ML20083E158

From kanterella
Jump to navigation Jump to search
Final Deficiency Rept Rdc 64(83) Re Pipe Whip Restraint Bracket Welds for B21/B33 Sys.Initially Reported on 821228. All Brackets Removed & Structural Steel Reworked to Original Condition
ML20083E158
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 12/15/1983
From: Edelman M
CLEVELAND ELECTRIC ILLUMINATING CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, RDC-64(83), NUDOCS 8312280483
Download: ML20083E158 (3)


Text

. _ _

s M

  • " n **

7 , ,

(> t y , 1 r . >. 3 P O. box 5000 - CLEVELAND. CHIO 44101 - TELEPHONE (216) 622-9800 - !LLUMINATING BLDG. - 55 PUBLIC SOUARE Serving The Best Location in the Nation MURRAY R. EDELMAN VICE MESIDENT December 15, 1983 NUCMAR Mr. James G. Keppler Regional Administrator, Region III Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137 RE
Perry Nuclear Power Plant Docket Nos. 50-440; 50-441 Pipe Whip Restraint Bracket Welds for B21/B33 Systems [RDC 64(83)]

Dear Mr. Keppler:

This letter serves ac the final report pursuant to 10CFR50.55(e) on the significant deficiency concerning the bracket welds for the Main Steam and Recirculation System Pipe Whip Restraints. This problem was identified to Mr. Pelke of the NRC Region III Of fice of Inspection and Enforcement on Eecember 28, 1982, by Mr. E. Parker for The Cleveland Electric Illuminating Company. This deficiency was formally identified in our first report dated January 26, 1983. Our second report dated April 15, 1983, and third report dated July 1,1983, were submitted to provide additional information on the deficiency.

This report contains a description of the deficiency, an analysis of the safety implications, and the corrective action taken.

Description of Deficiency Visual and Magnetic Particle inspection of the completed welds connecting the pipe whip restraint brackets to the drywell structural steel noted three welds with linear indications. Subsequent investigation into the cause of the Indications identified that the bracket material did not meet the requirements of the applicable welding code and the pre-qualified procedure that was followed.

The pipe whip restraint brackets were supplied by the General Electric Company, San Jose (GE NEBO) with the applicable welding code (AWS) specified in their Installation Specification 22A2598. The brackets were installed by General Electric Apparatus and Engineering Services (CE A&ES) in accordance with their welding procedure, WPS 1.1.8.1, Rev. 3. This procedure is a pre-qualified AWS procedure, however, it was not acceptable for use on the welding of the brackets due to the difference in the thickness of the bracket material and the thickness of material that the procedure was qualified for. Additionally, material verification of the bracket identified that the material is ASTM-A105 which is not a pre-approved material by the AWS Code.

8312280483 831215 gDRADOCK 05000440 PDR 9Q DE.C 7tEL2

A .

December 15, 1983 Mr. Jcmes G. Keppler All forty-eight Recirculation System and thirty-six Main Steam System Pipe Whip Restraint Brackets for a total of eighty-four were Installed prior to the identification of this deficiency. Installation of the eight remaining Main Steam brackets was stopped pending final evaluation.

Analysis of Safety Implications When pleing integrity is lost as a result of the occurrence of a postulated circumferential break, the pipe whip restraints act to limit the movement of the broken pipe to an acceptable distance. Unrestrained novement of the pipe could result in damage to other safety-related components or structures located near the pipe break.

Corrective Action Nonconf ornance report's P038-1347, P038-1346, and P038-1103 were initiated to track the problems identified with the bracket welds. GE NEB 0 addressed the welding problems on Field Deviation Disposition Requests KL1-125, KL1-257, and KL1-294.

GE NEB 0 and GE A&ES performed extensive metallographi * .ing on the bracket welds. The testing concentrated on the brackets from heat J-02159, as all f ailures identified prior to testing related to brackets from this heat. In addition, CEI contracted a local testing lab to perform independent netallographic tests to determine the cause of the weld problem and substantiate the results obtained by GE. The results of the various tests revealed the presence of underbead cracking in the weld heat af fected zones of the brackets from heat J-02159.

Brackets which were not from heat J-02159 were also evaluated using a UT procedure developed by GE NEB 0 to detect the presence of underbead cracking.

Most of the welds for these brackets exhibited UT results similar to those from heat J-02159. Further metallographic testing was performed on the welds to confirm the UT reports and to deternine the ccrrective action necessary for the non-J-02159 heat brackets. The results of this testing Indicated the presence of underbead cracking in most of the welds made on the brackets.

None of the installed brackets were considered acceptable due to the confirmed existence of weld defects or the likelihood that defects exist. All brackets Installed 'were removed and the structural steel they were welded to reworked to its original condition.

Brackets have now been installed as follows:

The eight brackets not previously installed and two new replacement brackets were welded using approved welding procedure WPS 1.1.4.2. The material was qualified for this procedure using an elevated preheat. The results obtained using the procedure were acceptable. The procedure eliminated the underbead cracking, but the logistics involved in preheating such a large mass of base material to a high temperature were prohibitive.

For this reason, a new procedure was qualified.

A. .

Mr. James G. Keppler December 15, 1983 Eighty-two new brackets were installed at their respective locations using an approved welding procedure WPS 1.1.9.4, which also eliminated the underbead cracking. WPS 1.1.9.4 was qualified for ASTM-A105 with preheating of the brackets and base material required. Additionally, the brackets received two layers of weld material to decrease the hardness properties in the heat affected zone.

Testing of the completed welds was performed in accordance with the original MT requirements for acceptance. Nondestructive testing of all welds was completed with no rejectable welds encountered. Review of the associated installation documentation will be completed by February 1,1984.

Additional corrective action taken by CE included a 100% review of their AWS Welding Program in response to Corrective Action Request 82-28. GE A&ES revised all AWS welding procedures for clarity and simplicity to prevent the use of unapproved weld material. The AWS Ceneral Welding Procedure GWP-1005 and Nuclear Quality Assurance Manual used by GE A&ES were also revised to address AWS welding in any identified problem areas. In addition, GE reviewed all AWS welds that were previously completed. These actions were taken to insure that no problems similar to those identified in this deficiency existed and to prevent the recurrence of these problems.

Sincerely, Murray R. delman Vice President Nuclear Group MRE:pab cc: Mr. M. L. Gildner NRC Site Of fice Director Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, D.C. 20555 U.S. Nuclear Regulatory Commission c/o Document Management Branch Washington, D.C. 20555 Records Center, SEE-IN Institute of Nuclear Power Operations 1100 Circle 75 Parkway, Suite 1500 Atlanta, Georgia 30339 i

.. .. . . . .