Interim Deficiency Rept Re Incomplete Welds at Member Connection Points on Seismic HVAC Hangers.Caused by Contractor Failure to Follow Design Drawings.Constructor to Perform Corrective Action
ML19347C051
Person / Time
Site: Grand Gulf  Entergy icon.png
Issue date: 10/06/1980
From: Mcgaughy J
MISSISSIPPI POWER & LIGHT CO.
To: James O'Reilly
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
References
10CFR-050.55E, 10CFR-50.55E, AECM-80-242, NUDOCS 8010160514
Download: ML19347C051 (2)


Text

- _ - . __ _ _ _ _ _ _ _ _ _ . . _ . _ ___ _ __ _. . ____

i o

j i

i i

, a MISSISSIPPI POWER & LIGHT COMPANY l Helping Buold Alississippi i

4 E P. O. B O X 16 4 0, J A C K S O N, MIS SISSIPPI 39205 OCteber 6, 1980 a

JAMES en=vPvMcGA,UGr*Y, ca anceur A j!

Office'of Inspection & Enforcement U. S. Nuclear Regulatory Ccemission

Region II 101 Marietta Street, N.W.

euite 3100 l Atlanta, Georgia 30303 ,

1

} Attention: Mr. J. P. O'Reilly, Director I

l

Dear Mr. O'Reilly:

},

i SGJECT: Grcnd Gulf Nuclear Statien

] Units 1 and 2 Docket ::os. 50-416/417

'_ Fila C260/15525/15526 I PRD-30/54, Status Report 11,

) H"AC Seicnic Hangers j

AECM-80/242 4

} On September 5,1980, Mississippi Pcver L Light Ccmpcny neti- ,

1 fied Mr. :!. Hunt of your of fice of a Potantially Reportabla Defi- j

cienci (PRD) at the Grand Gulf Nuclear Station (GGNS) constructicn i j site. The deficiency cencerns the failure of the centractor to j 4

follev design drawings for the installation of seismic HVAC hangers.

j The extent and safety implications of this deficiency remain

under investigation. We expect to provide our final report and de- I terminatien of reportability no later than January 15, 1981.  !

]

3 Yours truly,

[p g

%y J. P. McGaughy, Jr.

4 NDH:=t

At tachttent l cc
Mr. N. L. Stampley Mr. R. 3. McGehee Mr. T. 3. Conner 4 \

4 Mr. Victor Stello, Director f Division of Inspecticn 5 Enforcement h' U. S. Nuclear Regulatory Commission l Washington. D.C. 20555 8 01016 06/Y g

c.

1 STATUS REPORT NO. I FOR PRD-80/54 Description l Seismic HVAC hangers at the Grand Culf Nuclear Station (GCSS) were

, found to have ince:plete welds at member connection points. Further investigation revealed missing braces, undersized support members, and hangers that were not welded to the duct. Because of this con-dition, it is possible that the hangers would not perform their in-tended safety function during a SSE.

Apprcach to Resolution of the Deficiency, j This defici
ncy was caused by a contractor who did not follow design drawings. This contractor left the construction site before the de-i' ficiency was identified. MPSL and the constructor are investigating to determine the extent of the deficiency. The criteria described in 2egulatory Guide 1.29 is beinc considered in this investi2ation.

Reportability under 10C7R50.55(e) and 10C7R21 will be determined frca the investigaticn findings. The constructor will perform the necessary I action to correct the noncenforming hangers. These actions tre bein; perforned under 3echtel quality Acticn Request (QAR) F-223.

j Status of Preposed Resolution The investigation to determine the extent of this deficiency is being cenducted.

Reason for Final Report Delay Engineering analysis is ineceplete.

Projected Final Report Submittal Date January 15, 1981 i