Notice of Violation from Insp on 880426-0527.Violation Noted:Failure to Establish Measures to Assure That Stopwatches Properly Controlled,Calibr & Adjusted & Valve Not Tested Before Returning to Svc
ML20195K119
Person / Time
Site: Catawba  Duke Energy icon.png
Issue date: 06/17/1988
From: Brownlee V
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML20195K092 List:
References
50-413-88-18, 50-414-88-18, NUDOCS 8806290350
Download: ML20195K119 (2)


Text

.

ENCLOSURE 1 NOTICE OF VIOLATION Duke Power Company I;ocket Nos. 50-413, 50-414 Catawba Units 1 and 2 License Nos. NPF-35, NPF-52 During the Nuclear Regulatory Comission (NRC) inspection conducted .on April 26, 1988 through May 27, 1988, violations of NRC requirements were

  • identified. In accordance with the "General Statement of Policy and Procedure for NRC Enforcement Actions",10 CFR Part 2, Appendix C (1988), the violations are listed below: .

A. 10 CFR 50 Appendix B, Criterion XII as implemented by Quality Assurance Program (Duke 1-A, Amendment 11) Section 17.2.12 requires in part that measures be established to assure that instruments and other measuring and testing devices used in activities affecting quality are properly controlled, calibrated and adjusted at specified ' periods to maintain-accuracy within necessary limits. ,

Contrary to the above, the licensee failed to establish measures to assure that stopwatches used in activities affecting quality were properly controlled, calibrated and adjusted in that an uncontrolled personal wristwatch was used on May 18, 1988, to verify the motor operated . damper (1 ARF-02) in the containment air return fan discharge line opened with a 10 +/-1 second delay after a test signal. A program for calibrating stopwatches has not been established.

This is a Severity Level IV Violation (Supplement I). l l

B. Technical Specification 6.8.1 requires that written procedures shall be established, implemented, and maintained covering applicable procedures recommended in Appendix A to Regulatory Guide 1.33, Revision 2, Station Directive 3.2.2, Development and Conduct of the Periodic Testing Program, section 8.0 requires that after a valve has undergone maintenance and prior to its return to service, it shall be tested as necessary to demonstrate that the parameters affected by the maintenance are within l l

acceptable limits.

Contrary to the above, maintenance was performed on valve 2BB-61B on March 15, 1988, and the valve was returned to service without being tested to demonstrate that the parameters affected were within acceptable limits.

This is a Severity Level IV Violation applicable to Unit 2 only.

(SupplementI).

06290350 R 880617 g ADOCK 05000413 DCD

Duke Power Company 2 Docket No. 50-414 Catawba 2 License No. NPF-52 Pursuant to the provisions of 10 CFR 2.201, Duke Power Company is hereby required to submit a written statement or explanation to the Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555, with a copy to the Regional Administrator, Region II, and a copy to the NRC Resident Inspector within thirty (30) days of the date of the letter transmitting this Notice.

This reply should be clearly marked as a "Reply to a Notice of Violation" and should include for each violation: (1) admission or denial of the violation, (2) the reason for the violation if admitted, (3) the corrective steps which have been taken and the results achieved, (4) the corrective steps which will be taken to avoid further violations, and (5) the date when full compliance will be achieved. Where good cause is shown, consideration will be given to extending the response time. If an adequate reply is not received within the time specified in this Notice, an order may be issued to show cause why the license should not be modified, suspended, or revoked or why such other action as may be proper should not be taken.

FOR THE NUCLEAR REGULATORY COMMISSION ORIGINAL SIGNED BY VIRGIL !.. BROWNLEE Virgil L. Brownlee, Chief Reactor Projects Branch 3 Division of Reactor Projects Dated at Atlanta, Georgia this /7t" day of June 1988 i i