MONTHYEARML18017A9241999-10-15015 October 1999 Provides Supplemental Info Re 981223 Lar,Placing Plant Spent Fuel Pools 'C' & 'D' in Service.Info Provided Does Not Change Util Initial Determination That Proposed License Amend Represents No Significant Hazards Consideration ML18017A9141999-10-12012 October 1999 Forwards Addl Info Re Second 10-year ISI Program Plan Relief Requests,As Requested During 990923 Telcon ML18017A9131999-10-0606 October 1999 Provides Notification That Three SROs Licensed at Shnpp Have Been Reassigned from Position for Which Util Previously Certified Need for SRO License.Name,Docket Number & License Number for Subject Sros,Encl.Encl Withheld ML18017A8911999-09-30030 September 1999 Submits Comment on Encl 2 to 990617 Memo Titled Summary of Meeting with Nuclear Energy Inst. Encl 2 Was Titled Draft Technical Study of Spent Fuel Pool Accidents for Decommissioning Plants. Rept Which Provides Info Encl Also ML20216G3501999-09-29029 September 1999 Confirms Conversations Re NRC Staff Voluntary Response to Orange County Discovery Requests.Staff Will Voluntarily Answer Discovery Requests & Will Not Waive Any Objection or Privilege Under NRC Regulations.Related Correspondence ML20212M1081999-09-29029 September 1999 Confirms Intent to Meet with Utils on 991025 in Atlanta,Ga to Discuss Pilot Plants,Shearon Harris & Sequoyah Any Observations & Lessons Learned & Recommendations Re Implementation of Pilot Program ML20212J0741999-09-29029 September 1999 Refers to Proposed License Amend for Harris NPP Which Would Allow Licensee to Activate Two of Plant Spent Fuel Pools.Serves Copy of Orange County Second Set of Document Requests to NRC Staff,Dtd 990929.Related Correspondence ML18017A8941999-09-29029 September 1999 Forwards Response to NRC 990414 RAI Re GL 95-07, Pressure- Locking & Thermal-Binding of SR Power-Operated Gate Valves. ML18017A8881999-09-27027 September 1999 Submits Info Re Estimated Effect of Changes or Errors in ECCS Evaluation Models or in Application of Models,Per 10CFR50.46(a)(3)(ii) ML18017A8861999-09-21021 September 1999 Forwards Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Examinations. ML18017A8821999-09-14014 September 1999 Provides Notification That RO Licensed on Harris Plant No Longer Meets Requirements of 10CFR50.21,effective 990826. Name,Docket Number & License Number for Individual Provided in Encl.Encl Withheld,Per 10CFR2.790(a)(6) ML18017A8651999-09-0808 September 1999 Requests Relief from Section XI,IWA-5242(a) Requirement for HNP Class 2 Bolted Connections in Borated Sys.Compliance with Requirement Would Result in Unusual Difficulty Without Compensating Increase in Level of Quality & Safety ML18017A8581999-09-0303 September 1999 Provides Response to NRC 990805 RAI Re Amend Request to Increase Fuel Storage Capacity ML18017A8551999-09-0101 September 1999 Forwards Marked Up Copy of Approved FSAR Section 17.3 with Applicable Duplicated TS Requirements,As Committed to in 990602 Application for Rev to TS ML18017A8541999-08-20020 August 1999 Submits Closure Info for Rev 1,Suppl 1 to GL 92-01, Reactor Vessel Structural Integrity. Identified Discrepancies from Review of NRC Rvid Provided HNP-99-134, Forwards Rev 11 to Physical Security & Safeguards Contingency Plan,Iaw 10CFR50.54(p)(2) & 10CFR50.4(b)(4). Description of Changes Is Provided as Encl 2 to Ltr.Rev Withheld,Per 10CFR73.211999-08-18018 August 1999 Forwards Rev 11 to Physical Security & Safeguards Contingency Plan,Iaw 10CFR50.54(p)(2) & 10CFR50.4(b)(4). Description of Changes Is Provided as Encl 2 to Ltr.Rev Withheld,Per 10CFR73.21 ML18017A8351999-08-10010 August 1999 Corrects Statement Made in 980923 Ltr,By Clarifying That Operation of Inner & Outer Pal Doors Can Be Operated by Control Panels Located Inside & Outside Containment ML18016B0531999-08-0606 August 1999 Forwards Exercise Scenario with Controller Info & Simulation Data for Harris Nuclear Plant Emergency Preparedness Exercise Scheduled for 990921.Without Encl ML18016B0461999-08-0404 August 1999 Forwards LER 99-006-01 Describing Condition Which Resulted in Exceeding TS Requirements for CIVs & TS 4.0.4 for Generic Requirements for Surveillance Testing.Rev Includes Results of Investigation Into Failure to Recognize TS Requirements ML18016B0391999-07-30030 July 1999 Forwards Rev 35 to PLP-201, Emergency Plan. Rev Replaces All Pages of Previous Rev with Exception of EAL Flow Path, Side 1 & 2 & Annex H,Operations Map & Aperature Card. Changes Made by Rev,Listed ML18016B0421999-07-30030 July 1999 Informs That in Ltr Dtd 950330 CP&L Committed to Complete Assessment of Severe Accident Mgt Capabilities & Make Any Identified Enhancements by 981231.Actions Were Completed in July 1998 ML18016B0221999-07-26026 July 1999 Informs That CP&L Proposes to Provide Response to NRC 990414 RAI Re GL 95-07, Pressure-Locking & Thermal-Binding of SR Power-Operated Gate Valves, by 990930 ML18016B0171999-07-16016 July 1999 Forwards Corrected Pages to Annual Radioactive Effluent Release Rept, for 1998 for HNP ML18016B0051999-07-0101 July 1999 Informs of Scheduled Emergency Preparedness Exercise for Shnpp on 990921,per Requirements of 10CFR50,App E.List of 26 Objectives Selected for Evaluation During Exercise,Encl. Without Encl ML20212H7741999-06-23023 June 1999 Responds to Re Petition Filed by Orange County Board of Commissioners Re Proposed Expansion of Sf Storage Capacity at Shearon Harris Npp.Public Meeting Will Be Held at Later Date.With Certificate of Svc.Served on 990624 ML18016A9871999-06-14014 June 1999 Forwards Response to NRC 990429 RAI Re License Amend Request to Place Spent Fuel Pools C & D in Service,Dtd 981223.Info Does Not Change Initial Determination That Proposed License Amend Represents No Significant Hazards Consideration ML18016A9831999-06-10010 June 1999 Submits Notification That Reactor Operator Licensed at HNP Has Terminated Employment with Cp&L.Reactor Operator Info Encl.Effective 990528,individuals License Is No Longer Required & CP&L Requests That License Be Terminated ML20212H7521999-06-0404 June 1999 Encourages NRC to Schedule Open Public Forum Which Would Allow Local Citizens to Express Concerns Re Proposed Expansion of high-level Radwaste Storage Capacity at Shearon Harris Npp.With Certificate of Svc.Served on 990624 ML18016A9721999-05-28028 May 1999 Responds to 990309 RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs. ML18016B0011999-05-26026 May 1999 Forwards Ltr Received from Hj Jaffe Expressing Concern Re Cpl Proposal to NRC on Dec of 1998 to Make Harris Nuclear Plant Largest Storage Area for High Level Nuclear Waste in Nation ML18016A9631999-05-25025 May 1999 Forwards Periodic Update to FSAR for Hnp.Amend 49 Is Current Through 981128 (End of RFO 8).Some Changes & Analysis Completed After 981128 Have Also Been Included in Amend ML20206R2511999-05-19019 May 1999 Responds to Addressed to Chairman Jackson Requesting That NRC Grant Standing to Orange County Board of Commissioners in Shearon Harris Proceeding Currently Before Board.With Certificate of Svc.Served on 990519 ML20206Q5281999-05-17017 May 1999 Responds to 990304 Request for Two Rail Routes to Be Used for Transport of Spent Fuel from Brunswick Steam Electric Plant,Southport,Nc & Hb Robinson Steam Electric Plant, Hartsville,Sc to Shearon Harris Npp,Near New Hill,Sc ML18016A9511999-05-13013 May 1999 Submits Info Re Estimated Effect of Change to ECCS Evaluation Model,As Required by 10CFR50.46 ML18016A9601999-05-11011 May 1999 Forwards Resolution Adopted by Carrboro Board of Aldermen at 990504 Meeting.Resolution Expresses Town Concern Re Util Plans to Double high-level Nuclear Waste Storage at Shnpp ML18016A9481999-05-0606 May 1999 Forwards NRC Form 396, Certification of Medical Examination by Facility Licensee, for Senior Reactor Operator Licensed to Operate Hnp.Individuals Info Is Proprietary & Is Being Withheld from Public Disclosure,Per 10CFR2.790(a)(6) ML20206R2611999-05-0505 May 1999 Requests That NRC Grant Standing to Intervention Sought by Orange County Board of Commissioners Re Proposal by CP&L to Expand Storage of Hlrw at Shnpp.With Certificate of Svc. Served on 990519 ML18016A9451999-05-0404 May 1999 Provides Proprietary Notification That One SRO Has Been Reassigned from Position for Which Util Certified Need for SRO License & Another SRO Has Terminated Employment with Util.Proprietary Info Withheld,Per 10CFR2.790(a)(6) ML18016A9441999-05-0404 May 1999 Notifies NRC of Util Completion of Actions Re GL 96-01, Testing of Safety-Related Logic Circuits at Plant ML18016A9351999-04-30030 April 1999 Forwards Info Requested in 990324 RAI as Suppl to 981223 Application for Amend to License NPF-63 for Alternative Plan for Spent Fuel Pool Cooling & Cleanup Sys Piping ML18016A9311999-04-30030 April 1999 Forwards Annual Radioactive Effluent Release Rept for Jan- Dec 1998 & Rev 11 to ODCM for Shnpp HNP-99-068, Forwards Rev 0 to Physical Security & Safeguards Contingency Plan. Description of Changes Provided.Encl Withheld1999-04-28028 April 1999 Forwards Rev 0 to Physical Security & Safeguards Contingency Plan. Description of Changes Provided.Encl Withheld ML18016A9211999-04-27027 April 1999 Provides Rev 2 to ISI Relief Request 2RG-008, ISI of Class 1,2 & 3 Snubbers (Code Category F-A) Per Plant TS in Lieu of ASME Code Section XI, in Response to 990408 Telcon with NRC ML18016A9221999-04-27027 April 1999 Forwards Proprietary Notification That SRO Licensed on Shnpp Has Terminated Employment with Cp&L,Per 10CFR50.74(b). Proprietary Info Withheld,Per 10CFR2.790(a)(6) ML18016A9161999-04-22022 April 1999 Forwards Proprietary NRC Form 396, Certification of Medical Exam by Facility Licensee, for SRO Licensed to Operate Hnp. License for Individual Should Be Amended IAW Change Noted on Form.Proprietary Encl Withheld,Per 10CFR2.790(a)(6) ML18016A9201999-04-20020 April 1999 Informs of HNP Personnel Changes to Facilitate Proper Distribution of Correspondence.Records Should Be Updated to Reflect Noted Change ML20205M0431999-04-13013 April 1999 Eighth Partial Response to FOIA Request for Records.App Q & R Records Encl & Being Made Available in PDR ML18016A9121999-04-12012 April 1999 Forwards Diskette Containing Data Re Annual Exposure Rept for Individual Monitoring for Personnel Shnpp,Per 10CFR20.2206(b).Without Encl ML18016A9021999-04-12012 April 1999 Forwards Rev 34 to PLP-201, Shearon Harris NPP Emergency Plan, Replacing All Pages of Previous Rev with Exception of EAL Flow Path,Side 1 & 2 & Annex H Operations Map & Aperture Card.Changes,Listed.Rev Summary,Encl IR 05000400/19982011999-04-12012 April 1999 Discusses Safeguards Insp Rept 50-400/98-201 (Operational Safeguards Response Evaluation) on 980908-11.No Violations Noted.Licensee Performance During Evaluation Indicated Excellent Overall Contingency Response Capability 1999-09-08
[Table view] Category:INCOMING CORRESPONDENCE
MONTHYEARML18017A9241999-10-15015 October 1999 Provides Supplemental Info Re 981223 Lar,Placing Plant Spent Fuel Pools 'C' & 'D' in Service.Info Provided Does Not Change Util Initial Determination That Proposed License Amend Represents No Significant Hazards Consideration ML18017A9141999-10-12012 October 1999 Forwards Addl Info Re Second 10-year ISI Program Plan Relief Requests,As Requested During 990923 Telcon ML18017A9131999-10-0606 October 1999 Provides Notification That Three SROs Licensed at Shnpp Have Been Reassigned from Position for Which Util Previously Certified Need for SRO License.Name,Docket Number & License Number for Subject Sros,Encl.Encl Withheld ML18017A8911999-09-30030 September 1999 Submits Comment on Encl 2 to 990617 Memo Titled Summary of Meeting with Nuclear Energy Inst. Encl 2 Was Titled Draft Technical Study of Spent Fuel Pool Accidents for Decommissioning Plants. Rept Which Provides Info Encl Also ML20212J0741999-09-29029 September 1999 Refers to Proposed License Amend for Harris NPP Which Would Allow Licensee to Activate Two of Plant Spent Fuel Pools.Serves Copy of Orange County Second Set of Document Requests to NRC Staff,Dtd 990929.Related Correspondence ML18017A8941999-09-29029 September 1999 Forwards Response to NRC 990414 RAI Re GL 95-07, Pressure- Locking & Thermal-Binding of SR Power-Operated Gate Valves. ML18017A8881999-09-27027 September 1999 Submits Info Re Estimated Effect of Changes or Errors in ECCS Evaluation Models or in Application of Models,Per 10CFR50.46(a)(3)(ii) ML18017A8861999-09-21021 September 1999 Forwards Response to NRC Administrative Ltr 99-03, Preparation & Scheduling of Operator Licensing Examinations. ML18017A8821999-09-14014 September 1999 Provides Notification That RO Licensed on Harris Plant No Longer Meets Requirements of 10CFR50.21,effective 990826. Name,Docket Number & License Number for Individual Provided in Encl.Encl Withheld,Per 10CFR2.790(a)(6) ML18017A8651999-09-0808 September 1999 Requests Relief from Section XI,IWA-5242(a) Requirement for HNP Class 2 Bolted Connections in Borated Sys.Compliance with Requirement Would Result in Unusual Difficulty Without Compensating Increase in Level of Quality & Safety ML18017A8581999-09-0303 September 1999 Provides Response to NRC 990805 RAI Re Amend Request to Increase Fuel Storage Capacity ML18017A8551999-09-0101 September 1999 Forwards Marked Up Copy of Approved FSAR Section 17.3 with Applicable Duplicated TS Requirements,As Committed to in 990602 Application for Rev to TS ML18017A8541999-08-20020 August 1999 Submits Closure Info for Rev 1,Suppl 1 to GL 92-01, Reactor Vessel Structural Integrity. Identified Discrepancies from Review of NRC Rvid Provided HNP-99-134, Forwards Rev 11 to Physical Security & Safeguards Contingency Plan,Iaw 10CFR50.54(p)(2) & 10CFR50.4(b)(4). Description of Changes Is Provided as Encl 2 to Ltr.Rev Withheld,Per 10CFR73.211999-08-18018 August 1999 Forwards Rev 11 to Physical Security & Safeguards Contingency Plan,Iaw 10CFR50.54(p)(2) & 10CFR50.4(b)(4). Description of Changes Is Provided as Encl 2 to Ltr.Rev Withheld,Per 10CFR73.21 ML18017A8351999-08-10010 August 1999 Corrects Statement Made in 980923 Ltr,By Clarifying That Operation of Inner & Outer Pal Doors Can Be Operated by Control Panels Located Inside & Outside Containment ML18016B0531999-08-0606 August 1999 Forwards Exercise Scenario with Controller Info & Simulation Data for Harris Nuclear Plant Emergency Preparedness Exercise Scheduled for 990921.Without Encl ML18016B0461999-08-0404 August 1999 Forwards LER 99-006-01 Describing Condition Which Resulted in Exceeding TS Requirements for CIVs & TS 4.0.4 for Generic Requirements for Surveillance Testing.Rev Includes Results of Investigation Into Failure to Recognize TS Requirements ML18016B0421999-07-30030 July 1999 Informs That in Ltr Dtd 950330 CP&L Committed to Complete Assessment of Severe Accident Mgt Capabilities & Make Any Identified Enhancements by 981231.Actions Were Completed in July 1998 ML18016B0391999-07-30030 July 1999 Forwards Rev 35 to PLP-201, Emergency Plan. Rev Replaces All Pages of Previous Rev with Exception of EAL Flow Path, Side 1 & 2 & Annex H,Operations Map & Aperature Card. Changes Made by Rev,Listed ML18016B0221999-07-26026 July 1999 Informs That CP&L Proposes to Provide Response to NRC 990414 RAI Re GL 95-07, Pressure-Locking & Thermal-Binding of SR Power-Operated Gate Valves, by 990930 ML18016B0171999-07-16016 July 1999 Forwards Corrected Pages to Annual Radioactive Effluent Release Rept, for 1998 for HNP ML18016B0051999-07-0101 July 1999 Informs of Scheduled Emergency Preparedness Exercise for Shnpp on 990921,per Requirements of 10CFR50,App E.List of 26 Objectives Selected for Evaluation During Exercise,Encl. Without Encl ML18016A9871999-06-14014 June 1999 Forwards Response to NRC 990429 RAI Re License Amend Request to Place Spent Fuel Pools C & D in Service,Dtd 981223.Info Does Not Change Initial Determination That Proposed License Amend Represents No Significant Hazards Consideration ML18016A9831999-06-10010 June 1999 Submits Notification That Reactor Operator Licensed at HNP Has Terminated Employment with Cp&L.Reactor Operator Info Encl.Effective 990528,individuals License Is No Longer Required & CP&L Requests That License Be Terminated ML20212H7521999-06-0404 June 1999 Encourages NRC to Schedule Open Public Forum Which Would Allow Local Citizens to Express Concerns Re Proposed Expansion of high-level Radwaste Storage Capacity at Shearon Harris Npp.With Certificate of Svc.Served on 990624 ML18016A9721999-05-28028 May 1999 Responds to 990309 RAI Re GL 96-05, Periodic Verification of Design-Basis Capability of Safety-Related Movs. ML18016B0011999-05-26026 May 1999 Forwards Ltr Received from Hj Jaffe Expressing Concern Re Cpl Proposal to NRC on Dec of 1998 to Make Harris Nuclear Plant Largest Storage Area for High Level Nuclear Waste in Nation ML18016A9631999-05-25025 May 1999 Forwards Periodic Update to FSAR for Hnp.Amend 49 Is Current Through 981128 (End of RFO 8).Some Changes & Analysis Completed After 981128 Have Also Been Included in Amend ML18016A9511999-05-13013 May 1999 Submits Info Re Estimated Effect of Change to ECCS Evaluation Model,As Required by 10CFR50.46 ML18016A9481999-05-0606 May 1999 Forwards NRC Form 396, Certification of Medical Examination by Facility Licensee, for Senior Reactor Operator Licensed to Operate Hnp.Individuals Info Is Proprietary & Is Being Withheld from Public Disclosure,Per 10CFR2.790(a)(6) ML20206R2611999-05-0505 May 1999 Requests That NRC Grant Standing to Intervention Sought by Orange County Board of Commissioners Re Proposal by CP&L to Expand Storage of Hlrw at Shnpp.With Certificate of Svc. Served on 990519 ML18016A9451999-05-0404 May 1999 Provides Proprietary Notification That One SRO Has Been Reassigned from Position for Which Util Certified Need for SRO License & Another SRO Has Terminated Employment with Util.Proprietary Info Withheld,Per 10CFR2.790(a)(6) ML18016A9441999-05-0404 May 1999 Notifies NRC of Util Completion of Actions Re GL 96-01, Testing of Safety-Related Logic Circuits at Plant ML18016A9351999-04-30030 April 1999 Forwards Info Requested in 990324 RAI as Suppl to 981223 Application for Amend to License NPF-63 for Alternative Plan for Spent Fuel Pool Cooling & Cleanup Sys Piping ML18016A9311999-04-30030 April 1999 Forwards Annual Radioactive Effluent Release Rept for Jan- Dec 1998 & Rev 11 to ODCM for Shnpp HNP-99-068, Forwards Rev 0 to Physical Security & Safeguards Contingency Plan. Description of Changes Provided.Encl Withheld1999-04-28028 April 1999 Forwards Rev 0 to Physical Security & Safeguards Contingency Plan. Description of Changes Provided.Encl Withheld ML18016A9221999-04-27027 April 1999 Forwards Proprietary Notification That SRO Licensed on Shnpp Has Terminated Employment with Cp&L,Per 10CFR50.74(b). Proprietary Info Withheld,Per 10CFR2.790(a)(6) ML18016A9211999-04-27027 April 1999 Provides Rev 2 to ISI Relief Request 2RG-008, ISI of Class 1,2 & 3 Snubbers (Code Category F-A) Per Plant TS in Lieu of ASME Code Section XI, in Response to 990408 Telcon with NRC ML18016A9161999-04-22022 April 1999 Forwards Proprietary NRC Form 396, Certification of Medical Exam by Facility Licensee, for SRO Licensed to Operate Hnp. License for Individual Should Be Amended IAW Change Noted on Form.Proprietary Encl Withheld,Per 10CFR2.790(a)(6) ML18016A9201999-04-20020 April 1999 Informs of HNP Personnel Changes to Facilitate Proper Distribution of Correspondence.Records Should Be Updated to Reflect Noted Change ML18016A9121999-04-12012 April 1999 Forwards Diskette Containing Data Re Annual Exposure Rept for Individual Monitoring for Personnel Shnpp,Per 10CFR20.2206(b).Without Encl ML18016A9021999-04-12012 April 1999 Forwards Rev 34 to PLP-201, Shearon Harris NPP Emergency Plan, Replacing All Pages of Previous Rev with Exception of EAL Flow Path,Side 1 & 2 & Annex H Operations Map & Aperture Card.Changes,Listed.Rev Summary,Encl ML18016A8911999-04-0505 April 1999 Forwards non-proprietary App 4A,pages 20-25 & Proprietary Page 4-6 to re-issued Rev 3 of Holtec International Licensing Rept HI-971760.Pages Were Inadvertently Omitted from Reissued Rept.Proprietary Page 4-6 Withheld ML18016A8891999-04-0101 April 1999 Forwards Rev 99-1 to Plant EALs for NRC Review & Approval, Per 10CFR50,App E.Encl Provides Comparison of Currently Approved EALs & Proposed Rev 99-01.Approval of EALs Prior to June 1999,requested.With Four Oversize Drawings ML18016A8811999-03-31031 March 1999 Responds to NRC 990301 Ltr Re Violations Noted in Insp Rept 50-400/98-11.Corrective Actions:Post Trip/Safeguards Actuation Rept for 981023,RT Was Corrected,Required Reviews Completed & Approval Obtained on 990219 ML18016A8671999-03-19019 March 1999 Submits Response to RAI Re Spent Fuel Pool Water Level & Revised Fuel Handling Accident Analyses,Per 990317 Telcon with NRC ML18016A8631999-03-19019 March 1999 Forwards Shnpp Operator Training Simulator,Simulator Certification Quadrennial Rept, IAW 10CFR55.45(b)(5)(ii). NRC Form 474 & Required Info Re Simulator Performance Test Results & Schedules Also Encl ML18016A8691999-03-18018 March 1999 Forwards Resolution Adopted by Lee County,North Carolina Board of Commissioners Re Proposed Expansion of high-level Radioactive Waste Storage Facilities at Carolina Power & Light Shearon Harris Nuclear Power Plant ML18016A8511999-03-15015 March 1999 Forwards Proprietary & non-proprietary Version of Rev 3 to HI-971760, Licensing Rept for Expanding Storage Capacity in Harris SFPs 'C' & 'D'. Repts Are Reissued to Reflect Reduction in Proprietary Info.Proprietary Info Withheld ML18016A8601999-03-15015 March 1999 Informs NRC of Mod to Commitment for Hnp,Re Comprehensive Review of Implementation of TS Sr.Upon Completion of Listed Reviews,Surveillance Procedure Review Project Will Be Considered Complete 1999-09-08
[Table view] |
Text
CATEGORY 1 REGULATOINFORMATION DISTRIBUTION /ITEM (RIDE)
ACCESSION.; NQR:9708050318 DOC.DATE: 97/07/29 NOTARIZED: YES DOCKET I FACIL:50-400 Shearon Harris Nuclear Power Plant, Unit 1, Carolina 05000400 AUTH. NAME AUTHOR AFFILIATION ROBINSON,W.R. Carolina Power & Light Co.
RECIP.NAME RECIPIENT AFFILIATION Document Control Branch (Document Control Desk)
SUBJECT:
Forwards 120-day response to GL 97-07, "Degradation of Control Rod Drive Mechanism Nozzle & Other Vessel Closure, Head Penetrations."
DISTRIBUTION CODE: A075D COFZES RECEIVED:LTR I ENCL I SIZE:
TITLE: GL-97-01 Degraduation of Control Rod Drive Mechanism & Other Vessel NOTES:Application for permit renewal filed. 05000400 E RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL 0 PD2-1 LA 1 1 PD2-1 PD 1 1 PDl-1/HAROLD,J 1 0 ROONEY,V 1 1 R INTERNA FILE CENT+ 01 1 1 NRR/D /EMCB 3 3 R S/'EMMEB 1 1 RGN. 1 1 EXTERNAL: NRC PDR 1 1 0
C N
NOTE TO ALL "RZDS" RECZPZENTSz PLEASE HELP US TO REDUCE WASTEI CONTACT THE DOCUMENT CONTROL DESKI ROOM OWFN 5D"5(EXT. 4%5"2083) TO ELZMZNATE YOUR NAME FROM DZSTRZBUTZON LZSTS FOR DOCUMENTS YOU DON'T NEEDI I
TOTAL NUMBER OF COPIES REQUIRED: LTTR 11 ENCL 10
0 Caralina Power & Light Company William R. Robinson PO Box 165 Vice President New Hill NC 27562 Harris NUclear Plant SERIAL: HNP-97-152 10 CFR 50.54(f)
JUL 28 897 United States Nuclear Regulatory Commission ATTENTION: Document Control Desk Washington, DC 20555 SHEARON HARRIS NUCLEAR POWER PLANT DOCKET NO. 50-400/LICENSE NO. NPF-63 RESPONSE TO NRC GENERIC LETTER 97-01, "DEGRADATIONOF CONTROL ROD DRIVE MECHANISMNOZZLE AND OTHER VESSEL CLOSURE HEAD PENETRATIONS"
Dear Sir or Madam:
k Carolina Power Light Company (CP8cL) hereby responds to NRC Generic Letter 97-01 (GL 97-01),
"Degradation of Control Rod Drive Mechanism Nozzle and Other Vessel Closure Head Penetrations" for the Harris Nuclear Plant (HNP). As committed to in HNP letter dated April 25, 1997, Enclosure 1 provides the required 120-day written response to GL 97-01.
Please refer any question regarding this submittal to Mr. J. H. Eads at (919) 362-2646.
Sincerely, JHE/eoe Enclosure W. R. Robinson, having been first duly sworn, did depose and say that the information contained herein is true and correct to the best of his information, knowledge and belief; and the sources of his information are employees, contractors, and agents of Carolina Power & Light Company.
Nota (S al sssssssIstgp~
g, V4~+
My commission expires: g ( Wc oo fear soiARK Mr. J. B. Brady (NRC Senior Resident Inspector, HNP)
Mr. L. A. Reyes (NRC Regional Administrator, Region II) RBL)C c Mr. V. L. Rooney ( NRR Project Manager, HNP) 9'708050MB nDOCK 0S000eO0 970729'oe
>lllllllll P POR State Road 1134 New Hill NC Tel 919 362-2502 Fax 919 362-2095
Document Control Desk HNP l52/ Page 2 bc: Ms. D. B. Alexander Mr. W. D. Johnson Mr. H. K. Chernoff (RNP) Mr. R. M. Krich Mr. B. H. Clark Ms. W. C. Langston (PE&RAS File)
Mr. G. W. Davis Mr. R. D. Martin Mr. J. W. Donahue Mr. W. S. Orser Mr. W. J. Dorman (BNP) Mr. G. A. Rolfson Mr. G. D. Hicks Mr. D. L. Tibbitts Mr. W. J. Hindman Nuclear Records Nuclear Licensing File File:H-X-0545
GL 97-01 120-DAY RESPONSE INTRODUCTION'eneric Letter 97-01 (GL), "Degradation of Control Rod Drive Mechanism Nozzle and Other Vessel Closure Head Penetrations," was issued to request licensees to describe their program for insuring the timely inspection of PWR control rod drive mechanism (CRDM) and other vessel head penetrations (VHP). This response provides Harris Nuclear Plant (HNP) information relative to the information requested by the GL.
Prior to issuance of the GL, HNP worked with the Westinghouse Owners Group (WOG), the Electric Power Research Institute (EPRI), and the Nuclear Energy Institute (NEI) to understand the operational experience, identify technical issues, cause factors, relative importance, and solutions. One of these tasks was the development of safety evaluations that characterized the initiation of damage, propagation and consequences. These safety evaluations are contained in WCAP 13565 Revision 1, "Alloy600 Reactor Vessel Adapter Tube Cracking Safety Evaluation," and are applicable to HNP. The NRC reviewed the safety evaluations and issued a safety evaluation report (SER) to NEI on November 19, 1993. The safety evaluations and the SER establish the basis for HNP continued operation.
RESPONSE TO RE VESTED INFORMATIONITEM 1.1:
"1.1 A description of all inspections of CRDM nozzle and other VHPs performed to the date of this generic letter, including the results of these inspections."
R~es onse:
Visual examinations of the reactor vessel head, including the CRDM penetration areas, are performed during each refueling outage, based on HNP procedures which implement commitments to Generic Letter 88-05 "Boric Acid Corrosion of Carbon Steel Reactor Pressure Boundary Components in PWR Plants." In order to assure compliance with the assumptions of the safety evaluation provided in WCAP 13565 Rev 1, examinations of the CRDM penetration area for boric acid were included in the HNP Generic Letter 88-05 program, beginning in March of 1994. These examinations were performed during refueling outages ¹5, ¹6 and ¹7.
Additionally, consistent with the requirements of the ASME Code Section XI edition to which HNP is committed the following examinations have been performed during past outages: the weld joint located between the reactor vessel head flange and the reactor vessel head has been examined by a magnetic particle surface examination and an ultrasonic examination, selected cono-seal bolting have been examined using VT-1 examination techniques, and selected CRD housing to CRDM penetration welds have been examined using liquid penetrant examination techniques.
Although none of these examinations specifically examine the interface area between the reactor vessel head and the CRDM penetrations, they do necessitate that personnel perform these examinations within the reactor vessel head penetration region. Therefore, ifa reactor vessel head penetration experienced a leak, it is likely that the resulting boric acid build-up/corrosion would have been identified by the personnel performing one of these examinations.
System leakage tests for the RCS are also conducted following each removal and replacement of the reactor vessel head. After the RCS is placed into operation, the region around the reactor vessel head flange is visually examined using VT-2 examination techniques to identify any leakage. Such examinations have provided yet another opportunity to observe evidence of boric acid build-up/corrosion stemming from a leaking CRDM penetration.
None of these past examinations have identified evidence of leakage or boric acid corrosion originating from the reactor vessel closure head penetration areas.
No inservice volumetric examinations have been performed on the HNP reactor vessel closure head penetrations.
RESPONSE TO RE UESTED INFORMATIONITEM 1.2 THROUGH 1.4:
"1.2 Ifa plan has been developed to periodically inspect the CRDM nozzle and other VHPs:
a) Provide the schedule for first, and subsequent, inspections of the CRDM nozzle and other VHPs, including the technical basis for this schedule.
b) Provide the scope for the CRDM nozzle and other VHP inspections, including the total number ofpenetrations (and how many willinspected),
which penetrations have thermal sleeves, which are spares, and which are instrument or other penetrations."
1.3 Ifa plan has not been developed to periodically inspect the CRDM nozzle and other VHPs, provide the analysis that supports why no augmented inspection is necessary.
1.4 In light of the degradation of CRDM nozzle and other VHPs described above, provide the analysis that supports the selected course of action as listed in either 1.2 or 1.3, above. In particular, provide a description of all relevant data and/or tests used to develop crack initiation and crack growth models, the methods and data used to validate these models, t'e plant-specific inputs to these models, and how these models substantiate the susceptibility evaluation.
if Also, an integrated industry inspection program is being relied on, provide a detailed description of this program."
~Res ense:
Based on both domestic and foreign data relative to PWSCC, it is generally recognized that this cracking mechanism is strongly dependent on operating time and temperature. For the two domestic plants that have found evidence of CRDM cracking, D.C. Cook Unit 2 and Oconee Unit 2, the plant operating time and vessel head temperatures ranged from approximately 87K hours at 604'F and 127K hours at 602'F, respectively. The HNP reactor vessel design is such that a portion of the reactor coolant inlet flow is diverted up into the upper head region, thus maintaining the operating temperature within the area of the CRDMs close to that of the Reactor Coolant System cold leg temperature of approximately 551 F (i.e.,
Tcold reactor vessel head design). Based on the relatively short operating time for HNP (i.e., approximately 70K effective full power hours) and the Tcold reactor vessel head design, as compared against the other domestic plants that conducted volumetric inspections, HNP should be considered as one of the less susceptible plants in the domestic industry for PWSCC. Current HNP plant procedures require periodic visual examinations of the reactor vessel head penetrations in accordance with previous commitments made in response to Generic Letter 88-05, in addition to those other vessel head examination activities noted in the response to Item 1.0, above.
In a proactive effort to establish when volumetric examinations might be warranted for our plants, in 1994, CP&L evaluated the susceptibility of reactor vessel head penetrations for the H. B. Robinson Nuclear Plant (RNP) to PWSCC. The results of the plant-specific evaluation indicated that volumetric examinations would not be warranted prior to 1999 for RNP. Due to similarities in plant design and penetration materials, coupled with its longer operating time and hotter reactor vessel head temperature (i.e., approximately 150K hours and 598'F for RNP versus 70K hours and 551'F for HNP), the RNP conditions would be expected to bound those for the HNP reactor vessel head penetrations.
From a domestic industry perspective, each of the three PWR owners groups, the Electric Power Research Institute (EPRI), and the Nuclear Energy Institute (NEI) are cooperatively working to compile information on the estimated operating time from January 1, 1997, needed to initiate and propagate a crack 75% through-wall in a vessel penetration. This information willbe evaluated to determine ifan adequate number of plants have or are planning to examine as a part of an integrated industry inspection program. CP&L is a member of both EPRI and the Westinghouse Owners Group. This evaluation is expected to be completed by the end of 1997.
Additionally, Dominion Engineering, Inc., is currently working under contract with EPRI to develop a computer software module for use by utilities in accessing their plant-specific PWSCC risk probabilities. This software product is being based on the PWSCC risk model which has been previously applied to several domestic
0 I
1
plants by the contractor. CP&L is participating as a member of the UtilityAdvisory Group for this EPRI product. Once the beta testing version of the soRware is available in late 1997, CP&L plans to use the product for further evaluation of PWSCC risk at the CP&L plants. The final version of the software is anticipated to be available for use in 1998.
Carolina Power & Light Company (CP&L) currently has no confirmed plans or schedule for conducting volumetric examinations of reactor vessel head penetrations at HNP. The need and timing for future volumetric examinations at HNP will continue to be evaluated and updated, based on the results of the ongoing industry programs also described above. Once any confirmed plans for conducting volumetric examinations at the HNP are established, the NRC willbe informed accordingly, regarding the schedule and scope for these activities.
RESPONSE TO RE VESTED INFORMATIONITEM 2:
"2 Provide a description of any resin bead intrusions, as described in IN 96-11, that have exceeded the current EPRI PWR Primary Water Chemistry Guidelines recommendations for primary water sulfate levels, including the following information:
2.1 Were the intrusions cation, anion, or mixed bed?
2.2 What were the durations of these intrusions?
2.3 Does the plant's RCS water chemistry Technical Specifications follow the EPRI guidelines?
Identify any RCS chemistry excursions that exceed the plant administrative limits for the following species: sulfates, chlorides or fluorides, oxygen, boron, and lithium.
2.5 Identify any conductivity excursions which may be indicative of resin intrusions. Provide a technical assessment of each excursion and any follow-up actions.
2.6 Provide an assessment of the potential for any of these intrusions to result in a significant increase in the probability for IGA of VHPs and any associated plan for inspections"
~Res ense:
CP&L has reviewed the plant historical records to determine ifany incident of resin ingress, similar to those which occurred in 1980 and 1981 at the Jose Cabrera (Zorita) plant, has occurred at HNP. This data search was structured to identic all resin intrusion events into the primary coolant system with a magnitude greater than 1 ft3 ( 80 liters). The threshold of 1 ft3 was chosen as a conservative lower bound since it represents less than 15% of the estimated volume of resin released into the reactor coolant system during the two events at Jose Cabrera.
Routine analysis for sulfate in reactor coolant was performed for plant operation from January 3, 1987 to the present. A sulfate concentration in the range of 15 to 17 ppm peak concentration was used as the indicator of cation resin ingress.
This concentration is approximately equivalent to a volume of 1 ft~. The actual sulfate concentration has been less than 0.1 ppm (EPRI Guideline value).
Had sulfate increases indicated resin ingress to the magnitude of the threshold quantity identified above, additional data evaluation would have been conducted to look for a corresponding depression in pH or elevation in lithium as corroborating information of the incident. In the case of the use of sulfate data as the indicator, specific conductance would also have been included as confirmatory data had a significant in-leakage event been identified.
It was unnecessary to review plant records for boron, chlorides, fluorides and oxygen, because these species are not viewed as valid indicators of cation resin ingress and degradation within the primary coolant system of a PWR. Borate, chloride and fluoride anions could be associated with the anion portion of mixed bed resin (cation plus anion); however, ifmixed bed resin leakage to the RCS occurred, the cation portion of the resin would contain the sulfate indicator described above.
Detectable dissolved oxygen in reactor coolant, during power operation with appropriate hydrogen overpressure on the volume control tank and specified residual dissolved hydrogen in the reactor coolant, could not occur and, therefore, could not be associated with the resin in-leakage.
Based on the results of this review, it is concluded that a Zorita plant type resin intrusion has not occurred in the past at HNP.
The primary water chemistry control program at HNP is implemented in accordance with plant procedures which have been based on the EPRI Primary Water Chemistry Guidelines since March 13, 1991 and the Westinghouse Chemistry Criteria and Specifications prior to that. These industry guidelines were evaluated for applicability to HNP and applicable guidelines were incorporated into plant chemistry procedures with appropriate modifications when necessary.
1