UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 September 1, 2010 Mr. Michael Pacilio Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer (CNO), Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
QUAD CITIES NUCLEAR POWER STATION
Dear Mr. Pacilio:
On August 5, 2010, the NRC staff completed its performance review of the Quad Cities Nuclear Power Station. Our technical staff reviewed performance indicators (PIs) for the most recent quarter and inspection results for the period from July 1, 2009, through June 30, 2010. The purpose of this letter is to inform you of our assessment of your safety performance during this period and our plans for future inspections at your facility.
This performance review and enclosed inspection plan do not include security information.
A separate letter designated and marked as "Official Use Only--Security Information" will include the Security Cornerstone review and resultant inspection plan.
Plant performance for the most recent quarter at the Quad Cities Nuclear Power Station was within the Licensee Response column of the NRC=s Action Matrix, based on all inspection findings being classified as having very low safety significance (Green) and all PIs indicating performance at a level requiring no additional NRC oversight (Green). Therefore, we plan to conduct reactor oversight process (ROP) baseline inspections at your facility.
The enclosed inspection plan details the inspections, less those related to physical protection, scheduled through December 31, 2011. The inspections scheduled include: independent spent fuel storage installation, post approval license renewal, component design basis, initial and requalification licensed operator examinations, emergency preparedness, and outage related inspections. The inspection plan is provided to allow for the resolution of any scheduling conflicts and personnel availability issues well in advance of inspector arrival onsite. Routine resident inspections are not listed due to their ongoing and continuous nature. The inspections in the last 9 months of the inspection plan are tentative and may be revised at the end-of-cycle review.
M. Pacilio In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (630) 829-9703 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Mark A. Ring, Chief Branch 1 Division of Reactor Projects Docket Nos. 50-254; 50-265 License Nos. DPR-29; DPR-30
Enclosure:
Quad Cities Nuclear Power Station Inspection/Activity Plan cc w/encl:
Distribution via ListServ
M. Pacilio In accordance with 10 CFR 2.390 of the NRC=s ARules of Practice,@ a copy of this letter and its enclosure will be made available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Website at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
If circumstances arise which cause us to change the inspection plan, we will contact you to discuss the change as soon as possible. Please contact me at (630) 829-9703 with any questions you may have regarding this letter or the inspection plan.
Sincerely,
/RA/
Mark A. Ring, Chief Branch 1 Division of Reactor Projects Docket Nos. 50-254; 50-265 License Nos. DPR-29; DPR-30
Enclosure:
Quad Cities Nuclear Power Station Inspection/Activity Plan cc w/encl:
Distribution via ListServ DOCUMENT NAME: G:\\Branch TSS\\ALL MOC\\midcycle 2010 to 2011\\midcycle letters\\Quad Cities MOC Letter.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII E
NAME MRing:dtp:cs DATE 08/24/10 OFFICIAL RECORD COPY
Letter to M. Pacilio from M. Ring dated September 1, 2010
SUBJECT:
MID-CYCLE PERFORMANCE REVIEW AND INSPECTION PLAN -
QUAD CITIES NUCLEAR POWER STATION DISTRIBUTION:
Susan Bagley RidsNrrDorlLpl3-2 RidsNrrPMQuad Cities RidsNrrDirsIpab Resource Steven Reynolds Steven Orth Jared Heck Allan Barker DRPIII DRSIII Patricia Buckley Tammy Tomczak ROPreports Resource
Inspection / Activity Plan 09/01/2010 - 12/31/2011 Planned Dates Start End Inspection Activity Title No. of Staff on Site Quad Cities ISFSI
- ISFSI INSPECTION - SCHEDULE DEPENDENT 2
IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 09/01/2010 09/30/2010 BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
IP Radiological Hazard Assessment and Exposure Controls 71124.01 09/27/2010 10/01/2010 IP Occupational Dose Assessment 71124.04 09/27/2010 10/01/2010 IP Reactor Coolant System Activity 71151-BI01 09/27/2010 10/01/2010 BI EP
- EP EXERCISE INSPECTION / PI VERIFICATION 3
IP Exercise Evaluation 7111401 11/15/2010 11/19/2010 IP Drill/Exercise Performance 71151-EP01 11/15/2010 11/19/2010 IP ERO Drill Participation 71151-EP02 11/15/2010 11/19/2010 IP Alert & Notification System 71151-EP03 11/15/2010 11/19/2010 BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 12/06/2010 12/10/2010 IP RETS/ODCM Radiological Effluent 71151-PR01 12/06/2010 12/10/2010 BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
IP Verification of Licensee Responses to NRC Requirement for Inventories of Materials Tracked in NSTS 2515/179 03/14/2011 03/18/2011 IP Radiation Monitoring Instrumentation 71124.05 03/14/2011 03/18/2011 RENEWAL
- LICENSE RENEWAL 71003 - PHASE 1 - U1 2
IP Post-Approval Site Inspection for License Renewal 71003 05/09/2011 06/04/2011 OL PREP
- QUAD CITIES INIT PREP - 05/2011 3
OL - INITIAL EXAM - MAY/JUN 2011 - QUAD W90225 05/02/2011 05/06/2011 BI ENG
- INSERVICE INSPECTION - UNIT 1 1
IP Inservice Inspection Activities - BWR 7111108G 05/09/2011 06/09/2011 BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
IP Radiological Hazard Assessment and Exposure Controls 71124.01 05/16/2011 05/20/2011 IP Occupational ALARA Planning and Controls 71124.02 05/16/2011 05/20/2011 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 05/16/2011 05/20/2011 IP Occupational Exposure Control Effectiveness 71151-OR01 05/16/2011 05/20/2011 OL EXAM
- QUAD CITIES INIT EXAM - MAY-JUNE/2011 3
OL - INITIAL EXAM - MAY/JUN 2011 - QUAD W90225 05/30/2011 06/10/2011 ISFSI
- ISFSI INSPECTION - SCHEDULE DEPENDENT 2
IP Operation of an Independent Spent Fuel Storage Installation at Operating Plants 60855.1 07/01/2011 07/31/2011 BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 08/15/2011 08/19/2011
Inspection / Activity Plan 09/01/2010 - 12/31/2011 Planned Dates Start End Inspection Activity Title No. of Staff on Site Quad Cities BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
IP Reactor Coolant System Activity 71151-BI01 08/15/2011 08/19/2011 BI ENG
- COMPONENT DESIGN BASES INSPECTION 7
IP Managing Gas Accumulation In Emergency Core Cooling, Decay Heat Removal & Containment Spray System 2515/177 09/19/2011 10/21/2011 IP Component Design Bases Inspection 7111121 09/19/2011 10/21/2011 BI RP
- RADIATION PROTECTION BASELINE INSPECTION 1
IP Radiological Hazard Assessment and Exposure Controls 71124.01 10/03/2011 10/07/2011 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 10/03/2011 10/07/2011 IP RETS/ODCM Radiological Effluent 71151-PR01 10/03/2011 10/07/2011 BI EP
- EP ROUTINE INSPECTION / PI VERIFICATION 2
IP Alert and Notification System Testing 7111402 10/24/2011 10/28/2011 IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 10/24/2011 10/28/2011 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 10/24/2011 10/28/2011 IP Drill/Exercise Performance 71151-EP01 10/24/2011 10/28/2011 IP ERO Drill Participation 71151-EP02 10/24/2011 10/28/2011 IP Alert & Notification System 71151-EP03 10/24/2011 10/28/2011 BI OL
- BIENNIAL REQUAL PROGRAM INSPECTION 2
IP Licensed Operator Requalification Program 7111111B 10/24/2011 10/28/2011