5 Findings and Conclusions . . . . . . . . . . . . . . . . 39 l
l
9.0 Followup on Outstanding NRC Bulletins . . . . . . . .. . .. 40 l
9.1 IE Bulletin 79-14 . . . . . . . . . . . . . . . . . . . . 40
,
I
9.2 IE Bulletin 79-07 . . . . . . . . . . . . . . . . . . . . 40 )
1
10.0 Exit Meeting . . . . . . . . . . . . . . . . . . . . . . . . . 41
Appendix A: Notice of Violation and Deviation
I
g
i
1
1
!
!
!
.
.
t .
A
r
Attachments:
Attachment I: List of Persons Contacted
Attachment II: Isometric Drawings Used During Piping Inspections
Attachment III: Piping Related Non-Conformance Reports Reviewed )
' Attachment IV: Pipe Documentation Reviewed, Welding
l
Attachment V: List of Piping Procedures and Reconciliation Packages Reviewed
Attachment VI: Drawings and Documents Used During HVAC Systems Inspection
Attachment VII: Drawings and Documents Used During Electrical Power Systems
Inspection
Attachment VIII: Drawings and Documents Used During I&C Inspections
-i
f
I
l
l
L
l
l
l
_ _ _ _ _ -
, ,
...
,.
..
.. j
l
DETAILS .!
1. 0. Scope and purpose'of the Inspection l
l
This as-built team inspection was conducted by NRC inspectors to verify I
that selected systems have been constructed with an acceptable level'of. ,
quality and substantially in conformance with-NRC requirements, licensee '
commitments. and design specifications. The inspection included examination
of fluid piping systems; heating,. ventilation, and air conditioning-(HVAC)
~
systems; AC and DC electrical. power systems; instrumentation and control
(I&C)l systems; and plant structures. Extensive system walkdowns'were-
performed and various project' specifications, drawings, records and' design
calculations'were reviewed.
Infgeneral, the systems selected for inspection are' associated with meeting >
'
reactor safe shutdown and core cooling requirements. In addition, piping
'
. system inspections focused on those systems, including the reactor coolant
system (RCS), for which postulated pipe breaks were eliminated (for the-
purpose of defining mechanical loads)- based on " leak-before-break"
evaluations. The inspection-included portions of the following: )
- The Reactor Coolant and High and Low Pressure Safety Injection Systems- i
.
- . The control room, control building, battery rooms, and. diesel generator
building HVAC systems
Injection System pumps; the "B" Low Head Safety Injection System pump and
the control room, contro1Ebuilding, and diesel generator building HVAC
-systems
- The . Piping' Stress Reconciliation Program and the Building Loads Verification
Program
2.0: Persons Contacted'
Numerous licensee and licensee contractar personnel were contacted during
the inspection. Attachment I is a list of the principal individuals
who were contacted by the NRC inspectors.
L
L
.. .. _ _ _ - _ _ _ __ _ _ _ _ -
_
..
-s
. 4
.
3.0 Piping Systems Inspections
3.1' Scope and Objective
The scope of the piping system inspections included piping components, y
equipment and supports in portions of the Reactor Coolant Eystem and ;
Safety Injection System (SIS). The portions of systems inspected j
were the third loop of the RCS, including the pressurizer and pressurizer j
surge lines, and those portions of Train B of the Emergency Core Cooling l
System (ECCS) piping associated with Mode "D" of SIS operation. This !
mode represents the case of minimum required safeguards with the "B"
low head safety injection pump and the "C" high head safety injection
(charging) pump taking suction from the Refueling Water Storage Tank
(RWST) and delivering to the reactor through the RCS cold leg connections. ,
(Mode D in Section 6.3.1 of the FSAR). The specific portion: of each j
system inspected are tabulated below: !
~
-
The portion of RCS inspected was loop "3" including the 29" 0.D.
line from reactor vessel to steam generator, the 31" 0.D. line ,
to the reactor coolant pump, the 27h" 0.D. return line to reactor !
vessel, the 14" line to pressurizer, and the 6" 0.D. line from l
the top of pre;surizer to the relief valve (RV551B).
l
-
High Head Safety Injection System
-
P&ID Fig. No. 7-4: 3" and 4" 0.D. piping between the discharge
side of charging pump No. P21C to motor operated valve (MOV)
8133A and MOV 8133B.
-
P&ID Fig. No. 11-1: 4" 0.D. piping to MOV 867B and 3" 0D piping
to MOV 867C.
-
P&ID Fig. No. 11-2: 3" 0.0. piping to containment penetration
J No. X-113 and two 2" 0.D. branch piping to Globe valves No. 67
l and 68.
-
P&ID Fig. No. 11-4: Two 2" 0.D. SC-1 piping to check valves No. l
137 & 139 to 6" 0.D. headers discharging into the RCS cold legs .
No. 23 & 21 through check valves No. 552 and 548. j
l
Low Head Safety Injection System
-
P&ID Fig. No. 11-1: 10" 0.D. piping between the discharge side
of charging pump No. P21B to.MOV 8888B. Also, the cross-tie 10"
0.D. piping between the A and B trains of the discharge piping
from pumps P21A and P218 respectively. ;
-
P&ID Fig. No. 11-4: 10" 0.D. piping to containment penetration
X-60 to check valve No. 132. 6" 0.D. piping to check valves No.
107 and 548 to the discharge in the RCS cold leg loop No. 21. p
,
+
'
e e
h
1
- f) .
g, y '
fa
4 L .l
'*
.
$
- . !
,
..
.
!B
The-objective.of the inspection was to verify, by sampling review, l
that.the above' systems were designed and fabricated such that.they l
were capable ofl performing :their . intended functions as specified in -
'
~ l
the Final, Safety Analysis Report (FSAR): and whether the as-built
~
2
l
- specifications'and drawings, i
i
+ To achieve this objective, the inspect .-n. focused:on review of the
.
11cens Wgidocuments and installed hard, tare to ensure that, for those !
select 6d systems,: FSAR commitments wert ccrrectly translated into. i
'
specifications,: procedures,-drawings, and installed piping systems. '
Inspections: of the "as-built" piping . systems were conducted to -verify
consistency and agreement with the Piping and' Instrumentation Diagrams
(P& ids), pioing. isometrics,, and support detail drawings and to verify
an acceptable : level; of qt; alit) . The P& ids reviewed included those-
that will be used by the crerators during plant operation.
is, i
Review of Quality Assuraned 'and . Control records, relating to the
~ licensee's and. contractor's inspection.of selected piping..and. support'
-
y corrponents also was performed during the course.of the ' inspections.
o g In' addition to the w rification of as-built piping and support system
"
installations, the inspection also included a review of-the licen-
, see's program for reconciliation of as-built. configurations. This
inspection: activity provided the basis for NRC. review-of the licensee's-
[ actions in response to the requirements of I'.E. BulletinL79-14 for
- ?4 Seismic Analyses of As-Built Safety Related Piping Systems, i
4 . s
4
p 3.2 InspectionCriterfy
, The. governing criteria for the as-built piping. system inspections were:
t
s
4 - 2 10'CFR 50
W N I
Final Safety Analysis. Report (FSAR)
t < *
Safety Evalvdfon Report (SER)
%? ASME Section @ I, Class NB and NC, and Section IX
The veriffcation of correct piping system installation was performed
either by visual inspection or by independent measurements on !
-accessiblecompoiien$sandsupports.
+VA ( "1hedetailedcriteriausedforthe.inspectionoftheseinstallations
'
were .those :descr(bed in the specific . installation specifications.
.
'The in's pectick attributes'for piping and fittings included selected
,
verification' of the follosing: ,
b !
,
3
-
11 pear and angular measurements related to piping runs and
, j asupport' locations,
.r r r
- 3
' 't ' branch connection types and locations;
( l
,1 l
- .
'
..
%..
y '
r
?
< , ,
,
, , .
u .o
y
1., '
6-
~
,.
'
pipihg' bend and elbow radii;-
'
1
'
'
'
-
support mark numbers, functions.and locations;
- proper. flow direction marks on valves;
-
. piping wall thickness;-
'
correct-sequentialElocation of. valves on piping runs; and,
--
. proper identification and orientation 'of valves and Limitorque
operators..
L
! The. inspection attributes.for pipe supports' included selected veri-
fication of the following:
w .
.as-built'. configurations compared ,to support detail drawing (BZ
series), including dimensions of. members;
support orientation;.
..
' -
connection to the proper structure;
direction of restraint;
..
'
sizes'and quality of welds on hangers, including welded
attachments to piping;
l baseplate dimensions and location of structural attachments to
basepla.tes;
baseplate bolt (concrete expansion or Richmond insert)
'
tightness, edge distance and the bolt mark identification for
Hilti bolts;
restraint bleed holes open and' free of foreign material; 'l
load setting of spring hangers;
grouting of floor mounted baseplates and gap sizes for wall
mounted plates; and,
pipe routing and support locations such that movements of
piping due to vibration, thermal expansion, etc., would not
likely cause contact'with other pipes, supports, equipment or
components.
..
'
s
1
.w;
4
.- 7
.
3.3 Inspection Activities'
Inspection of the reactor coolant and safety injection systems
consisted of the following activities:
Walkdown inspection of as-built piping components (including
fittings and attachments), equipment and. system supports; !
Independent comparison of selected piping components and
supports to the attributes identified in Section 3.2; ;
Verification of valve tag numbers against Stone and Webster
Engineering Corporation SWECs P&ID and plant operation drawings; !
Review of selected QA inspection records, Non-Conformance and !
Disposition Reports (N&Ds) and Engineering and Design Coordi-
nation Reports (E&DCRs). Attachment II is a list of the piping
isometric drawings showing the piping components, equipment and ,
support installations examined during the course of the inspection.
A listing of piping related nonconformance reports reviewed is
provided in Attachment III.
The inspectors reviewed representative shop and field data
sheets, associated NDE reports, and material test reports for
base metal and weld filler materials as required by ASME III-NB
and NC, and ASME IX. Procedures to control sensitization (carbide <
sensitization) in austenitic stainless steel as prescribed in
FSAR Section 5.2.3.4.4 and Amendment 12 were reviewed.
3.4 Findings
Based on the review of documents and examination of piping system
installations, the following findings were identified.
a. Specification of weld length was not provided for a weld
connecting structural tube steel TS 3x3x0.25 to an embedment
plate on hanger No. 2CHS-PSR 2604 (shown on drawing No.
BZ-83B-24-2). Further, the distance between the embedment plate
and a reference location was not specified on the support
drawing. Thus, a concern was raised regarding the lack of ;
information provided on the drawings to specify the minimum i
required weld length fer both construction and QA personnel. In
response to the inspectors observation SWEC indicated that a
full weld length between adjoining members was assured even
though the length was not specified on the drawing. This was
accomplished through the size and location of all embedment
plates specified on structural drawings (RC-Series). When the
tolerances in the installation of both embedment plate and
1
i
l
- _ _ _ _ _ _ - _ _ _ _ _ .
c
.
.
. 8
.
piping are considered, the minimum attainable weld length (Sh") )
was equal to the required length according to design calculations. !
The actual length was measured as 5 3/4". The inspector had no j
further questions.
b. Manufacturer drawing for valve No. C-78, on the HHSI piping No.
'2-CHS-003-70-2 from the discharge side of charging pump P210, ,
was referenced as drawing No. 2006-300-001-116 on SWEC's piping I
isometric drawing No. 108302 but as drawing No. 2006-300-001-112 l
on SWEC's piping isometric drawing No. 108397. SWEC's review of
the discrepancy identified that the correct valve drawing No.
was 2006-300-001-112. Westinghouse [W) records indicated that
File No.116 was for an ASME Class 1 valve (C-88) and file No.
112 was for an ASME Class 2. valve (C-78). The N-5 data package
reflected the as-built condition (i.e. ASME Class 2 valve No.
C-78). SWEC determined that the reference to the W file No. 116
was a drawing error and indicated that it will be corrected.
The inspector concluded that the drawing discrepancy was not
significant since it had not affected the valve installation or
the ASME N-5 documentation.
c. During the piping walkdown inspection, a small clearance was
observed between the pipe clamp of hanger No. 2515-PSST-607 and
an existing structural beam W8x18 in the direction of pipe
movement. The clearance was measured as 11/16". A concern was
raised regarding the effect of the small clearance on piping
axial movement in the unrestrained direction. Another concern ,
was raised regarding the adequacy of QA walkdown inspection of
clearances between safety related structures and components.
With regard to the piping movement concern, the licensee issued
a clearance evaluation report (attachment A-4 to procedure
2BVM-236) for evaluation of the observed clearance. The evaluation
noted that, based on review of the piping stress calculation,
the predicted seismic pipe movement in the axial direction was
0.72", slightly exceeding the available clearance of 0.6875".
Evaluation of the minor contact of the clamp edge and the beam
flange during a seismic event indicated it could be accomodated
by the flexibility of the sway strut's pin connection. The
licensee's disposition of the finding was considered acceptable.
,
'
However, the failure of QC to detect the observed tight clearance
is a failure to effectively implement a procedure 2BVM-236 for
" Engineering and Quality Control Survey.of Component Spacing and
! Clearances" and is an example of the violation of Criterion X
j of Appendix B to 10 CFR 50. (87-20-01)
l
I
I
I
- - - -
t-
,bh
.
4 9 )
3:
l
d. All operational valve' tags.in the RCS Loop conformed to the.
applicable drawings except the tags were missing on valve numbers
-46 and 18 on 2" 0.D piping. A review of valve tagging records
indicated that the tags were placed on the valves by the licensee
prior to the end of the inspection.
e. Visual inspection of welds in the RCS and Safety Injection.
System revealed exceptionally' smooth ground surfaces, free of
surface irregularitie's. The resultant surface finish is considered l
conducive to meaningful in-service inspection (ISI). j
1
f. Independent determinations of. wall thickness at sixty-five- 3
locations using an ultrasonics "D" meter indicated that all
measurements exceeded code requirements minimum wall thickness.
I
g. lThe inspector reviewed seventeen non-conformance reports (NCRs) !
Lincluding.their dispositions. The NCRs were readily retrievable i'
using the licensee's tracking system and were found to be well
' documented and to have appropriate signatures. Disposition !
included weld repair, replacement, or use as-is. l
h. A loose nut was found on a stainless steel coupling flange in
the safety injection system (Item 6'on-ISO drawing CL-110-177-GAC).
Inspector re'iew
v of the licensee's practice for bolting of' flanged. I
connections: disclosed that no torquing procedures are employed j
for. connections of this type. .(Terquing procedures were only
utilized when torque values were specified by.the vendor). :These
joints were made using standard. pipe fitters. practice of tightening '
the bolts with a hand wrench in a manner that appropriately
compressed the gasket material and maintained the flange faces
parallel to each other. The QC inspection of bolted flanges <
verified proper materials and-fit-up of the joints. lThe joints - !
were monitored for leakage during the hydrostatic test and any
leaking-joints were tightened or the gasket was replaced as
necessary.
!
The inspector questioned the adequacy of the practice for bolting
flanged connections without more specific procedures. The
licensee responded that' Beaver Valley Unit 2 is committed to the
1971 Edition through Winter 1972 addendum of the ASME Code.
This edition of the Code provides no guidance regarding
installation of bolted joint connections. The ASME code
guidance for control of Bolt stress is contained in the
mandatory Appendix XII, Article XII-1000, first issued in 1981. l
The licensee irdicated that their practices for bolt tightening l
and control of bolt stress are consistent with these code
requirements. Review of the 1983 ASME Code Article XII-1000 by
the inspector confirmed that the licensee's practice was
!
l
I
l
i
!
_
. . .
.
..
k
..
..
- 10
.
i
consistent with the Code. The licensee'did indicate that torque
values would be specified for maintenance activities during
plant operation to a /oid possible leakage of contaminated water
and to meet ALARA esals.
The inspector had no further questions.
1. The inspector determined that welding and NDE activities
involving reactor coolant and safety injection systems conformed
to the requirements of ASME III Sections NB and NC, respectively,
and Section IX requirements. Field welding was performed by
Schneider Power, Inc. using a manually qualified austenitic
stainless steel weld procedure SPBV 300G (with type 316 filler
metal). The procedure utilized both the Tungsten Inert Gas
(TIG) and Shielded Metal Arc (SMA) process; the TIG process for
depositing the first three layers including consuming the insert
for the root pass and the SMA for the balance of layers. Shop
welding was performed by Power, Piping using a combination of
qualified SMA and TIG procedures. TIG procedure 8001A was used
to weld the root pass (open butt) and SMA procedure 8021 for the
remaining layers. A sampling of welder performance qualification
records indicated conformance to ASME IX requirements. The weld
data sheets and inspection reports verified that the specified
radiographic and liquid penetrant examinations were performed as
required. Filler materials were found to conform to specification
requirements including a 5% minimum calculated ferrite content.
J. A review of random certified test reports indicated conformance
to specified SA material specifications for piping components
including pipe, fittings, valves, flanges and bolting. These
included SA 351 Grade 304 (castings), SA 312 Grade 316 and SA
376 Grade 316 (piping), SA 182 Grade 316 and SA'193 Grade B6
(bolting).
k. The inspector determined that the licensee's subcontractors
implemented and documented the following controls and measures
for controlling sensitization in austenitic stainless steel:
(a) control of heat input as verified by calculation of welding
parameters and corrosion testing (ASTM 708) of field weld procedure
qualification test assemblies, (b) prohibition of post weld heat
treatment, (c) control of welding interpass temperature (350 F
max.) and (d) utilization of materials in the solution annealed
condition obtained by heating to 1800 F - 2000 F followed by
water quenching. For example, the documentation showed that the
27h" I.D. x 2.2" minimum wall thickness reactor coolant piping
, was furnished as a SA 351 -Grade 8A type 304 centrifugally cast
I product, heat treated at 2000 F for 4k hrs. followed by water
i
quenching and 100% inspection by liquid penetrant, radiography
and ultrasonics.
_ _ - _ _ _ _ _ - - _ _ _ _ _ _ _ _ - _ - _ - _ _ - _ _ _ _ - - _ _ _ _ _ _ - - _ _ - _ _ _ _ _ _ _ _ _ - _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ - _ _ - _ _ _ _ - _ _ _ - _ _ _
..
m ;
.
.
.
11 --
7
3.5 Conclusions
The installed' piping, piping components and supports inspected'were-
'found generally to be .of good quality and to satisfy the criteria ;
established in Section 3.2. . Quality records were found to be acceptable :
and "as-built" drawings-including those to be used by the operators 3
to support plant cperations were found substantially in agreement-
with the as-installed piping systems. One example.of QC failure'to-
identify a smaller clearance'between a piping clamp'and a; structural
beam t 1.specified.by procedure was identified. Analysis of the j
nonce.rorming condition indicated that it would not adversely. affect '
. safe plant operation.
4.0 Piping As-Built Verification and Stress Reconciliation Program .
4.1 : Overview of Licensee Pogram
.
.
i
The. reconciliation of design.and "as-built" piping stresses was-
performed and documented as part of the N-5. certification program. ,
Documents (calculation, drawings, etc.) generated.for the qualifi-
cation of piping pressure boundary were included 'in the N-5 package
upon completion.of the stress reconciliation.
The major features of the licensee's reconciliation program included: l
Walkdown verification of as-built installations against piping !
isometric drawings. '
-
Incorporation of. final input-to stress analysis in the piping
design specification.
Evaluation for_ disposition of discrepancies between as-analyzed
and'as-installed condition.
Re-analysis, if required, of piping systems involving disparities
identified in the previous evaluation stage. )
i
The piping as-built verification-ef. fort was the responsibility .of the
Installed Condition Verification Group (ICVG) which consisted of
representatives from the contractor, Schneider-Power Corporation !
(SPC), and SWEC Construction. SWEC's program required the certifi- j
cation of-members of the ICVG to the requirements of ANSI N45.2.6-1978 !
for inspection. l
'
Verification of as-built piping configurations was performed in
accordance with procedure FCP-509, for " Installed Condition Verifi-
cation of Piping". The procedure provided a listing of attributes
.which required verification by the ICVG. These included piping
layout dimensions, elevation, branch connections, valve and support j
locations, etc. The procedure also provided specific tolerances for i
performing installed condition measurements. The acceptable tolerances i
i
l
a. q
, ,
j
,
- t
..:
n, .
12-
- .
.of as-built pip'ing configurations from the as-analyzed condition were
consistent with'those in thetspecification-for field fabrication and. -t
erection of piping systems (2BV5-920). Thus,'the total permissible' 1
tolerances were allocated to installation related deviations rather i
than divided among installation and design reconciliation phases.
The procedure;for pipe stress reconciliation (28VM-156) provided.
detailed' description'of the several activities involved.in this
process inc16 ding the requirements for reconciliation of. piping
supports, nozzle. loads, welded attachme.nts and penetration loads'.
The procedure also addressed acceptable methods for the re-analysis
of piping systems which included'the use.of ASME code case N-411 for
alternate damping values for seismic analysis of Class 1, 2 and 3 .,'
. piping. SWEC indicated that when piping re-analysis was required,
neither the Independent Support Motion (ISM) in response spectrum
analysis nor the time history approach was employed in the piping
reconciliation evaluation. Both of these analysis: techniques wotild
be..less' conservative.than'the enveloped response spectra approach.that
was used.
4.2 Review'and Inspection Activities.
Evaluation.of the program for piping as-built verification and stress
reconciliation included the.following review and inspection activities: J
The procedures governing the piping' installation tolerances, l
. installed condition verification and pipe stress reconciliation
were reviewed,
Sample verification of selected piping.-system installations was
performed, and ;
A sample of piping and support reconciliation packages was
reviewed.
Details of NRC sample verification of various piping systems and the
inspection findings were addressed in Sections 3.3 and 3.4. The
sample of piping and support reconciliation packages reviewed, was
selected from the portion of Safety Injection system verified during
the as-built walkdown verification discussed in Section 3.0.
A list of reconciliation packages reviewed is provided in
Attachment V. ,
.
4.3 - Findings
The program for piping as-built verification and stress reconcili-
ation was found to be comprehensive and consistent with overall
industry practice. The. acceptable deviation between as-analyzed and
the as-installed configuration was generally equal to or more
conservative than that provided in the technical position of the
Welding Research Council bulletin WRC-316 on piping installation
tolerances. 1
l
l
i
..
.
'
7 13
'
.-
One area of concern was_ identified. relating. to the~ lack _ of a' require-
ment for performing-angular measurements between piping segments
.during the'as-built configuration verification effort. .It was noted,
however, that the requirements of the_ procedure which were verifi-
cation of (1) linear segment measurements, (2) the-global-location of:
one point;on each piping isometric,.(3) two measured piping elevations
on each isometric,.and (4).the location of nozzles, when viewed
collectively, was considered adequate' indication of angular orientation .
of. piping. segments.'.-One.possible but rare piping geometry was postulated i
, involving an offset in the piping line,.such as a large U-bend, beyond < '
which the pipe returns to its original. centerline. . In this~ case,-the-
'
segment lengths could remain the same even though..the entire' offset
could be rotated out.of.the~ intended plane of installation. The-
possibility:of such a condition going undetected was' considered. highly.
unlikely, since-it would significantly affect the location and
,
l
orientation of pipe supports. Angular deviations involving rotation 1
of the postulated piping configuration that' might result in linear :
support deviations within acceptable support installation tolerances
were. considered of no consequence.to the validity of the seismic
,
!
analysis.of the affected piping systems.
4.4 Conclusions
Base'd on NRC review of the piping as-built program and examina-
tion of completed-installations, it was concluded that the as-built i
records reasonably depict the actual installed configurations within i
acceptable. tolerances. Further, the system diagrams reviewed and
'
field verified during the course-of this inspection were consistent .'
.with the FSAR and SER descriptions. The quality of workmanship in
this area-was found to be generally good. The program for piping i
as-built = verification and stress reconciliation was either consistent j
with or more conservative than accepted industry practice. .The
overall piping as-built program was found to meet the intent and the
requirements set forth in NRC_IE Bulletin 79-14 for seismic analyses
of as-built safety related piping systems.
Based on the above analysis, the licensee's approach for detection of
piping angularity was considered adequate.
.!
I
--_ - - - _ _ _ _ _ _ _ - _ _ _ _ _ _ . _ _ __ _
i
..
..
-
,
14 j
.. ;
5.0 Heating,' Ventilation, and Air Conditioning (HVAC) Systems
-5.1. Scope j
An inspection of . heating, ventilation and air conditioning-(HVAC).
systems for .the control room, ' control building, battery rooms and -
diesel generator building was. conducted; Both normal and emergency
mode equipment was included.in.the. examination; The inspection
. consisted of a walkdown examination of ducts, filters, dampers, fans,
supports and other components. A review was performed of the Stone
and Webster Engineering Corporation (SWEC) building services drawings,
,
flow diagrams, support detail drawings, and of the contractor air
conditioning drawings'to verify their consistency and agreement..with
the as built installations. The verification was performed either by '
visual examination or by. independent measurements on accessible ;
. components and' supports. SWEC system specifications and. procedures
were. reviewed to assure compatibility with'the FSAR and SER licensing- ,
commitments. Quality Control inspection plans were reviewed to
establish the adequacy of the specified inspection attributes and
'
Quality Control records were reviewed for' selected commodities of the '
HVAC systems. Attachment VI is a listing of drawings and documents ,
reviewed as part of the HVAC systems inspection. !
!
'
5.2 Inspection Criteria
i
The criteria utilized for inspection of HVAC duct, components and
supports was derived from the FSAR, SER and SWEC design documents.
The specific attributes for'the walkdown included verification of.the
following;
Duct Inspection Attributes
proper size-and location
proper sheet metal configuration
acceptability of flanged connections
acceptable welding
.
access door location and operation
cleanliness of duct interior
branch connection type and. location
I proper location of duct stiffeners
duct configuration and installation damage
( : Damper, Fan and Filter Attributes
L
f name plate data consistent with FSAR and purchase order
!- specifications
locations as required by design documents and drawings
accessibility for manual operation and maintenance
. . . . . . . . . .
_ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
_ _ _ _ - _ - _ _ _ - _ _
.
.
-
15
.
component identification and marking
component proximity and potential for operability
interferences
installation of supplementary hardware including air
operated solenoid valves, limit switches and power supplies
Duct Support Inspection Attributes
Location and configuration
weld length, weld size and weld quality
proper attachment to support plates
dimensional verification of support configuration
bolt location and installation
baseplate installation, location and mounting to the
concrete
baseplate dimensions
Equipment Support Inspection Attributes
support or foundation configuration
anchor bolt size, location and tightness
weld size and quality
5.3 Control Room and Control Building HVAC
5.3.1 Inspection Activities
The ducts, duct supports, instruments and component supports
associated with the Control Room normal ard emergency HVAC
systems were examined using the inspection criteria and
attributes described in Section 5.2. The normal system from the
missile protected air intake, through the isolation dampers to
air co,ditioning units 2HVC*ACU201A and 8, and into the main
c v. bi roon. s rea was inspected. The e,nergency system from the
air intake, through dampers 2HVC*DMP204A and B. to the control
room pressurization filter and the duct to tho main control room
also were inspected. Instruments associated with chlorine
detection, radiation monitoring and temperature elements were
examined. The copper tubing and brazing associated with the air
conditioning refrigerant system were examined.
5.3.2 Findings
a. The inlet duct and piping (2HVC-036-2-3) from the
missile protected air intakes to the air conditioning
units 2HVC*ACV201 A and B were examined. From the
intake through the isolation dampers, the installation
was with round ductwork. The isolation dampers were
in the proper locations and the flanged connections
l. - _ _ _ _ _ - _ _ _ _ - _ _ _ _ _ _ - _ _ _ - _ _ _ _ - - _ _ _ - - - _ _ - - _ - - - - - _ _ - - - - _ _ . _ _
- ____-_____ _ ___ - _ _ _ _ . _ _ _ _ __
1... .
q
. t
l
l
E -
16 I
..
adequate. 'The transition from this round duct to the
rectangular duct was in accordance with the drawings. q
Supports were verified to be in the. proper locations,
have visually acceptable welds and to_be attached to
the. building as designed. The flow dampers in the
system were as described on the drawings, as were the
access doors.
'
~ b. In the inlet plen n of the air conditioning unit
2HVC*ACU201 B the inspectors noted that the internal
sound. proofing insulation had gaps and frayed edges. .!
that were not in.accordance with the-installation
specification. The. licensee initiated Construction
Deficiency Report (CDR) 4146 to repair this condition.
Failure of the quality control program to identify
this deficient condition is another example of a
violation of 10 CFR 50, Appendix B, Criterion X as
presented'in Appendix A. Review of the inspection
plan found that it was inadequate in that it did not
identify any inspection attributes for QC verification
of the insulation edge sealing. The. inspectors noted
that the internal' cleanliness of the ductwork and air
conditioner was adequate and that protection of the
interior of the air conditioning unit from damage
during work in progress was adequate.
c. Visual inspection and direct measurement of the
ventilation line 2HVC-012-5-3 showed the welding of
this round duct, fabrication, support locations and
installation of the motor operated isolation dampers
were in accordance with the drawings.
d. During the inspection of the copper refrigerant tubing
on air conditioning unit 2HVC*ACU201A, the inspector
observed that the joints in this nuclear safety related
'
- non ASME system for the Tee below valve 2HVC-79 and
valve 2HVC-113 did not appear to be adequately filled
with braze material. The licensee had previously
recognized that brazing of copper tubing was a problem.
Nine nonconformance reports had resulted in the identi-
fication of a trend in brazing problems,-(reference
DLC/SQCL-0285-GY - Trend No. TN-006). The corrective
action for this trend, in part, involved requalification
of the brazing procedure using a different brazing
flux and alloy combination. However, the licensee had
. not performed a visual inspection of the subject joints.
The licensee attributed this to the lack of quantitative
acceptance criteria in the governing code ANSI B31.5;
however, ANSI B31.5 does require a visual examination
to be performed leaving it to the user to develop
p quantitative acceptance criteria. Futhermore, in
reviewing the quality control inspection reports the
gimmi g i qi*g-it- rua i n-T .yr
.,
,
'
- } { ._^
.4 -
l
C%f
-
17
r
inspector noted the proper annular clearanc'e as required
by ANSI B31.5 was not. included as an inspection attribute.
' Failure of the Quality Assurance Program to include
<, the above requirements of ANSI B31.5 a's committed to
is another example of a violation'of 10 CFR 50,
Appendix B, Criterion X.
e. The inspector observed that the' bolted foundation .
-connection of fan 2HVC*FN241A was improperly. torqued
'
-l
in that a bolt could.be turned by hand.
'
The.
licensee initiated.CDR SD-006 to correct this.
deficiency., The quality control procedure requires
that a minimum of two bolts be torqued and that the j
inspector verify all bolts are tightened.'
.
Failure to !
effectively implement the quality control procedure:is
.
1
another. example of a violation of 10 CFR 50, Appendix '
B;. Criterion X.
..
.
f. Inspection of the ductwork from the air conditioning l
units into the control room did not reveal any
inconsistencies with the drawings. Welding was
adequate on the supports, access doors were properly
located, 'and discharge vents in the control room were
as described on the drawings.
5.4 Emergency Battery Room HVAC
5.4.1 Inspection Activities
The ventilation system. ducts, supports, inst'ruments and
components associated with Battery Rooms 2 and.3 exhaust systems
were examined using the acceptance. criteria and attributes .
described in Section 5.2. The-inspection included from the air-
inlet fire dampers and'all accessible portions of the. system to
the exhaust missile barriers. Inlet fire dampers 2HVZ*DMPF 231A
and B, fire damper 2HVZ*DMPF 204B, and fans 2HVZ*FN 216A and B -
with associated control circuits were examined. The location,
identification and configuration of the system components were
~
checked for consistency with the SWEC design documents.
h
_ . . . . . -
_ _ _ - --- - - - - - - _
p
1
.
I .- ,
-
,
18
4-
t
H5.4.2. Findings
'
., . a. The identification-tags on the two sets of fire dampers .
2HVZ*DMPF 231A and B associated with'the air intake into
Battery' Rooms 2-3.were found reversed although the physical
configuration of the dampers was correct. The licensee i
Lissued a Construction-Deficiency Report to correct-the tags
on these fire dampers.
. b .- Other accessible portions of the system were; inspected and .;
measurements.taken. The name. plates;on the exhaust fans -l
2HV2*216A and B were observed to'be correct and mounting
. bolts' instrumentation and ductwork were in accordance with
,
drawing requirements.
- 5.5 Diesel Generator! Building HVAC
5'.5'.1 Inspection Activities
~The ventilat' ion ' system ducts, supports, components and' instruments. i
associated with the Diesel Generator Building HVAC system were
'
examined using the inspection criteria and attributes described
in Section 5.2. The inspection included a walkdown of the system
.from the' missile protected air intake to the ventilation ports
~
in the A and B~ Generator Buildings.- Included in the inspection
were the intake plenums, axial fans 2HVD*270A and B, dampers t
2HVD*DMP 201A and B and the. exhaust duct and supports to the
floor penetration at elevation 759' 0". Temperature elements
2HVD*TE21A.and B were examined and the associated wiring termi- .j
nations were verified at the instruments. Exhaust fans 2HVD*FN222A '
and.B for elevation.759' 0" were found satisfactory. The duct,-
dampers and outlets for elevation 732' 6" in the Diesel Engine 2~
compartment were examined and found satisfactory.
I
5.5.2 Findings
a. One section of horizontal duct in a 36 X 72 inch run'was
found installed in reverse in comparison to drawing SM-7-1.
-The as-built installation was evaluated by SWEC engineering
in Request for Information 3815-QC and found acceptable as
the maximum span between reinforcing angles was less than
the required 24 inch spacing specified by the design. A
drawing revision was initiated to correct drawing SM-7-1 to
reflect the as-built configuration. Failure of QC to
identify this discrepancy is another example of a violation-
of 10 CFR, Appendix B, Criterion X.
,
_
..
- 4:
-
T19
-
i
b. No' deviations from the drawing requirements were noted,
except as stated above,.for measurements-taken during
. inspection of accessible duct and supports.
<c. The procurement package for. fans 2HVD*FN271A and 8 was
reviewed. .This package included the procurement specifi- ;
cation, receiving inspection,-storage and issue '
documentation for. installation. No deficiencies were found
in this' package.
'5.6 ' Conclusions
l
The installed hardware was found generally acceptable,and the i
majority of the items installed in accordance with the design !
requirements. .However, a number of commodities were identified which
did not meet the design intent.(findings'5.3.2 b, d,.and e; 5.4.2 a;
and 5.5.2 a). These in'cluded failure to note frayed edges on the !
insulation in the control room air conditioning unit. inlet plenums; l
failure to assure the corrective action of the brazing problems !
. identified in the trend analysis program was effective; and failure
~
to' identify and correct improper bolt. torquing. .A review of the
inspection records and procedures indicated that inspection personnel
were generally provided appropriate criteria. However, inspection
criteria was-lacking for both visual examination of brazed joints and !
verification of duct insulation edge sealing.
!
i
l
.
p
I
..a 20 j
,
,
l
.
6.0 Electrical Power Systems
6.1'. Scope of Electrical Power System Inspections
L;'
-This' inspection was conducted to ascertain whether the installed
' electrical power systems were in conformance with requirements of
110CFR50' Appendices A and B and the commitments of the Final Safety .f
Analysis Report (FSAR), and Safety Evaluation Report (SER). The i
-ability to achieve _the surveillance requirements of the Technical
Specifications was also examined. l
!
The objective of'the. inspection activities was to determine, by ;
selective sampling, if the above requirements and commitments were .j
translated into design, purchase, and installation documents; studies; _
and drawings and_into the installed hardware. The. inspection consisted j
of a' review of these-selected documents and visual inspection to '
verify that the installed hardware reflects the design commitments' 1
and is of acceptable quality. The specific documents, reviewed'during'
the electrical power systems inspection are listed in' Attachment VI.
.
1
The selected systems were as follow's: ]
. .
i
-
A niliary transformer 2B ,ource to.4KV bus 2D 4
o
Station Service transformer 20 source to 4KV bus 2D . i
Bus' tie between 4KV bus 2D to 4KV bus 20F [ Class 1E, Train B, l
purple] l
Emergency Diesel Cenerator 2-2 supply to 4KV bus 20F !
_4KV bus 20F supply to Charging Pump 2B [High head safety
injection (HHSI)]
4KV bus 20F supply to Low Head Safety Injection (LHSI) pump '
2B
4KV bus-20F supply to 4KV/480v Load Center Transformer 2-9P-
Load Center Transformer 2-9P 480V supply to Load Center l
2-9P
.
Load Center 2-9P 480V supply to Motor Control Center (MCC) ;
I 2-E06 :
480V MCC 2-E06. supply to Battery Charger 2-2 l
Battery Charger 2-2125VDC supply to 125VDC bus 2-2 l
Battery 2-2, 125VDC supply, to 125VOC Bus 2-2
125VDC Bus 2-2' supply to 125VDC Distribution Panel 2-2 l
125VOC Distribution Panel 2-2 supply to 120VAC Inverter 2-2
120VAC Inverter 2-2 supply.to 120VAC Vital Panel '
2-2A[ Channel 2 white]'
l
6.2 Inspection Criteria l
The "as-built" electrical power systems were inspected to verify
their ability to provide reliable power to the class 1E loads. The j
ability of the installed hardware to provide the proper magnitude and
quality of electrical power was evaluated. The electrical systems !
I:
.
.:
7.
'21
-
H _w ere examined to determine that the supplied voltage would not exceed
the high-and low design limits when the off-site source. voltages vary
plus or minus 5%. The electrical system design was. examine'd to verify-
that when-the low voltage-limit is. reached,'the class IE portion of
the 4KV. system would be separated from the preferred off-site. source
and supplied power from its respective on-site Emergency Standby
Diesel Generators; to verify that electrical distribution components .
.would be ' operated.within their steady state and transient voltage,
current and frequency design limits;.and to sustain a single failure
and'the ability of the unaffected redundant-. system to perform.its
safety function. This requires that physical separation be maintained
to preclude' electrical failures or external conditions,such as fire,
flooding, high energy missiles or high energy pipe ruptures from
~
causing common mode failures. The electrical protection features
were inspected for their ability to minimize system' disturbance ~for
' overload or faulted conditions.
The following attributes were inspected to ensure that the abov'e
criteria were satisfied and that the installed equipment has an
acceptable level of-quality:
Alpha numeric and color identification of electrical cables,
raceways and equipment as specified in the FSAR and installation
specification. 9'
!<
Location and configuration of the electrical raceways and
equipment as shown on drawings.
The. electrical raceway and equipment supports as specified on-
drawings and in procedures.
Electrical cable raceway routings as shown on the cable pull I
tickets.
Cable manufacture, insulation type, Jacket type and conductor
type and size as listed on the purchase specification and cable
pull ticket.
Cable terminations as specified on the termination tickets.
Physical damage to cables, raceways and equipment.
Installed electrical equipment maintenance as specified by
procedures.
Electrical equipment design name plate data as indicated in
purchase specifications.
Updating of electrical load flow, voltage fault current and
protection coordination studies to "As-Built" conditions as
identified on drawings, cable pull tickets, manufacture test
data, name plate data, and purchase specification vendors data. l
Agreement of electrical power systems with their purchased l
design limits. !
Protective relay setpoints as specified on setting sheets and l
relay coordination curves (verified by review of calibration
sheets and visual inspection).
'
4
=.:
-.
' i 22
.
..
'. . Acceptable battery capacity test .results for each class 1E battery.
Proper engineering disposition of Nonconformance and Disposition
Reports
6.3 Inspection Activities
For.the equipment and systems inspected, the'name plate design data-
was recorded for comparison with the purchase specification, test ,
results, one 'line diagrams, three line diagrams, inputs. to the load
' flow-voltage study and fault current study. Protective relay types &
setpoints were recorded for comparison with setpoint data and
coordination curves. A walkdown of the Train "B" Class-1E electrical
system from the 138KV and 22KV off-site power sources and the on-site
emergency diesel generator source to selected components covered the !
following:
-
. Cable bus from transformer 2B 'to 4KV bus 20 breaker 2D7
Cable bus from transformer 2D to 4KV bus 20 breaker 203
!
Cables.2NNSDNH305 & 306 from-4KV bus 2D breaker 2010 to
4KV bus 20F (Train B purple) breaker 2F7. .
Generator lead cables 2EGSBPH300 & 301 from the generator !
to the Excitation Panel.
Generator output cables 2EGSBPH302 & 303 from'the ;
Excitation Panel into the duct bank. (No further walkdown i
'
of these cables and raceways could be conducted because
they remained within the concealed duct bank untilithey
reached the 4KV bus 2DF breaker 2F10.) ;
Cable 2CHSBPH301 from 4KV bus 20F br!aker 2F12 to High Head j
'
Safety Injection (Charging Pump) CHS*P218. <
Cable 2SISBPH301 from 4KV bus 20F breaker 2F8 to Low Head
Safety Injection Pump 2 SIS *P218.
Cable 2ENSBPH301 from 4KV bus 20F breaker 2F11 to Load
Center Transformer TR*2-9P.1
Bus duct from TR*2-9P, 480 volt secondary to Load Center
,480VUS*2-9, input breaker 38. l
Cable 2EHSBPL210 from Load Center outgoing supply from
breaker SB to 480 volt Motor Control Center MCC*2-E06.
Cable 2VBA2P1001 from MCC*2-E06 starter 1C to to Battery
Charger BAT *CHG2-2.
- Cable, 2VBA2PL002 & 3, to a disconnect switch on 125VDC
j
~
transition bus. Also connected to this bus was the battery,
BAT *2-2, output breaker BAT *BKR2-2,
,
Cables 2VBB2PL600 & 601 from this breaker to battery BAT *2-2.
Cables 2VBB2PL602 & 603 from transition bus to 125VOC
switchboard DC*SWBD2-2.
<
Cable 2VBB2PL604 & 605 to uninterruptible Power Supply
Inverter UPS*VITBS2-2. The 125VDC input fuse and breaker
data for the inverter were recorded.
Cable 2VBS2WL507 from inverter manual by pass switch to
Junction Box 2JB-8857. The cable was spliced in the
junction box and continued as cable 2VBS2WL501 from the
switchgear train B(Purple) area in the service building to
panel, PNL*VITBS2-2A located in the control building.
t.
- c a
.. .
i
!
.
.J
'l
.:
23
.
1
6.4 ~ Findings
a. Transformer. Nameplate Data and Impedance Calculations
!
Station service transformers 2A and 28 and unit !
transformers 2C and 2D test impedance values were either,
partially omitted or shown incorrectly on the main one and
three-line diagrams. Also, the impedance values'for
transformer 2A and 20 name plates were given at a different:
MVA base than specified. Further, the test. impedance values
for transformers 2A and 2B were transposed in the station
service voltage and load analysis, E-68, and in the station
service fault analysis, E-74. The licensee issued an
Engineering & Design Coordination Report (E&DCR), number ,
2PS-4731, dated March 25, 1987 to correct the above drawing
deficiencies,
i
The voltage drop and short circuit study calculations (E-68 & !
E-74), which were completed after transformer test data was
received, utilized the transposed impedances. Following
identification by NRC the licensee used the correct impedan'ce
values in the computer model to evaluate the effects. The
computer run was.made using the corrected impedances for each. l
transformer and indicated that the worst case was a 0.5%.
increase in interrupting current and a worst case voltage drop
on the 4160 volt system of 0.3%. Neither of these current or ;
voltage changes would affect the adequacy of the design or
installed equipment. Although this error did not have any
effect upon the "As-Built" electrical system,.it is indicative
of lack of attention to drawing and calculation quality control. ;
This is another example of_ failure.to effectively implement the
requirements of 10 CFR, Appendix B, Criterion X.
-l
The inspector questioned if the serial numbers on the name I
plates of transformers TR 2A and 2R had been interposed. The ;
licensee contacted the manufacture (McGraw Edison) and were i
advised to compare the number on the load tap changer (LTC) i
switch compartment for verification. The comparison verified i
that the correct manufacture's nameplates are on the correct I
transformers. However, the licensee stated that new name plates i
would be obtained to reflect impedance on a 32 MVA bases to
agree with the purchase specification and test report.
'
'
b. Color Coding of Electrical Equipment
Title 10 of the Code of Federal Regulations part 50.55a i
Codes and Standards invokes IEEE Standard 279-1971. IEEE
-
,
x q
..y
-
24 j
.
Standard 279-1971 in paragraph 4.22 requires that identification j
n of electrical equipment and circuits be'provided. The standard I
states that this identification.shall distinguish between-
redundant portions of the protection system'during the design,. j
- construction, maintenance and operation of the plant.
The Beaver Valley Unit 2 Final Safety Analysis Report (FSAR) 'q
commits to follow IEEE-Standard 279-1971 and IEEE Standard- !
384-1974 " Criteria for Separation of Class 1E Equipment and. 1
Circuits". The standard IEEE 384 requires that all electrical'
systems and components be~ identified.to distinguish redundancy
down to the channel level. l
f
FSAR section 8.3.1.1.9 states in part that " Each piece of safety j
related electrical ' equipment. can be readily identified' by the !
aster.isk that forms part of the identification mark number.-This
- identification is physically attached to the equipment.in a.
conspicuous location along.with a color coded marker that
identifies the assigned emergency train or channel, This is
further addressed in section 8.3.1.3 for identification of j
cables, raceways and electrical equipment. The identification !
. . method as implemented during design, construction, and testing
operations will support the evaluation of system availability, !
goals during operations and the' performance of maintenance tasks."
During an inspection from September 29 to October 3, 1986 the j
licensee was informed that the electrical equipment had not been 1
identified by color as committed.to in the FSAR. The' licensee
stated that the. methods used for identification at unit 1 would ;
be applied to unit 2. j
On. March 18, 1987 the inspector observed that the following j
types of safety related electrical equipment had'not been '
identified by' color as committed-to in the FSAR: !
!
4,160 volt switchgear
480 volt unit substations
480 volt motor control centers .
125' volt DC batteries !
125 volt DC battery chargers l
125 volt DC battery distribution panels
120 volt AC Inverters 4
-
120 volt AC vital bus distribution panels j
Failure to identify by color the above listed electrical equip- )
ment.is a deviation.
'
(412/87-20-02)
The licensee took prompt corrective action to place the
respective train or channel color designation next to the
equipment name plates. Therefore, written reply to the ,
deviation is not required. {
i
-
,
,
1..
. ..
'
. -
. 25.
...
I
c. Discrepancy Between Vendor and Licensee Battery Test Report ;
!
.The inspector reviewed the Battery 2-2 vendor's (Exide) capacity.- t
test which was conducted to demonstrate conformance.to the j
licensee's specification.;The inspector also reviewed the i
licensee's Battery 2-2 Discharge Test Procedure which was used: 1
to conduct the acceptance test. The inspector noted that the 4
vendors.100% measured capacity time.had been increased'15.5% as !
determined by the licensee's test. The reasons for the !
difference in measured times are as follows: I
The' vendor's test was conducted per.IEEE Standard ')
450-1974 i
~The licensee's. test was conducted per IEEE Standard I
450-1980
The vendor terminated the test with a average cell. l
1 voltage of 1.8558, which corresponds to 111.35 volts for j
the battery. !
The licensee terminated the test when the battery .
j
voltage reached 110 volts, which is an average of 1.84
'
volts per cell.
~ No deficiencies were identified,
d. Emergency Diesel Generator Nameplate Ratings
The inspector noted that the emergency' diesel generator had a. i
name plate rating of 4662 KW for both the 160 hour0.00185 days <br />0.0444 hours <br />2.645503e-4 weeks <br />6.088e-5 months <br /> and the 2 of
l
24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> ratings. The FSAR lists the 160 hour0.00185 days <br />0.0444 hours <br />2.645503e-4 weeks <br />6.088e-5 months <br /> rating but not the 1
2 of 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> rating. The vendor (Colt Industries) stated that I
both ratings.are correct. DEMA standards call for the 2'of 24 ]
hour rating to be 110 % of the continuous 4,238 KW rating, which !
is 4662 KW .The 160 hour0.00185 days <br />0.0444 hours <br />2.645503e-4 weeks <br />6.088e-5 months <br /> rating is also 110% of the continuous j
rating. The vendor recommends that a major overhaul inspection 1
be performed if the unit is operated for 160-hours continuous '
at 110% or for 2 hours2.314815e-5 days <br />5.555556e-4 hours <br />3.306878e-6 weeks <br />7.61e-7 months <br /> out of 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> for 80 times in succession
at 110%. Neither the 160 hour0.00185 days <br />0.0444 hours <br />2.645503e-4 weeks <br />6.088e-5 months <br /> nor the 2 of 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> rating are
limiting because the worst case emergency diesel loading listed
in the FSAR is 3725 KW and the Technical Specification surveillance
requirements limit the auto connected loads-to not exceed the I
2000 hour0.0231 days <br />0.556 hours <br />0.00331 weeks <br />7.61e-4 months <br /> rating of 4535 KW The inspector had no further concern.
No deficiencies were identified
l
i
!
]
-..
.
..
26
-
6.5 Conclusions ,
The inspector found that the state of workmanship of the electrical I
systems inspected conformed to the criteria of paragraph 6.2 with the
exceptions noted in findings 6.4 a and b.
!
!
-
1
.,
g-
.
1
!
' '
27 !
t
l
7.0 Instrumentation and Cont'rol 1
!
7.1 Scope' ,
.
The' inspection of~the. Instrument and Control (I&C) systems
consisted of. a walkdown'.exumination of impulse lines,- .
!
instruments,: instrument cables, control panels, instrument racks,
control cables and control functions. 'I&C systems associated
with the reactor coolant system (loop 3), high head. safety
_
injection' system (pump C), low head safety injection system (pump.
.8), control room HVAC system,. control building HVAC and the
- diesel generator building HVAC were inspected.
.The'SWEC design' specifications, procedures and drawings were ,
~
,
reviewed to assure that FSAR and SER licensing commitments had
. been properly translated into the design.- Quality control
-
documentation was reviewed for selected components. Attachment ~VIII'
-lists the drawings and documents used.~during the I&C inspections.
7.2. ' Inspection Criteria
Theas-built'walkdown'of the'I&C systems examined'the installed
commodities with respect to the following attributes which were
' derived.from the FSAR and SWEC design documents:
Impulse Line and Support Inspection Attributes
-
tubing and fitting cleanlin'ess-
'
-tubing and component identification
minimum bend.'and slope requirements
. tubing integrity
. tubing restraints and anchors properly. located
redundant channels properly separated
seismic clearances maintained
support configuration, dimensions and welding. quality
acceptable
~
Instrument and Control Cables and Terminations
l
cables properly identified
cable integrity
-
conductors properly located and terminated
redundant cables properly separated ;
cable routing in accordance with design criteria
i
i
L
- .:
a '.
a.. '
28:
<1
..,
j
Controls Inspection Attributes l
redundant components. properly identified.
functional requirements for controls achieved
7.3 Inspection Activities
- Instrument Impulse Lines
The instrument impulse lines listed below were. visually examined. l
The. location and' identification of components and root valves were ').
. , . verified. Tubing slope, configuration and integrity..were examined !
from the root valve to the associated instrument. Tubing supports l
were. inspected for location, configuration, member size, weld quality !
,
and weld size.
Impulse line RK*305AB was visually inspected from the high head- .
safety injection line 2CHS-750-270-2 to pressure indicator !
l
' Impulse line RK-305AA was visually examined from the high head j
safety injection line 2CHS-750-481-2 to the pressure indicator ;
<
2CHS-PI153A. !
Impulse'line.RK-326N was visually examined from.the reactor- l
coolant system' piping to flow transmitter 2RCS*FT43A. i
Impulse line RK-3260 was examined from the reactor coolant
. system piping to pressure transmitter 2RCS*PT402.
'
Impulse line RK-332F was examined from the low head safety
-
injection system piping to flow indicating ' switch 2 SIS *FIS970A.
Impulse line RK-332G was examined from the low head' safety
injection system piping to flow indicating switch 2 SIS *FIS9078
.
Instrument Cables
The instrument and control cables and terminations listed below were
visually examined.
?
I
!
1
l
1
,
,.
..'
l
0 29
4
r
Cables 2HVCBBC001 and 2HVCBYC001 for the control room _ 1
HVAC: chlorine detectors were examined in the' reactor ;
protection rack RK*2RC-PRT-B.
Terminations.for cables 2RCSIRX025, 2RCSIRX007, and
~
2RCSIRX013 associated with reactor coolant system flow,
pressure and temperature transmitters were examined in 1
rack RK*2PRI-PROC 1. .l
- -
1
Terminations for cables 2RCS2WX011 and 2RCS2WX025
associated with reactor coolant system temperature and .,
- pressure transmitters were examined-in rack l
RK*2PRI-PROC-1.
Termination of cable 2 SIS 3BX004 for safety injection
. system flow transmitter 2 SIS *FT-940 was examined in
rack RK*2PRI-PROC 3, #
-
- Terminations for cables 2FWS3BX002, 2RCSIRX026,
2RCS3BX018,-2RCS2WX026 and'2CCPWPX006 were examined at
the following instrument connections: 2 FWS * LT497,
'2RCS*FT434, 2RCS*FT436, 2RCS*PT402 and 2CCP*FT107C
respectively.
Cable 2RCSIXR014 at reactor coolant system temperature
element 2RCS*TE433'was examined.
Cable terminations 2HVDARX002 and 2HV0BWX002 at diesel
generator HVAC temperature elements'2HVD*TE21A and B'
respectively.
Cable 2RMS10X005, 2RMS10X006, 2RMSINC005, 2RMSINX003,
2RMSINK500 and 2RMSINX006 terminations at the radiation
monitoring system panel 2RMC-RQI301.
Cables and terminations for 2SISAOC053 and 2SISAOC054
from the safety injection system flow switch
2 SIS *FIS970A to junction box 2JB*1023 and to the
Limitorque operator for valve 2 SIS *MOV8890A.
Cables and terminations for 2SISBPC053 and 2SISBPC054 I
,.
l1 from the safety injection system flow switch
i 2 SIS *FIS9708 to junction box 2JB*1024 and to the
Limitorque operator for valve 2 SIS *MOV88908.
Cables 2HVCAOC089 and 2HVCBPC091 terminated at control !
room HVAC temperature switches 2HVC*TS151A and B
respectively, i
!
l
L
.: .
,
w
30 >
.
i1
-' Cables and terminations' associate'd with reactor' coolant
. system instrumentation at.the inboard and outboard
sides of the containment. penetration 2RCP*20D.
The cables were verified for proper! termination' point-at the
pane.1 or instrument. ' Cable _ lugs-and crimping, cable ~ separation, ,
training and bend radii were also examined.
'
The cables and.~ .l
terminations were examined'for co'nsistency with SWEC and vendor! l
' wiring diagrams.
Instrument Components-
The following.' instruments and components were examined:
.
Instrument transmitter rack 2CES*RAK1300 and the. i
associated reactor coolant system instruments and 1
,
tubing were examined.
Pressure indicators and supports for 2CHS-PI153A/B on
the high head safety injection system '
Reactor coolant system flow transmitter 2RCS*FT434'
Reactor coolant pressure transmitter:2RCS*PT402 l
i
Low head safety injection system flow switches
2 SIS *FIS970A/B and associated supports .j
i
Diesel generator HVAC temperature elements 2HVD*TE21A/B - j
-
Battery room HVAC flow switches 2HVZ-FS217 and i
'2HVZ-FS204- !
1
Control _ room HVAC temperature elements-2HVC*TE24A/B,
differential pressure transmitters 2HVC*PDS201A/B,
radiation monitoring device 2RMC*RQI301, isokenetic
velocity probe 2RMC*RN301, chlorine detectors.
2HVC*AIT21A/B/C and temperature.. switches 2HVC*TS151A/B
Reactor coolant system temperature element 2RCS*TE433 :
hi Chemical and volume control system flow transmitter.
2CHS*FT122
l
Safety injection system flow transmitter 2 SIS *FT940
~
i
l
7.4' Findings l
The inspectors had the.following findings:
i
_______________J
p
.1
.
.
31
.
a. The vertical welds on a mounting bracket for instrument
2RCS*LIS1321 were found 31/2 inches long in lieu of the
drawing requirement of 4 inches. The inspector informed
the licensee of this condition and the licensee issued i
Nonconformance aad Disposition Report 34729. The nonconformance. !
report dispositioned the condition " accept-as-is". The licensee 1
stated that the associated drawings and calculations will be
revised to incorporate the actual weld length. Quality Control i
did not detect that engineering requirements were not fully i
! satisfied. This is another. example of the failure to satisfy
the requirements of 10.CFR, Appendix B, Criterion X.
b. A Girard tubing clamp was found improperly installed on anchor
2RCS-TSA134A. One half of the clamp was rotated 90 such that
the radius of the clamping surface did not not match that of :
the tubing. The licensee was informed of the condition and
took corrective action. Startup Work Request 13931 documents >
the satisfactory reinstallation and inspection of this clamp.
This is a QC deficiency as bolted hardware and tubing clamps are j
required by procedure to be inspected for proper assembly and 1
torque. This was an isolated example of an improperly installed
clamp. However, it is another incidence-of failure of Quality
Control to identify a nonconforming condition and is another
example of the failure to satisfy the requirements of 10 CFR,
Appendix B, Criterion X. j
c, The inspectors identified a loose flex conduit connection to a
limit switch on valve 2CHS-MOV8133B. The licensee was notified l
of this condition and the conduit was tightened in accordance ,
with Startup Work Request 12789. The procedure requires that Quality '
Control verify proper assembly of flexible conduit. Failure !
of QC to identify this nonconforming condition is another example. l
of the failure to satisfy the requirements of 10 CFR, Appendix
B, Criterion X.
b
'
d. The inspectors identified a loose ultraseal tubing coupling near
valve 2FWS*303. The licensee was informed of the condition and
Startup Work Request 13689 was issued and the coupling was
tightened. The procedure requires that QC verify that couplings
l are installed hand tight. Failure of QC to identify the loose
coupling is another example of not implementing the requirements
of 10 CFR, Appendix B, Criterion X.
I
f
,
!
l
f
W>m
^$ 6i
M '
{d .32
m
4
h .' w
W
& '
e. -The inspector identified an oil leak near the high head safety
% injection oil pump 2CHS-P21C. The licensee issued Startup Work
y Request 12263 to. replace the outboard bearing housing covee
X gasket. The inspector reviewed post maintenance test and
quality control records from a' prior. gasket replacement on this-
pump.. The pump, appears;to have operated satisfactorily.immediately
after the first gasket replacement. Operator walkdownstof the.
. pump compartment had not yet identified the oil leak at the time
it was found by the NRC inspector.
f. .The inspectors observed that flex hose on tubing isometric
'
-RK-305Slwas not' properly installed in that the antitorque arrows
were. misaligned. :The licensee issued.a Construction Deficiency.
Report as a' result of this observation to rework the installation.
..The installation procedure requires that QC verify alignment.of
- the antitorque markings on the flexible hose after installation.
' Failure of QC to identify this non-conforming condition is another
L
"
example of the failure to effectively implement the requirements
of 10 CFR,. Appendix B, Criterion.
lg. While examining instrumentation equipment in the safeguards
.- building, the inspector identified an anchor bolt for auxiliary ,
feed pump 2FWE*P22 installed beyond the specified allowable l
angular offset from perpendicular to the skid. ~The licensee
. issued Nonconformance and Disposition Report 34611 to add a
beveled washer under'the anchor bolt nut. ' Failure of QC to-
' identify'this nonconforming condition is another example of the ;
-failure to effectively implement the requirements of 10 CFR, i
Appendix B, Criterion X. i
h. Melted polyethylene fire retardant material and black adhesive
- tape;were found on stainless steel piping located near the root "
The inspector was informed
~
valve for instrument 2RCS*PT402.
that the examination of the exposed stainless steel piping in
accordance with specification 2BVS-901 had not yet been performed.
The licensee's Assistant Director for QC indicated that a
nonconformance and disposition report had been generated to l
clean the surface of the piping.
1. The impulse line to flow transmitter 2 SIS *FT940 was observed to
be 1/8-inch from the inside of wall sleeve S-6201. Nonconformance
and Disposition Report 35360 issued.during the team inspection
dispositioned the installation accept-as-is based upon the lack
of seismic differentia 1' movement between the tubing and the wall
sleeve. The licensee indicated that a previous specification i
requirement for a minimum gap of 1/2 inch between the tubing i
runs and the sleeve interior had not been completely backfitted. l
The licensee committed to investigate all tubing through sleeve
installations that had been accepted prior to the specification
change.
,
c
J
1
.. 1
'O '
,
rpr
p
Y o 33 l
-
1
l
F i
. I
s
J3 Conclusions <t ,.
.q '
,
The'qualiCy of the. installed system hardware was found generally J'
i
'N , acceptable and in accordance with licensing commitments and
,
design requirements. . However, several minor examples were found
*
where the as built'phnt deviated from the design specifications.
'r (Findings 7.4 a, b, c, d, f, and g). Two loose connections, one
involving flexible conduit and the second involving a loose tubing
. connection, were identified. While the associated QC inspection
g '
. , i it. tributes explicitly addressed the need to verify tight connections, ;
yp~
ii
the possibi)ity exists that unauthorized rework was performed and -i
reto(ted in the loose connections. The examples of an under length
ki ' i '; y
.seld; ,(mproperly installed tubing clamp, misaligned flexible hose,
t- s
anchor tsolt excessjve angularity, and lack of separation between a ,
. ly
@ !
/J / 8' '
addreslsedb./qQCfuspectionattributesandshouldhavebeendetectedtubin9
,, <- during performance of the QC inspection. The identified deficiencies
,
'
'
i are not signfficant concerns since they would not have resulted in
- p f '? adverse. consequences on operational plant safety. However, these j
~
'
,f .
it. ems jndicate that QC personnel should give more attention to detail '
(,',during'cbnductofinspections.
'
', ,
l
",]
'
?.s '
9 'l
N' . i ?i 'i
o
e
l
[, !
.
68 f
k
w. .'
C
4
-
L .
,, p ,,
?
)
'
M: ..
,
,
.
. 1
,y ;a.^ '
i
s.
[i i
f '34 ,
q[ -
]
.j
L8.0 . Structures ~
]
i8.1' Scope of Inspection.:
' Inspection in'thisL area focused on licensee' activities regarding 'the
-. evaluation ofj Category -I structural systems for' fin'al as-built loads
from mechanical and, electrical components.in; addition to.other design
x loads. The inspection objective was to verify, through sampling.
review and examination,-that fina1' structural attachment loads were
etracked and evaluated foritheir effect on.. structural components'
allowable stresses and loads.
>>
To achieve this objective,-the inspection focused:on:
'
Review of the structural' calculation confirmation program,
' '
-
Performance of walkdown ~ inspections of selected areas for.
identification of attachments to the bui.1 ding structure, and
,
> Review'of structural design packages performed for the
evaluation of final. attachment loads on structural elements.from
the areas selected above.
8.2., Inspection Criteria
The ' criteria used for the- evaluation of licensee activities in this
area were:
.
10.CFR 50
Fina1L Safety Analysis Report (FSAR)
<
'
.. Safety Evaluation Report'(SER)- .l'
- '
.
Standard Review P.lan (SRP)
-
.
AISC Steel Construction Manual, Seventh Edition -
8.3 Building Loads Verification Program
i
The verification.of building loads was conducted under the struc- '
tural~ calculation confirmation program (Procedure 2BVM-168). The
program was established by SWEC and consisted of the following
activities:
1
Maintenance and review of existing calculations, I
i
Identification of need for new/ revised calculations,
l
Generation of new/ revised calculations, and i
Close-out of calculation confirmation.
!
+ ,
g
o
'
i
a
'
&
u
..;
35 l
.
The need'for-new/rev'ised' calculations was intended to ensure that
major structural ~. elements (slabs, walls,' columns, beams, etc.)~were
either specifically evaluated for final loads .orfqualified by com-
parison to other structural elements'. Specific activities performed
during the confirmation effort . included:
'
' Confirmation ,of. concrete ; structures for support loads
,
Qualification'of equipment anchorages, and
Confirmation of support' loads on structural steel.
For.each of.the above activities, the procedure addressed the !
general requirements for selection of structural elements or i
components-to be reviewed, data collection, and the method for '
- performing the confirmation calculation. .The major features of the i
confirmation program with regard to'the above activities are
presented below.
.
Concrete Structures ,
'!
The original design of various Category I concrete structures
included a. live load allowance to account for anticipated system
support' attachment loads. 'Four heavily loaded concrete slabs in.the
fuel, control-and auxiliary buildings and the main steam cable vault.
were selected for evaluation by the inspector. SWEC indicated that a
100"4 walkdown was performed in the selected areas to account'for
attachments from conduits (larger than 1".0.D.), cable trays, HVAC
duct.and pipe supports. Supports from major piping systems, rupture
restraints'and equipment supports were not included in_the walkdown
since they were explicitly accounted for in the original design.
'The procedure required the evaluation of all out-of plane support
-
attachment design loads, forces and movements. The individual dead
weight contributions from attachments were summed and converted to an
equivalent' uniform dead weight. Variable loads from system attachments
were summed using the square root of the sum of the squares technique,
and converted to an equivalent uniform variable load.
'
SWEC indicated that results of the evaluation had confirmed the-
adequacy of the original design of concrete slabs for the selected
areas. The scope of structural confirmation for concrete slabs was
not expanded based on results of evaluation from the selected areas.
, The qualification of embedded plates was also required as part of the
concrete structures confirmation effort. The evaluation was based on !
a load file which included plate number, locations, types, applied '
loads from attachments, and source of load by support drawing numbers.
Embedded plates were identified by plate number or structural drawings
RC-800 series, and by location on drawings RC-700 series. The method
for qualification of embedded plates was provided in procedure BVM-153. i
e
i
!
l
- - _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ -
b
e...
a;
>
j t
'l
r.. >
36 !
.
g
l
The approach was based on three levels of analysis. The firs.t was l
based on a screening ~ approach of applied attachments' load ve'ctors
'against allowable load vectors. Embedded plates which' failed the:
screening test required an evaluation using:two interaction. equations
for out-of plane and in plane forces and moments, respectively. Plates
which failed.'the second level of analysis,. required more detailed-
calculations using an in-house computer code APE (Approximate Plate'
Evaluation) developed by SWEC or a more refined finite element i
l- analysis using the in-house computer code BAP. l
Equipment Anchorage
E
>
Activities related to the confirmation of equipment -Tnchorage
, ' included the evaluation of anchor bolts and embedded plates using
!
design loads generated from the equipment seismic qualification
~(2BVM-176). The qualification was required for Category I and
,
non-category I equipment identified by procedure 2BVM-165 :" Hazard
Analysis Program".
f.
li Structural Steel
lJ ^ '
' The original sizing of structural steel members was ' based on the
.
l
'
addition of concentrated loads (5,10, 20 & 50 kips) to account for
anticipated attachment loads on beams, girders, columns, etc. The '
initial phase of evaluation was based on site walkdowns by SWEC. 1
Twenty-four. heavily loaded areas were selected for this purpose. A' l
tracking System of all large bore (L/B) pipe, duct and. cable tray. j
support loads was started'in 1983. The tracking system was merged in
1985 with the Pipe Hanger Information System (PHIS) developed by the
' Engineering Mechanics Division (EMD).
-
The PHIS covered attachments
.from pipe hangers and duct supports (87-Drawings). 'As a result ~of
'
. required structural modifications based on the above evaluation, a
second phase review.was. initiated to address all' safety related ,
structural steel elements in category I 2 areas. This review included
'the remaining areas which were not covered in the first phase.
Procedure 2BVM-160 provided details of the tracking system, the
method for performing the evaluation of local effects from attach-
ments to structural steel and standard stiffner selection table for
W-shapes. The evaluation for local effects was based on
original piping support loads or reconciled loads when they exceeded
the design values. Identification of field-run attachments to
structural steel was addressed in procedure 2BVM-184.
SWEC indicated that approximately thirty-five (35) modifications were
required in the annulus racks area (between the crane wail and the
containment) and three (3) modifications in the auxiliary building
roof as a result of the first phase evaluation. However, no
modifications were required as a result of.the second review.
- _ _ _ _ _ _ _ _ - _ _ - _ _ _ - _ _ _ _ _ _ _ - _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ - _ _ - _ _ - _ - _ _ _ - _ _ _ _ _ - _ _ _ _ _ - _ - -
g ,
-)
, _
g'h[3) '
}
).- 7 ,
g
, i
k
'
[.*
1
37-
, .j
- l3
'
8.4 Inspection Activities. I
J
' Inspection of. licensee activities in this area consisted of:
,
'(1) visual walkdown examination of selected safety related areas for-
identification'of-type'and density of attachments to structural
]
l
steel; and (2) review of sample evaluation packages'of structural j
concrete steel elements to assess their conformance to establish .
procedure guidance. !
4
The listing below identifies the areas examined during the walkdown-
and the structural elements selected for further review:
I
.
Reactor. Bldg.'EL.- 756'-0", annulus area: Beam No. 7 (W 18/60) *
-
between column lines 10 & 11 (Owg. No. RS-853-A)
Reactor Bldg..EL. 767'-10", annulus area: Beam No. 117;(W 24/68)
~
.
E
between column lines 9 & 10 (Dwg. No RS-850-A) l
Reactor. Bldg. EL. 740'-3", cubicle "C" platform between columns j
3,,4 &~5 (DWG, No. RS-850-E).
"
NOTE: Qualification was performed for the platform
'
in cubicle "A". Platforms in cubicles "B" & "C'! I
were qualified based on similarity of steel layout- l
and general loading in the area. Calculations.for-
'
i
beams Nos. 33 arid' 42 in cubicle. "A"Jwere examined.
Reactor Bldg. EL.' 7178-0", annulus area: Radial Beams
No. 146 & 184 on column lines 10 & 13. Major loads on these
beams are from racks No. 27 & 35.
- o Reactor Bldg. annulus rack-No. 5~and lateral trusses at
elevations 701' - 11" and 710'-2" (Bet. Column lines 1&4).
Reactor annulus Column No. 15.
Auxiliary Bldg. roof beams No. 81 & 109 (DWG. No. RS 836-A)
Control Bldg. concrete slab (28'-0" x 20'-9") at El. 725'-6":
42'-6" east of column line No. 12 and 27'-3" south of column
-line No. C.
!
l
!
l
l
j
1
i
.
]
1
.. .
38 i
. l
-
8.5 Findings and Conclusions )
1
<
Based on the NRC review of the licensee program and examination of i
activities in the area of building verification, it was concluded ;
that the program adequately accomplished the objectives-in this area. ,
The program was also found to provide adequate guidelines regarding q
the performance of the confirmation effort. Documentation of i
evaluation for selected areas was consistent with established, j
required and typical design practice. In general, the activity was i
found to meet the intent of the regulations and no violations were
identified. i
1
4
$
4
l
!
I
i
l
!
l
l
4
.
.
I
l
1
)
I
!
1
I,
l
-
'
l
,_
}
- '
39
l .: 'i
i
9.0 Followup on Outstanding NRC. Bulletins- i
.9.1 (Closed) IE BulleEin 79-14-
Bulletin 79-14. addressed the requirements for seismic analysis of- I
as-built safety related piping systems. The criteria for. performing .!
'
the seismic analysis of Beaver Valley Unit'2 safety related piping
systems.was addressed in the FSAR and was reviewed and found acceptable
by.the NRC in the Safety Evaluation Report. The program for piping. !
as-built'and stress reconcillation was~ reviewed in Section 4.0 of. !
'
.this report and found acceptable. Walkdown inspection of piping and. i
, support installations for two systems (Reactor Coolant and Safety - 1
Injection) during this inspection confirmed that as-built records
reasonably depict the actual 1 installation configurations within
acceptable tolerances. Based on the above conclusions, the licensee's.
activities in this regard are considered sufficient to close this -l
7 bulletin.
9.2 -(Closed) IE Bulletin 79-07
Bulletin 79-07 addressed significant discrepancies identified in l
some piping stress analysis computer codes regarding 'the' summation
of codirectional spectral components and intermodal responses'during' ;
the performance of seismic response spectrum' analysis. The bulletin q
required that all piping' computer programs be checked against either i
piping benchmark problems or compared to other piping computer
programs.
-l
The' licensee response letter of May 16, 1979.to the.NRC indicated i
that none of the computer c" des.used by U7C for piping stress
analysis at Beaver-Valley, Unit No. 2 were-identified to have the i
summation. discrepancies noted above. -The response further indicated
that the computer codes NUPIPE 03/01 through 03/10 were used in the
piping seismic analysis. Verification of the computer code (NUPIPE !
03/10) was addressed'in response to the April 2. addendum to the !
March _13, 1979 order to show cause for Beaver Valley Unit No. 1.
.SWEC confirmed that in-house benchmarking linked all major versions
of NUPIPE to version 03/10. In addition, the verification of NUPIPE
against other NRC piping benchmark problems was found to be
acceptable (NRC letter from L. Shao to W. White (SWEC) on l
December- 18,1979). Based on the licensee response and the NRC con-
firmatory evaluation, I.E. Bulletin is closed.
l
i
n
i
l
. l
'*
40
.
10,0 Exit Meeting
The Inspectors met with licensee representatives on March 26, 1987 and
presented the findings of the inspection. The licensee did not identify .
l
any proprietary information contained within the scope of the inspection. 1
i
'
.j
i
!
i
l
!
l
l
.
l
J
,-
.-
.
i
.- q
-
0
'
ATTACHMENT I: LIST OF PERSONS CONTACTED
Duquesne Light
C. E. Ewing, Manager Quality Assurance
D. K. Rohm, Assistant Director Quality Control
R. J. Swiderski, Manager
T. P. Noonan, Superintendent Operations & Maintenance
W. Reimer, Supervising Engineer
J. P. Godlecki, Sr. Test Engineer
L. M. Rabenau, Lead Compliance Engineer ,
S. A. Loehlein, Sr. Test Engineer '
O. L. Claridge, Compliance Engineer
S. C. Fienner, Director Quality Control
C. P. Williams, Director Start-up
J. R. Kanynick, Director Maintenance
R. P. Harris, Materials Engineer
Stone & Webster
R. C. Wittschen, Licensing Engineer
N. F. Kokot, FA Engineer
G. M. Byrnes, Asst. Project Engineer
A. P11zga, Lead Structural Engineer
A. Wong, Principal Structural Engineer
P. Talbot, Asst. Superintendent Engineering
P. Castrichini, Principal Engineer
Nuclear Regulatory Commission
J. Strosnider, Section Chief - Materials & Processes
E. Gray, Lead Reactor Engineer
F. Paulitz, Reactor Engineer
K. Manoly, Lead Reactor Engineer
H. Kaplan, Lead Reactor Engineer
R. Gramm, Sr. Resident Inspector
R. Winters, Reactor Engineer
A. Asars, Resident Inspector
J. Beall, Senior Resident Inspector
l
L. Prividy, Resident Inspector
l
l
l
}
)
. - _ _ _ _ _ - _ - _ _ _ _ - _ _ _ _ _ _ _ - _ . _ _ _ _ _ _ - _
J)!lifjlJi11!ll j2IIi jl ,jlI
~ <
' 1
"
k
-
- y
f _
-
,
_ _
2
.
_
1 v ._
e-
11111431113541 .R
-
v-
. ' . . . - . . . . . e7
vvvvv..vvv..vvR0
S
eeeeevveeevvee
RRRRReeRRReeRR6-
1
__
_
T - RR- - RR- - 83
R 29534- 340- 5730
O 56139569957855 3
P - - - - - - - - - - - - - - B-
P AAAAAAAAAAAAAA70
U 1111111111111101
S 8888888888888811 _
_
s -
m
,
e
_ d t 1212121242 3312I1212142 33434344 -
-
N s 1 11 1
0 y ... . . . . 3 :. . . . .0 . . . . . . 1 1111 1 -
vvv.vvvv.v0vvvvvv vvvv.1 1 v.vvvvvvv ...
.
1
S . .
~
T
C n
eeeveeeeve0eeeeee7eeeev.vv'.eeeeeeee.3
RRReRRRReR RRRRRR0RRRReveevRRRRRRRRv'.vvvvevv.
. . . .
.
_
_ E o - - - R- - - - R1 - - - 1 - - - ReRRe eveeeeRe
-
P i S 841 1133 20890019 8065 R- R04239213ReRRRR R
S t T 29121080441100109878337 45 33442333 - R- - - - 0-
N c R 0238320212 2212107509082497000000004 419214
I
e O 1 5- 1 - - - 4009- 59396911 _
i P AA8ABAAA 35AAAAAA BAAAA- AAAAAAAA- - - - - - - -
G n- P 77787888A12788888078777AAAA77777777AAAAAAAA
N I U 0000000033000000010000011110000000011111111 .
I
S 1111111188111111111111188881111111188888888
P y
I t
,
P e
f
G a
N S
_
I
_
_ R S
-
_
U G GF - E D D
D N G- EH P F HF
I
SHDEKD HK . . 5 .G . .F.G F E J
v .8 .v.. v.....
_
D W 44vv.. . FN
E A .- . . . . . .v eevv v . ev vevv evvvvv
_ S R
D
.vvvvv vve..RRee e..vRe.eRee - Reeeee _
-
U veeeee eeRvv RR Rvve RvR RR RRRRR _
eRRRRR RR eeCC- - eeRC e C- - C- - - - -
S O R- - - - - - - CRRAACC CRR AARCAOCCACCCCC
G S CCCCCCCCA* GFAA A- - CEC ADAAADAAAAA _
N I
CAAAAAAAAKCC22EH PJRA3GCF1HGM0FJJEM
I
AJFFFDRKL3AA- - 0O 101G 0A3 244 23314 _
W R G212O0OOO 4417- - - - - - 3 9 5- - - 4- - - - -
A E - - - - - - 8- 2278 271829 72601226418
R D G 7120051109231111 090712501210110010 _
_ D I
N 7333593317007788 333178517711711111
_
E I
199933333 33- - - - - - - - - 2- - - - - -
_
_ C N P 0999888880000000 888000080088088888
I
H I
1000000001111111 000111101111100000
R C P 1111111111111111 111111111111111111
T S
E
M
O
S
I
_
I
I
_
7
N _
E -
M
H
C
A 2
_
-
T 11
T 555572 .
A . . v
vvvvv.vve
.....
eeeeevRR-
eeR
S RRRRRe 4 _
m T - - R077
e R 23456 323
t O 11111611 -
s P - - - - - A
y P AAAAAAAA7 _
S U 999990000
S 999997771
t
n _
a
lo
o
C
r 5
o 157686
t
c ...... _
a vvvvvv
e eeeeee
R RRRRRR
- - - -
254188
G 133323 _
N 922222
I
- - - - _
P 000000
I 111111
P 111111
-
li lil('llll1li!lIlllIIlil(llll11lllll\ lt lL
I'
l1I)Iii'
-
i
-
-
-
-
, -
.
_
,
-
-
_
_
_
_
_
D _
E _
.
W
E
_
_
I
V
E
R -
.
S _
_
T
R
.
.
O m
P _
E ._
-
-
R
_
.
E
C
N
A
M
R
O
F
N
O
C
N A
O 15219488338930 4 3
N 2953689213663361225 _
8803230390820039309
D 9994549434355534519
E 2223332333333368371
T
A
.
.
_
L .
E
R
G
_ N
I
P
-
- I
_ P -
-
l
i
l
T .
N
E
M
H
C
A
T
T
A
.
lll!l!l!I(li!lll!!ll!! !IlI1 I ! I b
lili' ;il! ' il
.
,
I
. -
3
$
,
n -
o
g ni s
s
e
r
Ii
n
p
t
s
n
iotrm aoe e
I .t tlft r4
d
u fIi
o P
nii
ol
Jo 1.4
al
casy
s
u.
d
e
87 eev
E teS
c
o
gM1
nS
6. - itE
cMd1/
28 irss
bnsg08 soR6
nce
P
r iAs2.
d s7/
84 eSe.9
pat 71 F
aI en2/ er 8
ci 7 uP5/
5a 2 s l
/ dopP1 q - 6
leClP/ nfoP1 fnriC/ uAC/
WRCI2 I OBI 1 oaPPF3 DQD1
-
-
4 -
3 -
s 0
t -
r S -
o
p
M -
E
e M -
R - -
R
-
-
-
I
D -
E
W
E
.
-
l - 8 d
I
a 2 o
V i
r
5 R
E 0 -
R e 80 8 -
ts 0 05
N aT 3t 35
MR - K - 5
C y y1
T R ae a0
A C Kr K -
T H ci cf
N
E
M MW MH
M
U
C
O
D g e
l
n g
r
G a S i
t0
N i
G p o h3
I r L6 i A F 6 g0
D e I1 P 8 y1 i1
L ts C33 F7 pd37 r-
E aT F7 y C8 ooF4 WR
W MR - - 4' k
s
8 rB 0 T
C - 21 17 D 22 sC
E e n8G u 54 e87 i-
P s o17 d 31 kv1# te
I
a y- - n rl - rp .
P B uAf a Af aaAf ui
GSH S SH PVSH CP
V
I
s
T
N .no 3
1 5
E i 10 4
M rt F5 1
H ea - 00F
C dc nF6-
A li
o2n
T ef tri
T
A
Wi l
reaw
enbd
a wzul
-
u oiha
- Q HMCB
s 9 g
sn n
eo . 5 i
ri v rp
ut e 5 . ei
da R v dP
ec 238 .e i
ci
of
G383
O572
vR
e
er
ne
ri O006 R1 4 hw
Pl 3667 0 0 co
a - 777 A8 A8 SP
du V- - - 1 - 1 -
lQ )BRRR )0R )2R ))
e 1PQQQ 20Q 20Q 12
W& (S1PP (8P (8P ((
101
s t200F
t FF55-
e - - F4
de 99F 9
lh 000Z0
eS 006N-
W
a
- - - - 5
SSSS1
WW
// /
W
t CCCCS BB B
a RRRR- - - -
D 22222 AB C
ll1jll(!llll( tli(ll\l(llll1 l lllII l lllllll!
_.
.
.
.
G
N
I , -
P S-
I T- G
'. R N
2 0 O I
1 2 2 F P P
4 - O P I
- 7 U' P
0 8 N S
5 O I
I E _
F T S P Y _
O C T I R .
_
E R P O _
R O G G
E P , N E
P SS I
T
D U ST P A
. . 1 N S ER I
C _
O O A RO P _
N N E TP C
T T
N P SP F
O U O M
I
__
K O E T P N I
C P G A F
_
IG O E
O E A C O PN I
S _
D R P
.
I I T
R N RB A F .
B O OU C O
A I FT I _
F T F N _
A TD I
O _
D L NN R I
_
T L L EA E T
C E A M V A
E
J
B
I
F
T UG
S CN N
N OI O C
L
I _
_
U R I
DB I
N
_
S O U T O
/ F D I
C _
E N IAT D E
._
.
L N A R , N R _
T O ET O _
I I
N TR C S
D
T
T
T O
A
C TI CP
RP D E
E R
S
_ __
E N I
A U L T
_
N E F C NS L S
V I
S M I I
G- A
M E U C R IT T E _
T A R C E B SC S P _
N X U O P A EU N I
E E D D S F DD I P _
M E
H S C
C T
A N
O
R
P
_
T E _
_
T M _
A U
C
O _
D 7 6 6 6
8 8 8 8
/ / / /
E 3 9 7 6
T 2 1 2 2
A / / / / .
D 2 2 0 6
1 1
_
._
._
. ._
V 2 3 _
E 1 _
R
_
_
_
_
_
.
_
. _
O 1 7 6
N 5 5 _
_
0 3 1 9 1 _
S T 2 0
T N 9 7 - 5 -
R E -
O M S - M - M _
_
P U V V V _
.
-
P C B P B P B
U O . C
S D 2 1
2 F 2 _
__
_
D _
N _
A
G T
N FN
I
OE _
P M _
I
EU C C C C _
.
P PC E O T O O _
YO P R R R R _
TD S P C P P _
_
.
-
E
P M
O E .
C TO 1 2 3 4 5
S IN
l l
i
- .
< .
'
-
-
-
-
- ~
.
.:
,
N
O
I
_
T .
A
2 L Y
1 0 2 U Y
4
t 2 L 2 Y
C
.
- - 6 3 8 ,
0 7 A 3 6 5
5 8 C - 3 4 -
T
-
F S S R A
O S S S S
E
.
P P P
R - - - -
T S S S
S I I I
S S S
E 2 2 2
. . 2 P
O O I
R R R
N N P E E E _
B B B
T T O M M M
E R T U U U
K O E M N N N
C P G ME -
O E A UT T T T
D R P DS R R R
NY O O O
ES P P P
D P P P
DN U U U
S S S
AOI
T NT E E E
C OC P P P
E IE I I I -.
J TJ P P P
B AN
U UI F F F
S L O O O
/ AY
E VT N N N
L EE O O
T F IO I I
I
GA T T T
T NS A
I I
A A
I I
D T RD L L L
E N EA I I I
N E EE C C C
I
S M NH N N N
M E U I
O O O
A R C GW C C C
X U O NO E E E
E D D EL R R R -
E .
S C _
_
T O -
N R
E P
M
U
C
O
D 7 6 6 6
8 8 8 8
/ / / /
E 8 1 8 0
T 2 3 2 3
A / / / /
D 1 0 0 0
1 1 1
.
V
E 3 1 3 4
R
N
O 6 7
I
9 9 6
T 0 0 7
A
I - - -
L
I E A A1 A
C O. 1 1 1
N N 8 8 8 2
O X 7 7 7
C T
E N - - - -
R E
M ) ) ) )
T U N B B B
L C ( ( ( (
I O P P P P
U D N N N N
B
-
S
A
G T
N FN
I
P M
I
EU C C C C
P PC L L L L
YO A A A A
TD C C C C
-
_
E
P M
O E .
C TO 6 7 8 9
S IN
_
-
_
1 m
6_
.
S
J.
k, -
.
-,
.
m
s
- t
r
o
n- p
io- e
R
-
t .
s
a' n
m o .
-
u r i
o o s t m
m
e f n a %
. n n eo n
a 4 AB - i ci i~ .,,
l 1 1201120 22- nt d _
.
l
O3 O0110O1133 'r ' ai gr'. %
e X34 O0000O0111 o ms no 21
c R41 - CCCCCCC088-
0000PFPCVV
f ro io 11
i
s 1A16
95E08A6UUUUUUUPOO-
7
t9CCC fs
op
rC31,S
e 8 - _
_
N M 8CT 592SSSSSSSUMM s3QQQ ni en005 _
O 4PSW293HHHHHHHH- - e2- - - oD 0 314207429 ng426 ,
-
1CFH6 CCCCCCCCSS26 u 625 c 670318215162 ii- - 0
TI 02K M4F22222222HH98 qG147 nd 331866463677 gsSA0 a
C 2EE
,
1 P - - - - CC20 eU398 on 538948832394 nePP- >
E
P 7TMMM5STTTTTTTT.2216 RS313 Ha 343233331323 ED22D
S
N
m
m
I
-
,-
S
,
w
M u .
E 3
T .
S m
Y .
S m
._
m
C ._
,
A
V
H
G ,
N ,
I
R .
._
U _
D _
.
C
-
D DO - -
E O 0E
.F
.
._
S -
11C11 -
U - -
.v .
S
-
s
. A A -ve..... m
4-AA3 H QJBAB 8CC2 2 LDJC0 eRvvvvv C
T
N
E i
n
a 1469147Q69989299915.6'
. ..................v.7
2ABA A 67891
666533
. . . . .
R
42
eeeee 9GDE
1RRRRR 3122
5
- vvvvvvvvvvvvvvvvvvvev.v......vvvvv
-
M w 410 ,056 - . . .
U a BeeeeeeeeeeeeeeeeeeeRevevvvvvveeeee Z1 86388 Zvvv
C r RRRRRRRRRRRRRRRRRRRR ReReeeeeeRRRRR B C- - 3eee
O D - -
A R RRRRRR C CACCC RRR
D 0CJA8AFCFHKCDEBADEAK0H H GFDC8 19999999 1
8448999555599985554404A7CBDEFG86655 43333333 4776
D 08833334444333333388387677777711133 25557555 2856
N 0 2 2
A
-
1 1 1
.
S _
C -x
N .
m
I
W ,
A -_
R
D
4
- .
I ,l 4
V s
n
n
3c.v
T o
N
E
i
t i
o l5.
c1R
e
M a t
H c a lB 4
C i t
sl &3 -
-
A f iCma 9 -
T a&e
S-
i
T
A
c
e
tHtE1.
s sM1V
.
-
-
-
-
p n f yS3B _
S I
oSAB2 _
.
-
-
_
.
.
.
.
-
-
m
.
m l _
ce k 6 7 e 6
it a 1 8 e 8
s fIo synms - e s . / t /
e L . dv e 0 Sd 0 s
r yiSo v l re c 2 n 1 t
u nre i &r e aaR nn l/ l a / 1l
d ooSCt' okR rtd ao a1 r a- 1
e g Aa e r een1 li
c e 8 rn 1 0. u
s .
c iter l17 rgo0 dMa- l t i4 d g1 uog 7e .
_
o
cte&l48 unW1 3 ietST
tD ic n2 in8 tin 3 .
0. R
-
r eah a ./ si ee a ei- cti _
P pCtVt73 stt- ne S vpah7 nzV uct6 2t _
s O s1 escP heb- rsec- haB rel - s _
nA ,nP/ reuC choM unreP crP trop 0e
IQ&HII2 PTDF SSJS SIAMI SBS SEBI PT
.
=
s _
.
t .
s r .
e op
-
_
c ~
.
i e
I t R
V o
N y -
T c
N n n
E o e _
M i i
H s s c
C u i i s
A o v f t
T e e e s
T n R D e
A a u
l n n q
l
o o e
e 51 i53 i
R
c 00 t- - t
s SS48 4 cll c p
i
2071 uAA u9 u
M 553323 r222 r8 6 -
115555 t333 t6 0 t 93531
00- 4- s333 s6106+ r286763 _
00QQ-Q n- n 4 44 a562819
- - PPPP oKKK oE9D11 t932033 _
DD2222 CRRR CS6S44 S811111 _
-
-
._
-
-
K
0CCB G43
C' 11 J C 2 1OOO 432 3 C 32342242 D2
2 s DCCCB A A A A ... F 2 A . .
o OOOOOHF 012 .. 0 02 . 7 .D 0 . . . 03 ........ G . .vv
0 vv 0 0 .v 0vvvvO 0vvv.v 0 vvvvvvvv 6vvee
in . . . . .O3 9 . .ee 954 9 .e
5eeee. 9eeeve 9 .eeeeeeee 1 eeRR
w vvvvv.. vvRR - vR RRRR RRReR vRRRRRRRR
K
- RR
a
r
eeeeevv Zee Z .. Ze Z v Z R Ze 77
RRRRRee BRR11 Bvv BR2 BDCCSe B432 3 BR32342242 BD821
D RR - - ee - - 1OOOR - - - 2- - - - 3- - -
01789 11513 1RR 171 1 - - - - 1742 6 1884680394 1 GGG
5877778 44455 4 401 435374 433360 4223334403 48666
1111192 23333 254 277 214434 211172 2222222233 21111
2 2- - 2 2 2 2 2
1 136 1 1 1 1 1 -
-
-
-
.
.
.
.
-
-
s
n -
i
o
t
a
ic
.
-
f
i
c
e
p
S
-
s
e
r
u
-
d
e
c -
o
r -
P
.
.
.
_
_
-
-
_
.
. -
. -
_
_
-
- _
_
_
..
_
- _
_
. _
_
_
I _
_
V _
_
.
.
_
T _
N
_
E
M
H s _
u
.
C .
A o ..
e
.
T
n
.
T
A a
.
.
.
l .
I
e
e
s -
i
-
M
-
-
_
-
A
1
.
e
v -
R -
C
9 J A
2 6 1 A
- 0 8 A 3
S 0 4 2 2 8 .
C - A 5 8 2
R 0 4 . 3 2 5
- 5 v 4 5 3
0 1 . e - 3 9
8 0 v R 0 9 0
0 0 e 3 3 3 1
3 s 0 - R B, 2 2 2 -
a 1 0 0 0 0 1 .
_
n - 1 8 A 1 1 1 1
i 1 0 9 1 8 8 8 A 4 9
w 0 2 2 2 2 2 2 6 - 3 6
a 1 - - 0 M 1 5 L
r 0 E C E e e e 5 4 R 2 .
.
D
.
2 L IR T l l l
4 1 - - , 1
-
0 - i 3 - 9 0 B -
C
E
F 8 D F i i
0 V
F F
D
7
-
3
-
8
0 D
6 0
1 9
W W 0 H W W W E M M 0 E 4 3
S S 1 2 S S S N S S 1 N 1 0
-
-
-
-
-
-
-
-
s
n -
i
o
-
t
a
i
c .
f" -
i
c
e
p
S
.
.
-
_ .
-
_
-
e
r
u
d _
.
e
c
o
r
P -
.
-
_.
_
_
,
'
j ,
'
y.
, 9
.
d
e~
l s
s l r e
V r
ic o eg g
s'
0- e' r
r
a
r
e,
0 - t' t t l y A n
p- :
6e n aen- a o bl 1 o
m
u
n". l
re mto h t ip 6 li
to7 db2 oC0 oaCrC2 Ss1 stp 3 at1
P4 ii0 ea16 t 1 tt e 4 e46 upu
2 nt3 tC38 ol37 u S ni y36 li
88 Buss- ilca3 96 -
h- Ua- a / Mo8 A ofr 8 or / r m 6 rl 8
cs ts l rs6 rs/ dcies/ res2 irres8 tas/
nu Vsu ueu2 Vtu4 Viittu7 ttu2 aeetu/ ctu1
N eB 0bB swB/ 0nB2 ctB2
X- O
s
u 8u no 1 8o / 3oiea 0l l
/ ntB/
oa 2ttwsB9 inoy / lesB/n 2 -
I
Q2 4S2 IP21 4C22 1SSRB28 CB21 VIPS 21 EI21 -
T n
, C
E i
o ..
P t
S a
N
I i
c
f
S i
M c -
e
.
E s .
T p p
S S 4 m m_
_
Y 4 2 u 5 _
S e 0 2 tP .1
.
_
- c 3 n 4 4
rs84~.ar
.
_
R s i - y 8 ns8
E nn vs l h us'-
s ar eu/ l e / ou/
- W
O
oa
ir
rr
e e' acB nt
s- e- relas tB1
a
ot 1 iB1 m
P yee0'
l 1 oa / t 2
tT 5 Sm3 tt- d b9 nips 8 W2/ CW 0 a2/
a 0 r2 ei2 cCS3 e a0 eimr0 9 01 9
,
lu-
_
L tes37 no8 Mw 7 n 25 t C37 Gxue24 e^ yg1 _
A Scr 8 mof 6 S8 el r8 aV 8 uPv 8 c 4 rn 2 c 5 _
C
I
R i
ies/ eiss8 V
tvmu3 ttnu/ - dr1
rrB1 .saaB5 6aa2
/ geos/
eeaB2 s0wB2 ereDB/ rmv ioBv
rs/
rstu5 lu0eu1 a dru3 .vp . mA is/ is
cmv
ais
ml u. rs.
ip
_
T neo / _ytr / 1l e/ mir / 2 eue r o' e eue _
C
E
USf21 'SST21 4 C g1 EDe21 In0o 5P21 / toe ' SPR PC2R RPR
Stf&21 _
L
E
.
.
G
N _
I
-
R _
U -
D .
m
-
D .E m
E e I
S cd
U
S s
t4
l7
u-
ivo6
rL-
a8 s
s
a
T i
aE e E l t
N
E
s
y
F
s-
S& Ca
s6
M l nei nei8' Ce
U a ocs ogs/ Dg
C n iiy i ay2 Vas
O A tvl ttl1 td
D ar a al a/ 5l a
ten ton 2 2oo
D SSA SVA1 1VL
N
A
S
G
N
I
W
A
R
D
. r
- i n
c
e P
v
l
ao p
i
ti U S . e
V s 5 ntneCl c t7
t
r
G8 e a o pA a s
mc y c
l
e i8
T
.
E/ e12 a l
S/
_
_
N o R0 rnimTdiei48 c E7 R 3 .
E p U1 aofa argr / i
8 S n _
M e N erireetae88 n 8/ A o- .
H R il gd L c r t - 1 h 2 F
C
A
r57 lcvaoi eotV/
e0 unurxNl tab 1
c
e
42
// 3. W
R
T S1 NEQPEGESB21 T 31 8P
T
A
_
_
._
_
_
_
t
A B B A n
s
4753464777M6775785784 795ee -
o
786779
...rr
er .
..................... ea
in vvvvvvvvvvvvvvvvvvvvv
eeeeeeeeeeeeeeeeeeeee
. .....vvvhu ni .
vvvvvveeeTC OD
w
a
E'RRRRRRRRRRRRRRRRRRRRR
R- - - -
EeeeeeeRRR
RRRRRRR- - Deg dne
.
.
r ABCDEFGJKLMNPQRST0VWX RWZCna li n
D D111111111111111111111 DABEFJVAAALii oai _
C222222222222222222222 L111111111TLD MML
L O _
T M _
-
.
_
- _
g _
_
d _
_
_
_
_
_
4
_
e 5 _
-
cs 486
I n 5 nn 8/8
I
o 8 3 ao /4/
V i - / 8 mi 927
ts 6 K6 K/ K K rt 2/1 1
_
T, ae - S1 S8 S S oi /1/
N nv P6 E/ E/ E E fs 611
E ir D8 7 6 - - no
op
M du R/ 1 1 13 1 5490
H rC 7 4V 4B 41 4G cs 8906
C o 2/ 29 20 20 21 ni 1413 .
A o V1 22 23 23 24 oD 2665 _
T C B1 11 11 11 11 N 1123
T
A
._
_
_
_
_
_
_
_
_
n 1
e&o 2 - 6
v 5 6 8 5 3 9'
_
i 1 1 1
i tt - - - - - - - - 6 -
tna D D D5 F6 26 F5 F P8 P6 _
cin B3 V3 B8 B8 G8 B8 B3 B/ B8
eoi V8 B8 V/ V/ D/ V/ V8 R4 R/
t pd / / 3 5 6 3 8
n_
1
otr
reo
22 22 22 22 22 22 26
V/ V/ V/ V/ V/ V/ V/ V0 V/
/ 2/ 22
PSo B9 B9 B4 B3 B3 B7 B9 B1 B7 _
C
.
_
_
_
_
& n s 3 .g 0 _
o'
le3 2 n 2 _
g i g i
n t b . n. r s .
ig
l n a
tdI iceav iv
I e l n l nW
i
nv
l oe _
li
nn R tR ao ao 1 air .
ut eayl 6 u cin cil n. ct
2 Parm ra68 P17 itw24 itaw25 i a27
nausoi2/ 38 r ao28 rano28 rn38
l
eieregx41 e4/ trd4/ trrd4/
ml tiea 3 a 5 cak 1 caek 7
eptlP2
ti4/
cm 1 _
brcsTtiP/ bP1 e plP/ erP2 _
aeuM rC0 aC/ l eaC0 l enaC/ l eC/
CTN CTF1 CF1 ESWF1 ESIWF2 ETF1
_
e
r
_
u
d
e
c
o
r
_
P
n
o 7
g
i n88 8 8
5 t3
le io2/ n1 n 1
n 8
7
n /
8 c
e.
pv
b yt ./
aaav3
2 io.
tv
i
d
n
n.
yi
o /
at /
2
o 8
i 2
t/ atnR
l
se Cwne
eiR-
ae
cR to
u iovtR
e
r a 3 dsa 8 cni gcm i nr al17
nars5 yf17 eG
Tl3
l05
e yl4
dal03
ie 7
rmy03 iRet0 ai13 n ml28 _
ea4 dwa4 tpt48 l
Te4 wt4/ atea4/
l t- . eet- . cie / di k- en0 mntt 8
bsPv bcsPv eufP7 ntdcP ceP1 rassP1
anCe manCe l qaC/ auniC adC/ el ynC/ _
CIFR ERIFR EESF1 HPaTF RIF2 PPSIF2
_
n
o1
i- _
tV s _
cB p _
g e2 gm
n p nu
a s . iP1 _
t
D
a iRa
t
nPO.
adi
RnB
t
agV
-
ey i2
rHts rg
o ep or .
_
twfm t a O.
ooau oh
MLSP MCP _
_
.
_
'
.
.
- _
L
a
,
_
_
_
_
2 56
813345
Z 24233237.
v........vv....
81A 53A CCCCA8A .
9149 . 536674365639667 Cevvvvvvvveevvvvvv
OReeeeeeeeRReeeeee _
S s . ...vv............... K RRRRRRRR RRRRRR
N a Evvvveevvvvvvvvvvvvvvv R .1 11
O n ReeeeRReeeeeeeeeeeeeee v 21112221 - 211111 _
I i
RRRR RRRRRRRRRRRRRRR AeR- - - - - - - BA- - - -
T w 8- - CF - - - - - - 8R RA0NN0QSAASY00FG
C a 0YZDFJJGAABCNRSY8YAABF 0 00266666555536622
E r 0118888ACBBBGGGG7GCAAA 0033322222000032233
P D 1111111464444444444444 1533333333333333333 _
S
N
I
C
I&
G
N
I
R
U
D
D
E
S
U __
S s _
T f e 7
N o -6 l
8
E n 8 . b /
_m
.
M
io
n s / 9
U oss 6 se 1
C t ita 1 nsA /
O
D
a
c
tnl 7/ as5 1 _
laeC A
m 39 79 TrA3
_
_
i
67 T -
D f l uy r8 r
es _
N
A
i
c
e
a rtdS
ttenV
ssfaBv
5 letV9
.
eS/
vtB1
.l
ete
vti
S o nna e ei / eil
G S IiS22R Lm21 Lmb
N
IW
_
A _
R
D _
_
l
l
_
i
V _
_
T _
N
E
M
H
C
A s 4
T a s s
T d ge dg . - t e 6
A n n nr 6 fnn v na n 6 f l7 f 8
afo iA 8 oai e dol e 8 o fb8 o /
oi 7 b / tb R nil 7. 6 m / oa/ 0
n ts8 uc 8 nSu ata78 ytu 3 n C4 n 3 _
onat/ Ti / o T 6 at0/ tnr / o s n / o s/ _
s i
otr9 m 9 it tts59 iet 6 il t
iol2
il t0
e tino/ fs8 tnd 7 nnn / l ns8 tan 1 a tan 1
r
lace ace
i m 16
a t e p2 oi2- aens0 eeIP1 ian.- ti9
u l amp e2 l
mat 5 mm C bmi7 .8 ax m1
d l
cuu9 nS 4 l u r 6 u u gF 5 a r 02 l ru1/ na5 liru1
e airs 2 g M a rso 8rrn eet5 atr .0 i o latr.
c
o
trt 7
sbsd-
ihV . t tk p
stBv sscpP3ssbov a aPv ses / r
/ttin. cPn- . tct83 mC8 tct8
- ses- _
r nannP ei e nnauC/nnuie rflCe nl nP0 eRP nl nP
P IFI aI DW2R I
IRSF6IITtR ToPFR IEII1 TSI iEII
_
_
_
L_
- -.
e
-
, ~
.
l
_
l
i
V
T _
N _
E
M
H -
C
A
T .
_
T
.
-
A
-
_
A
08448
11111
-
s M . . . .. _
g Rvvvvv
n - eeeee
i
0RRRRR
w 8 - -
a 00ABCA
r 097795
D 178877
-
-
-
.
.
-
.
-
.
-
n ,
o
2 i -
t
a
c
if
i
-
.
c -
e
p -
S -
-
.
_
.
.
-
_
,
.
_
_.
~
_
-
7 6 _
8 8 3
/ le78 / f 4 .
_
_
f 2 fb/ f 4 o 2
oe2 oa2 o 2
l/ C2 / n s _
nb1 n / nl 0 oss ._
s oa ol1 oa 1 ita _
e
r
iC- ia ii tnl
t ti9 tx 0 laeC
_
u al9 ax aa 1 m
uy
.
d na5 n a 5, nis5 .
_
e ii i
o i
re lart -
c mx8 mC8 mTl8 tte
o
r
r a- r - r b- ssf
eoP eRP eRaP nna
P TCI TSI TSCI IiS
~ _
._
.
-
.
-
-