|
---|
Category:LICENSEE EVENT REPORT (SEE ALSO AO
MONTHYEARML20024J3201994-10-0707 October 1994 LER 94-022-00:on 940907,TS Violation Occurred Due to Inadequate Fire Watch.Retrained Personnel Associated W/ Painting activities.W/941007 Ltr ML20029E2001994-05-13013 May 1994 LER 94-006-00:on 940414,SS Recognized That Required Frequency for Performing STP 057-3705 Had Been Exceeded. Caused by Inadequate Supervisory Methods.Corrective Action: Inhouse Tracking Process Will Be created.W/940513 Ltr ML20029C8741994-04-26026 April 1994 LER 93-026-01:on 931117,isolation of RCIC Sys Occurred Due to Apparent Failure of Relay.Three Relays Associated W/ Isolation Replaced & Shipped to Mfg for Failure Analysis.W/ 940426 Ltr ML20029C7021994-04-19019 April 1994 LER 90-003-05:on 900206,discovered Deficiencies in Thermo-Lag Fire Barrier Envelope Around Redundant Safe Shutdown.Firewatches Established in Areas Where Thermo Lag Used as barrier.W/940419 Ltr ML20046C3891993-08-0202 August 1993 LER 93-014-00:on 930701,installed Sprinkler Sys as Substitute for Passive fire-rated Barrier Due to Deficiency Identified in Fire Barrier Separation Requirements.Declared Fire Barriers Surrounding Valves degraded.W/930802 Ltr ML20046B8981993-07-29029 July 1993 LER 93-013-00:on 930629,high Pressure Core Spray Pump Failed to Start & Run During Surveillance Test Due to Failed Overfrequency Relay.Relay Tested & Installed in Switchgear. W/930729 Ltr ML20046A2361993-07-22022 July 1993 LER 93-008-01:on 930429,relief Request Improperly Prepared for Insvc Testing Program Results in Noncompliance W/Main Steam Isolation Valve Testing Requirement.Caused by Personnel Error.Testing Frequency Revised ML20045G6111993-07-0202 July 1993 LER 93-012-00:on 930603,deficiency in Plant Surveillance Test Procedures Identified.Caused by Primary Causal Factor Inattention to Detail During Initial Procedure Development Process.Surveillance Test Procedures performed.W/930702 Ltr ML20045D6991993-06-21021 June 1993 LER 93-011-00:on 930521,determined That Mode Switch Placed in Refuel Position During Testing of Switch Interlock Functions.Caused by Conflicting Info in Surveillance Procedures.Operating Procedure revised.W/930621 Ltr ML20045C0141993-06-14014 June 1993 LER 93-010-00:on 930514,SDC Lost for Approx Three Minutes When One SDC Suction Valve Closed Due to Initiation of Spurious ESF Actuation Signal.Caused by Personnel Error. Procedural Guidance revised.W/930614 Ltr ML20045C0021993-06-14014 June 1993 LER 93-003-01:on 930225,incidents Discovered Which Caused Interlock Mechanism in Upper Containment Airlocks at Elevation 171 to Operate Improperly.Case Study Training Class Developed for Airlock incidents.W/930614 Ltr ML20045A1461993-06-0404 June 1993 LER 93-009-00:on 930504,discovered That Surveillance Test Procedure for Control Bldg Chilled Water Sys Quarterly Pump Missed Due to Cognitive Personnel Error.Administrative Procedure Will Be revised.W/930604 Ltr ML20045A4261993-06-0101 June 1993 LER 93-002-02:on 930212,discovered That TS SRs Not Properly Implemented in Logic Sys Functional Tests Due to Inattention to Detail While Preparing Revs of Relevant Surveillance Test Procedures (Stp).Relevant STPs revised.W/930601 Ltr ML20044H3571993-06-0101 June 1993 LER 93-008-00:on 930429,investigation Determined That Relief Request for Inservice Testing of Pumps & Valves in Conflict W/Msiv Testing Requirements.Caused by Personnel Error.Relief Request 40 revised.W/930601 Ltr ML20044G7401993-05-26026 May 1993 LER 93-006-00:on 930419,MSIV Failed to Stroke Closed When Given Close Signal from CR Due to Poppet Sticking.Caused by Insufficient poppet-to-guide Rib Clearance.Stricter Controls Imposed to Control clearances.W/930526 Ltr ML20044F2541993-05-20020 May 1993 LER 93-007-00:on 930420,noted That an Isolation of Inboard & Outboard MSIV & Ms Line Drains Occurred.Caused by Lack of Personnel Knowledge of Unique Maint Conditions.Precaution Will Be Added to Sys Operating procedure.W/930520 Ltr ML20044D8511993-05-17017 May 1993 LER 93-005-00:on 930415,discovered That RCIC Steam Line Flow - High Timer Function Never Performed on Monthly Basis. Caused by Failure to Include Test in Initial Procedure Development Process.Procedures revised.W/930517 Ltr ML20024H2381991-05-21021 May 1991 LER 91-003-01:on 910322,Div II Control Power Circuit Deenergized,Resulting in Deenergization of Charcoal Filter Train Suction Dampers.Caused by Inadequate Work Plan.Plan Revised to Document Restoration of wiring.W/910521 Ltr ML20024G7441991-04-22022 April 1991 LER 91-003-00:on 910322,control Bldg Local Air Intake Radiation Monitor Control Power Circuit Deenergized, Resulting in Isolation of air-operated Dampers.Caused by Inadequate Work Plan.Work Plan revised.W/910422 Ltr ML20024G7181991-04-19019 April 1991 LER 91-004-00:on 910321,RCIC Turbine Main Steam Supply Line Outboard Containment Isolation Valve Isolated.Caused by Negative Trip Setpoint of Trip Unit Being Reached.Caution Added to RCIC Sys Operating procedures.W/910419 Ltr ML20029C1211991-03-14014 March 1991 LER 91-001-00:on 910212,use of Inadequate Control Room Filter Initiation Signal Due to Discrepancies Between Logic Diagrams.Main Control Room Doses Due to MSLB Outside Containment recalculated.W/910314 Ltr ML20029B1341991-02-26026 February 1991 LER 90-033-01:on 901104,RWCU Sys Isolation Occurred While Performing Plant Mod to Power Supply Wiring in Control Room Panel 1H13-P642.Caused by Removal of Terminal Screw.Power Supply reterminated.W/910226 Ltr ML20028H3961990-12-18018 December 1990 LER 90-032-01:on 901021,discovered That Five Snubbers Removed from Standby Svc Water Sys Piping in Violation of Tech Spec 3.7.4.Caused by Scheduling Error & Inadequate Review.Training Will Be Completed on 910331.W/901218 Ltr ML20024F7481990-12-10010 December 1990 LER 90-040-00:on 901110,technician Inadvertently Shorted Relay Terminals,Energizing Relay & Causing Emergency Diesel Generator to Start Unexpectedly.Caused by Personnel Error. Generator Manually secured.W/901210 Ltr ML20044B1951990-07-12012 July 1990 LER 90-003-01:on 900206 to 08,deficiencies Found in thermo-lag Fire Barrier Envelopes Redundant Safe Shutdown Circuits.Fire Watch Established.Util Working W/Vendor to Resolve discrepancies.W/900712 Ltr ML20044A3781990-06-22022 June 1990 LER 90-023-00:on 900523,discovered That Annulus Ventilation Radiation monitor,1RMS*RE11A Inoperable.Caused by Failure of Radiation Monitor Sample Pump & Failure of Switch to Actuate.Flow Switches replaced.W/900622 Ltr ML20043F4721990-06-0808 June 1990 LER 90-021-00:on 900509,RWCU Sys Differential Flow High Trip Instrumentation Inoperable for Period Greater than Allowed by Tech Spec.Caused by Misinterpretation of Tech Spec 3/4.3.2,Table 3.3.2.-1.4.Personnel retrained.W/900608 Ltr ML20043D5831990-06-0101 June 1990 LER 90-020-00:on 900504,radwaste Operator Entered High Radiation Area W/O Dose Rate Meter,Alarming Dosimeter or Radiation Protection Technician Coverage.Caused by Personnel Error.Training Provided to operators.W/900601 Ltr ML20043B8031990-05-24024 May 1990 LER 90-019-00:on 900425,RWCU Sys Isolation & ESF Actuation Occurred After Completion of Channel Check of Riley Temp Trip Unit.Caused by Unit Exceeding Differential Temp Setpoint of 46 F.Unit replaced.W/900524 Ltr ML20043B3301990-05-21021 May 1990 LER 90-017-00:on 900419,inadequate Fire Barrier in Shake Space Occurred Contrary to Tech Spec.Caused by Oversight. Roving Fire Watch Scheduled.Maint Will Rework Voids & Install Seismic Gap seal.W/900521 Ltr ML20043C0281990-05-19019 May 1990 LER 90-018-00:on 900420,ESF Actuation Occurred Causing Reactor Water Sample Containment Isolation Valve to Close. Caused by Failure of Fuse Which Deenergized Isolation Logic of Valves.Fuse replaced.W/900518 Ltr ML20042G7981990-05-10010 May 1990 LER 90-016-00:on 900414,insulator Fault on Local Grid Resulted in Trip of 500 Kv Breaker.Caused by Spurious Alarm Signal from Control Room Local Intake Radiation Monitor 1RMS*RE13B.Sys Returned to Normal operation.W/900510 Ltr ML20042G8001990-05-0909 May 1990 LER 90-015-00:on 900409,loss of Div II Reactor Protection Sys Bus Occurred Due to Trip of Electrical Protection Assembly.Another Trip Also Occurred on 900415.Caused by Faulty Integrated Circuit logics.W/900509 Ltr ML20042G4501990-05-0707 May 1990 LER 90-013-00:on 900405,discovered That Control Bldg Chiller Motor Current Limiter C Set Incorrectly at 56% Instead of 100%.Caused by Incorrect Setting & Maint Activities.Loop Calibr Data Sheet revised.W/900507 Ltr ML20042G4531990-05-0707 May 1990 LER 90-014-00:on 900407,reactor Scram Occurred While Testing Main Turbine Combined Intermediate Valves.Caused by Low Pressure Signal from Emergency Trip Sys of Electrohydraulic Control Sys.Two Solenoid Valves replaced.W/900507 Ltr ML20042F4731990-05-0101 May 1990 LER 90-012-00:on 900401,ESF Actuations Occurred Due to Electrical Protection Assembly Breakers Trip.Caused by Voltage Regulator Failure.Replacement Voltage Regulator Card Installed in MG 1C71-S001B.W/900501 Ltr ML20042E2231990-04-0909 April 1990 LER 90-007-00:on 900311,control Bldg Ventilation Sys Isolated & Filtration Unit Initiated.Caused by Severe Electrical Transient.Performance of Radiation Monitors Improved Prior to Implementation of procedures.W/900409 Ltr ML20012C0741990-03-12012 March 1990 LER 90-004-00:on 900211,Div II Emergency 125-volt Dc Bus Experienced Voltage Spike,Causing Topaz Inverter to Trip & Resulting in Loss of Power to Control Room Panel.Cause Unknown.Setpoint Changes Being evaluated.W/900312 Ltr ML20012C4191990-03-0808 March 1990 LER 90-003-00:on 900206,found That Several Minor Deficiencies Existed in thermo-lag Fire Barrier Envelopes Redundant Safe Shutdown Circuits.Util Currently Working W/ Vendor to Resolve Identified discrepancies.W/900308 Ltr ML20011E2491990-01-31031 January 1990 LER 88-018-04:on 880825,reactor Scram Occurred Due to Main Generator Exciter Brush Failure.Preventive Maint Procedure Revised to Establish Specific Wear Criteria at Which Brushes to Be replaced.W/900131 Ltr ML20011E2461990-01-31031 January 1990 LER 89-036-01:on 891007,discovered That Various motor- Operated Valves Energized,Contrary to Assumptions Contained in Plant Fire Hazards Analysis.Cause Not Stated.Operations Initiated Required Fire Watches on valves.W/900131 Ltr ML20011E1191990-01-30030 January 1990 LER 90-001-00:on 900103,isolation of RCIC Steam Supply Inboard Isolation Valve Occurred During Surveillance Testing of RCIC Sys.Caused by Technician Lifting Wrong Lead,Causing ESF Actuation.Lead Relanded on terminal.W/900130 Ltr ML20011E1181990-01-30030 January 1990 LER 89-033-01:on 890916,loss of Power to Div II 120-volt Ac Distribution Panel Caused auto-start of Standby Gas Treatment & Annulus Mixing Sys,Resulting in ESF Actuations. Caused by Transformer Failure.Valves opened.W/900130 Ltr ML20005G1641990-01-10010 January 1990 LER 89-044-00:on 891211,unplanned ESF Actuation Occurred, Resulting in Isolation of Rcic.Caused by Technician Failing to Perform Steps of Surveillance Test Procedure in Sequence.Div II Isolation Signal reset.W/900110 Ltr ML20005G1661990-01-10010 January 1990 LER 89-045-00:on 891212,Div I Standby Svc Water Pumps Received Automatic Start Signal Due to Spurious Low Svc Water Pressure Signal When Normal Svc Water Pump Secured. Signal Cleared & Sys Restored to Normal lineup.W/900110 Ltr ML20005E8521990-01-0202 January 1990 LER 89-043-00:on 891201.two Outboard MSIVs Inoperable Due to Failure of Corresponding Fast Closure solenoid-operated Valve.Caused by Incomplete Removal of Silicone Lubricant. Lubricant Removed by Application of Acetone.W/900102 Ltr ML20005E8511990-01-0202 January 1990 LER 89-042-01:on 891201,main Turbine Generator Tripped, Resulting in Reactor Scram.Caused by Sensing Fault on Offsite 230 Kv Line.Sys Maint Procedure Being Revised to Include Test of Failed Portion of relay.W/900102 Ltr ML20005E1381989-12-26026 December 1989 LER 89-041-00:on 891125,unplanned ESF Actuation Occurred as Result of Two Leads Shorted Together During Testing of Control Circuitry,Causing Valve Isolation from Suppression Pool.Sys Lineup Restored to Normal position.W/891226 Ltr ML20011D6201989-12-18018 December 1989 LER 89-040-00:on 891117,surveillance Test of Div II Penetration Valve Leakage Control Sys Air Supply Header Pressure Not Performed within Allowable Tolerance.Addl Training of Scheduling Group Will Be provided.W/891218 Ltr ML20011D1371989-12-14014 December 1989 LER 89-039-00:on 891114,discovered That Required post-maint Overall Leak Rate Test on Upper Containment Airlock Not Performed After Replacement of Inflatable Seal.Caused by Personnel Error.Maint Procedure revised.W/891214 Ltr 1994-05-13
[Table view] Category:RO)
MONTHYEARML20024J3201994-10-0707 October 1994 LER 94-022-00:on 940907,TS Violation Occurred Due to Inadequate Fire Watch.Retrained Personnel Associated W/ Painting activities.W/941007 Ltr ML20029E2001994-05-13013 May 1994 LER 94-006-00:on 940414,SS Recognized That Required Frequency for Performing STP 057-3705 Had Been Exceeded. Caused by Inadequate Supervisory Methods.Corrective Action: Inhouse Tracking Process Will Be created.W/940513 Ltr ML20029C8741994-04-26026 April 1994 LER 93-026-01:on 931117,isolation of RCIC Sys Occurred Due to Apparent Failure of Relay.Three Relays Associated W/ Isolation Replaced & Shipped to Mfg for Failure Analysis.W/ 940426 Ltr ML20029C7021994-04-19019 April 1994 LER 90-003-05:on 900206,discovered Deficiencies in Thermo-Lag Fire Barrier Envelope Around Redundant Safe Shutdown.Firewatches Established in Areas Where Thermo Lag Used as barrier.W/940419 Ltr ML20046C3891993-08-0202 August 1993 LER 93-014-00:on 930701,installed Sprinkler Sys as Substitute for Passive fire-rated Barrier Due to Deficiency Identified in Fire Barrier Separation Requirements.Declared Fire Barriers Surrounding Valves degraded.W/930802 Ltr ML20046B8981993-07-29029 July 1993 LER 93-013-00:on 930629,high Pressure Core Spray Pump Failed to Start & Run During Surveillance Test Due to Failed Overfrequency Relay.Relay Tested & Installed in Switchgear. W/930729 Ltr ML20046A2361993-07-22022 July 1993 LER 93-008-01:on 930429,relief Request Improperly Prepared for Insvc Testing Program Results in Noncompliance W/Main Steam Isolation Valve Testing Requirement.Caused by Personnel Error.Testing Frequency Revised ML20045G6111993-07-0202 July 1993 LER 93-012-00:on 930603,deficiency in Plant Surveillance Test Procedures Identified.Caused by Primary Causal Factor Inattention to Detail During Initial Procedure Development Process.Surveillance Test Procedures performed.W/930702 Ltr ML20045D6991993-06-21021 June 1993 LER 93-011-00:on 930521,determined That Mode Switch Placed in Refuel Position During Testing of Switch Interlock Functions.Caused by Conflicting Info in Surveillance Procedures.Operating Procedure revised.W/930621 Ltr ML20045C0141993-06-14014 June 1993 LER 93-010-00:on 930514,SDC Lost for Approx Three Minutes When One SDC Suction Valve Closed Due to Initiation of Spurious ESF Actuation Signal.Caused by Personnel Error. Procedural Guidance revised.W/930614 Ltr ML20045C0021993-06-14014 June 1993 LER 93-003-01:on 930225,incidents Discovered Which Caused Interlock Mechanism in Upper Containment Airlocks at Elevation 171 to Operate Improperly.Case Study Training Class Developed for Airlock incidents.W/930614 Ltr ML20045A1461993-06-0404 June 1993 LER 93-009-00:on 930504,discovered That Surveillance Test Procedure for Control Bldg Chilled Water Sys Quarterly Pump Missed Due to Cognitive Personnel Error.Administrative Procedure Will Be revised.W/930604 Ltr ML20045A4261993-06-0101 June 1993 LER 93-002-02:on 930212,discovered That TS SRs Not Properly Implemented in Logic Sys Functional Tests Due to Inattention to Detail While Preparing Revs of Relevant Surveillance Test Procedures (Stp).Relevant STPs revised.W/930601 Ltr ML20044H3571993-06-0101 June 1993 LER 93-008-00:on 930429,investigation Determined That Relief Request for Inservice Testing of Pumps & Valves in Conflict W/Msiv Testing Requirements.Caused by Personnel Error.Relief Request 40 revised.W/930601 Ltr ML20044G7401993-05-26026 May 1993 LER 93-006-00:on 930419,MSIV Failed to Stroke Closed When Given Close Signal from CR Due to Poppet Sticking.Caused by Insufficient poppet-to-guide Rib Clearance.Stricter Controls Imposed to Control clearances.W/930526 Ltr ML20044F2541993-05-20020 May 1993 LER 93-007-00:on 930420,noted That an Isolation of Inboard & Outboard MSIV & Ms Line Drains Occurred.Caused by Lack of Personnel Knowledge of Unique Maint Conditions.Precaution Will Be Added to Sys Operating procedure.W/930520 Ltr ML20044D8511993-05-17017 May 1993 LER 93-005-00:on 930415,discovered That RCIC Steam Line Flow - High Timer Function Never Performed on Monthly Basis. Caused by Failure to Include Test in Initial Procedure Development Process.Procedures revised.W/930517 Ltr ML20024H2381991-05-21021 May 1991 LER 91-003-01:on 910322,Div II Control Power Circuit Deenergized,Resulting in Deenergization of Charcoal Filter Train Suction Dampers.Caused by Inadequate Work Plan.Plan Revised to Document Restoration of wiring.W/910521 Ltr ML20024G7441991-04-22022 April 1991 LER 91-003-00:on 910322,control Bldg Local Air Intake Radiation Monitor Control Power Circuit Deenergized, Resulting in Isolation of air-operated Dampers.Caused by Inadequate Work Plan.Work Plan revised.W/910422 Ltr ML20024G7181991-04-19019 April 1991 LER 91-004-00:on 910321,RCIC Turbine Main Steam Supply Line Outboard Containment Isolation Valve Isolated.Caused by Negative Trip Setpoint of Trip Unit Being Reached.Caution Added to RCIC Sys Operating procedures.W/910419 Ltr ML20029C1211991-03-14014 March 1991 LER 91-001-00:on 910212,use of Inadequate Control Room Filter Initiation Signal Due to Discrepancies Between Logic Diagrams.Main Control Room Doses Due to MSLB Outside Containment recalculated.W/910314 Ltr ML20029B1341991-02-26026 February 1991 LER 90-033-01:on 901104,RWCU Sys Isolation Occurred While Performing Plant Mod to Power Supply Wiring in Control Room Panel 1H13-P642.Caused by Removal of Terminal Screw.Power Supply reterminated.W/910226 Ltr ML20028H3961990-12-18018 December 1990 LER 90-032-01:on 901021,discovered That Five Snubbers Removed from Standby Svc Water Sys Piping in Violation of Tech Spec 3.7.4.Caused by Scheduling Error & Inadequate Review.Training Will Be Completed on 910331.W/901218 Ltr ML20024F7481990-12-10010 December 1990 LER 90-040-00:on 901110,technician Inadvertently Shorted Relay Terminals,Energizing Relay & Causing Emergency Diesel Generator to Start Unexpectedly.Caused by Personnel Error. Generator Manually secured.W/901210 Ltr ML20044B1951990-07-12012 July 1990 LER 90-003-01:on 900206 to 08,deficiencies Found in thermo-lag Fire Barrier Envelopes Redundant Safe Shutdown Circuits.Fire Watch Established.Util Working W/Vendor to Resolve discrepancies.W/900712 Ltr ML20044A3781990-06-22022 June 1990 LER 90-023-00:on 900523,discovered That Annulus Ventilation Radiation monitor,1RMS*RE11A Inoperable.Caused by Failure of Radiation Monitor Sample Pump & Failure of Switch to Actuate.Flow Switches replaced.W/900622 Ltr ML20043F4721990-06-0808 June 1990 LER 90-021-00:on 900509,RWCU Sys Differential Flow High Trip Instrumentation Inoperable for Period Greater than Allowed by Tech Spec.Caused by Misinterpretation of Tech Spec 3/4.3.2,Table 3.3.2.-1.4.Personnel retrained.W/900608 Ltr ML20043D5831990-06-0101 June 1990 LER 90-020-00:on 900504,radwaste Operator Entered High Radiation Area W/O Dose Rate Meter,Alarming Dosimeter or Radiation Protection Technician Coverage.Caused by Personnel Error.Training Provided to operators.W/900601 Ltr ML20043B8031990-05-24024 May 1990 LER 90-019-00:on 900425,RWCU Sys Isolation & ESF Actuation Occurred After Completion of Channel Check of Riley Temp Trip Unit.Caused by Unit Exceeding Differential Temp Setpoint of 46 F.Unit replaced.W/900524 Ltr ML20043B3301990-05-21021 May 1990 LER 90-017-00:on 900419,inadequate Fire Barrier in Shake Space Occurred Contrary to Tech Spec.Caused by Oversight. Roving Fire Watch Scheduled.Maint Will Rework Voids & Install Seismic Gap seal.W/900521 Ltr ML20043C0281990-05-19019 May 1990 LER 90-018-00:on 900420,ESF Actuation Occurred Causing Reactor Water Sample Containment Isolation Valve to Close. Caused by Failure of Fuse Which Deenergized Isolation Logic of Valves.Fuse replaced.W/900518 Ltr ML20042G7981990-05-10010 May 1990 LER 90-016-00:on 900414,insulator Fault on Local Grid Resulted in Trip of 500 Kv Breaker.Caused by Spurious Alarm Signal from Control Room Local Intake Radiation Monitor 1RMS*RE13B.Sys Returned to Normal operation.W/900510 Ltr ML20042G8001990-05-0909 May 1990 LER 90-015-00:on 900409,loss of Div II Reactor Protection Sys Bus Occurred Due to Trip of Electrical Protection Assembly.Another Trip Also Occurred on 900415.Caused by Faulty Integrated Circuit logics.W/900509 Ltr ML20042G4501990-05-0707 May 1990 LER 90-013-00:on 900405,discovered That Control Bldg Chiller Motor Current Limiter C Set Incorrectly at 56% Instead of 100%.Caused by Incorrect Setting & Maint Activities.Loop Calibr Data Sheet revised.W/900507 Ltr ML20042G4531990-05-0707 May 1990 LER 90-014-00:on 900407,reactor Scram Occurred While Testing Main Turbine Combined Intermediate Valves.Caused by Low Pressure Signal from Emergency Trip Sys of Electrohydraulic Control Sys.Two Solenoid Valves replaced.W/900507 Ltr ML20042F4731990-05-0101 May 1990 LER 90-012-00:on 900401,ESF Actuations Occurred Due to Electrical Protection Assembly Breakers Trip.Caused by Voltage Regulator Failure.Replacement Voltage Regulator Card Installed in MG 1C71-S001B.W/900501 Ltr ML20042E2231990-04-0909 April 1990 LER 90-007-00:on 900311,control Bldg Ventilation Sys Isolated & Filtration Unit Initiated.Caused by Severe Electrical Transient.Performance of Radiation Monitors Improved Prior to Implementation of procedures.W/900409 Ltr ML20012C0741990-03-12012 March 1990 LER 90-004-00:on 900211,Div II Emergency 125-volt Dc Bus Experienced Voltage Spike,Causing Topaz Inverter to Trip & Resulting in Loss of Power to Control Room Panel.Cause Unknown.Setpoint Changes Being evaluated.W/900312 Ltr ML20012C4191990-03-0808 March 1990 LER 90-003-00:on 900206,found That Several Minor Deficiencies Existed in thermo-lag Fire Barrier Envelopes Redundant Safe Shutdown Circuits.Util Currently Working W/ Vendor to Resolve Identified discrepancies.W/900308 Ltr ML20011E2491990-01-31031 January 1990 LER 88-018-04:on 880825,reactor Scram Occurred Due to Main Generator Exciter Brush Failure.Preventive Maint Procedure Revised to Establish Specific Wear Criteria at Which Brushes to Be replaced.W/900131 Ltr ML20011E2461990-01-31031 January 1990 LER 89-036-01:on 891007,discovered That Various motor- Operated Valves Energized,Contrary to Assumptions Contained in Plant Fire Hazards Analysis.Cause Not Stated.Operations Initiated Required Fire Watches on valves.W/900131 Ltr ML20011E1191990-01-30030 January 1990 LER 90-001-00:on 900103,isolation of RCIC Steam Supply Inboard Isolation Valve Occurred During Surveillance Testing of RCIC Sys.Caused by Technician Lifting Wrong Lead,Causing ESF Actuation.Lead Relanded on terminal.W/900130 Ltr ML20011E1181990-01-30030 January 1990 LER 89-033-01:on 890916,loss of Power to Div II 120-volt Ac Distribution Panel Caused auto-start of Standby Gas Treatment & Annulus Mixing Sys,Resulting in ESF Actuations. Caused by Transformer Failure.Valves opened.W/900130 Ltr ML20005G1641990-01-10010 January 1990 LER 89-044-00:on 891211,unplanned ESF Actuation Occurred, Resulting in Isolation of Rcic.Caused by Technician Failing to Perform Steps of Surveillance Test Procedure in Sequence.Div II Isolation Signal reset.W/900110 Ltr ML20005G1661990-01-10010 January 1990 LER 89-045-00:on 891212,Div I Standby Svc Water Pumps Received Automatic Start Signal Due to Spurious Low Svc Water Pressure Signal When Normal Svc Water Pump Secured. Signal Cleared & Sys Restored to Normal lineup.W/900110 Ltr ML20005E8521990-01-0202 January 1990 LER 89-043-00:on 891201.two Outboard MSIVs Inoperable Due to Failure of Corresponding Fast Closure solenoid-operated Valve.Caused by Incomplete Removal of Silicone Lubricant. Lubricant Removed by Application of Acetone.W/900102 Ltr ML20005E8511990-01-0202 January 1990 LER 89-042-01:on 891201,main Turbine Generator Tripped, Resulting in Reactor Scram.Caused by Sensing Fault on Offsite 230 Kv Line.Sys Maint Procedure Being Revised to Include Test of Failed Portion of relay.W/900102 Ltr ML20005E1381989-12-26026 December 1989 LER 89-041-00:on 891125,unplanned ESF Actuation Occurred as Result of Two Leads Shorted Together During Testing of Control Circuitry,Causing Valve Isolation from Suppression Pool.Sys Lineup Restored to Normal position.W/891226 Ltr ML20011D6201989-12-18018 December 1989 LER 89-040-00:on 891117,surveillance Test of Div II Penetration Valve Leakage Control Sys Air Supply Header Pressure Not Performed within Allowable Tolerance.Addl Training of Scheduling Group Will Be provided.W/891218 Ltr ML20011D1371989-12-14014 December 1989 LER 89-039-00:on 891114,discovered That Required post-maint Overall Leak Rate Test on Upper Containment Airlock Not Performed After Replacement of Inflatable Seal.Caused by Personnel Error.Maint Procedure revised.W/891214 Ltr 1994-05-13
[Table view] Category:TEXT-SAFETY REPORT
MONTHYEARRBG-45144, Monthly Operating Rept for Sept 1999 for River Bend Station. with1999-09-30030 September 1999 Monthly Operating Rept for Sept 1999 for River Bend Station. with ML20216G1201999-09-0909 September 1999 Rev 3 to Rbs,Cycle 9 Colr RBG-45110, Monthly Operating Rept for Aug 1999 for River Bend Station, Unit 1.With1999-08-31031 August 1999 Monthly Operating Rept for Aug 1999 for River Bend Station, Unit 1.With RBG-45087, Special Rept:On 990510,LPCI a & LPCS Injected Into Rv for Less than Two Minutes.Caused by Electrical Transient in One of ECCS Power Supplies.Operators Verified Reactor Cavity Level & Closed Injection Valves to Stop Injection1999-08-0606 August 1999 Special Rept:On 990510,LPCI a & LPCS Injected Into Rv for Less than Two Minutes.Caused by Electrical Transient in One of ECCS Power Supplies.Operators Verified Reactor Cavity Level & Closed Injection Valves to Stop Injection ML20210K4721999-08-0303 August 1999 SER Accepting Licensee 180-day Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power-Operated Gate Valves RBG-45091, Monthly Operating Rept for July 1999 for River Bend Station, Unit 1.With1999-07-31031 July 1999 Monthly Operating Rept for July 1999 for River Bend Station, Unit 1.With ML20210C6391999-07-0202 July 1999 Rev 2 to River Bend Station,Cycle 9 Colr RBG-45055, Monthly Operating Rept for June 1999 for River Bend Station, Unit 1.With1999-06-30030 June 1999 Monthly Operating Rept for June 1999 for River Bend Station, Unit 1.With ML20196J8031999-06-24024 June 1999 Rev 1 to Rbs,Cycle 9 Colr RBG-45028, Monthly Operating Rept for May 1999 for River Bend Station, Unit 1.With1999-05-31031 May 1999 Monthly Operating Rept for May 1999 for River Bend Station, Unit 1.With RBG-45016, Monthly Operating Rept for Apr 1999 for River Bend Station, Unit 1.With1999-04-30030 April 1999 Monthly Operating Rept for Apr 1999 for River Bend Station, Unit 1.With ML20206A2111999-04-21021 April 1999 Safety Evaluation Authorizing Pump Relief Request PRR-001 & Valve Relief Request VRR-001 & Denying Valve Relief Request VRR-002 RBG-44969, Monthly Operating Rept for Mar 1999 for River Bend Station, Unit 1.With1999-03-31031 March 1999 Monthly Operating Rept for Mar 1999 for River Bend Station, Unit 1.With ML20205S0601999-03-31031 March 1999 Rept on Status of Public Petitions Under 10CFR2.206 with Status Change from Previous Update,990331 ML20205D5481999-03-26026 March 1999 SER Accepting Util Proposed Alternative to Exam Weld AA with Weld Volume Coverage of 62 Percent for First 10-year Insp Interval Pursuant to 10CFR50.55a(a)(3)(ii) & 10CFR50.55a(g)(6)(ii)(A)(5) RBG-44930, Monthly Operating Rept for Feb 1999 for River Bend Station, Unit 1.With1999-02-28028 February 1999 Monthly Operating Rept for Feb 1999 for River Bend Station, Unit 1.With RBG-44826, Monthly Operating Rept for Dec 1998 for River Bend Station Unit 1.With1998-12-31031 December 1998 Monthly Operating Rept for Dec 1998 for River Bend Station Unit 1.With ML20198K2701998-12-22022 December 1998 Rev 1 to RBS Cycle 8 Colr RBG-44773, Monthly Operating Rept for Nov 1998 for River Bend Station, Unit 1.With1998-11-30030 November 1998 Monthly Operating Rept for Nov 1998 for River Bend Station, Unit 1.With RBG-44727, LER 98-S01-00:on 981021,identified That Contract Employee with Temporary Access Authorization Failed to Disclose Complete Criminal & Employment History.Individual Denied Access to Plants for Five Years.With1998-11-17017 November 1998 LER 98-S01-00:on 981021,identified That Contract Employee with Temporary Access Authorization Failed to Disclose Complete Criminal & Employment History.Individual Denied Access to Plants for Five Years.With ML20195C4841998-11-0606 November 1998 SER Accepting QA Program Change to Consolidate Four Existing QA Programs for Arkansas Nuclear One,Grand Gulf Nuclear Station,River Bend Station & Waterford 3 Steam Electric Station Into Single QA Program ML20155H3491998-11-0303 November 1998 Safety Evaluation Granting Requests for Relief RR2-0001, RR2-0002 & RR2-0003 RBG-44719, Monthly Operating Rept for Oct 1998 for River Bend Station, Unit 1.With1998-10-31031 October 1998 Monthly Operating Rept for Oct 1998 for River Bend Station, Unit 1.With ML20155C1351998-10-26026 October 1998 Rev B to Entergy QA Program Manual RBG-44677, Monthly Operating Rept for Sept 1998 for River Bend Station, Unit 1.With1998-09-30030 September 1998 Monthly Operating Rept for Sept 1998 for River Bend Station, Unit 1.With ML20154E2171998-09-28028 September 1998 Follow-up Part 21 Rept Re Defect with 1200AC & 1200BC Recorders Built Under Westronics 10CFR50 App B Program. Westronics Has Notified Bvps,Ano & RBS & Is Currently Making Arrangements to Implement Design Mods ML20151S5421998-09-0303 September 1998 Safety Evaluation Opposing Licensee Thermal Model as Currently Implemented.Evaluation Recommended to Be Used in Any follow-up Site Insp RBG-44629, Monthly Operating Rept for Aug 1998 for River Bend Station, Unit 1.With1998-08-31031 August 1998 Monthly Operating Rept for Aug 1998 for River Bend Station, Unit 1.With ML20236X2351998-08-0505 August 1998 Part 21 Rept Re Defect Associated W/Westronics 1200AC & 1200BC Recorders Built Under Westronics 10CFR50,App B Program.Beaver Valley,Arkansas Nuclear One & River Bend Station Notified.Design Mod Is Being Developed RBG-44600, Monthly Operating Rept for July 1998 for River Bend Station1998-07-31031 July 1998 Monthly Operating Rept for July 1998 for River Bend Station RBG-44564, Monthly Operating Rept for June 1998 for River Bend Station, Unit 11998-06-30030 June 1998 Monthly Operating Rept for June 1998 for River Bend Station, Unit 1 ML20249A6431998-06-12012 June 1998 SER Accepting 980427 Request for Change to River Bend QA Manual Program Description,Per 10CFR50.54(a)(3) RBG-44539, Monthly Operating Rept for May 1998 for River Bend Station, Unit 11998-05-31031 May 1998 Monthly Operating Rept for May 1998 for River Bend Station, Unit 1 RBG-44501, Monthly Operating Rept for Apr 1998 for River Bend Station, Unit 11998-04-30030 April 1998 Monthly Operating Rept for Apr 1998 for River Bend Station, Unit 1 ML20217M8951998-04-30030 April 1998 QA Program Manual ML20217P8281998-04-0707 April 1998 Safety Evaluation Accepting Relief Authorization for Alternative to Requirements of ASME Section Xi,Subarticle IWA-5250 Bolting Exam for Plants,Per 10CFR50.55a(a)(3)(i) RBG-44458, Monthly Operating Rept for Mar 1998 for River Bend Station, Unit 11998-03-31031 March 1998 Monthly Operating Rept for Mar 1998 for River Bend Station, Unit 1 RBG-44423, Monthly Operating Rept for Feb 1998 for River Bend Station Unit 11998-02-28028 February 1998 Monthly Operating Rept for Feb 1998 for River Bend Station Unit 1 ML20203L6631998-02-11011 February 1998 Rev 0 to River Bend Station,1998 Emergency Preparedness Exercise RBG-44385, Monthly Operating Rept for Jan 1998 for River Bend Station, Unit 11998-01-31031 January 1998 Monthly Operating Rept for Jan 1998 for River Bend Station, Unit 1 RBG-44353, Monthly Operating Rept for Dec 1997 for River Bend Station, Unit 11997-12-31031 December 1997 Monthly Operating Rept for Dec 1997 for River Bend Station, Unit 1 RBG-44460, Forwards Annual Radiological Environmental Operating Rept, for Period Jan-Dec 19971997-12-31031 December 1997 Forwards Annual Radiological Environmental Operating Rept, for Period Jan-Dec 1997 ML20203H9891997-12-12012 December 1997 Part 21 Rept Re Potential Manufacturing Defect of Enterprise DSR-4 & DSRV-4 Edgs.Cooper Energy Svcs Supplied 1A-7840 Adjusting Screw to Affected Utils & Sites.River Bend Station Replaced W/Acceptable Assemblies ML20202E9941997-12-0101 December 1997 ISI Plan Second Ten-Yr Interval (Dec 1,1997-Nov 30,2007) ML20199K9741997-11-30030 November 1997 Brief Aerial Photography Analysis of RBS at St Francisville,LA:1996-1997 RBG-44337, Monthly Operating Rept for Nov 1997 for River Bend Station, Unit 11997-11-30030 November 1997 Monthly Operating Rept for Nov 1997 for River Bend Station, Unit 1 ML20202F0191997-11-28028 November 1997 Safety Evaluation Approving Transfer of License NPF-47 for River Bend Station,Unit 1 ML20199H3711997-11-19019 November 1997 SER Accepting Approving Request Relief from Requirements of Section XI, Rule for Inservice Insp of NPP Components, of ASME for Current or New 10-year Inservice Insp Interval IAW 50.55(a)(3)(i) of 10CFR50 RBG-44295, Monthly Operating Rept for Oct 1997 for River Bend Station Unit 11997-10-31031 October 1997 Monthly Operating Rept for Oct 1997 for River Bend Station Unit 1 RBG-44243, LER 97-S03-00:on 970911,contract Employee Was Granted Temporary Access After Failing to List Prior Employment Termination & Access Denial.Caused by Employee Failure to Provide Accurate Info.Updated Info Re Employee1997-10-13013 October 1997 LER 97-S03-00:on 970911,contract Employee Was Granted Temporary Access After Failing to List Prior Employment Termination & Access Denial.Caused by Employee Failure to Provide Accurate Info.Updated Info Re Employee 1999-09-09
[Table view] |
Text
- _ . - _ . - . . - ._ _ =.
e 4 e s
GULF STATES UTILITIES COMPANY 41vt A ElND STATON POST (WFtCE BGX 220 ST F RANCISVILLE. LOU'5)AN A 7077h A6f A CODE Eb4 C:!b 0094 346 fsf.51 k
June 4, 1993 RBG- 38500 File Nos. G9.5, G9.25.1.3 ,
1 U.S. Nuclear Pegulatory Conunission Document Control Desk Washington, D.C. 20555 i
Gentlemen: !
River Bend Station - Unit 1 '
Docket No. 50-458 Please find enclosed Licensee Event Report No.93-009 for River Bend Station -Unit 1. This repon is submitted pursuant to 10CFR50.73. i Sincerely, i t
J&csnu .-pr J. E. Booker Manager - Safety Assessment and Quality Verification River Bend Nuclear Group '
7t1 9Q Qg t i UJPS/FRC/bCH/JEV/kvm r
t i
b 9306090437 930604 PDR .
ADDCK 05000458 b
S PDR / '
, 1
. cc: U.S. Nuclear Regulatory Commission 611 Ryan Plaza Drive, Suite 400 ,
Arlington, TX 76011 i i
NRC Resident Inspector ,
P.O. Box 1051 St. Francisville, LA 70775 INPO Records Center 700 Galleria Parkway l' Atlanta, GA 30339-5957
\1r. C.R. Oberg Dublic Utility Commission of Texas 7800 Shoal Creek Blvd., Suite 400 North Austin, TX 78757 Department of Environmental Quality Radiation Protection Division P.O. Box 82135 Baton Rouge, LA 70884-2135 ATTN: Administmtor e
i h
f
l l
'tiAC F GH'.P366 U S. NUCL E AR REGULATORY COMMISSION APPROVED BY OMB NO. 3150-0104 EXPIRES 5/31/95
] l l
It I(
LICENSEE EVENT REPORT (LER) % . , , .
o: ,
- e. .. . . . .
n
, : , ,n , - a , ,
..C: >fn e q j 'P.) %m ber Of d,q * ,P F3C & , % T p ;ie b ' ' ', F i t >4 s - 1 s .3 I
} A t ii j f f N A PJ E (1, DOCh.E l NLMBE R I?) OAGE p i!1YLH DEND STATION 05000 158 , of 5 jW W QUAHTERLY IN-SLHVlCL INSPECTION SlJHVEILLANCE FOR CONTHOL HUILDING LCHII. LED WATER PD!D 'D' WAS >!1SSED DUE TO A COGNITIVE H131AN FHROH i LVENT DATE (5) ~~lf L ER NUMDER (6- le DEPORT NUMBER (7) 01HER F ACILITIES INVOLVED (8) l . ,
[ ' '
_' l l 05000
- j , .m 05 0-1 93 l 93 OOD 00 ! 06 01 93 05000
~ OEDE iiRi~~J [THIS REPORT IS SUBMITTED PURSUANT 10 THE REOutREMENTS OF 10 CFR 4: CW cne or motN (11)
MODE (9) ] h < D 4N r: 2J C5 c; 50 75;il : 1 ,) 73 71 m i F pOyjER 7 .:42,oi. su .ut, t .173 3o2) m 73 71 <:,
! LEVEL (10) b
- 4 ;m a '
s 50 :> % y 50 73.a H2."1 M OTHER i
i a 4:f m 13 x 50 73w1 so 73.aicovlent) s s 4 m :: 4t,i', 52 73; . ,
j [
i 50 73 c: i ..n L41 j y jr 4y ~1
[
o 7m2. sc73 w :n >
~
l LICENSE E CONTACT FOR THIS LER (12) j- .m e r , .
! D.N. LORFITG. SUPERVISOH - NUCLEAM LICENSING (501) 381 1157 .a ,
[ COMPLETE ONE LINE FOR E ACH COMPONENT F AILU AE DrSCRIBED IN THIS REPORT (13)
. J . . m -
n i
0, r
i
===-_-.= -
l L_
.n
(
ps
,, Sueu SSiON DATE (15)
IIBSTRACT _ ' 1: - > <e wr > " n , 'E t G e s p:M t term res (16)
At 1800 on May 4,1943, with the reactor in Operational Condition 4 (Cold Shutdown) for planned outage (PO) 43-01, Operations personnel discovered that surveillance test procedure (STPF410-6312. " CONTROL BLDG CHILLED WATER SYSTEM QUARTERLY PUMP j AND VALVE OPERABILITY DIV H" had not been completed for the control building chilled l water pump. HVK"PID, within the required Technical Specification time frame, rendering HVK-P1D inoperable on 4/18/93. The redundant pump HVK*PlB, was already inoperable due to failure of the applicable portion of (STP)-410-6312 on 2/10/93. Therefore, the Division H control building ventilation system (HVK/HVC) was rendered inoperable. Therefore, this report is submitted pursuant to 10CFR50.73(a)(2)(i)(B) as operation prohibited by the Technical Specifications and 10CFR50.73(a)(2)(vii)as an event in which a single cause or condition caused an independent train to become inoperable.
i .
The root cause of this event was a cognitive error in that comments were not properly l
transferred from the STP data package cover sheet to the " green shect." Corrective actions include procedural improvement, briefings for Operations personnel, and revision of
[ Administratis e Procedure ( ADM F0015, " Station Surs eillance Test Prognun" to require including ,
j
{ a copy of the STP data package cover sheet with each " green sheet" with an estimated l p completion date of Julv 31, 1993. pl
- =a
REQUIRED NUMBER OF DIGITS / CHARACTERS FOR EACH BLOCK DLOCK NUMBER OF NUMBER DIGITS / CHARACTERS 1 UP TO 46 FACIUTY NAME DOCKET NUMBER 3 IN ADDITIO TO 05000 3 VAR;ES PAGE NUMBER 4 UP TO 76 TITLE 5 EVENT DATE 2 PER BLOCK 7 TOTAL E LER NUMBER 3 FOR SEQUENTIAL NUMBER 2 FOR REVISION NUMBER 7 R PORT DATE 2P B OCK UP TO 18 -- FACiUTY NAME 8 TOT AL - DOCKET NUMBER CM F ANE NOMD 3 IN ADD l TION TO 05000 9 1 OPERATlNG MODE 10 3 POWER LEVEL
FiEOUtPEVENTS OF 10 CFR CHECK BOX THAT AFPUES g UP TO 50 FOR NAVE 14 FOR TELEPHONE CAUSE VAR;ES 2 FOR SYSTEM 13 4 FOR COVPONENT EACH COMPCNENT FA! LURE 4 FOR MANUFACTURER NPROS VAR'ES
'4 SUPP1 EMENT AL REPORT EXPECTED CHECK BOX THAT APPUES 15 EXPECTED SUBMl$510N DATE 2 PER BL CK
~ ~,g:a .
- = -
NFiC FORM 366A U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB NO. 3150-0104 m EXPIRES 5/31/95
. ESDMATED BURDEN PER RESPONSE TO COMPLY W"H TH S LICENSEE EVENT REPORT (LER) E*TES u REa'ARINEe"ENThA OT IN YT B OH s TEXT CONTINUATION E"EjS $'*u'$$E ey gc, u BB 7 il o,,N ,A THE PAPERWORK REDVCTION PROJECT (31S$0104h OFFICE 08 MANAGD TNT AND BJDGET. WASHLNG TON, DC FJ503 f ACluTY NAME til DOCFfT NUMBER pp LER NUMBER (4) P AGE (3)
SE QJE NLAt RUSON NUVBER NUMBER !
OF RIVER BEND STATION 05000 458 _
93 _ 009 00 2 5 ,
t TLxT tit more spe:e es rewr1 ust 0%ttorw COV*s O'MC f0!m WAt UD REPORTED CONDITION t
.At 1800 on May 4,1993, with the reactor in Operational Condition 4 (Cold Shutdown) for planned outage (PO)-93-01, Operations personnel discovered that surveillance test procedure (STP)-410-6312, " CONTROL BLDG CHILLED WATER SYSTEM Q'UARTERLY PUMP AND VA.LVE OPERABILITY DIV II" had not been completed for the control building ,
chilled water pur.p (*P*), HVK"PlD within the required Technical Specification time frame, rendering HVK*PlD inoperable on 4/18/93. The redundant pump (*P*) HVK*PIB, was already inoperable (reference TR LCO 93-023) due to failure of the applicable portion of (STP)-410-6312 on 2/10/93. Therefore, the Division II control building ventilation system (HVK/HVC) (*VI*) was rendered inoperable. To document the non-compliance with the :
surveillance requirement, this repon is submitted pursuant to 10CFR50.73(a)(2)(i)(B) and -
10CFR50.73(a)(2)(vii) as an event in which a single cause or condition caused an independent train to become inoperable. .
INVESTIGATION The surveillance was determined to be overdue based on the Technical Specification surveillance interval requirement and verification of the date and time of the previous perfonnance. This STP is the quarterly in-service inspection (ISI) test for the Division II control building chilled water pumps (HVK*PIB/PID) and their associated valves. This STP t is required by Technical Specification Surveillance Requirement 4.0.5 which states that >
inservice testing of ASME Code Class 1, 2, and 3 pumps and valves shall be perfonned in accordance with Section XI of the ASME Boiler and Pressure Vessel Code at the surveillance intervals specified in Section XI. In this case, the surveillance interval is at least once every 92 days.
Following discovery, Operations personnel reviewed the Technical Specification requirements ,
under Section 3.7.2, entered the action statement requiring that the Division I control building filter train be opemted in the emergency mode (limiting condition for operation i (LCO)93-170), and initiated a condition report (CR NO. 93-0252) to investigate this event.
The STP was successsfully performed in its entirety by 5/14/93 at 0800.
On 10/30/92 a full perfonnance of STP-410-6312 was successfully completed for both HVK*PIB & PID. A panial perfonnance limited to the HVK"PID ponion was satisfactorily completed on 12/23/92 to verify pump reference values. The next full !
NRO FORu 366A (S 92; U _ _ , . . _ _ _ - - . _ _ _
NhC FORM 366A U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY oMB NO. 3150-0104 m er; EXPIRES 5/31/95 l
. ESTIVATED BJADEN PER RESPONSE TO COVPLY WN TH'S LICENSEE EVENT REPORT (LER) '1"2Es*EGid573RE?S$
c DQ,dv"2 TEXT CONTINUATlON @v"'c "
tai J"c S"o^y'y'ls%"7,5"1$"yT',$'s.,S[$ I THE PA*IRWORK REDUCTION PRCLlECT (3%C104), OFFCE 05 I MANAGEMENT A*JD LJDGET, W ASHINGTON, DC 20503, FA':lLITY NAME (q DOCRET NUMBER (2) LER NUMBER (4) PAGE 13)
SEQ 4NTm EEv$QN NUMBER NUMBER 000 HIVER BEND STATION 458 33 009 -
00 3 5 w m.,c.=,,,,.w.u..m n . m = - m on perfonnance date of the STP was scheduled for completion by 2/22/93. On 2/10/93, the STP was signed in and the portion of the test for HVK*PIB failed. The Shift l Supervisor / Control Opemting Foreman (SS/COF) elected to secure the STP as a partial unsatisfactory perfonnance for HVK*PlB only, declared HVK*PIB inoperable and initiated a tracking limiting condition for operation, TR LCO 93-023, on HVK*PIB. Comments were entered on the data package cover sheet of STP-410-6312 indicating a partial perfonnance and failure of HVK*PIB only. This left HVK*PID untested pending resolution of issues concerning the test methodology.
The SS/COF then filled out the surveillance test scheduling completion / exception fonn l
, (" green sheet") to document the panial perfannance and test exception request for HVK*PIB. The comment contained in the STP data package cover sheet which indicated that only the HVK"PlB ponion had been perfonned and that the test exception being requested was only for HVK*PlB was not transferred to the " green sheet". The " green sheet" is routed to the STP scheduling group for scheduling subsequent STPs and tracking test exceptions. Upon receipt of this " green sheet," the STP scheduling group listed a test i exception for the entire STP (no " comments" to indicate that the exception was for PIB only) against TR LCO 93-023, effectively removing the entire STP from the schedule tracking system with the HVK*PID portion unperfonned. The surveillance for HVK*PID expired with the 25 percent tolerance on 4/17/93 based on the satisfactory perfonnance of 12/23/93; .
however, this condition went undetected due to the erroneous test exception of 2/10/93. A subsequent unrelated review of STP " comments" detected the missed surveillance on 5/4/93.
ROOT CAUSE Based on a task analysis of this event and personnel interviews, the root cause for missing the scheduled perfonnance due date on HVK*PID was a cognitive error that occurred when comments were not properly transferred from the STP data package cover sheet to the " green ,
sheet. " The February 27,1993 surveillance test of main steam line isolation valve (MSIV)
IB21*AOVFO22B was dispositioned as " acceptable with comments" when in fact the valve was stuck. Following this event (ref. LER 93-006), GSU reviewed all current STP perfonnances, for a total of 1200. Out of these STPs, this event (LER 93-009) was the only incorrectly identified test exception discovered as a result of this review. Therefore, GSU i concludes that this is an isolated case of cognitive human error, and is not indicative of a programmatic problem.
AC FORY 3%A fB 92)
I PAC FORM 366A U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB No. 3150-0104 ts s21 EXPIRES 5/31/95
. ES'TMATED BJRDEN PER RESPONSE TO COMPLY W'TH TH'S i
' "'" " I LICENSEE EVENT REPORT (LER) 5 "TENEGATNERDEN $$hAdo"T E JMTm?
E '
TEXT CONTINUATION %Sj$$@S "'*T3 E"'w"MC."rR*d 70AU,%'"
e yo .
THE PAPERWORK REDUCTON PRWECT (3'S3 0104h DFFCE OF !
MANAGEMENT AND BUDGET.WASM:NGTON, DC 20503. I F ACILITY NAME (t) DOCK.ET NUMBER (2) LIR NUMBf R qs) PAGE(4 bEGUENiaAL 8'EV'hCN i YEAR NUMBER NJMBER 05000 OF RIVER BEND STATION 458 93 009 00 4 5 wam - av.c..,.w. w .. - - . a c w m n The event described in LER 93-006, differs signiGcantly from the subject event (LER 93- ,
009). The incorrect disposition of the surveillance on the MSIV resulted from an improper evaluation of the condition of the valve. In the current event, LER 93-009, the test exception was properly indicated on the STP cover sheet but the comments were not I transferred to the " green sheet."
Ll A review of previous LERs revealed a similar event, LER 89-034. In this case, the " green sheet" was not properly 611ed out to indicate a panial perfonnance of the ten-hour run for :
the standby gas treatment system 'A' train under STP-257-0201. When the data was entered into the surveillance test scheduling tracking system (STSTS), the " green sheet" was misinterpreted and the surveillance was updated as a full perfonnance of STP-257-0201. The error was not detected on input, nor during independent verification following input. This resulted in missing the required ten-hour run of the SGTS 'B' train. ;
CORRECTIVE ACTION Administrative Procedure (ADM)-0015, " STATION SURVEILLANCE TEST PROGRAM" has been revised to include a requirement that a copy of the data package cover sheets for all ISI STPs will be transmitted to the STP scheduling group along with the green sheet. This revision also includes clariGcation of requirements and instructions for Hlling out the green ,
sheet emphasizing " partial perfonnances" and " test exception" comment requirements.
In 1989, Operations issued a departmental memo to SS/COFs to provide additional detail and conventions to be used in 611ing out ISI STP green sheets. The content of this memo has t been re-emphasized to the SS/COFs. This memo will be revised to add additional guidance by July 1,1993.
Administrative procedure (ADM)-0015 will be revised to require including a copy of the STP l data package cover sheet with each " green sheet." The estimated completion date for this I revision is July 31, 1993.
All Operations senior reactor operators (SROs) will be briefed on this event and its corrective actions via required reading, estimated to be completed by 8/31/93.
h.4C f DAV 366A (5 92; L
h"RC FORM 366A U.S. NUCLEAR REGULATORY COMMISSION APPROVED BY OMB NO. 3150-0104 3 82: EXPIRES 5/31/95
. ESTIMA7D BsRDEN PER RESPONSE TO COMPLY W:TM TM S INGORMATON COJICTON REQUEST: SC O NPS F ORWARD LICENSEE EVENT REPORT (LER) COMMEN7S REGARDtNG BURDEN ESTWTE TO THE INFORVATON TEXT CONTINUATION AND RECORDS REawoRy couy: MANA,GEMENT sm was-,NoroN,DRANCH oc cm lVNBB,7,7141, ty To U.S NJCL THE PAPERWORK REDUCTON PRajECT (3tSocod) OFFICE OF MANAGEMENT AND BUDGET, W ASMtNGTON, DC 20$03 i
F ACIUTY NAME (1) DOCF ET NUMBE R (2) LER NUMBE R is) PAGE (2)
SEQ JE *.T. A. F<E rbON NUVBER NUVBGR 05000 OF llIVER BEND STATION 458 ~
009
~
00 93 5 5 Tux e,w w.;. v.w.a . .~. cw.w unc u .ve <m Additional enhancements to the program which are under evaluation include the following:
Inclusion of lessons learned from this event in position-specific continuing training for all plant staff personnel responsible for surveillance testing.
Development of an ISI component ID matrix by Opemtions and the STP scheduling ,
group.
1 SAFETY ASSESSMENT :
The purpose of STP-410-6312 is to insure the operability of pumps, HVK*PIB and l HVK*PID by perfonning in-service testing of these components to the ASME Section XI {
Standard within the frequency required by this code. Although HVK*PID was inoperable from 4/17/93 until 5/4/93, without the required actions of Technical Specification 3.7.2 being entered, the satisfactory performance of this same STP on 5/14/93 verified that HVK"PlD was functional during this period of time and was capable of perfonning its intended safety function per design. .
i i
o NRC FOAV 366A (5-92)