Forwards Rev to Oregon State University Radiation Center & Triga Reactor Emergency Response Plan, Per 10CFR50.54(q). Rev Reflects Changes,Tests & Experiments Evaluated,Per 10CFR50.59
ML20115E029
Person / Time
Site: Oregon State University
Issue date: 10/13/1992
From: Andrea Johnson
Oregon State University, CORVALLIS, OR
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
Shared Package
ML20115E031 List:
References
NUDOCS 9210210304
Download: ML20115E029 (8)


Text

_

, RADLulON (Win October 13,1992 U. S. Nuclear Regulatory Commission Document Control Desk Washin0 ton, D. C. 20555

Reference:

Oregon Stato Univc 'ty TRIGA Reactor (OSTR),

Docket No. 50 245 ulconso No. R 106

Subject:

10 CFR 50.54(q) Report of Changes to the OSTR Emergency Responso Plan Which Do Not Decrease the Effectivonoss of the Plan 1 oncoy Gentlemen:

Sint Univunn y As a result of our annual review of the OSTR Emergency Responso Plan, cortain changos to the plan woro datormined to be necessary. (See Attachment A) This letter represents our formal report of the changos in accordance with 10 CFR 50.54(q). Based on our evaluation of the revisions, imuon center AUO Which was conducted under the provisions of 10 CFR 50.59, we have cmen. oregon concluded that nono of the changes reduco the plan's omorgency response 9mi sw) offectivonoss or create an unreviewed safety question. A copy of this avaluation is onclosed.

All of the changes to the plan, and the 10 CFR 50.59 ovaluation supporting the changes have been reviewod and approved by tho OSTR Reactor Operations Committee. As you can see from information provided in the oveluation and itomized in Attachment A, all of the changes involve typographical corrections or other relatively minor modifications necessory to keep the plan curront. In addition to the plan itself, a number of conforming.

changes were modo to the Emergency Responso Plan implementing Procedures (ERIPs)in order to keep them up to date.

To make it easy to updato your copy (s) of the plan, Attachment B includes oil of the current replacement pages for the plan. If you have any concerns or questions about the reported changes to the OSTR Emergency Responso Plan, please lot me know.

Yours sincerely,

'l elephone i 503 737 D4I 7 -

303 m. man A.G.Jhhn. n Director r- ag}/dd/daddhitc 50.54,erp 19007l5c: See Page 2 i

/

9210210304 921013 3 l DR ADOCK 0500 l

I i

U, S. Nuclear Regulatory Commission l Page 2 of 2 October 13,1992 cc: Mr. Al Adams. Project Manager, Non Power Reactor, Decommissioning, and Environmental Projects Directorate, U.S. Nuclear Regulato_ry Commission, M.S. OWFN 11 B 20, Washin0 ton, D.C. 20555 w/ Attachments A & B Regional Administrator, USNRC, Region V w/ Attachrnents A & B Ore 0on Department of Enorgy, Salem, Oregon ATTN: Mr. David Stewart Smith w/Attachmonts A & B Prof. C. E. Binnoy, Chairman, Reactor Operations Committoo w/Attachmont A Prof. B. Dodd, Roactor Adtninistrator w/Attachmont A -

Prof. J. F. Higginbotham, Senior Health Physicist w/ Attachment A T. V. Andersun, Roactor Supervisor w/Attachmont A A. D. Halli Reactor Opo ~ator w/ Attachment A m.

ATTACHMENT A . BLVIS1QRP TQ TJ1E_QSilLEMERGENCY RESPQNSE_ PLAN 2.0 DEFINITIONS Add the following definitions:

ANNUAL Every 12 months, with an interval not excooding 15 months.

BIENNIAL Every 24 months, with an interval not excooding 30 months.

MONTHLY Every four weeks, with an interval not to exceed six wooks.

QUARTERLY Every throo months, with an interval not excooding four months.

EEMI ANNUAL Every six months, with an interval not exceeding sovon and one half months.

8.2.1.b.Ill:

Change "The 14 channel area radiation monitoring system ....." to "The multi-channel area radiation rnonitoring system ....."

8.4.b.

Correct the typographical error in the spelling of " communication" Figure A 1 Update the rnap by adding the now Corvallis bypass.

Figure A 3 Updato the map of the Radiation Contor floor plan.

Appendix B B.2.b.

Change to:

b) Corvallis Fire Department (HAZMAT Team #5 Vehiclo),

Boxes Numbered 1 5 Replace the Inventory Checklists with new, updated ones.

4 9 I

Rev. 11/90 OSU TRIGA REACTOR (OSTR)

.5 CllANGEs, TESTS AND EXPERIMENTS EVALUATED UNDER THE PROVISIONS OF 10 CFR 50.59  :

i l NUMBLR: 92-10 DATE: September 2, 1992- .

111LE: Minor Revisions to the Radiation Center and TRIGA Reactor Emergency Responso Plan ,

l DESCRIPTION As a result of the annual' emergency response drill and emergency plan

'.. review, it is proposed to make a number of minor changes to the emergency plan. These changes are detailed below:

l I

2.0 DEflNITIONS ,

Add the following definitions: <

j. ANNUAL Every 12 months, with an interval not exceeding 15 months.

B1DLNJAL -

Every 24 months, with an interval not exceeding 30 months.

_ liONTtiLY Every four weeks, with an interval not to exceed six weeks.

M I B LY Every three months, with an interval not exceeding four ma,iths,.. I Ef.fiJdNNUal ,

Every s >

' months,ix months, with an interval not exceeding seven and- one-hal f-p I

3 e

g;4 y .- +m-q. -* **v-'-- v -~

8.2.).b.lil:

Char.ge "lhe 14-channel area radiatioh monitoring system ... '

multi-channel area radiation monitoring system ....."

8.4.b.

Correct the typographical error in the spelling of "co.wnunim '

figure A-Update ihe map by adding the new Corvallis bypass, figure A-3 Update the map of the Radiation Center floor plan.

Appendix B B.2.b.

Change to:

b) Corvallis fire Department (HA! MAT Team #5 Vehicle),

Boxes Numbered 1 - 5 Replace the Inventory Checklists with new, updated ones, SAFETY EVALUATION Adding the definitions with respect to frequencies makes the emergency response plan consistent with the OSTR Technical 5)ecifications and ANSI /ANS 15.1, it further clarifies exactly what is meant ay annual etc. in the emergency plan, and allows the operational flexibility necessary to schedule routine actions required by the plan.

Changing the very specific "14 channel" ARMS description to the more general " multi-channel" concept allows for the f act that- the ARM systems are in.the process of being replaced by newer, more up-to-date equipment, and accomodates the fact that the exact number of ARMS will change as this process occurs. There will still be about 10-12 systems operational, which more than adequately provides good area coverage. Safety will_ be increased because the new ARMS will be more reliable than the old ones.

Correction of typographical errors and updating the maps and floor plan have no safety significance. They just keep the plan current and correct.

The Corvallis fire Department is now the lead department- in HAZMAT Region #5 in Oregon. They have a new HAZMAT vehicle-and the orp #tunity was taken to revise and repack Radiation' Center emergency equipment and supplies normally kept at the fire department. The new system allows equipment to be accessed more easily and, therefore, increases safety. -

4 lhe inventory Checklists are revised from time to time to keep them current. Replacing them with the la W t lists just keeps the plan up-to-date.

l 1here are no safety-related changes to the inventories.

The emergency plan changes described above were reviewed and approved by the Reactor Operations Committee (ROC) prior to being implemented. ROC 1 approval included a review of this evaluation and the Committee's conclusion

that the changes did not require a change in the OSTR Technical Specifications and did not constitute an unreviewed safety question as defined in 10 CFR t 50.59(a)(2) (see over). This evaluation also included a review of applicable

, radiation protection aspects and was found to be consistent with the Radiation Center's commitment to Al. ARA.

3 CONF 0RMING PROCEDURAL CllANGES As a result of the training, emergency plan review and drill, the need

for e number of changer in the ERIPs was identified. These do not require a safety evaluation, and are included here for information and completeness.

ERIP 0 >

Page SHP-0-10

3. Change " protective clothing" to " protective equipment".

ERIP 1

page SilP-1-10
4. Change " protective clothing" to " protective equipment".

ERIP 2 Page SHP-2-6 5

3. Change " protective clothing" to " protective equipment".

ERIP 5 Page E-5-6

! Change "R.J. Walker" to "R.H. Farmer".

Page E-5-17 Delete this page.

ERIP 7 Page E-7-4 Update this page with a new list.

] .

f i

Page E-1-5 Change the State Police phone number to: 9-757-4163.

I Add:

Disaster Operations Center............. 7-4133.

Environmental llealth & Safety. . . . . . . . . . 7-2273 l i Page E-7-6  !

Delete R.J. Walker from the list of names on the Radiological i- Assessment Team.

ERIP 8 Pages E-8-2 & E-8-5
Delete the word " associate" from the title of Stephen Binney.

4 APPROVALS i

The following signatures indicate review and approval by the Reactor i Operations Committee and review by licensed operators, if any ROC member does i

not completely concur with or understand the proposed change / test / experiment then that member should hold- this form unsigned and notify the ROC Chairman.

The matter will then be discussed at the next meeting of the Committee. If 4

' any individual ROC member is unable to sign the sheet due to absence or illness this will be so noted, l

S. E. Binneyt+ '

j -A. G. Johnson

  • _ _

h(

i D. L. Amort * ,( C. Ringl'e*

'J. S T. V. Anderson *+

[ bon A. H. Robinson

  • g B. Dodd*+ \P R. A. Schmitt*

A. D. Hall +' [W.H.Warnes*~ 8 h J. F. Higginbotham*+ /ge (Chairman,' Reactor Operations Committee (Signs Last)

  • Member, Reactor Operations Committee-i- + licensed Operator

- -- - + - - . .-

ATTACHMENT B REPLACEMENT PAGES FOR THE OSTR EMERGENCY RESPONSE PLAN

_1992 Ememencs Resnonse Plan Undato

1. Check that the control copy number for your replacement pages is the same as that on your copy of the plan. If it is not, call Brian Dodd (503) 737 7047.
2. Replace the front cover .with the new blue page showing the latest revision date of September 1992.
3. Remove section "2.0 Definitions" in its entirety and replace with the new section 2.0 pages 21 through 2-4.
4. Replace individual pages 8 2,8 9, A 2 and A 4 with the revised copios provided.
5. Remove Appendix B in its entirety and replace with the revised Appendix B, pages B 1 through B-11,
6. Replace the back cover page with the new blue page.

i I

t I

O Oregon State University Radiation Center and TRIGA Reactor -

Emergency Response Plan O

Approved by the Nuclear Regulatory Commission May 17,1984 Last Revised September-1992 Q control copy # h_

00 C318 Kin,3 7

Pn ADOCH C o{

L