Letter Sequence Meeting |
|---|
|
Results
- Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval, Approval
Other: ML20087D526, ML20091E427, ML20091E667, ML20096C267, ML20101P455, ML20101T673, ML20128N324, ML20128Q523, ML20132D461, ML20133E065, ML20133G264, ML20134E393, ML20135B283, ML20137G089, ML20137M414, ML20138M184, ML20141G663, ML20141P193, ML20148G166, ML20149E148, ML20155G379, ML20197B758, ML20198D937, ML20202F052, ML20204G480, ML20205D265, ML20206B182, ML20207E030, ML20207Q913, ML20209C232, ML20211G583, ML20212M102, ML20214P255, ML20214P273, ML20214S958, ML20214U381, ML20214U731, ML20214X272, ML20215G796, ML20215L534, ML20216D570, ML20216E230, ML20235F214, ML20235G486, ML20236C261, ML20236G303, ML20236H463
|
MONTHYEAR05000267/LER-1982-007, Forwards LER 82-007/01T-0.Detailed Event Analysis Encl1982-03-0808 March 1982 Forwards LER 82-007/01T-0.Detailed Event Analysis Encl Project stage: Other 05000267/LER-1982-007-01, /01T-0:on 820222,control Rod Pairs for Regions 7 & 28 Did Not Insert Automatically Following Manual Scram. Possibly Caused by Binding or Sticking of Control Rod Drive Mechanism.Control Rods Exercised to Eliminate Sticking1982-03-0808 March 1982 /01T-0:on 820222,control Rod Pairs for Regions 7 & 28 Did Not Insert Automatically Following Manual Scram. Possibly Caused by Binding or Sticking of Control Rod Drive Mechanism.Control Rods Exercised to Eliminate Sticking Project stage: Other ML20087D5261984-03-0202 March 1984 Requests Exemption from Requirements of Sections Iii.G,J,L & O to 10CFR50,App R.Fire Protection Provisions Believed Adequate to Protect Health & Safety of Public in Event of Accidents Involving Fires.Affidavit Encl Project stage: Other ML20084C5891984-04-16016 April 1984 Provides Advance Notification of Intent to Propose Tech Spec Changes to Circulation speed-high Trip Setting Listed in Table 4.4-3 & Surveillance Requirement SR 5.3.7 for Secondary Coolant Monitoring Project stage: Other ML20084Q4221984-05-10010 May 1984 Forwards Application to Amend License DPR-34,revising Tech Specs to Change Circulator speed-high Steam Trip Setting (Table 4.4-3).Change Would Increase Circulator Availability While Providing for Initiation of Protective Actions Project stage: Request ML20084Q4361984-05-10010 May 1984 Application to Amend License DPR-34,revising Tech Specs to Change Circulator speed-high Steam Trip Setting.Change Would Increase Circulator Availability While Providing for Initiation of Protective Actions Project stage: Request ML20084Q4441984-05-10010 May 1984 Proposed Tech Spec Table 4.4-3, Instrument Operating Requirements for Plant Protective Sys,Circulator Trip. Significant Hazards Considerations Encl Project stage: Other ML20091E6671984-05-10010 May 1984 Forwards List of Correspondence on Fire Protection,Per 840427 Request.List Identifies Ltrs Originated from NRC & Util Relevant to Fire protection,10CFR50,App R,Branch Technical Position 9.5-1,cable Separation & Plant Issues Project stage: Other ML20091E4271984-05-11011 May 1984 Forwards Summary of Fire Protection Review to Determine Conformance of Facility to Section Iii.G of 10CFR50,App R, Per 840427 Commitment.Fire Protection Provisions Adequate Project stage: Other ML20092M5471984-06-22022 June 1984 Responds to 840608 Meeting Re Application of 10CFR50,App R Fire Protection Requirements to Facility.Schedule for App R Review & Submittal & Proposed Fire Protection Regulatory Guidance Resolving HTGR Issues Encl Project stage: Meeting PNO-IV-84-014, on 840623,reactor Tripped on High Pressure Signal & 6 of 7 Control Rod Pairs Failed to Drop.Cause Unknown.Drive Mechanisms Will Be Removed for Exam1984-06-25025 June 1984 PNO-IV-84-014:on 840623,reactor Tripped on High Pressure Signal & 6 of 7 Control Rod Pairs Failed to Drop.Cause Unknown.Drive Mechanisms Will Be Removed for Exam Project stage: Request ML20092P6261984-06-26026 June 1984 Confirms Util Commitment to Fully Investigate 840623 Event in Which Six Control Rod Pairs Failed to Insert Into Core Under Automatic Velocity Limited free-fall Sys.Nrc Approval of Resolutions Will Be Obtained Prior to Reactor Startup Project stage: Other ML19318H9481984-06-26026 June 1984 Summary of 840608 Meeting W/Util in Bethesda,Md Re Fire Protection Issues at Plant.List of Attendees & Meeting Agenda Encl Project stage: Meeting ML20090C5261984-07-0606 July 1984 Responds to NRC Concerns Re Fire Protection Review,Bldg 10 Licensing Requirements,Control Rod Failure to Scram, Documentation of Disciplinary Actions,Clearance Tags & Radiological Emergency Exercise Scenario,Per 840625 Meeting Project stage: Meeting ML20094D7741984-07-18018 July 1984 Informs of Control Rod & CRD Insp & Testing in Response to NRC 840709 Insp.Major Power Consumption & Scram Verification of All 37 CRD & Orifice Assemblies Completed & Insp Underway.Plan for Further Action Described Project stage: Other ML20096C2671984-08-17017 August 1984 Forwards Revised Schedule for App R Review,Submittals,Plant Mods & Fire Protection Safe Reactor Shutdown/Cooldown Capability Incorporating NRC Concerns & Comments Project stage: Other ML20096C0321984-08-21021 August 1984 Provides Findings & Positions Re Investigation of 840623 Failure of Six Control Rods to Automatically Insert Upon Scram.Summary of Work on Four CRDs & Description of Tests Encl.Corrective Actions Listed Project stage: Other ML20098B3051984-09-0707 September 1984 Ro:On 840904,while Removing CRD & Orifice Assembly,Motor Overcurrent Condition on Auxiliary Transfer Cask Shutters Occurred,Preventing Full Closure.Caused by One Control Rod String Not Fully Retracted.Work Temporarily Discontinued Project stage: Other ML20093K1941984-09-24024 September 1984 Submits Info Re Status of Damaged Control Rod Removal on Fuel Deck.Related Info Encl.Possibly Caused by Absorber Strings Not Fully Retracted,Despite Full Retract Limit Switch Indication Project stage: Other ML20099K7271984-11-0808 November 1984 Provides Status of Control Rod Drive & Orificing Assembly (Crdoa) Refurbishing Efforts.Further Investigation of Crdoa Determined That Cause of Inability of Absorber String to Fully Retract Was Cable Failure Project stage: Other ML20101P4551984-12-14014 December 1984 Advises That Final Installation of Oil Mist Detection Sys Completed Wk of 841105,per 840625 Commitment.Sys Inoperable During Initial Checkout.Manufacturer Repaired & Balanced Entire Sys on 841115,however,on 841121 Sys Inoperable Again Project stage: Other ML20112C0491984-12-27027 December 1984 Responds to NRC 841025 Request for Addl Info Re 840510 Application for Amend to License DPR-34,revising Tech Spec Re Helium Circulators Overspeed Trip Setpoint.Analysis Value Encl Project stage: Request ML20112G5061985-01-0404 January 1985 Forwards Status of Planned Audit Response to NRC July 1984 Audit of Plant Operations,Per Denton .Repts Covering Technical Details of Listed Subjs Will Be Provided by 850131,per 841128 & 29 Meetings Project stage: Meeting ML20101T6731985-01-25025 January 1985 Forwards Table 5.0.1,omitted from Rept 3 of App R Fire Protection Evaluation,Originally Submitted by Project stage: Other ML20106B5311985-01-25025 January 1985 Advises That Util Will Perform Turbine Load Rejection from Full Load Test at End of Cycle 4.Tech Spec Amend Will Be Submitted Project stage: Other ML20106B5331985-01-31031 January 1985 Forwards Investigation Into Sources of Chloride in Fort St Vrain Primary Circuit. Rept Re Investigations of Effects of Chlorides on Major Components in Primary Circuit Will Be Sent by 850228 Project stage: Other 05000267/LER-1985-001, :on 850126,scram Occurred on Neutron Flux Rate of Change High from wide-range Channels on Scram Channels a & C.Caused by Welding Machine in Close Proximity to Flux Detectors.Weld Machine Turned Off1985-02-25025 February 1985
- on 850126,scram Occurred on Neutron Flux Rate of Change High from wide-range Channels on Scram Channels a & C.Caused by Welding Machine in Close Proximity to Flux Detectors.Weld Machine Turned Off
Project stage: Other 05000267/LER-1984-012-01, :on 841105,reserve Shutdown Hopper of CRD & Orifice Assembly Discharged 40 Lb Reserve Shutdown Matl During Testing.Caused by Formation of Boric Acid Crystals. Absorber Matl to Be Replaced1985-02-28028 February 1985
- on 841105,reserve Shutdown Hopper of CRD & Orifice Assembly Discharged 40 Lb Reserve Shutdown Matl During Testing.Caused by Formation of Boric Acid Crystals. Absorber Matl to Be Replaced
Project stage: Other ML20132G5021985-03-12012 March 1985 Evaluation of CRD Mechanism & Reserve Shutdown Sys Failures & Pcrv Tendon Degradation Issues Prior to Fort St Vrain Restart Project stage: Other ML20112G4631985-03-18018 March 1985 Forwards Ga Technologies,Inc Rept 907838, Investigation Into Sources of Chloride in Fort St Vrain Primary Circuit, Re Effects of Chloride on Major Components in Primary Circuit.Final Review & Clearance to Be Forwarded by 850326 Project stage: Other ML20100H1121985-03-26026 March 1985 Forwards Evaluation of Fort St Vrain Metallic Components Exposed to Primary Coolant Chloride Contamination, Per 850318 Commitment Project stage: Other ML20117M0591985-04-26026 April 1985 Expresses Appreciation for Opportunity to Discuss Quality Aspects of CRD & Orifice Assembly (Crdoa) Refurbishment Program on 850424 in Arlington,Tx.Discusses 850418 Audit to Confirm 18 Crdoas Completed W/High Quality Project stage: Other ML20128Q5231985-05-15015 May 1985 Responds to Re Contradictory Statements Submitted in Three Util Ltrs.Circulator Speed Instruments Not Relied Upon in 10CFR50,App R,Re Fire Protection Evaluation Because of Close Proximity Between Loops Project stage: Other ML20128N3241985-05-17017 May 1985 Informs of Completion of Mod Work to Automate G&J Wall Sprinkler Sys,Per 840817 App R Commitment Project stage: Other ML20132C9781985-05-17017 May 1985 Safety Evaluation Re CRD Instrumentation Project stage: Approval ML20126B6291985-05-20020 May 1985 Responds to Commitment Log Item CL-1055 Re Verification of Operability of Surge Diodes on CRD Brake & Limit Switch Relays.Diodes & Functions Listed.Action Request DCAR-704 Initiated to Provide Relocation of Diodes Project stage: Other ML20127J8221985-06-0707 June 1985 Informs of Acceptability of Devcon 5-minute Epoxy for Use in Cementing Resistance Temp Detector Temp Sensors to CRD Cavity & Motor,Based on Test & Inservice Exposure of Epoxy to High Temps Project stage: Other ML20127K6371985-06-0707 June 1985 Forwards Interim Tech Specs for Control Rods for Use During Plant Startup.Specs Describe Program to Assure Control Rod & Reserve Shutdown Sys Reliability.Operating Limit of 250 F Max on Control Rod Motor Temp Anticipated Project stage: Other ML20127L8851985-06-13013 June 1985 Forwards Results of Engineering Evaluation of Design Changes Introduced in CRD & Orifice Assembly Bearings.Physical Comparison Testing of Original & Replacement Shim Motor Bearings Underway to Establish Operating/Design Margins Project stage: Other ML20127N6951985-06-14014 June 1985 Elaborates on Util Commitments to Listed Plant Activities, Including CRD Mechanism Temp Recording,Requalification, Surveillance & Preventative Maint,Backup Reactor Shutdown Procedure,Tendons & Pcrv Integrity & Electrical Sys Project stage: Other ML20209E8991985-06-25025 June 1985 Discusses Status of CRD & Orificing Assembly (Crdoa) Refurbishment Efforts.First 37 Crdoas Refurbished & Installed.Summary of Design Changes & Test Results Encl Project stage: Other ML20132C9481985-07-0101 July 1985 Evaluation of CRD Orifice Assembly Bearing Rept from Public Svc Co of Co Project stage: Other ML20132E6231985-07-0303 July 1985 Forwards Interim Tech Specs for Reactivity Control Sys.Tech Specs Will Provide Basis for Program to Assure CRD & Reserve Shutdown Sys Reliability.Specs Include Change to Criteria for Insertion of Reserve Shutdown Matl Project stage: Other ML20132D4611985-07-11011 July 1985 Documents 850708 Telcon Re Interim Fire Protection Measures Committed to in or Lee .Fire Watch Frequency Increased.Personnel Will Carry Flashlights at All Times Per Operating Order 85-11,prior to Plant Startup Project stage: Other ML20132C9391985-07-12012 July 1985 Forwards Eg&G 850701 Evaluation of CRD Orifice Assembly Bearing Rept from Public Svc Co of Co, Per Util 850613 Submittal.Installed Bearings Acceptable Replacements for Original Design.Review of 850607 Submittal Also Encl Project stage: Approval ML20133G2641985-07-16016 July 1985 Documents 850715 Telcon Re App R Fire Protection Evaluation Schedule.Util Will Complete Mod Item 4.2 Re Penetration Seals by 850717.Revised Completion Date Allows for Installation of Final Seal,Surveillance Testing & Sign Offs Project stage: Other ML20134E8651985-07-17017 July 1985 Issue 1 to Procedure SR-TE-9-X, Inserted Rod Position Verification Project stage: Other ML20132F0231985-07-19019 July 1985 Forwards Safety Evaluation Re Environ Qualification of Electric Equipment Important to Safety & Authorizes Interim Operation in dry-out Mode at Max 15% of Rated Power,Based on Listed Conditions,Until Technical Review Completed Project stage: Approval ML20132F0721985-07-19019 July 1985 Safety Evaluation Documenting Deficiencies in Licensee Program for Environ Qualification of Electric Equipment Important to Safety.Licensee Response to Generic Ltr 84-24 Inadequate.However,Operation at 15% Power Authorized Project stage: Approval ML20134E8601985-07-31031 July 1985 Forwards Issue 1 to Procedure SR-TE-9-X, Inserted Rod Position Verification, in Response to Concerns Discussed at 850221 Meeting & in Project stage: Meeting 1985-02-25
[Table View] |
Text
r' PUBLIC SERVICE COMPANY OF COLORADO P. O. BOX 84O + DENVER.
COLORADO 80201 h
-a OSCAR R. LEE VICE PRESIDENT July 6, 1984 Fort St. Vrain Unit No. 1 P-84194 Mr. John T. Collins 3@@]QW] h Regional Administrator, Region IV U. S. Nuclear Regulatory Commission e
611 Ryan Plaza Drive, Suite 100 JUL I O 1984 Arlington, TX 76011 j
SUBJECT:
June 25, 1984 Meeting
Dear Mr. Collins:
As discussed during the June 25, 1984 meeting between the NRC and PSC, PSC agreed to submit a response to the NRC concerning the various subjects covered in the meeting. The subjects covered and PSC's responses are as follows:
A.
NRC COMMITMENTS AS A RESULT OF BTP 9.5-1 APPENDIX A REVIEW During our meeting on June 25, 1984 you drew our attention to several items that PSC had committed to in 1978 as a result of the BTP 9.5-1 fire protection review.
The 1978 commitment involved 17 specific items, of which a review since our June 25th meeting confirms that 14 of the 17 items were completed as required.
The three items remaining are: #7, Add a hydraulic oil mist detector above each Hydraulic Power Unit; #8, Add fire detectors in the locations specified on Table 2.0-1.
These detectors will alarm and annunciate in the control room and alarm locally; #10, Provide the capability to fully open building ventilation exhaust dampers (Turbine Building and Access Control Bay) during a fire condition to remove smoke and corrosive gases.
/
8407130332 840706 dO
~
PDR.ADOCK 05000267 D
) D F
PDR
Letter #P-84194 Page 2 A brief history of the three unfinished items, #7, 8 and 10 is as follows:
The project to install items 7 and 8 was well underway in late 1981 and early 1982, i.e. design work was completed and the material was ordered in late 1981, the paperwork authorizing construction being completed in early 1982. Construction actually began in late 1982 with approximately 45% of the work being completed when Engineering had to place a hold on construction.
It was determined, at that time, that the Vendor, Pyrotronics, had discontinued manufacturing the line of equipment we had ordered, but, unfortunately, no one had bothered to notify PSC. Since our design was based on one manufacturer's equipment, Engineering was forced to start over on the project.
The redesign is now complete, new material has been ordered from Kiddie and the paperwork to authorize constr.ction is in the approval cycle. The new material is scheduled for delivery by August 15, 1984.
With this material delivery schedule, the project will be completed and placed in service during October 1984. The equipment purchased and being installed to detect the oil mist (Item #7) was "first of kind" equipment and with all first of kind equipment there is an element of uncertainty when applying it to resolve a specific problem. We should therefore be prepared to expect a period of time during which adjustments and modifications may have to be made to make this equipment reliable.
The construction work associated with Item #10 was completed. The equipment has not been placed in service as the cold checkout and functional tests have not been completed. The personnel responsible for this work have been advised to complete the tests and place this equipment in service during July 1984.
In 1978 when these commitments were made to the NRC, the Nuclear Engineering Division was under different executive management, and for whatever reason, no formal consnitment date or priority for completion of this work was established.
Even though no formal commitment dates were established, PSC has completed 14 of the 17 items within a reasonable time. We have worked on the remaining three items, with varying degrees of success due to setbacks caused by factors beyond our control, indicating that regardless of firm conunitment dates, the commitment to NRC to complete the project has not been overlooked.
As previously stated, Item #10 will be completed this month and Items 7 & 8 will be completed during October 1984.
I must presume this covers the six items you were concerned about and mentioned in our meeting on June 25, 1984.
B.
BUILDING 10 LICENSING REQUIREMENTS The subject of whether Building 10 was properly completed under the provisions of 10 CFR Part 50.59, or whether PSC should have applied for a plant modification license amendment to build Building 10 under the provisions of 10 CFR Part 50.54(f) was discussed.
I subsequently received your letter, John T. Collins to 0. R. Lee, G-84208, dated the day of the meeting, June 25, 1984, requesting a response to this and related issues by July 25, 1984. The requested response is being prepared and will.be submitted by July 25, 1984.
i
Letter #P-84194 Page 3 C.
NRC NOTIFICATION OF CONTROL R0D FAILURE TO SCRAM At our meeting on June 25, 1984, you questioned whether the PSC shift supervisor on duty Saturday morning, June 23, 1984, when six control rod pairs failed to scram, consciously chose not to report the failure of the rod pairs to scram to the NRC.
The PSC shift supervisor did, of course, notify the NRC duty officer of the scram event, including the reactor conditions and the cause of the scram, immediately after completing the actions necessary to safely shutdown the reactor.
During the scram event, the shift supervisor correctly observed that the reactor was shutdown by an adequate margin even with the six rod pairs failing to scram.
Furthermore, the six rod pairs were driven into the reactor core shortly after it was observed that they had failed to properly insert upon receiving the scram signal. All of these immediate actions had been completed by the time the shift supervisor notified the NRC duty officer of the scram event.
My personal review of the circumstances surrounding the actions taken by the PSC shift supervisor during and after the scram event disclosed the following:
1.
Due to the difficulties encountered by the PSC shift supervisor in communicating with the NRC duty officer, who was not familar with HTGR terminology, the actual scram event notification process was extremely arduous.
As a consequence, the notification did not facilitate a detailed and complete understanding of the scram event, and did not cover the failure of the six rod pairs to scram, which by that time had been properly mitigated.
2.
With respect to the failure of the six rod pairs to scram, the PSC shift supervisor made the determination that the situation involved a maintenance problem, and the failure was treated accordingly. Plant Trouble Reports, PTR 6-753 through PTR 6-758, were routinely initiated for each of the six rod drives that failed to scram, and the PTR's were approved by the shift supervisor during the shift.
It should be noted that the NRC's SRI frequently reviews PTR's, a fact known to the shift supervisor. A person consciously attempting to avoid notifying the NRC of a Fort St. Vrain problem would certa. inly not initiate a PTR on the problem.
3.
Subsequent to the scram ever t but prior to the conclusion of the shift, the PSC shift su>ervisor directed the reactor operator to make an entry in the R.0.'s log that it was necessary to manually insert the rods in the six affected regions to get the " rod in" lights. A copy of the log is routinely furnished to the NRC's SRI on a daily basis, a fact also known to the shift supervisor.
A person consciously attempting to avoid notifying the NRC of a Fort St. Vrain problen would certainly not have a log entry made recording the problem.
r Letter #P-84194 Page 4 In conclusion, my review did not disclose that there was any indication of a conscious attempt by the PSC shift supervisor to avoid notifying the NRC of the failure of the six rod pairs to scram.
The reactor scram immediate reporting requirements (in the absence of any Technical Specification violations or continuing conditions that would constitute an unusual event) did not focus on the failure of the six rod pairs to scram, particularly since the rod pairs had been successfully inserted manually. When other PSC management personnel approximately eight hours later became aware that the NRC had not been notified that six rod pairs had failed to scram, it was their judgment that even if notification of the NRC was not explicitly required, in this case NRC notification was warranted.
Consequently, notification of the failure of the six rod pairs to scram was provided to the NRC.
Having the opportunity to reflect on the implications of the circumstances which arose during the scram event, I agree that it would have been better if the PSC shift supervisor had reported the failure of six rod pairs to scram to the NRC duty officer.
D.
DOCUMENTATION OF DISCIPLINARY ACTIONS Regarding the NRC's request to use the documentation of disciplinary actions in personnel records to verify the completion of disciplinary actions, I have contacted our attorney as I indicated I would. He is studying the legal implications of the NRC's request for access to this documentation.
After an initial review, he has asked for additional time to complete his legal review of this matter. Once we have received our attorney's legal advise, I am confident we will be able to reach agreement on a mutually acceptable and legally proper resolution of the NRC's request.
E.
CLEARANCE TAGS In response to your inquiry concerning clearance tags that are several years old, a program has been initiated to ensure the currentness of these tags.
Under this program older tags will be removed and new tags will be placed on the affected equipment.
F.
RADIOLOGICAL EMERGENCY EXERCISE SCENARIO You inquired as to when PSC would be providing the background information for the 1984 Fort St. Vrain Radiological Emergency Exercise.
The required information was provided to Mr. Eric Johnson (NRC) in a letter from Mr. Don Warembourg (PSC), P-84170, dated June 11, 1984. A copy of this letter was also sent directly to Mr. James Montgomery on June 11, 1984.
Letter #P-84194 Page 5 G.
TEMPORARILY INSTALLED CONTROLLER IN LN2 SYSTEM Your mention of the controller, hung with bailing wire, during the June 25, 1984 meeting precipitated a review to determine why this device was installed in 1980, and why it remains in service on a Temporary Change Request (TCR) after four years. The original design of the LN2 storage tank had a Foxboro level control system to automatically transfer LN2 from the outside tanks to the indoor storage / surge tank.
That system failed and our operating personnel installed a replacement system on an emergency basis using the TCR to document and justify the work.
The temporarily installed equipment has been operating satisfactorily. A major project to modify the LN2 system was being considered in 1981 and it was therefore decided to incorporate the temporary change into a permanent modification along with the overall system modification.
The system modification was scheduled to be done during the 3rd refueling.
A great number of equipment changes were involved in the modification of different portions of the LN2 system. As a result of the time and difficulties involved in physically modifying the whole system, it was determined just prior to the third refueling that only a small portion of the system would be modified during this refueling. These limited modifications did not encompass that portion of the LN2 system which included the temporary controller.
PSC Engineering will review the temporary controller and the LN2 system modifications yet to be completed and determine if the system modification to be done during 4th refueling will encompass the temporary controller.
If it does not, we will proceed with a plan to make the temporary controller permanent no later than the 4th refueling.
In the interim, the controller will be more securely mounted.
If you have any questions concerning these responses, please contact either C. H. Fuller at (303) 785-2223 x202, or M. H. Holmes at (303) 571-8409.
Very truly yours,
@/&
- 0. R. Lee, Vice President Electric Production ORL/MHH:km