Attaunaent 1 DLOP 228. Rev. I INITIAL NOSIGNIFICANTNhZAR05CONSIDERATIONDETERMINATION
(
AND NOTICIllG ACTION Docket flo.
50-275/323 Facility:
Diablo Canyon 1 & 2 Licensee:
Pacific Gas & Electric Co_
Date of application: 9/20/85 Request for:
inservice snubber Tech Spec change to allow performance of first,6n of power visual inspection for Unit 2 following completi ascension program I
LAR f 10 (See attached notice or press release for more details.)
Initial Determination:
(X ) Proposed determination - amendment request involves no significant hazards considerations' (NSHC).
(
) Final determination - amendment request invo'lves significant hazards considerations (SHC).
Basis for Determination
(
) Licensee's f4SHC discussion has been reviewed and is accepted. See attached amendment request.
(x ) Basis for this determination is presented in the attached notice.
(
) Other (state):
860057 (Attach additional sheets as needed.)
Initial floticing Action:
(Attach appropriate notice or input for r.onthly FRit)
)!
1.
( X ) Monthly FRN.
flotice of opportunity for hearing (30 days) and request for comments on proposed NSHC determination - monthly FRN input is attached (Attachment 8).
2.
(
) Individual FRf( (30 days). Same notice matter as above.
Time does not l
allow waiting for next monthly FRN (Attachments 9a and 9b).
(THIS FORM SHOULD BE TYPED EXCEPT FOR UNUSUAL, URGEl(T CIRCUMSTANCES.)
7 N
ze.
$ S Ib I Jo t 9 t) m c
'O d((dLiWilL*lll 4
- pd 9 (*
c' s
DLOP 228 Rev. 1 1:
-Q 3.
(
) L6 cal media notice. Valid exigent circumstances exist (evaluated below).
i determination is attached C;ing pub.lic comments on proposed NSHC Local media notice request Atta'chment 10).
4.
(
) No notice. A valid emergency situation exists (evaluated below) and there is no time for public notice on proposed NSHC determination.
(No attachment.)
5.
(
) Individual FRN (30-days'). Licensee's claim of exigent or emergency I
circumstances is invalid (evaluated below). Notice'of opportunity for hearing (30 days) and request for comments on proposed NSHC determina-tion is attached (Attachments 9a and 9b). Letter of explanation to licensee is also attached.
6.
(
) Individual FRN (30-days). The amendment request involves SHC. Notice l
of opportunity for prior hearing is attached (Attachment 5). Letter to licensee also attached.
7.
(
) Individual Short FRN. Valid emergency circumstances exist (evaluated below).
There is no time for the usual 3.0-day FRN.
(Attachment 16).
Evaluation of exig,ent or emergency. circumstances (if applicable):
e i
~
(attach additional sheets as needed)
Approvals Date l
/d///W 1.
e w
/r///fPd" 2.
3.
Y, b
l 8(
(OELO) '
Lw4lb[
t Additional approval (for noticing actions types 3, 4, 5, 6 and 7):
4.
(Assistant Director)
Additional approval (for noticing action types 4 and 5):
5.
i (Director, Division of Licensing)
Attachment:
as indicated cc:
Original - Docket File (with note " Docket File only")
)
Project Manager Licensing.Assis tant 8r17ic~h Files N N 7