Forwards Corrected Schedule of Proposed App R Mods Noted in .Mod Re Emergency Lighting Will Be Completed,As Discussed in 860826 Ser,Within 12 Months Following NRC Approval
ML20207E030
Person / Time
Site: Fort Saint Vrain Xcel Energy icon.png
Issue date: 12/29/1986
From: Robert Williams
PUBLIC SERVICE CO. OF COLORADO
To: Berkow H
Office of Nuclear Reactor Regulation
References
P-86677, TAC-54373, NUDOCS 8701020044
Download: ML20207E030 (3)


Text

'

h Public Service-

=%

= _ _

December 29, 1986 Fort St. Vrain R.O. WILLIAMS, JR.

Unit No. 1 fuc[ tan oic"dAnons P-86677 Director of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington,.D. C.

20555 Attn: Mr. H. N. Berkow, Director Standardization and Special Projects Directorate Docket No. 50-267

SUBJECT:

Correction to Construction Schedule for Appendix R Modifications

REFERENCE:

PSC Letter, Williams to Berkow, dated November 20, 1986, (P-86597)

Dear Mr. Berkow:

This correspondence corrects a comment made under the STATUS line of the attachment to the referenced letter.

We inadvertently indicated that the modification regarding the Emergency Lighting (Item l'o. 4.4) would be installed by startup following 4th refueling.

We want to reassure the Commission that this modification will be completed, as discussed in the SER forwarded to us dated August 26, 1986, within 12 months following NRC approval of the PSC proposal.

We apologize for any misunderstanding this may have caused with the Staff.

w If you have any questions, please contact Mr. M. H. Holmes at l

(303)480-6960.

Very truly yours, 07010:0044 061229

/#st/

PDR ADOCK 05000267 F

PDR R. O. Williams, Jr.

/,

f OU Vice President Nuclear Operations

,p R0W/FT:pa Attachment

g y

Attachment to

$.i P-86677 s

SCHEDULE-0F PROPOSED MODIFICATIONS (CORRECTED)

.! TEM

. DESCRIPTION STATUS

'4.1 Fire Doors' Modification Complete 4.2-Penetration Seals Modification Complete 4.3 Fire' Dampers Modification Complete 4.4 Emergency Lighting To be completed by 8/26/87

. 4.5 Fire Detection

-To be completed by 1/87 4.6

'ACM Backfeed Install by.Startup r,

Following 4th Refueling

' Ventilation Damper

' Modification Complete 4.7 Back-up Bottle 4.8 Portable Ventilation Modification Complete Fans 4.9 Turbine Water Removal Install by Startup Pump Following 4th Refueling 4.10 Cable Re-routes (A)

. Reactor Plant Exhaust To be completed by 1/87

-Fan (B)

Bearing Water Make-up To be completed by 1/87 (C)'

Surge Tank Level To be completed by 1/87 Instrumentation (D)

Feedwater Flow To be completed by 1/87 Monitoring i

(E)

'Feedwater Flow To be completed by 1/87 Associated Cables e

o i

l

s '.

g Attachment to 5

P-86677 ITEM DESCRIPTION STATUS (F)

ACM Fuel Oil Transfer To be completed by 1/87 j

Pump 9

-(G)

Helium Flow Instrument Modification Complete j;..

Cables ff.

(G.1)

Helium Flow Instrument Modification Complete Fuses (H).

Main Steam Temperature To be completed by 1/87 Indication (I)

Bearing Water Pumps To be completed by 1/87 (J)

Emergency Water To be completed by 1/87 Booster Pumps 4.11 Valve Operability (A).

Accumulator / Actuator Install by Startup Modification Following 4th Refueling (B)'

Valve Operator Back-up Modification Complete Bottles (C)

Local Control Valve Modification Complete (D)

' Manual-Bypass Modification Canceled (E)

Access Ladders Modification Complete (F)

Valve Tagging Modification Complete 4.12 Service Water Return Modification Complete Pump

- -