Category:CORRESPONDENCE-LETTERS
MONTHYEARPLA-5120, Forwards Change J to SSES Security Training & Qualification Plan.Without Encl1999-10-22022 October 1999 Forwards Change J to SSES Security Training & Qualification Plan.Without Encl ML18040B2951999-09-0808 September 1999 Requests Info Re Any NRC or Susquehanna Documented Concerns with MSIV Reliability Prior to Plant Trip & Assurance to Public That NRC Able to Detect Mgt Problems Early PLA-5094, Forwards,For Review,Change 00 to SSES Physical Security Plan.Without Encl1999-08-24024 August 1999 Forwards,For Review,Change 00 to SSES Physical Security Plan.Without Encl ML18040A9741999-07-0808 July 1999 Forwards Rev 30 to SSES Emergency Plan, Adding EAL to Account for Potential Conditions Associated with Dry Cask Storage Sys Being Installed at Plant ML20207G5051999-06-0707 June 1999 Informs That NRC Office of NRR Reorganized Effective 990328.As Part of Reorganization,Divison of Licensing Project Management Created PLA-5072, Forwards Change Nn to SSES Physical Security Plan.Util Determined That Changes Do Not Decrease Safeguards Effectiveness of Plan,Per 10CFR50.54(p).Encl Withheld from Public Disclosure,Per 10CFR73.211999-06-0404 June 1999 Forwards Change Nn to SSES Physical Security Plan.Util Determined That Changes Do Not Decrease Safeguards Effectiveness of Plan,Per 10CFR50.54(p).Encl Withheld from Public Disclosure,Per 10CFR73.21 ML18040A9731999-05-24024 May 1999 Submits Response to RAI Re Exemption from Biennial Exercise Schedule.Changing of Drill Date Will Not Reduce Level of Emergency Preparedness at Plant ML20195B2181999-05-20020 May 1999 Forwards Proprietary Decommissioning Status Rept for 10% Interest in Sses,Units 1 & 2.Proprietary Info Withheld,Per 10CFR2.790 ML18040B2901999-04-30030 April 1999 Forwards Summary Rept of Safety Evaluations Approved During Period from 961024-981029,per 10CFR50.59(b).Format of Rept, Listed PLA-5041, Forwards Proprietary & Redacted Decommissioning Rept of Financial Assurance for Util 90% Interest in Sses,Units 1 & 2,per 10CFR50.75(f)(1).Proprietary Info Withheld,Per 10CFR2.7901999-03-29029 March 1999 Forwards Proprietary & Redacted Decommissioning Rept of Financial Assurance for Util 90% Interest in Sses,Units 1 & 2,per 10CFR50.75(f)(1).Proprietary Info Withheld,Per 10CFR2.790 ML18040A9691999-03-12012 March 1999 Forwards Revised Proposed Amend 227 to License NPF-14, Proposing Changes to ANFB-10 Critical Power Correlation & MCPR Safety Limits ML17164A9891999-03-12012 March 1999 Informs That Util 990312 Ltr (PLA-5040) Submitted to NRC, Missing Encl C.Requests to Replace Package in Entirety with Encl ML18040A9721999-03-11011 March 1999 Requests That Date for full-participation SSES Exercise, Scheduled for Week of 991115,be Changed Due to FEMA Region III Scheduling Conflicts.Fema Requests That Exercise Date Be Changed to Week of 001031 PLA-4852, Forwards non-redacted Version of Pp&L,Inc Corporate Auditing Rept 739459-2-98,dated 980210.Informs That Document Contains Info to Be Withheld IAW 10CFR2.7901999-02-18018 February 1999 Forwards non-redacted Version of Pp&L,Inc Corporate Auditing Rept 739459-2-98,dated 980210.Informs That Document Contains Info to Be Withheld IAW 10CFR2.790 ML20203G5821999-02-17017 February 1999 Second Final Response to FOIA Request for Documents. Documents Listed in App C Being Released in Entirety. Documents Listed in App D Being Withheld in Part (Ref FOIA Exemption 5) ML20202F4761999-01-29029 January 1999 First Partial Response to FOIA Request for Documents.Records in App a Encl & Being Released in Entirety.App B Records Being Withheld in Part (Ref FOIA Exemption 7C) ML18040A9671999-01-29029 January 1999 Notifies That Util Implemented Severe Accident Mgt Strategy in Accordance with Ltr Dtd 950327.Emegency Plan Revs Which Were Required to Implement Strategy Were Submitted by Ltr Dtd 981125 ML18040A9681999-01-29029 January 1999 Requests Exemption from Requirements of 10CFR50 App E,Items IVF.2.b & C,To Allowed to Reschedule Federally Observed Full Participation Emergency Exercise for SSES from Wk of 991115 to Wk of 001031 ML18040A9651999-01-12012 January 1999 Submits Addl Info Re Proposed Amend 184 to License NPF-22 for ANFB-10 Critical Power Correlation & MCPR Safety Limits ML18030A1021998-12-16016 December 1998 Forwards Tables as Requested During 981202 Telcon Re Proposed Amend 184,dtd 980804,re ANFB-10 Critical Power Correlation & MCPR Safety Limits.Tables Provide Roadmap Identifying Applicability of References to TSs ML18030A4331998-11-25025 November 1998 Forwards Rev 29 to SSES Emergecny Plan.Changes Has Been Made Without Commission Approval as It Does Not Decrease Effectiveness of Plan & Plan as Changed Continues to Satisfy Applicable Requirements of App E to 10CFR50 ML20195J9101998-11-18018 November 1998 Forwards Notice of Withdrawal of Application for Amends to Facility Operating Licenses (Notice).Notice Has Been Filed with Ofc of Fr.Amends Would Have Revised TS to Eliminate HPCI Pump auto-transfer on High Suppression Pool Level ML20155F7201998-11-0303 November 1998 Final Response to FOIA Request for Documents.Documents Listed in App B Being Encl & Being Released in Entirety. Documents Listed in App C Being Withheld in Part (Ref Exemption 7C) ML18026A2941998-10-19019 October 1998 Forwards SSES ISI Outage Summary Rept for Unit 1 Tenth Refueling & Insp Outage ML18030A4321998-10-12012 October 1998 Forwards Rev 28 to SSES Emergency Plan, IAW Requirements of 10CFR50.54q.Change Is Summarized PLA-4993, Forwards Change Mm to SSES Physical Security Plan.Encl Withheld,Per 10CFR73.211998-10-12012 October 1998 Forwards Change Mm to SSES Physical Security Plan.Encl Withheld,Per 10CFR73.21 ML18030A1001998-10-12012 October 1998 Forwards Rev 27 to SSES Emergency Plan. Changes Become Effective Upon Implementation of Improved Tech Specs ML18030A4311998-09-29029 September 1998 Forwards Rev 27 & 28 to SSES Emergency Plan ML20151W4951998-09-10010 September 1998 Informs That as Part of NRC Probabilistic Risk Assessment Implementation Plan,Commission Assigned Two Senior Reactor Analysts (Sras) to Each Regional Ofc.T Shedlosky & J Trapp Has Been Assigned SRAs for Region I IR 05000387/19980081998-09-0808 September 1998 Provides Response to Violations Noted in Insp Repts 50-387/98-08 & 50-388/98-08.Corrective Actions:Current Administrative Controls on Fuel Level in EDG Day Tanks Will Remain in Effect Until TS Change is Approved ML18030A0991998-09-0808 September 1998 Provides Response to Violations Noted in Insp Repts 50-387/98-08 & 50-388/98-08.Corrective Actions:Current Administrative Controls on Fuel Level in EDG Day Tanks Will Remain in Effect Until TS Change Is Approved ML18026A4961998-08-31031 August 1998 Responds to NRC 980731 Ltr Re Violations Noted in Insp Repts 50-387/98-03 & 50-388/98-03.Corrective Actions:Procurement & Affected User Group Personnel Visited EDG Vendor Facilities to Appraise Vendor Work Practices & Discuss Expectations IR 05000387/19980031998-08-31031 August 1998 Responds to NRC 980731 Ltr Re Violations Noted in Insp Repts 50-387/98-03 & 50-388/98-03.Corrective Actions:Procurement & Affected User Group Personnel Visited EDG Vendor Facilities to Appraise Vendor Work Practices & Discuss Expectations ML20202F5501998-07-17017 July 1998 Responds to PP&L Corp Auditing Repts 739459-97,739459-1-97 & 739459-2-98 Re SSES Investigations Into Missed Alarm Tests ML20236P9451998-07-15015 July 1998 Forwards Emergency Response Data Sys Implementation Documents Including Data Point Library Updates for Oconee (Number 255),Dresden (Number 257) & Susquehanna (Number 258) ML18030A4291998-07-0808 July 1998 Forwards Final Version of SSES TS Implementing Improved TS of NUREG-1433.Implementation of Proposed Amend Is Predicted on NRC Issuance of Amends & Proposed to Not Exceed 90 Days from Date of Amend Issue ML18017A2181998-07-0808 July 1998 Forwards Final Version of SSES TS Implementing Improved Tech Specs of NUREG 1433.Implementation of Proposed Amend Is Predicated on NRC Issuance of Amends & Is Proposed to Not Exceed 90 Days from Date of Amend Issuance ML18026A2901998-06-0909 June 1998 Forwards Rev 26 to Emergency Plan IAW 10CFR50.54q.Summary of Changes Listed ML18026A2891998-05-22022 May 1998 Submits Withdrawal of Expedited Review/Approval of Tech Specs/Bases 3/4.3.7.11 & 3/4.11.2.6 & Response to Request for Addl Info Re Offgas Sys Mods ML18026A4941998-05-12012 May 1998 Responds to NRC Request to Resubmit Proposal to Change TS for Plant,Units 1 & 2,to Support Implementation of Improved TS & to Implement Provisions of GL 86-10 Re Relocation of Plant'S Fire Protection Program from TS to Another Document ML20202H1331998-04-16016 April 1998 Partially Deleted Ltr Re Concerns Raised to NRC Concerning PP&L Susquehanna Facility NUREG-0619, Informs That Staff Finds PP&L 980330 Request for Relief from Requirements of Section 4.3 of NUREG-0619,exams of Feedwater Nozzle Bore & Inner Radius for Another Operating Cycle to Be Acceptable1998-04-15015 April 1998 Informs That Staff Finds PP&L 980330 Request for Relief from Requirements of Section 4.3 of NUREG-0619,exams of Feedwater Nozzle Bore & Inner Radius for Another Operating Cycle to Be Acceptable ML20216B6811998-04-0101 April 1998 First Partial Response to FOIA Request for Documents. Forwards Documents Listed in App a Being Released in Entirety ML17159A2341998-03-30030 March 1998 Forwards LER 97-007-01,per 10CFR50.73(a)(2)(i)(B).Revised LER Submitted to Modify Previous Position W/Regards to Entry Into TS 3.0.3 for Event PLA-4865, Forwards Listed non-redacted Pp&L,Inc Corporate Auditing Repts.Informs That Document Contains Info to Be Withheld IAW 10CFR2.7901998-03-11011 March 1998 Forwards Listed non-redacted Pp&L,Inc Corporate Auditing Repts.Informs That Document Contains Info to Be Withheld IAW 10CFR2.790 ML17159A1781998-03-0202 March 1998 Forwards Proposed Amends 203 & 161 to License NPF-14 & NPF-22,revising Tech Specs to Be Consistent w/NUREG-1433,rev 1, Std Tech Specs for GE Plants,Bwr 4. PLA-4856, Forwards Proposed Amends to Licenses NPF-14 & NPF-22, Revising TS to Be Consistent w/NUREG-1433,rev 1, Std TS for GE Plants,Bwr 4. Proposed TS Consistent w/NUREG-1433,rev 1, Encl1998-03-0202 March 1998 Forwards Proposed Amends to Licenses NPF-14 & NPF-22, Revising TS to Be Consistent w/NUREG-1433,rev 1, Std TS for GE Plants,Bwr 4. Proposed TS Consistent w/NUREG-1433,rev 1, Encl PLA-4854, Provides Summary of Investigations That PP&L Performed in Response to Concerns Identified by Former Nuclear Plant Operator.Summary Requested by Cj Anderson on 9802131998-02-27027 February 1998 Provides Summary of Investigations That PP&L Performed in Response to Concerns Identified by Former Nuclear Plant Operator.Summary Requested by Cj Anderson on 980213 ML20203M5071998-02-26026 February 1998 Final Response to FOIA Request for Documents.Records in App a Being Placed in PDR & Encl.Records in App B Partially Withheld (Ref FOIA Exemption 6) ML20203B5931998-02-23023 February 1998 Ack Receipt of & Wire in Amount of $55,000 in Payment for Civil Penatly Proposed by NRC Ltr . Corrective Actions Will Be Examined During Future Inspections 1999-09-08
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARPLA-5120, Forwards Change J to SSES Security Training & Qualification Plan.Without Encl1999-10-22022 October 1999 Forwards Change J to SSES Security Training & Qualification Plan.Without Encl ML18040B2951999-09-0808 September 1999 Requests Info Re Any NRC or Susquehanna Documented Concerns with MSIV Reliability Prior to Plant Trip & Assurance to Public That NRC Able to Detect Mgt Problems Early PLA-5094, Forwards,For Review,Change 00 to SSES Physical Security Plan.Without Encl1999-08-24024 August 1999 Forwards,For Review,Change 00 to SSES Physical Security Plan.Without Encl ML18040A9741999-07-0808 July 1999 Forwards Rev 30 to SSES Emergency Plan, Adding EAL to Account for Potential Conditions Associated with Dry Cask Storage Sys Being Installed at Plant PLA-5072, Forwards Change Nn to SSES Physical Security Plan.Util Determined That Changes Do Not Decrease Safeguards Effectiveness of Plan,Per 10CFR50.54(p).Encl Withheld from Public Disclosure,Per 10CFR73.211999-06-0404 June 1999 Forwards Change Nn to SSES Physical Security Plan.Util Determined That Changes Do Not Decrease Safeguards Effectiveness of Plan,Per 10CFR50.54(p).Encl Withheld from Public Disclosure,Per 10CFR73.21 ML18040A9731999-05-24024 May 1999 Submits Response to RAI Re Exemption from Biennial Exercise Schedule.Changing of Drill Date Will Not Reduce Level of Emergency Preparedness at Plant ML20195B2181999-05-20020 May 1999 Forwards Proprietary Decommissioning Status Rept for 10% Interest in Sses,Units 1 & 2.Proprietary Info Withheld,Per 10CFR2.790 ML18040B2901999-04-30030 April 1999 Forwards Summary Rept of Safety Evaluations Approved During Period from 961024-981029,per 10CFR50.59(b).Format of Rept, Listed PLA-5041, Forwards Proprietary & Redacted Decommissioning Rept of Financial Assurance for Util 90% Interest in Sses,Units 1 & 2,per 10CFR50.75(f)(1).Proprietary Info Withheld,Per 10CFR2.7901999-03-29029 March 1999 Forwards Proprietary & Redacted Decommissioning Rept of Financial Assurance for Util 90% Interest in Sses,Units 1 & 2,per 10CFR50.75(f)(1).Proprietary Info Withheld,Per 10CFR2.790 ML17164A9891999-03-12012 March 1999 Informs That Util 990312 Ltr (PLA-5040) Submitted to NRC, Missing Encl C.Requests to Replace Package in Entirety with Encl ML18040A9691999-03-12012 March 1999 Forwards Revised Proposed Amend 227 to License NPF-14, Proposing Changes to ANFB-10 Critical Power Correlation & MCPR Safety Limits ML18040A9721999-03-11011 March 1999 Requests That Date for full-participation SSES Exercise, Scheduled for Week of 991115,be Changed Due to FEMA Region III Scheduling Conflicts.Fema Requests That Exercise Date Be Changed to Week of 001031 PLA-4852, Forwards non-redacted Version of Pp&L,Inc Corporate Auditing Rept 739459-2-98,dated 980210.Informs That Document Contains Info to Be Withheld IAW 10CFR2.7901999-02-18018 February 1999 Forwards non-redacted Version of Pp&L,Inc Corporate Auditing Rept 739459-2-98,dated 980210.Informs That Document Contains Info to Be Withheld IAW 10CFR2.790 ML18040A9681999-01-29029 January 1999 Requests Exemption from Requirements of 10CFR50 App E,Items IVF.2.b & C,To Allowed to Reschedule Federally Observed Full Participation Emergency Exercise for SSES from Wk of 991115 to Wk of 001031 ML18040A9671999-01-29029 January 1999 Notifies That Util Implemented Severe Accident Mgt Strategy in Accordance with Ltr Dtd 950327.Emegency Plan Revs Which Were Required to Implement Strategy Were Submitted by Ltr Dtd 981125 ML18040A9651999-01-12012 January 1999 Submits Addl Info Re Proposed Amend 184 to License NPF-22 for ANFB-10 Critical Power Correlation & MCPR Safety Limits ML18030A1021998-12-16016 December 1998 Forwards Tables as Requested During 981202 Telcon Re Proposed Amend 184,dtd 980804,re ANFB-10 Critical Power Correlation & MCPR Safety Limits.Tables Provide Roadmap Identifying Applicability of References to TSs ML18030A4331998-11-25025 November 1998 Forwards Rev 29 to SSES Emergecny Plan.Changes Has Been Made Without Commission Approval as It Does Not Decrease Effectiveness of Plan & Plan as Changed Continues to Satisfy Applicable Requirements of App E to 10CFR50 ML18026A2941998-10-19019 October 1998 Forwards SSES ISI Outage Summary Rept for Unit 1 Tenth Refueling & Insp Outage ML18030A4321998-10-12012 October 1998 Forwards Rev 28 to SSES Emergency Plan, IAW Requirements of 10CFR50.54q.Change Is Summarized ML18030A1001998-10-12012 October 1998 Forwards Rev 27 to SSES Emergency Plan. Changes Become Effective Upon Implementation of Improved Tech Specs PLA-4993, Forwards Change Mm to SSES Physical Security Plan.Encl Withheld,Per 10CFR73.211998-10-12012 October 1998 Forwards Change Mm to SSES Physical Security Plan.Encl Withheld,Per 10CFR73.21 ML18030A4311998-09-29029 September 1998 Forwards Rev 27 & 28 to SSES Emergency Plan ML18030A0991998-09-0808 September 1998 Provides Response to Violations Noted in Insp Repts 50-387/98-08 & 50-388/98-08.Corrective Actions:Current Administrative Controls on Fuel Level in EDG Day Tanks Will Remain in Effect Until TS Change Is Approved IR 05000387/19980081998-09-0808 September 1998 Provides Response to Violations Noted in Insp Repts 50-387/98-08 & 50-388/98-08.Corrective Actions:Current Administrative Controls on Fuel Level in EDG Day Tanks Will Remain in Effect Until TS Change is Approved ML18026A4961998-08-31031 August 1998 Responds to NRC 980731 Ltr Re Violations Noted in Insp Repts 50-387/98-03 & 50-388/98-03.Corrective Actions:Procurement & Affected User Group Personnel Visited EDG Vendor Facilities to Appraise Vendor Work Practices & Discuss Expectations IR 05000387/19980031998-08-31031 August 1998 Responds to NRC 980731 Ltr Re Violations Noted in Insp Repts 50-387/98-03 & 50-388/98-03.Corrective Actions:Procurement & Affected User Group Personnel Visited EDG Vendor Facilities to Appraise Vendor Work Practices & Discuss Expectations ML18017A2181998-07-0808 July 1998 Forwards Final Version of SSES TS Implementing Improved Tech Specs of NUREG 1433.Implementation of Proposed Amend Is Predicated on NRC Issuance of Amends & Is Proposed to Not Exceed 90 Days from Date of Amend Issuance ML18030A4291998-07-0808 July 1998 Forwards Final Version of SSES TS Implementing Improved TS of NUREG-1433.Implementation of Proposed Amend Is Predicted on NRC Issuance of Amends & Proposed to Not Exceed 90 Days from Date of Amend Issue ML18026A2901998-06-0909 June 1998 Forwards Rev 26 to Emergency Plan IAW 10CFR50.54q.Summary of Changes Listed ML18026A2891998-05-22022 May 1998 Submits Withdrawal of Expedited Review/Approval of Tech Specs/Bases 3/4.3.7.11 & 3/4.11.2.6 & Response to Request for Addl Info Re Offgas Sys Mods ML18026A4941998-05-12012 May 1998 Responds to NRC Request to Resubmit Proposal to Change TS for Plant,Units 1 & 2,to Support Implementation of Improved TS & to Implement Provisions of GL 86-10 Re Relocation of Plant'S Fire Protection Program from TS to Another Document ML17159A2341998-03-30030 March 1998 Forwards LER 97-007-01,per 10CFR50.73(a)(2)(i)(B).Revised LER Submitted to Modify Previous Position W/Regards to Entry Into TS 3.0.3 for Event PLA-4865, Forwards Listed non-redacted Pp&L,Inc Corporate Auditing Repts.Informs That Document Contains Info to Be Withheld IAW 10CFR2.7901998-03-11011 March 1998 Forwards Listed non-redacted Pp&L,Inc Corporate Auditing Repts.Informs That Document Contains Info to Be Withheld IAW 10CFR2.790 PLA-4856, Forwards Proposed Amends to Licenses NPF-14 & NPF-22, Revising TS to Be Consistent w/NUREG-1433,rev 1, Std TS for GE Plants,Bwr 4. Proposed TS Consistent w/NUREG-1433,rev 1, Encl1998-03-0202 March 1998 Forwards Proposed Amends to Licenses NPF-14 & NPF-22, Revising TS to Be Consistent w/NUREG-1433,rev 1, Std TS for GE Plants,Bwr 4. Proposed TS Consistent w/NUREG-1433,rev 1, Encl ML17159A1781998-03-0202 March 1998 Forwards Proposed Amends 203 & 161 to License NPF-14 & NPF-22,revising Tech Specs to Be Consistent w/NUREG-1433,rev 1, Std Tech Specs for GE Plants,Bwr 4. PLA-4854, Provides Summary of Investigations That PP&L Performed in Response to Concerns Identified by Former Nuclear Plant Operator.Summary Requested by Cj Anderson on 9802131998-02-27027 February 1998 Provides Summary of Investigations That PP&L Performed in Response to Concerns Identified by Former Nuclear Plant Operator.Summary Requested by Cj Anderson on 980213 ML20216B7031998-02-22022 February 1998 Partially Deleted Ltr Requesting Copy of OI Rept on Plant, Unit 2,case 1-96-039 PLA-4851, Provides Info That Was Requested by Cj Anderson on 980213 Re Former Util Employee Concern on Radwaste Control Room Offgas Panel Alarm Testing1998-02-18018 February 1998 Provides Info That Was Requested by Cj Anderson on 980213 Re Former Util Employee Concern on Radwaste Control Room Offgas Panel Alarm Testing ML20203M5791998-02-10010 February 1998 Enters Appeal Due to Lack of Response to FOIA Request 97-473 ML18030A0971998-02-0202 February 1998 Forwards Proprietary Response to RAI Re Proposed License Amend 209 to TS Supporting Cycle 11 Reload.Proprietary Info Withheld,Per 10CFR2.790 ML20203G6071998-01-26026 January 1998 Forwards Redacted Version of Pp&L,Inc Corporate Auditings Interim Rept 739459-97,dtd 971015 & Affidavit Pursuant to 10CFR2.790 Justifying That Redacted Portions Be Withheld from Public Disclosure.Without Rept IR 05000387/19970031998-01-0606 January 1998 Provides Updated Response to Violations Noted in Insp Repts 50-387/97-03 & 50-388/97-03.Corrective Actions:Util Currently Scheduling Issuance of All Procedural Revs by End of First Quarter 1998 ML18017A2931998-01-0606 January 1998 Provides Responses to Improved TS Section 3.8 Per 970324 NRC Rai.Schedule 980628 for Improved TS Implementation. Submittal of Revised Specifications Is Planned for Jan 1998 ML18030A4071998-01-0606 January 1998 Provides Updated Response to Violations Noted in Insp Repts 50-387/97-03 & 50-388/97-03.Corrective Actions:Util Currently Scheduling Issuance of All Procedural Revs by End of First Quarter 1998 PLA-4828, Expresses Appreciation for Support Received by Former Project Manager C Poslusny1997-12-29029 December 1997 Expresses Appreciation for Support Received by Former Project Manager C Poslusny IR 05000387/19970041997-12-22022 December 1997 Resolves Commitments Made in Response to NOV Issued As Part of NRC Insp Repts 50-387/97-04 & 50-388/97-04 Dtd 970805. Proposed FSAR QA Program Description Changes,Reason for Changes & Basis Included for Approval ML18026A4901997-12-22022 December 1997 Resolves Commitments Made in Response to NOV Issued as Part of NRC Insp Repts 50-387/97-04 & 50-388/97-04 Dtd 970805. Proposed FSAR QA Program Description Changes,Reason for Changes & Basis Included for Approval ML20203M5741997-12-0505 December 1997 FOIA Request for Copy of Latest OI Rept on Susquehanna Ses Including All Exhibits & for Any Other Communication Between NRC & Susquehanna Ses/Pp&L PLA-4818, Forwards Redacted Version of Pp&L,Inc Corporate Auditings Rept 739459-1-97,dtd 971201 & Affidavit Pursuant to 10CFR2.790 Justifying That Redacted Portions Be Withheld from Public Disclosure.Without Rept1997-12-0404 December 1997 Forwards Redacted Version of Pp&L,Inc Corporate Auditings Rept 739459-1-97,dtd 971201 & Affidavit Pursuant to 10CFR2.790 Justifying That Redacted Portions Be Withheld from Public Disclosure.Without Rept 1999-09-08
[Table view] Category:UTILITY TO NRC
MONTHYEARML18026A3941990-09-0101 September 1990 Requests Waiver of Compliance from Tech Spec 3.8.1.1 to Evaluate Increase in Action from 72 H to 15 Days Re Ac Sources Based on 900829 Borescopic Insp of Emergency Diesel Generator ML17157A2741990-08-0808 August 1990 Forwards Topical Rept PL-NF-90-001, Application of Reactor Analysis Methods for BWR Design & Analysis. IR 05000387/19900801990-08-0303 August 1990 Responds to Violations Noted in Insp Repts 50-387/90-80 & 50-388/90-80.Corrective Actions:Util Conducted Operator Training on How to Implement Eops If Suppression Chamber Pressure Not Available ML18030A0741990-08-0303 August 1990 Responds to Violations Noted in Insp Repts 50-387/90-80 & 50-388/90-80.Corrective Actions:Util Conducted Operator Training on How to Implement EOPs If Suppression Chamber Pressure Not Available ML18026A2351990-07-0202 July 1990 Forwards Application for Proposed Amend 132 to License NPF-14,revising Tech Spec to Support Cycle 6 Reload ML18030A0721990-06-19019 June 1990 Forwards Rev 1 to SEA-EE-183, Evaluation of Unit 1 Computer Class 1E - Non-Class 1E Interfaces & Rev 1 to SEA-EE-184, Evaluation of Unit 1 Annunciator Class 1E - Non-Class 1E Interfaces. ML18026A3931990-06-0707 June 1990 Requests NRC Approval to Install Mod at Plant Determined to Constitute Unreviewed Safety Question When Evaluated.Util Will Implement Administrative Controls to Ensure Larger Min Vol Met for Diesel E Prior to Tech Spec Change ML18030A3671990-05-14014 May 1990 Forwards Proprietary Conclusions of Investigation Re Two False Negative Analytical Results from Two Blind Spike Urine Samples.Investigation Satisfactorily Evaluated Samples. Encl Withheld (Ref 10CFR2.790) ML20043A2461990-05-11011 May 1990 Forwards Draft of Proposed Decommissioning Financial Assurance Plan,Per 10CFR50.33 & 50.75,for Review.Telcon Scheduled for 900515 to Discuss Comments ML18030A0711990-03-19019 March 1990 Responds to Questions Delineated in 900131 Ltr Re Diesel Generator Events That Occurred During Sept & Oct 1989.Draft Procedures for Proposed Intake Air Temp Test Program Transmitted to NRC on 900205.Revised Procedures Encl ML18017A1871990-02-15015 February 1990 Forwards Books 1 & 2 to, Unit 2 Third Refueling & Insp Outage;Outage Summary Rept. IR 05000387/19890331990-02-0505 February 1990 Responds to NRC 900105 Ltr Re Violations Noted in Insp Repts 50-387/89-33 & 50-388/89-31.Corrective Actions:Rhr Svc Water Pump 2P506B Remains in Inoperable Status Until Cause of Deviation Determined & Condition Corrected ML18030A0701990-02-0505 February 1990 Responds to NRC 900105 Ltr Re Violations Noted in Insp Repts 50-387/89-33 & 50-388/89-31.Corrective Actions:Rhr Svc Water Pump 2P506B Remains in Inoperable Status Until Cause of Deviation Determined & Condition Corrected ML18040A9601990-02-0202 February 1990 Forwards Schedules That Provide Details of Tasks Required to Complete Activities Re Diesel Generators & Advises of Plan to Have Spare Parts on Site in Timely Manner to Support Each Diesel Insp ML20006B4501990-01-25025 January 1990 Forwards Preliminary Scope & Schedule for Security Upgrade Project.Encl Withheld (Ref 10CFR73.21) ML17156B6031990-01-25025 January 1990 Forwards NPDES Discharge Monitoring Rept for Dec 1989 & State of Pa,Dept of Environ Resources Monthly Facility Rept Form (01-112).Noncompliances for Zinc on Cooling Tower Blowdown on 891228 & for Missed Sample Noted ML18040B2671990-01-0505 January 1990 Forwards Rev 0 to SEA-CW-037, Analysis of B & C 1989 Diesels Failure. Rept Details Util Analysis of Overpressurization Incidents Which Occurred in Sept & Oct 1989 of Diesel Generators ML18040B2651989-11-27027 November 1989 Forwards Response to Generic Ltr 89-21.Table of USIs for Which Technical Resolution Has Been Achieved Encl ML19325F1991989-11-0909 November 1989 Responds to Generic Ltr 89-07, Power Reactor Safeguards Contingency Planning for Surface Vehicle Bombs. Util Has Developed & Issued Procedure Which Includes Safeguards Contingency Planning Using Approach Noted in Generic Ltr ML19325D7411989-10-19019 October 1989 Forwards Application for Amends 126 & 77 to Licenses NPF-14 & NPF-22,respectively,requesting Emergency Temporary Relief from Certain Requirements of Tech Specs 3.2.2 on One Time Basis for Period of 3 Months ML19325C3771989-10-11011 October 1989 Forwards Change DD to Physical Security Plan.Change Withheld (Ref 10CFR73.21) ML18040B2581989-10-0202 October 1989 Forwards Final Response to Request for Addl Info Re Generic Ltr 88-01, NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping. Listed Items Included in Previous & Current Ref Responses ML18040A9441989-09-12012 September 1989 Responds to Remaining Questions Raised During NRC Insp of Training Programs.Training Procedure Re Technical Exam Bank Instrumentation & Control Training Exams.Health Physics Technicians Trained Re High Radiation Levels PLA-3251, Forwards Response to Regulatory Effectiveness Review Rept. Util Established Team to Evaluate Appropriate Scope for Planned Major Project to Upgrade Security.Scope of Project to Be Finalized & Approved in Nov 1989.Response Withheld1989-08-31031 August 1989 Forwards Response to Regulatory Effectiveness Review Rept. Util Established Team to Evaluate Appropriate Scope for Planned Major Project to Upgrade Security.Scope of Project to Be Finalized & Approved in Nov 1989.Response Withheld ML18040A9421989-08-22022 August 1989 Requests Concurrence W/Scheduling of 1990 Annual NRC Observed Emergency Preparedness Exercise at Plant on 900502. Concurrence Requested by 890930 ML18040B2531989-08-10010 August 1989 Discusses Insp of Operational Status of Emergency Preparedness Program.Susquehanna Review Committee 1987 & 1988 Emergency Plan Audits Encl W/Other Supporting Documentation ML20246A0191989-06-30030 June 1989 Submits Comments on Containment Performance Improvement Program (Cpi).Believes Program Will Be Generic Approach to Improving Containment Performance During Severe Accident PLA-3218, Submits Info Re Settlement Agreements for Discrimination Matters Arising Under Energy Reorganization Act of 1974. No Settlements Made Between Licensee & Any Employees in Section 210 Proceedings1989-06-27027 June 1989 Submits Info Re Settlement Agreements for Discrimination Matters Arising Under Energy Reorganization Act of 1974. No Settlements Made Between Licensee & Any Employees in Section 210 Proceedings ML18040B2501989-06-20020 June 1989 Forwards Summary Rept of Safety Evaluations Approved During 1988.Changes Include Backseating Control Box to Electrically Backset HV-202168 to Reduce Steam Leakage & Rerouting Condensate Supply Line to Main Condenser Keepfill PLA-3194, Forwards Change CC to Physical Security Plan.Change Withheld (Ref 10CFR73.21)1989-05-30030 May 1989 Forwards Change CC to Physical Security Plan.Change Withheld (Ref 10CFR73.21) ML18040A9301989-04-28028 April 1989 Responds to 890322 Request for Addl Info Re Plant Fire Protection Review Rept.Analysis of Circuits Having Potential for Being Impacted by Fire Resulting in Multiple High Impedence Faults Will Be Completed by Last Quarter 1989 ML18040B2441989-04-14014 April 1989 Forwards Application for Amends to Licenses NPF-14 & NPF-22, Resulting from Mods Performed to Essential Svc Water Sys,Per 10CFR50,App R,Consisting of Proposed Amends 23 & 70 PLA-3173, Forwards Change Bb to Physical Security Plan.Encl Withheld (Ref 10CFR73.21)1989-03-22022 March 1989 Forwards Change Bb to Physical Security Plan.Encl Withheld (Ref 10CFR73.21) ML18040A9271989-03-10010 March 1989 Forwards Rev 6 to ISI-T-100.0 for Unit 1 & Rev 3 to ISI-T-200.0 for Unit 2 Pump & Valve Inservice Insp Testing Program. ML18040A9261989-03-0707 March 1989 Discusses Util Position Re Completion & Implementation of NRC Requested Actions Specified in Suppl 1 to NRC Bulletin 88-007, Power Oscillations in Bwrs. ML17156B0131989-02-0202 February 1989 Forwards Proprietary Rept & Affidavit Supporting Proposed Amend 119 to License NPF-14 ML17156A9771988-12-15015 December 1988 Forwards Rev 11 to Susquehanna Units 1 & 2 Emergency Plan ML18040B2331988-11-22022 November 1988 Forwards Listed Addl Info Re Plant Fire Protection Review rept.W/16 Oversize Drawings ML17156A9211988-11-0909 November 1988 Forwards Proprietary GE Rept, Tech Spec Improvement Analysis for Reactor Protection Sys for Susquehanna Steam Electric Station,Units 1 & 2. Rept Withheld (Ref 10CFR2.790) ML18040A9111988-09-15015 September 1988 Informs That Mods Re Fire Barrier Upgrades,Hvac Fan Switches,Ct Secondaries & Raceway Wrapping Completed Except as Listed ML18040A9101988-08-10010 August 1988 Forwards Application for Amend to License NPF-14,extending Operation During Cycle 4 W/One Circulation Loop Out of Svc. Fee Paid ML18040B2221988-08-10010 August 1988 Responds to Generic Ltr 88-01, NRC Position on IGSCC in BWR Austenitic Stainless Steel Piping. Staff Position on Matls, Water Chemistry,Crack Evaluation & Repair Criteria & Insp Schedules Among Topics Addressed.Flaw Evaluations Encl ML18040B2201988-07-27027 July 1988 Forwards Comments to Each Specific SALP Category,Per 880707 Meeting W/Nrc.Presentations from Meeting Also Encl ML18040A9061988-07-21021 July 1988 Forwards GE Rept, Susquehanna Unit 1 CRD Housing Cap Screw Corrosion. Rept Completes Action on Item ML18040A9031988-07-19019 July 1988 Forwards Approved Version of Topical Rept PL-NF-87-001-A, Qualification of Steady State Core Physics Methods for BWR Design & Analysis, Per 880428 Ltr ML18040A9041988-07-19019 July 1988 Forwards Rev 39 to Updated FSAR for Susquehanna Steam Electric Station Units 1 & 2 Per 10CFR50.71 ML18040B2131988-06-24024 June 1988 Forwards 1987 Annual Rept for Allegheny Electric Cooperative,Inc ML18040A9021988-06-15015 June 1988 Provides Revised Response to NRC 871130 Ltr Re Violations Noted in Insp Repts 50-387/87-19 & 50-388/87-19.Corrective Actions:Incumbent Will Be Removed from Emergency Plan Position of Radiation Protection Coordinator PLA-3028, Responds to Suppl 1 to Bulletin 85-003, Motor-Operated Valve Common Mode Failures During Plant Transients Due to Improper Switch Settings. No Revs to Design Review for Original Bulletin Required as Result of Suppl1988-05-31031 May 1988 Responds to Suppl 1 to Bulletin 85-003, Motor-Operated Valve Common Mode Failures During Plant Transients Due to Improper Switch Settings. No Revs to Design Review for Original Bulletin Required as Result of Suppl ML18040A8691988-04-0606 April 1988 Forwards Application for Proposed Amends 110 & 61 to Licenses NPF-14 & NPF-22,respectively,revising Tech Specs Re Radiation Monitoring Instrumentation.Fee Paid 1990-09-01
[Table view] |
Text
,
ACCELERATED DISTRIBUTION DEMONSTRATION SYSTEM REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)
ACCESSION NBR: 9009100349 DOC. DATE: 90/09/01 NOTARIZED: NO DOCKET FACIL:50-387 Susquehanna Steam Electric Station, Unit 1, Pennsylva 05000387 50-388 Susquehanna Steam Electric Station, Unit 2, Pennsylva 05000388 AUTH. NAME AUTHOR AFFILIATION KEISER,H.W. Pennsylvania Power & Light Co.
RECIP.NAME RECIPIENT AFFILIATION MARTIN,T.T. Region 1 (Post 820201)
SUBJECT:
Requests waiver of compliance from TS 3.8.1.1.
DISTRIBUTION CODE: A001D COPIES RECEIVED LTR ENCL SIZE- D TITLE: OR Submittal: General Distribution S NOTES:LPDR 1 cy Transcripts. 05000387 LPDR 1 cy Transcripts. 05000388 RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL D PD1-2 LA PD1-2 PD THADANI,M D INTERNAL: ACRS NRR/DET/ECMB 9H NRR/DOEA/OTS B 1 1 NRR/DST 8E2 NRR/DST/SELB 8D NRR/DST/SICB 7E NRR/DST/SRXB 8E NUDOCS-ABSTRACT OGC/HDS2 EG FILE 01 RES/DSIR/EIB EXTERNAL: NRC PDR NSIC NOTES D
D D
NOTE TO ALL "RIDS" RECIPIENTS:
PLEASE HELP US TO REDUCE,WASTE! CONTACT THE DOCUMENT CONTROL DESK, ROOM P 1-37 (EXT. 20079) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!
TOTAL NUMBER OF COPIES REQUIRED: LTTR 25 ENCL
Pennsylvania Power 8 Light Company Two North Ninth Street ~ Allentown, PA18101-1179 ~ 215/770-5151 Harold W. Keiser Senior Vice President-Nucfear 21 5i770-4194 September 1, 1990 Mr. Thomas T. Martin, Administrator U.S. Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406 SUSQUEHANNA STEAM ELECTRIC STATION REQUEST FOR WAIVER OF COMPLIANCE Docket Nos. 50-387 PLA-3438 FILES A17-2 R4 1-2 & 50-388
Dear Mr. Martin:
The purpose of this letter is,to request a waiver of compliance from Technical Specification 3.8.1.1 (A.C. Sources-Operating)
Action b. This 72-hour action was entered at 1200 hours0.0139 days <br />0.333 hours <br />0.00198 weeks <br />4.566e-4 months <br /> (i.e.,
noon) on August 30, 1990. This submittal,evaluates an increase in the action time from 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to 15 days.
it is requested that the waiver increase the action time by 4 days
't this time, however, (from 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to 7 days). This time will be utilized to prepare an emergency Technical Specification change request that will represent PP&L's formal request for the full extension to 15 days.
Descri tion of Condition On August 29,1990, during a borescopic inspection of Emergency Diesel Generator OG501D, heavy scoring of. the cylinder liners on five engine cylinders was observed. Further inspection revealed damage to several additional cylinder liners and the presence of aluminum oxide in the engine. The aluminum oxide was introduced to the engine as residual material from sandblasting performed on the engine intercoolers during a recent maintenance activity. Intake air, passing through the intercoolers, picked up this residual material and introduced it to the engine. Once in the engine, the aluminum oxide became an abrasive acting between the engine cylinders and cylinder liners, resulting in the heavy scoring observed on the cylinder liners.
A review of recent engine lube oil samples taken on OG501D revealed the presence of increased levels of chrome. The source and significance of this condition was not immediately recognized but coupled with the inspection results noted above, we now know the source of the chrome to be from the scored cylinder liners.
9009100349 90090k ,ok PDR ADOCK 05000387 Q PDC
Mr. Thomas T. Martin Page 2 Files A17-2/R41-2, PLA-3438 September 1, 1990 The maintenance overhaul which lead to the introduction of aluminum oxide into OG501D was similar to overhauls performed on Emergency Diesel Generators OG501A,B, and C over the past six months. As such, the potential for a similar condition on these three engines exists. The results of our investigation of this potential are as follows.
Investi ation Results The source of the aluminum oxide in OG501D has been confirmed to be the intercoolers installed in that engine. These intercoolers had previously been installed in OG501A. During the overhaul evolution they had been removed from OG501A, inspected and cleaned, (including sandblasting the tube side of the cooler with aluminum oxide) and then reinstalled in OG501D. Precautions against introduction of aluminum oxide to the shell side of the cooler were inadequate. The sequence of the engine overhauls was:
- 1. OG501C
- 2. OG501A
- 3. OG501D
- 4. OG501B similar sequence of intercooler removal, cleaning and reinstallation existed for each engine except for OG501C. Since it A
was the first engine to undergo its overhaul, new intercoolers delivered from the vendor were reinstalled in it. As a result we have high confidence that this condition does not exist. in OG501C.
The intercoolers that were removed from OG501C were reinstalled in OG501A. The boroscopic inspection that revealed the scoring of the cylinder liners on OG501D has already been completed on OG501A.
These inspections revealed no visible damage. During this inspection period, the air intake manifold was removed from OG501A to support installation of an engine modification. No evidence of aluminum oxide was present. Xn addition, two recent lube oil samples taken on OG501A were reviewed. Unlike the sample for OG501D, the level of chrome present in the lube oil was normal.
The damage from introduction of aluminum oxide manifests itself quickly. OG501D has only 20 hours2.314815e-4 days <br />0.00556 hours <br />3.306878e-5 weeks <br />7.61e-6 months <br /> of run time since completion of its maintenance overhaul. Conversely, OG501A has 43 hours4.976852e-4 days <br />0.0119 hours <br />7.109788e-5 weeks <br />1.63615e-5 months <br /> of run time since its maintenance overhaul which we believe is adequate to result in cylinder liner scoring in the presence of even small quantities of aluminum oxide. For these reasons we have a high confidence level that OG501A does not have this condition. The intercoolers that. were removed from OG501D were reinstalled in OG501B. This engine has yet to undergo its post overhaul inspection. A review of recent lube oil samples was performed and
Mr. Thomas T. Martin Page 3 Files A17-2/R41-2, PLA-3438 September 1, 1990 an increased level of chrome was observed. As a result, OG501B was declared inoperable at 1200 on August 30,1990 and Tech Spec Action 3.8.1.l.b was entered on both units. An immediate inspection was performed and evidence of aluminum oxide was found in the air intake manifold, confirming the existence of the condition on OG501B.
OG501E, the spare diesel generator at Susquehanna, is presently substituting for OG501D. It was not part of the recent overhauls.
Its intercoolers have not been recently removed and sandblasted.
A review of lube oil samples on this engine shows normal levels of chrome. Based on this information, a similar condition does not exist on OG501E.
Re irements for which Waiver is Re ested It is requested that the LCO Action time for Tech Spec Action 3.8.1.1.b on both units be extended from 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to 7 days to allow continued operation of Unit 1 and 2. This extension will provide us with sufficient time to prepare, submit, and allow NRC review of an emergency Technical Specification change that will justify the additional time necessary to finish performing a thorough inspection, cleaning, and restoration of OG501B.
Com ensato Actions We have confirmed that the three aligned Diesel Generators do not have the degraded condition experienced by OG501B and D. As such, their reliability during this period of time is not impaired. As noted above, Diesel Generators OG501A and C have recently undergone a rigorous maintenance overhaul and installation of modifications to improve their reliability.
The following additional compensatory measures will also be performed in support of the extended action time:
The spray pond bypass valve on each division will be maintained open to assure availability of Diesel Generator Cooling.
- 2. Per Technical Specification 3.8.1.1, Action B.2., we are required to perform Surveillance Requirement 4.8.1.1.2.a.4 within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. It is proposed that this surveillance be performed every 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> thereafter for the duration of the extended action time. This will serve to provide additional assurance of the reliability of the three operable diesel generators.
Mr. Thomas T. Martin Page 4 Files A17-2/R41-2, PLA-3438 September 1, 1990
- 3. To further reduce the risk of challenges to the offsite power supply, discretionary power changes on both Units 1 and 2 will be avoided.
4 ~ No discretionary maintenance or modification work will be performed on the following systems: ECCS (including the support functions provided by ESW and RHRSW), RCIC, CRD system, DC power systems, and AC Power Distribution
~
systems.
Safet Si nificance and Conse ences of .Pro osed Re est The proposed request is not a significant safety concern as described above. We have already identified the unique cause of this condition and confirmed the three aligned Diesel Generators are operable. The additional time is needed to assure thorough inspection, cleaning and restoration of OG501B. The compensatory actions outlined above further reduce the probability of any safety consequences from this request.
PP&L has performed a risk evaluation of a 12-day extension to the 72-hour action time. This evaluation is based upon the 1986 Individual Plant Evaluation for SSES that has been submitted to the NRC. The equation used to quantify the estimated increase in total plant damage is:
Annual"'isk (1 ~ 4 x 10 ) f~ + (7 ~ 0 x 10 ) kg where f> = annual fraction when the A, B, C and D diesel generators are in service and the E diesel generator is available to be put in service (normal configuration),
and fz = annual fraction when only three diesel generators are operable, and one of the three is the E diesel generator (current configuration).
The value of 1.4 x 10 /year is based on the IPE evaluation of the affect of opening the spray pond bypass valve for both divisions.
The value of 7.0 x 10 /year is based on the IPE evaluation of the current diesel generator configuration. The evaluation of this equation for the 72-hour action time results in an annual risk for total plant damage of 1.45 x 10 . For 15 days, the result is 1.63 x 10 . This yields an increase of 13%. This evaluation assumed that the aforementioned compensatory actions 1. and 4. are implemented.
Mr. Thomas T. Martin Page 5 Files A17-2/R41-2, PLA-3438 September 1, 1990 PPGL does not believe that this increase is significant for the following reasons:
- 1. The result is lower than the total plant damage frequency submitted to the NRC in the original (1986) IPE (2.1 x 10 ~/year), and 2 ~ The percentage increase is lower than what was accepted by the NRC in their safety evaluation of PP&L's submittal to extend the same action times in support of tying in the 'E'iesel generator 334 (
Reference:
Amendment Nos. 51 and 19, dated December 3, 1985).
No Si nificant Hazards Considerations 1~ This proposal does not involve a significant increase in the probability or consequences of an accident previously evaluated. The three remaining Diesel Generators will be operable. Therefore Susquehanna will be in a configuration that is bounded by prior deterministic analysis, assuming a single failure has occurred. Furthermore, as described above, the risk of total plant damage on an annual basis has increased, but it is not considered significant because:
- a. it is lower than the total plant damage frequency in the original IPE, and
- b. the percentage increase is lower than what was accepted by the NRC in a prior safety evaluation to extend the same action times in order to tie in the 'E'iesel generator.
- 2. This problem does not create the possibility of a new or different kind of accident from any accident The evolution involved is one of restoration to previously'valuated.
acceptable standards. No change in the operation or function of the Diesel Generators is proposed.
- 3. This change does not involve a significant reduction in a margin of safety. If an emergency iswere existing LCO or the extension, it to arise during the possible to address the safe operation of both units with the three remaining operable Diesel Generators. Furthermore, compensatory actions have been proposed to assure the reliability of these diesels and other safety systems which mitigate the risk of an event should one occur. This does not represent a significant reduction in a margin of safety.
Mr. Thomas T. Martin Page 6 Files A17-2/R41-2, PLA- 3438 September 1, 1990 Environmental Conse ences As stated above, anticipated ~
that for the duration of the Susquehanna will be proposed waiver in a it condition that is functionally meets the design basis (assuming a single failure has occurred). Therefore, no environmental consequences that have not been previously considered are anticipated.
Conclusion Both units at Susquehanna SES are currently in a 72-hour LCO on the B Diesel Generator due to the introduction of a foreign material (aluminum oxide) into the engine. A waiver of compliance is requested to allow a 4-day extension of this LCO. This extension will be used to ensure sufficient time to prepare, submit, and allow NRC review of an emergency Technical Specification change that will justify the additional time necessary to restore the B Diesel Generator to operable status. It is proposed that this waiver be approved immediately with the following conditions:
- 1. The waiver will become effective at 1200 hours on September 2, 1990. t
- 2. The waiver will expire upon declaring the B Diesel Generator operable, but not to exceed 4 days.
Any questions on this request should be directed to Mr. J. M. Kenny at (215) 770-7904.
Very truly yours, H. W. Keiser cc: NRC Document Control Desk .(original)>