IR 05000254/2017006

From kanterella
(Redirected from ML18058B594)
Jump to navigation Jump to search
Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2017006; 05000265/2017006)
ML18058B594
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 03/02/2018
From: Karla Stoedter
NRC/RGN-III/DRP/B1
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
Shared Package
ML18057B069 List:
References
IR 2017006
Download: ML18058B594 (7)


Text

UNITED STATES rch 2, 2018

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2 (REPORT 05000254/2017006; 05000265/2017006)

Dear Mr. Hanson:

The NRC has completed its end-of-cycle performance assessment of Quad Cities Nuclear Power Station, Units 1 and 2, reviewing performance indicators (PIs), inspection results and enforcement actions from January 1, 2017, through December 31, 2017. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility. The NRC concluded that overall performance at your facility preserved public health and safety.

The NRC determined the performance at Quad Cities Nuclear Power Station, Units 1 and 2, during the most recent quarter was within the Licensee Response Column (Column 1) of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low safety significance (i.e., Green) and all PIs were within the expected range (i.e., Green).

Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through December 31, 2019. This updated inspection plan now includes planned security inspections which were formerly transmitted under separate correspondence. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last 12 months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.

In addition to baseline inspection, the NRC inspection schedule includes two infrequently performed inspections. The inspections include Inspection Procedure (IP) 60853, On-Site Fabrication of Components and Construction of an ISFSI [Independent Spent Fuel Storage Installation], and IP 60855.1, Operation of an Independent Spent Fuel Storage Installation at Operating Plants. This letter and its enclosure will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.

Please contact me at 630-829-9731 with any questions you have regarding this letter.

Sincerely,

/RA/

Karla Stoedter Chief, Branch 1 Division of Reactor Projects Docket Nos. 50-254; 50-265 License Nos. DPR-29; DPR-30 Enclosure:

Inspection Plan cc: Distribution via LISTSERV