Notification of NRC RFI for Post-Approval Site Inspection for License Renewal Phase IV Inspection Report 05000254/2022010 05000265/2022010
ML22228A103
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 08/16/2022
From: Matthew Domke
NRC/RGN-III/DRS/EB1
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
References
IR 2022010
Download: ML22228A103 (6)


See also: IR 05000254/2022010

Text

August 16, 2022

Mr. David P. Rhoades

Senior Vice President

Constellation Energy Generation, LLC

President and Chief Nuclear Officer (CNO)

Constellation Nuclear

4300 Winfield Road

Warrenville, IL 60555

SUBJECT: QUAD CITIES NUCLEAR GENERATINGNOTIFICATION OF NRC REQUEST

FOR INFORMATION FOR POST-APPROVAL SITE INSPECTION FOR LICENSE

RENEWALPHASE IV; INSPECTION REPORT 05000254/2022010;

05000265/2022010

Dear Mr. Rhoades:

On November 14, 2022, the U.S. Nuclear Regulatory Commission (NRC) will begin an

inspection in accordance with Inspection Procedure 71003 (Phase IV). This onsite inspection is

scheduled to be performed November 14, 2022 through November 18, 2022.

The purpose of the inspection is to review the implementation of the Aging Management

Program (AMP) elements during the Period of Extended Operation. The inspection team will

select for review a sample of the sites AMPs.

This Request for Information is separated into three Sections (A, B and C). Section A

information will be used to facilitate the AMP sample selections. The team leader will make

AMP selections and inform the licensee. Based on these selections, the licensee will provide

the additional information requested under Section B. This information will be used as part of

the inspection preparation and implementation. Requests under Section C should be available

to the inspectors during the on-site week of inspection. See the table below for specific dates:

Requested Action: Date:

Section A Information October 3, 2022

Section B Information October 17, 2022

Section C Information November 14, 2022

Experience has shown that this inspection is resource intensive both for the NRC inspector and

your staff. In order to minimize the impact to your onsite resources, and to ensure a productive

inspection for both sides, we have enclosed a request for documents needed for this inspection.

It is important that all of these documents are up-to-date, and complete, in order to minimize the

number of additional documents requested during the preparation and/or the onsite portion of

the inspection.

D. Rhoades -2-

We understand that our regulatory contact for this inspection will be Mr. R. Swart of your

organization. If there are any questions about this inspection or the material requested, please

contact the lead inspector Matthew Domke at 630-829-9562.

This letter does not contain new or amended information collection requirements subject

to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information

collection requirements were approved by the Office of Management and Budget, Control

Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget Control

Number.

This letter and its enclosure will be made available for public inspection and copying at

http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in

accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections,

Exemptions, Requests for Withholding.

Sincerely,

Signed by Domke, Matthew

on 08/16/22

Matthew Domke, Reactor Inspector

Engineering Branch 1

Division of Reactor Safety

Docket Nos. 50-254, 50-265

License Nos. DPR-29, DPR-30

Enclosure:

Document Request for License Renewal

Phase IV Inspection

cc: Distribution via LISTSERV

D. Rhoades -3-

Letter to David P. Rhoades from Matthew Domke dated August 16, 2022.

SUBJECT: QUAD CITIES NUCLEAR GENERATINGNOTIFICATION OF NRC REQUEST

FOR INFORMATION FOR POST-APPROVAL SITE INSPECTION FOR LICENSE

RENEWALPHASE IV; INSPECTION REPORT 05000254/2022010;

05000265/2022010

DISTRIBUTION:

Jessie Quichocho

Lou McKown

RidsNrrDorlLpl3

RidsNrrPMQuadCities Resource

RidsNrrDroIrib Resource

John Giessner

Mohammed Shuaibi

Diana Betancourt-Roldan

Allan Barker

DRPIII

DRSIII

ADAMS Accession Number: ML22228A103

Publicly Available Non-Publicly Available Sensitive Non-Sensitive

OFFICE RIII

NAME MDomke:mb

DATE 08/16/2022

OFFICIAL RECORD COPY

QUAD CITIES NUCLEAR GENERATING STATION-REQUEST FOR INFORMATION

FOR THE UPCOMING POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL

(PHASE IV)

Inspection Procedure: IP 71003, Post-Approval Site Inspection for License Renewal

(Phase IV)

Inspection Dates: November 14-18, 2022 (on-site)

Inspection Report: 05000254/2022010 and 05000265/2022010

Lead Inspector: Matthew Domke, Reactor Inspector

On November 14, 2022, the U.S. Nuclear Regulatory Commission (NRC) will begin a Post-

Approval Site Inspection for License Renewal (Phase IV) at Quad Cities Nuclear Generating

Station. The purpose of the inspection is to review the implementation of the aging

management program elements during the Period of Extended Operation (PEO). The

inspection team will select for review a sample of the sites Aging Management Programs

(AMPs).

This Request for Information (RFI) is separated into three Sections, A, B, and C. Inspectors will

refine selections from Section A so that the licensee can provide additional information

requested under Section B. This information will be used as part of the inspection preparation

and implementation. Requests under Section C should be available to the inspectors during the

on-site inspection week.

Requested Action: Date:

Section A Information October 3, 2022

Section B Information October 17, 2022

Section C Information November 14, 2022

A. Information Requested to Facilitate AMP Sample Selection

(1) Provide a list of all site AMPs.

(2) Provide copies of corporate and/or site-specific program document/procedure related

to overall aging management program.

(3) Provide list of AMPs that were new or enhanced in the License Renewal Application

(LRA).

(4) Provide list of AMPs that had commitment changes since entering the PEO.

(5) Provide list of AMPs that have incorporated newly identified structures, systems, and

components (SSCs) since entering the PEO. List or describe which SSCs were

incorporated.

(6) Provide list of AMPs that have incorporated components from One-Time Inspection

activities since entering the PEO.

Enclosure

(7) Provide any self-assessments and/or audits related to license renewal program

implementation and/or AMP effectiveness.

(8) Provide a list of corrective action documents that were initiated as result of license

renewal activities, self-assessments, and/or audits (since entering the PEO).

(9) Electronic copies of Updated Final Safety Analysis Report, Technical Specifications,

Technical Specifications Bases, Technical Requirements Manual, and Individual Plant

Examination of External Events (IPEEE).

(10) Site-specific responses and/or evaluations for NRC generic communications

associated with license renewal that were issued after entering the PEO.

(11) Risk-ranking of top 250 basic events from your internal and external events

site-specific probabilistic safety analysis (PSA) sorted by Birnbaum Importance,

Risk-Reduction Worth, Risk-Achievement Worth, and Fussell-Vesely (Provide in Excel

format). Please include basic event names/description.

(12) Provide a list of the top 10 risk important systems for the internal events model and

external events model.

B. Information Requested for Each AMP Selected for Review (As Applicable)

(1) Program basis documents and administrative procedures describing key program

attributes such as program objectives, scope, detection and monitoring methods,

administrative controls, acceptance criteria, corrective actions, and scope expansion

requirements.

(2) Provide a summary document listing which implementing procedures are included in

the selected AMP and what are their required performance frequency.

(3) Copies of implementing procedures for program activities (e.g., visual examination

procedures, ultrasonic examination procedures, maintenance procedures, system

walkdowns, etc.)

(4) Completed Work Orders (WOs) for the most recent aging management activities

performed, including associated inspection and testing reports, as applicable. This

request is limited to the last two completed activities (per procedure). If this request

becomes too onerous based on the number of WO reach out to the lead inspector for

additional scope clarification.

(5) Copies of aging related corrective actions documents associated with the selected

AMP, and SSCs under its purview (for the last three years). A search of corrective

actions documents should include keywords such as: aging, age management,

degradation, wear, delamination, peeling, crazing, chipping, leak, crack,

corrosion, rust, leaching, embrittlement, fatigue, blister, spalling, oxidation,

loss of function, failed acceptance criteria, flow-accelerated, or other site-specific

terms/codes used in aging monitoring as appropriate.

(6) Updated license renewal scoping drawings showing the SSCs within the scope of the

AMP.

2

(7) Any gap analyses performed to assess the differences between the current AMP and

the recommendations in the latest revision of NUREG-1801, Generic Aging Lessons

Learned (GALL), and subsequent Interim Staff Guidance.

(8) Copy of evaluations performed for applicable external and internal operating

experience (OE) issues associated with license renewal. This request is limited to OE

items issued after entering the PEO.

(9) Description of instances where examination scope expansion was required based on

the examination of an SSC in accordance with the AMP. Please describe the logic to

select the scope expansion, and any resulting changes to the AMP. (This request is

limited to work performed in the PEO.)

(10) Description of instances where AMP examinations/inspections were eliminated or

deferred. (This request is limited to work performed in the PEO.)

(11) Description of instances where examination/inspection scope changes were required

based on limitations encountered during the examination. (This request is limited to

work performed in the PEO.)

C. Information Requested to be Available During the Onsite Week of Inspection

(1) Provide a brief presentation (informal) to the inspection team regarding aging

management at the site. Topics to be covered:

a. How are aging related issue identified, documented and evaluated within the

corrective action program and/or other aging tracking software/program.

b. Describe which individuals and/or organizations are responsible for identifying

and evaluating aging related issues.

c. Describe the responsibilities regarding age management, if any, of the following:

i. System/Strategic Engineers

ii. AMP Owners

iii. Corporate office

(2) Copy of simplified system drawings (a.k.a. Horse Notes or Training Notes).

(3) A computer with network access to the sites corrective action program.

3