Interim Deficiency Rept Re Procurement of Namco Controls Limit Switches,Initially Reported on 810210.Util Will Replace All Limit Switches W/Switches Purchased Directly by Util.Final Deficiency Rept Will Be Provided by 810829
ML19343C113
Person / Time
Site: Perry  FirstEnergy icon.png
Issue date: 02/11/1981
From: Davidson D
CLEVELAND ELECTRIC ILLUMINATING CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
10CFR-050.55E, 10CFR-50.55E, NUDOCS 8102180665
Download: ML19343C113 (2)


Text

9> Wo r -

v c

t l.u D t L t C i n l C I L L u.. ' i l t p G C rJ.....;. t ' 'i n;

n u-r i iu a

.s 2

P o Box 5000 e CLEVELAND. oMto 441C1 e TELEPMCNE (216) 622 9900 e ILLUU.N ATING BLcG, e 55 PUBLIC $ OVA AE Serving The Best Location in the Nation Dahrg1 R. Davidson WCE PRESrcENT SYsTEu ENGENEEneNG ANO co%sTeucTION February ll, 1981 Mr. James G. Keppler Director, Region III Office of Inspection and Enforcement U.S. Nuclear Regulatory Co==ission 799 Roosevelt Road Glen Ellyn, Illinois 60137

Dear Mr. Keppler:

Perry duelear Power Plant Interi= Report on Procurement of NAMCO Controls Li=it Switches This letter is an interi= report as required by 10CFR50.55(e) (3) on NAMCO Controls li=it switches. This proble= was identified to Mr. Landsman of the NRC Region III Office of Inspection and Enforce =ent on February 10, 1981, by Mr. W. J. Kacer of The Cleveland Electric Illu=inating Cc=pany.

Description of Deficiency The Cleveland Electric Illu=inating Co=pany (CEI) awarded pro-curement specifications to various valve vendors for the fabri-cation of equipment to be installed in the Perry Nuclear Power Plant. These specifications required our vendors to procure NAMCO limit switches, Model EA 180 and EA 740 to be installed on so=e of these valves. As a result of an audit conducted by CEI Quality Assurance, it was deter =ined that the overall NAMCO Controls Quality Assurance Progra= vas inadequate in imple=enting require =ents defined by their Quality Assurance Manual, 10CFR50, Appendix 3, and CEI's Quality Assurance require =ents.

Analysis of Safety Implications Without'an adequate Quality Assurance Progra= there is no assur-ance that the product CE1 has received was fabricated the same as the prototype which NAMCO qualified to IEEE 323. Without an effective quality progra= i=ple=ented on the fabrication of the NAMCO li=it switches, CEI cannot place any credibility in NAMCO's

_ Certificate of Co=pliance supplied with the li=it switches.

j3 c>/:P s

/ ()

810218 3 616dr

f N

Mr. James G. Keppler February 11, 1981 Corrective Action In order to rectify this potential problem, CEI will replace all those limit switches which have been procured through vendors from NAMCO with new ones purchased direct by CEI. An addendum to NAMCO's Quality Assurance Program will be imposed upon NAMCO by CEI. This addendum was written by CEI and must be applied to the switches NAMCO will be supplying for this new contract. A Perry Project inspector will be at NAMCO during the entire fabrication to assure CEI Quality requirements will be met.

The questionable limit switches procured from NAMCO by CEI's vendors, to be used in a safety-related application, are being tagged "non-conforming" and placed on hold-to prevent inadvertent use.

These switches will not be used for any safety-related applications.

Based on the receipt of these new limit switches, a final report should be st.b-mitted by August 29, 1981.

Very truly yours, d

W Dal Davidson Vice-President System Engineering and Construction DRD: bas cc: Mr. Jack Hughes NRC Resident inspector, PNPP Director of Inspection and Enforcement l