O Public Service-

O*;1.,.

P.O. Box 840 Denver, CO 80201- 0840 July 16, 1985 Fort St. Vrain OSCAR R. LEE Unit No. 1 VICE PREslDENT P-85249 7 p.,4 s "} g' LN (

Regional Administrator Region IV U. S. Nuclear Regulatory Commission g 22m 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76011 Attn: Mr. E. H. Johnson J

Docket No. 50-267

SUBJECT:

Appendix R, Fire Protection Evaluation

REFERENCE:

P-85113, PSC Letter, Lee to Johnson, dated 4/1/85, Report No. 4 - Exemptions and Modifications

Dear Mr. Johnson:

This documents a

telephone conversation between PSC and Mr. R. E. Ireland of your staff on July 15, 1985.

As discussed in that conversation, PSC will complete Modification Item 4.2 described in Reference 1, Penetration Seal:,. by July 17, 1985 instead of July 15, 1985 as originally committed. At this time all penetration seals have been installed except one. The revised completion date allows for installation of the final penetration seal, surveillance testing, and final sign offs.

If you have any questions, please contact Mr.

M. H. Holmes at (303) 571-8409.

Very truly yours, hW

0. R. Lee, Vice President Electric Production ORL/FWT:pa g $

g6 (o

0P 1

I 8500080615 850716 f v1 f