Second Interim Deficiency Rept Re ASME Code Section III, Class 3 Piping Supports Supplied by Transamerica Delaval, Inc W/O Matl Certification.Initially Reported on 830325. Supports Reanalyzed.Next Rept by 830701
ML20073T107
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 04/29/1983
From: Edelman M
CLEVELAND ELECTRIC ILLUMINATING CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, RDC-67(83), NUDOCS 8305100333
Download: ML20073T107 (2)


Text

r o

^

4 P.O. BOX 5000 - CLEVELAND. OHlo 44101 - TELEPHONE (216) 622-0800 - ILLUM NATING BLDG. - 55 PUBLic SQUARE Semng The Best Location in the Nation MURRAY R. EDELMAN April 29, 1983 VICE PRESIDENT NUCMAR Mr. James G. Keppler Regional Administrator, Region 11I Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137 RE: Perry Nuclear Power Plant Docket Nos. 50-440; 50-441 Piping Supports Supplied by Transamerica Delaval, Inc.

[RDC 67(83)]

Dear Mr. Keppler:

This letter serves as the second interim report pursuant to 10CFR50.55(e) concerning ASME Code Section III, Class 3, piping supports supplied to the Perry Nuclear Power Plant by Transamerica Delaval, Inc. Mr. P. R. Pelke of your office was first notified on February 23, 1983, by Mr. E. Riley of The Cleveland Electric Illuminating Company (CEI) that this problem was being evaluated and an initial report was submitted March 25, 1983.

This report contains a description of the deficiency, of the method planned for status of the evaluation, and the date for submittal of our next report on this subject.

Description of Deficiency Specification 562-4549-00, Section 2:05 Item 3a and Section 2:16 Item 1, require that most piping components are to be built to the ASME Code Section III, Class 3. Transamerica Delaval, contracted under specification 562-4549-00, supplied skid mounted piping supports without material certification and identification as outlined in ASME NF-2130 and NF-2150.

Status of Evaluation Transamerica Delaval is presently reanalyzing their ASME Section III, Class 3, pipe supports and auxiliary skid for compliance to the requirements of Section III Subsection NF of the ASME Boiler and Pressure Vessel Code. Delaval has indicated that this analysis will not be completed until the later part of l May.

0305100333 830429 -

fDR ADOCK 05000440

_./ N 7 l PDR 1

1 MAY 4 G83 1

r

, Mr. Jrmea G. Ksppler April 29, 1983 Upon receipt from Delaval of this analysis The Cleveland Electric Illuminating Company and Transamerica Delaval will identify the needed modifications to upgrade the supports to meet the requirements of ASME Section III, Subsection "NF".

At this time, the full extent of the modification is not known. A follow-up report will be issued by July 1, 1983.

Please call if there are any additional questions.

Sincerely,

& tAA4 ,

Murray R. Edelman Vice President Nuclear Group MRE:pab cc: Mr. M. L. Gildner E/.C Site Office Director Office of Inspection and Enforcement U.S. Nuclear Regulatory Commission Washington, D.C. 20555 U.S. Nuclear Regulatory Commission c/o Document Management Branch Washington, D.C. 20555 Records Center, SEE-IN Institute of Nuclear Power Operations 1100 Circle 75 Parkway, Suite 1500 Atlanta, Georgia 30339 i