Part 21 Rept,Correcting Final Deviation Disposition Request Status Re Unqualified Test Switch.No Changes Planned Since Emergency Buses Found to Have Adequate Separation
ML20135H775
Person / Time
Site: Grand Gulf  Entergy icon.png
Issue date: 09/17/1985
From: Sherwood G
GENERAL ELECTRIC CO.
To: Rossi C
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE)
References
REF-PT21-85, REF-PT21-85-419-000 MFN-114-85, PT21-85-419, PT21-85-419-000, NUDOCS 8509240215
Download: ML20135H775 (1)


Text

GENER AL $ ELECTRIC NUCLEAR ENERGY BUslNEss OPERATIONS GENERAL ELECTRIC COMPANY e 17s CURTNER AVENUE o SAN JOSE, CAUFORNIA 9s12s MC682,(408)925-5040 MFN-114-85 September 17, 1985 U. S. Nuclear Regulatory Commission Office of Inspection and Enforcement Washington, D.C. 20555 Attention: C. E. Rossi Gentlemen:

SUBJECT:

10CFR PART 21, REPORTABLE CONDITION UNQUALIFIED TEST SWITCH -

ADDITIONAL INFORMATION

Reference:

G. G. Sherwood (GE) letter to J. M.' Taylor (NRC), "10CFR Part 21, Reportable Condition Unqualified Test Switch," dated June 17, 1985 The purpose of this letter is to inform you of a change in the FDDR status for

~

Grand Gulf from that given in the referenced letter. Mississippi Power &

Light (MP&L) has informed GE that they have evaluated.the condition documented in the referenced letter and determined that Grand Gulf has adequate sepa-ration from the emergency buses. Based on this evaluation, MP&L will not implement any changes.

Very truly yours, lenn .S rwoo , Manager Nuclear Safety & Licensing Operation GGS: pes /103W Attachment cc: J. M. Taylor J. N. Grace G. G. Zech L. S. Gifford f/1 g,2g2;;tgqg.