ML20128L823

From kanterella
Jump to navigation Jump to search
Revised Application for Amends to Licenses DPR-39 & DPR-48, Revising TSs Needed to Implement Option B to 10CFR50,App J
ML20128L823
Person / Time
Site: Zion  File:ZionSolutions icon.png
Issue date: 10/04/1996
From: Mueller J
COMMONWEALTH EDISON CO.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20128L830 List:
References
NUDOCS 9610150202
Download: ML20128L823 (6)


Text

commonw ratai raimn n>ninan>

Zion ( enerating 5tation e 101 Sluloh lloulevard tion. n.wnrc ra a emwosi October 4,1996 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555 l

l

Subject:

Zion Station Units I and 2 I Revision to Application for Amendment to Facility Technical Specifications Re. Containment Leakage Testing per Option B to 10 CFR 50, App. J Operating Licenses DPR-39 and DPR-48 j NRC Docket Nos. 50-295 and 50-304 j i

I

Reference:

Letter from J. H. Mueller, Commonwealth Edison, to U.S. Nuclear Regulatory Commission, dated September 20,1996 This letter revises Commonwealth Edison's (Comed's) previous application to amend the Zion Unit 1 and 2 Technical Specifications to implement Option B to 10 CFR 50, Appendix J.

Background

The referenced letter transmitted a revised application to amend, pursuant to 10 CFR 50.90, Appendix A of the Zion Unit I and 2 Facility Operating License, DPR-39 and DPR-48. The proposed amendment consisted of Technical Specifications changes needed to implement Option B to 10 CFR 50 Appendix J at Zion Station. The proposed amendment included an exception to the requirements of NEl 94-01, Revision 0, Section 9.2.3, that would have permitted the minimum elapsed time between the first and last tests in a series of consecutive satisfactory Type A tests to be 18 months, rather than the 24 months specified in the NEl document. Comed has determined that this exception is not needed for Zion Units I and 2, and is therefore revising the amendment application accordingly.

Revised Amec_Iment Application Although only Attachments A, B, and E, are affected by the revision, the entirs amendment application is being re-submitted to preclude confusion. The changed portions of the text in I

Attachments A, B, and E, are indicated by revision bars in the right margin. The revised amendment application is comprised of the following attachments to this letter: 1 9610150202 961004 PDR ADOCK 05000295 gb6/ gg ggN /f 9 PDR lW!llyg ,

m c cv n,nr Res/ama ,j,

l Page 2 of 3 Attachment A provides a description and safety analysis of the proposed changes to the Technical Specifications.

1 Attachment B provides an annotated copy and a clean copy of the affected pages of the Technical Specifications .

)

l Attachment C provides an evaluation of Significant Hazards Considerations in i accordance with 10 CFR 50.92.

Attachment D provides an evaluation of the need for an Environmental Assessment in accordance with 10 CFR 51.21 and 10 CFR 51.22.

Attachment E provides a description of the implementation plan for the Containment Leakage Rate Testing Program.

I Attachment F provides the disposition of previously approved exemptions to 10 CFR 50 Appendix J Option A.

The evaluation of Significant Hazards Considerations submitted as Attachment C to the referenced letter (and resubmitted as Attachment C to this letter) remains valid. The removal of the exception to NEI 94-01, Rev. O, does not alter Comed's previous conclusion that the proposed amendment does not involve a significant increase in the probability or consequences of an accident previously evaluated, does not create the possibility of a new or different kind of accident from any accident previously evaluated, and does not involve a significant reduction in a margin of safety.

The proposed amendment revision has been reviewed and approved by Zion Station Onsite and Offsite Review personnel in accordance with Comed procedures. To the best of my 4 knowledge and belief, the statements contained in this revised amendment application are true and correct. In some respects these statements are not based on my personal knowledge, but i obtained information furnished by other Comed employees, contract employees, and 3 consultants. Such information has been reviewed in accordance with company practices, and I believe it to be reliable.

Comed is notifying the State of Illinois of this revised application for amendment by transmitting a copy of this letter and its attachments to the designated state official.

Page 3 of 3 Please direct any questions you may have concerning this submittal to this office.

Respectfully, I >)).R J. H. Mueller Site Vice President Zion Station Subscribed and Sworn to before me, a Notary Public in and for the State of t /ll,Wd and County of ,[al; ;

this M*L day of d)c/ade , i996.

Aw . kid.u bFFICfAL SEAL ['N '

Notary Public 0 ,

THERESA I. SLAY 1 NotaryPublic,StateofIllinois

  • YJ_Comission Expires 7/13/99 Attachments cc
    NRC Regional Administrator - RI!!

Zion Project Manager - NRR Senior Resident Inspector - Zion Station Office of Nuclear Facility Safety - IDNS IDNS Resident Inspector Zion Nuclear Licensing Administrator Master Files Reg. Assurance File DCD Licensing IL:\liCgsoupJerst96 014upp2\ term >tr.wpf

1 ATTACHMENT A DESCRIPTION AND SAFETY ANALYSIS FOR PROPOSED CHANGES Description of Proposed Change Commonwealth Edison (Comed) company proposes to amend Appendix A, Technical Specifications, of Facility Operating Licenses DPR-39 and DPR-48 for Zion Station Units 1 and 2 respectively, to implement Option B to 10 CFR 50 Appendix J. This option allows use of a performance based program for Type A, B, and C containment leakage tests.

l Description and Bases of Current Requirements l

The current Technical Specifications reference 10 CFR Part 50, Appendix J (as modified by approved exemptions) as specifying the frequency of Type A, B, and l C containment leakage testing. Although not explicitly stated in the

! specifications, these references refer to Option A of Appendix J. The test frequency requirements of Option A are very prescriptive, requiring three Type l A tests during a ten year service period, and, in general, Type B and C tests  ;

each refueling outage, not to exceed two years.

The purpose of containment leakage tests, as stated in Appendix J, is to assure that (1) leakage through the primary reactor containment, and systems and components penetrating containment, does not exceed allowable leakage rate ,

values as specified in the technical specifications or associated bases, and l (2) periodic surveillance of reactor containment penetrations and isolation  !

valves is performed, so that proper maintenance and repairs are made during '

the service life of the containment, and systems and components penetrating the primary containment.

)

The stated basis for the current Technical Specifications containment leakage l requirements is to provide a current assessment of potential leakage from containment during simulated accident conditions, thus assuring that public exposure would be well below 10 CFR 100 values in the event of a design basis i accident.

l

! Reason for Requesting an Amendment

\ l Comed is requesting an amendment to the Zion Units 1 and 2 Technical Specifications to allor implementation of Option 8 to 10 CFR 50 Appendix J for conducting Type A, B, and C containment leakage rate testing. Option B establishes requirements for performance based programs in which test intervals are based on system and component performance history.

A performance based program is much more cost effective than the prescriptive Option A program currently required by the Unit I and 2 Technical ,

l Specifications, since it permits extending the interval between tests if the '

performance history shows that more frequent testing provides little or no ,

additional assurance of safety.

1 l

ATTACHMENT A An estimate of this cost effectiveness can be determined from the Final Rule for 10 CFR Part 50, published in the Federal Register on September 26, 1995.

The Final Rule states that the cost associated with complying with current Appendix J requirements has been estimated to be $165,000 for a complete battery of Type B / C tests, and $1,890,000 for Type A tests. The Final Rule also states that over the average remaining lifetime of 20 years, the present value of all remaining leak testing is about $7 million per reactor at a five percent discount rate. It was also estimated that approximately 75 percent of this cost could be averted with a performance based rule. Since the l

remaining lifetime for Units 1 and 2, without plant life extension, is approximately 17 years, the total potential savings for Zion Station realized by implementing Option B is approximately $8.9 million.

The Proposed Rule published in the Federal Register on February 21, 1995 states that " relaxing the frequency of Type A, B, and C tests leads to an increase in overall reactor risk of approximately two percent. This increase is considered to be marginal to safety." Therefare, implementation of Option B at Zion Station will result in significant financial savings for Zion Station with only a marginal increase in risk.

Description and Bases of the Proposed Requirements A general description of the proposed changes to the current Technical Specifications is provided below. The specific changes proposed are shown in annotated and clean copies of the affected pages provided as Attachment B to this LAR.

  • Limiting Conditions for Operation (LCO's) 3.10.1 and 3.10.2, and the associated Surveillance Requirements 4.10.1 and 4.10.2 in Section 3.10/4.10, " Containment Structural Integrity," have been revised such that acceptance criteria and references to 10 CFR Part 50 Appendix J have been deleted and replaced with references to the Containment Leakage Rate Testing Program.
  • A new specification (6.10) has been added to Section 6.0,

" Administrative Controls," to establish the minimum requirements for a l Containment Leakage Testing Program in accordance with Option B of l 10 CFR Part 50, Appendix J.

  • New Specification 6.10 requires that the program be in accordance with the guidelines contained in Regulatory Guide 1.163, which endorses NEI 94-01 (with certain exceptions) as providing methods acceptable to the NRC staff for complying with the provisions of Option B of 10 CFR Part 50, Appendix J. A description of the Comed plan for implementing this program is provided as Attachment E to this LAR.

l I

1 1

2

e

  • ATTACHMENT A
  • The program required by new Specification 6.10 allows a limited duration exception to the NEI 94-01 requirements for Type B testing for one Unit 1 penetration, P-16. This exception will provide Comed an opportunity to complete a modification that will permanently eliminate the need to test the penetration. A discussion of the basis for this exception is provided Attachment F to this LAR.
  • New Specification 6.10 also documents the values for the peak calculated containment internal pressure for the design basis loss of coolant accident (P,), the maximum allowable containment leakage rate (L.) at P.,

and the leakage rate acceptance criteria for the containment and containment air locks, which were previously stipulated in SR 3.6.1.1 and SR 3.6.2.1 respectively.

I

  • Finally, new Specification 6.10 states that the-program must also be in accordance with previously approved exemptions. A description of these exemptions is provided for information in Attachment F to this LAR.

The bases for Option B to 10 CFR 50 Appendix J are documented in the Proposed Rule and the Final Rule issuing Option B to 10 CFR 50 Appendix J, as published in the Federal Register on February 21, 1995, and September 26, 1995, respectively. As documented in these publications, the implementation of a performance based program can provide licensees with substantial savings while incurring only marginal additional industry wide risk.

The bases for the specific changes proposed to the current Technical Specifications are documented in a letter from the NRC to the NEI dated November 2,1995, which promulgated model Technical Specifications for implementing Option B to 10 CFR 50 Appendix J. The overall objective of the model specifications is to (1) replace references to 10 CFR 50 Appendix J in the LC0's and Surveillance Requirements with references to a licensee prepared performance based program, and (2) add t set of minimum program requirements to the administrative section of the Technical Specifications. This objective formed the bases for the changes to the Zion specifications.

Schedule Requirements Comed plans to utilize the provisions of Option B to extend Type A, B, and C testing frequencies during Z2R14. Currently, entry into Mode 4 at the close of Z2R14 is expected to occur in late October, 1996. Therefore, Comed is requesting NRC approval of the proposed changes in support of entry into Mode 4.

]

3

_ , _ , - _ -_ _