PNO-I-98-002, on 980130,operators Declared Both Trains of Component Cooling Reactor & Reactor Plant River Water Sys Inoperable Due to Failure to Meet TS Surveillance Testing Requirements.Entered TS 3.0.3 & 4.0.3

From kanterella
Jump to navigation Jump to search
PNO-I-98-002:on 980130,operators Declared Both Trains of Component Cooling Reactor & Reactor Plant River Water Sys Inoperable Due to Failure to Meet TS Surveillance Testing Requirements.Entered TS 3.0.3 & 4.0.3
ML20206R764
Person / Time
Site: Beaver Valley
Issue date: 02/02/1998
From: David Kern, Neil Perry
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
References
PNO-I-98-002, PNO-I-98-2, NUDOCS 9901200192
Download: ML20206R764 (2)


_ _ , _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ _ _ _ _ _ _ _ _ _ . _ _ _ _ _ . _ _

. y i

February 2, 1998 l

[

! PRELIMINARY NOTIFICATION OF EVENT OR UNUSUAL OCCURRENCE PNO-I-98-002 I l

This preliminary notification constitutes EARLY notice of events of POSSIBLE l

, safety or public interest significance. The information is as initially received without verification or evaluation, and is basically all that is known by Region I staff in King of Prussia, Pennsylvania on this date.

Facility Licensee Emergency Classification l Duquesne Light Co. Notification of Unusual Event Beaver Valley 1 2 Alert Shippingport, Pennsylvania Site Area Emergency l Dockets: 50-334,50-412 General Emergency X Not Applicable  !

Subject:

BEAVER VALLEY UNIT 1 FORCED SHUTDOWN GREATER TRAN 72 HOURS  ;

At 7:40 p.m. on January 30, 1998, operators declared the both trains of j the component cooling reactor (CCR) and reactor plant river water (RW) systems inoperable due to failure to meet TS surveillance testing requirements. Operators immediately entered TS 3.0.3 and TS 4.0.3 and initiated efforts to complete surveillance test requirements which had been missed.

A detailed surveillance test program review identified that TS  ;

4.7.3.1.b(c) and 4.7.4.1.b(c) were not previously satisfied for either Unit 1 or Unit 2. These surveillance requirements require valve position verification each 31 days and valve cycling each 18 months for system j valves which service safety-related equipment. The program review identified that previous surveillance test scope was too narrow in that it did not include all CCR and RW valves which serviced safety-related equipment as defined in the station material equipment list (Q List). The revised interpretation of the TS requirements identified approximately 110 additional valves inside containment and several hundred valves outside containment which may require surveillance. A conference call was conducted on January 31 between Duquesne Light Company (DLC) and the j NRC to discuss the issue and DLC's progress toward establishing a basis

.for requesting enforcement discretion to allow additional time to complete the surveillance requirements. Following this discussion, DLC management concluded that insufficient time remained for DLC to properly prepare and review justification for enforcement discretion. ,

1 Unit 1 operators began a TS required shutdown at 6:04 pm on January 31.

The unit achieved cold shutdown (mode 5) at 5:35 pm on February 1. Unit

! 2 has remained in mode 5 since an unrelated forced shutdown on December i 16, 1997. DLC anticipates restarting both units approximately February 5, following completion of required surveillance tests.

9901200192 990202 PDR IS E Il i

43f PNO-I-98-OO2 PDR h yf/ o

The contents of this PN have been communicated to the Pennsylvania, Ohio and West Virginia state governments.

The resident inspectors observed DLC efforts to address the TS surveillance testing issue and monitored portions of the reactor shutdown. The inspectors will continue to evaluate associated licensee corrective actions prior to restart.

Contact:

Neil Perry David Kern (610)337-5225 (412)643-2000 ,

l l

1 i