MONTHYEARIR 05000461/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Clinton Power Station (Report 05000461/2024005) ML24220A2772024-08-0707 August 2024 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000461/2025010 ML24179A3112024-06-27027 June 2024 05000461; Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information IR 05000461/20230062024-02-28028 February 2024 Annual Assessment Letter for Clinton Power Station (Report 05000461/2023006) ML24054A7112024-02-23023 February 2024 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000461/2024011 ML24064A1222024-02-0606 February 2024 Biennial Problem and Identification Inspection Request for Information IR 05000461/20220062023-03-0101 March 2023 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2022006) ML23005A0682023-01-0505 January 2023 Notification of NRC Fire Protection Team Inspection Request for Information: Inspection Report 05000461/2023010 ML22312A5362022-11-0808 November 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000461/2023401 IR 05000461/20220052022-08-22022 August 2022 Updated Inspection Plan for Clinton Power Station (Report 05000461/2022005) IR 05000461/20210062022-03-0202 March 2022 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2021006) ML21333A0832021-11-29029 November 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Teams), Inspection Report Report 05000461/202201 IR 05000461/20210052021-09-0101 September 2021 Updated Inspection Plan for Clinton Power Station; Report 05000461/2021005 ML21215A5732021-08-0303 August 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21076A5112021-03-17017 March 2021 Information Request to Support Upcoming Temporary Instruction 2515/194 Inspection; Inspection Report 05000461/2021013 ML21071A1882021-03-12012 March 2021 Information Request to Support Upcoming Problem Identification and Resolution Inspection at Clinton Power Station IR 05000461/20200062021-03-0404 March 2021 Annual Assessment Letter for Clinton Power Station Unit 1 (Report 05000461/2020006) ML20329A0662020-11-24024 November 2020 Information Request for an NRC Triennial 10 CFR 50.59 (Evaluation of Changes, Tests and Experiments) Baseline Inspection IR 05000461/20200052020-09-0101 September 2020 Updated Inspection Plan for Clinton Power Station, Unit 1 (Report 05000461/2020005) ML20183A1932020-06-30030 June 2020 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report 05000461/2020010 IR 05000461/20190062020-03-0303 March 2020 Annual Assessment Letter for Clinton Power Station, (Report 05000461/2019006) IR 05000461/20190052019-08-28028 August 2019 Updated Inspection Plan for Clinton Power Station (Report 05000461/2019005 ML19136A1852019-05-15015 May 2019 Byron Station, Clinton Power Station, Dresden Nuclear Power Station, LaSalle County Station, and Quad Cities Nuclear Power Station-Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency IR 05000461/20180062019-03-0404 March 2019 Annual Assessment Letter for Clinton Power Station (Report 05000461/2018006) ML19037A4772019-02-0606 February 2019 Information Request to Support Upcoming Problem Identification and Resolution Inspect at Clinton Power Station ML19003A1912019-01-0303 January 2019 Request for Information for an NRC Triennial Baeline Design Bases Assurance Inspection; Inspection Report 05000461/2019011 IR 05000461/20180052018-08-28028 August 2018 Mid-Cycle Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2018005) ML18088A5662018-03-28028 March 2018 Information Request for an NRC Triennial 10 CFR 50.59 (Evaluation of Changes, Tests and Experiments) Baseline Inspection 05000461/2018010 IR 05000461/20170062018-03-0202 March 2018 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2017006) ML17333A0782017-11-28028 November 2017 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000461/2018002 IR 05000461/20170052017-08-28028 August 2017 Updated Inspection Plan for Clinton Power Station, Unit 1 and Quarterly Assessment Letter (Report 05000461/2017005) ML17146B2492017-03-31031 March 2017 Inspection Plan for Clinton Power Station for Triennial Fire Protection Baseline Inspection Report 2017 008 ML17076A3382017-03-16016 March 2017 Notification of NRC Baseline Inspection and Request for Information 05000461/2017002 IR 05000461/20160062017-03-0101 March 2017 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2016006) IR 05000461/20160052016-08-31031 August 2016 Mid-Cycle Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2016005) ML16098A3242016-04-0707 April 2016 Information Request to Support Upcoming Temporary Instruction 191 Inspection at Clinton Power Station ML16076A2542016-03-15015 March 2016 Ltr. 03/15/16 Clinton Power Station, Unit 1 - Request for Information for an NRC Triennial Baseline Component Design Bases Inspection; Inspection Report 05000461/2016009 (Jen) ML16076A2462016-03-15015 March 2016 Ltr. 03/15/16 Clinton Power Station - Notification of NRC Inspection and Request for Information (Vlm) IR 05000461/20150062016-03-0202 March 2016 Annual Assessment Letter for Clinton Power Station Unit 1 (Inspection Report 05000461/2015006) IR 05000461/20150052015-09-0101 September 2015 Mid-Cycle Assessment Letter for Clinton Power Station, Unit 1 (Report 05000461/2015005) IR 05000461/20140012015-03-0404 March 2015 Annual Assessment Letter for Clinton Power Station, Unit 1, (Report 05000461/2014001) ML14245A2362014-09-0202 September 2014 Mid-Cycle Assessment Letter for Clinton Power Station, Unit 1 ML14177A3812014-06-25025 June 2014 Notification of NRC Supplemental Inspection (95001) and Request for Information IR 05000451/20130012014-03-0404 March 2014 Annual Assessment Letter for Clinton Power Station, Unit 1 (Report 05000451/2013001) ML13308B1302013-11-0101 November 2013 Ltr 11/1/13 Clinton Fire Protection Request for Information ML13246A2152013-09-0303 September 2013 2013 Clinton Power Station Mid-Cycle Letter Combined IR 05000461/20130082013-07-25025 July 2013 IR 05000461-13-008, May 20 - 24, 2013, June 3 - 7, 2013, and June 17 - 21, 2013, Clinton Power Station, Component Design Bases Inspection (CDBI) IR 05000461/20120012013-03-0404 March 2013 Annual Assessment Letter for Clinton Power Station (Report 05000461/2012001) ML13038A3122013-02-0707 February 2013 Request for Information for an NRC Triennial Baseline Component Design Bases Inspection Report 05000461-13-008 ML12249A4462012-09-0404 September 2012 Mid-Cycle Assessment Letter for Clinton Power Station, Unit 1 2024-08-07
[Table view] Category:Letter
MONTHYEARML24211A2302024-09-11011 September 2024 – Request for Partial Site Release for Facility Operating License No. NPF-62 RS-24-087, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station2024-09-0909 September 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors for Clinton Power Station IR 05000461/20240112024-09-0909 September 2024 Commercial Grade Dedication Inspection Report 05000461/2024011 IR 05000461/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Clinton Power Station (Report 05000461/2024005) ML24222A3952024-08-23023 August 2024 Regulatory Audit Report to Support the Review of the Amendments to Revise Reactor Water Cleanup Valve Isolation Timing IR 05000461/20240022024-08-0909 August 2024 Integrated Inspection Report 05000461/2024002 ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24220A2772024-08-0707 August 2024 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000461/2025010 ML24212A2212024-08-0202 August 2024 License Renewal Regulatory Audit Regarding the Environmental Review of the License Renewal Application (EPID Number: L-2024-LNE-0000) (Docket Number: 50-461) ML24157A3242024-07-11011 July 2024 Issuance of Amendment No. 254 Revision of Reactor Water Cleanup Isolation Valve Timing ML24158A0772024-07-0303 July 2024 Notice of Consideration of Approval of Partial Site Release, Public Meeting, and Request for Comments (EPID L-2023-LLA-0088) - Letter ML24163A3252024-06-28028 June 2024 Aging Management Regulatory Audit Plan ML24163A3242024-06-28028 June 2024 LRA - Portal Letter ML24179A3112024-06-27027 June 2024 05000461; Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML24176A0272024-06-25025 June 2024 Confirmation of Initial License Examination, July 2025 RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes IR 05000461/20240122024-05-20020 May 2024 Biennial Problem Identification and Resolution Inspection Report Report 05000461/2024012 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report RS-24-050, Additional Information Supporting Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation2024-05-0909 May 2024 Additional Information Supporting Request for License Amendment to Revise Technical Specifications Related to Reactor Water Cleanup Isolation Instrumentation IR 05000461/20240012024-05-0707 May 2024 Integrated Inspection Report 05000461/2024001 ML24103A1032024-05-0101 May 2024 SHPO Consultation Letter for Clinton License Renewal ML24120A3462024-04-30030 April 2024 Ltr. to Douglas Lankford, Chief, Miami Tribe of Oklahoma; Re., CPS Section 106 Consultation ML24120A3452024-04-30030 April 2024 Ltr. to Lester Randell, Chairman, Kickapoo Tribe of Indians of the Kickapoo Reservation in Kansas; Re., CPS Section 106 Consultation ML24103A0992024-04-30030 April 2024 Achp Scoping Letter for Clinton License Renewal ML24120A3432024-04-30030 April 2024 Ltr. to Darwin Kaskaske, Chairman, Kickapoo Tribe of Oklahoma; Re., CPS Section 106 Consultation ML24120A3442024-04-30030 April 2024 Ltr. to Gena Kakkak, Chairman, Menominee Indian Tribe of Wisconsin; Re., CPS Section 106 Consultation ML24103A1152024-04-30030 April 2024 Ltr. to Geoffrey Standing Bear, Principal Chief, the Osage Nation; Re., CPS Section 106 Consultation RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24107B0312024-04-29029 April 2024 Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping Process ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition ML24089A2222024-04-11011 April 2024 LRA - Acceptance and Opportunity for Hearing - Letter ML24092A3452024-04-0101 April 2024 Updated Safety Analysis Report (Usar), Revision 23 RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24092A3552024-04-0101 April 2024 Request for Information for NRC License Renewal Inspection: Inspection Report 05000461/2024010 RS-24-023, Report on Status of Decommissioning Funding.2024-03-22022 March 2024 Report on Status of Decommissioning Funding. ML24045A1422024-02-29029 February 2024 License Renewal Application Receipt and Availability - Letter IR 05000461/20230062024-02-28028 February 2024 Annual Assessment Letter for Clinton Power Station (Report 05000461/2023006) ML24054A7112024-02-23023 February 2024 Request for Information for NRC Commercial Grade Dedication Inspection: Inspection Report 05000461/2024011 ML24045A0242024-02-14014 February 2024 Application for Renewed Operating License RS-24-005, Additional Information Supporting Request for Partial Site Release2024-02-0808 February 2024 Additional Information Supporting Request for Partial Site Release ML23338A1102024-02-0606 February 2024 Issuance of Amendment No. 252 Revision of Technical Specification 3.8.3, Diesel Fuel Oil, and Starting Air IR 05000461/20230042024-02-0202 February 2024 Integrated Inspection Report 05000461/2023004 ML23361A1572024-01-24024 January 2024 Audit Plan in Support of Review of License Amendment Request Regarding Revision of Technical Specifications Related to Reactor Water Cleanup Isolation ML24004A0792024-01-18018 January 2024 – Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0041 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000461/20234022023-12-27027 December 2023 Security Baseline Inspection Report 05000461/2023402 ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 IR 05000461/20235012023-12-0505 December 2023 Emergency Preparedness Biennial Exercise Inspection Report 05000461/2023501 ML23284A2512023-11-22022 November 2023 Amendment No. 250 to Adopt TSTF-332 2024-09-09
[Table view] |
Inspection Report - Clinton - 2015006 |
---|
|
|
Text
UNITED STATES arch 2, 2016
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR CLINTON POWER STATION, UNIT 1 (REPORT 05000461/2015006)
Dear Mr. Hanson:
On February 10, 2016, the U.S. Nuclear Regulatory Commission (NRC) completed its end-of-cycle performance review of Clinton Power Station, Unit 1. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2015, through December 31, 2015. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC determined the performance at Clinton Power Station, Unit 1, in the beginning of the assessment period was within the Regulatory Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because of a greater-than-green Security cornerstone input as described in our letter to you dated October 23, 2014 (ADAMS Accession Number ML14302A082). Per Inspection Procedure 95001, the NRC completed a supplemental inspection for this issue on February 27, 2015, as documented in our letter to you dated March 27, 2015 (ML15089A120). This greater-than-green security finding was closed as of the start of the second quarter of 2015 in accordance with Inspection Manual Chapter 0305.
The NRC determined the performance at Clinton Power Station, Unit 1, for the most recent quarter was within the Regulatory Response Column of the NRCs ROP Action Matrix because of one inspection finding in the Mitigating Systems Cornerstone having low to moderate safety significance (i.e., White) and all performance indicators indicating that your performance was within the nominal, expected range (i.e., Green). This White finding was related to your failure to review the suitability of application of the design for the replacement Division 3 shutdown service water pump and to ensure the pump internals would not degrade under expected operating conditions in a way that impacted the safety function. As described in our Final Significance Determination of a White Finding with Assessment Follow-up and Notice of Violation letter issued on August 11, 2015 (ML15223B382), this White finding was considered an Action Matrix input at the start of the first quarter of 2015. In accordance with the guidance in Inspection Manual Chapter 0305, Clinton Power Station, Unit 1, remained in the Regulatory Response Column of the ROP Action Matrix for the entire assessment period. The NRC completed a supplemental inspection for this White finding per Inspection Procedure 95001 on February 4, 2016. You will be provided with the results of that inspection and the impact on your Action Matrix status on a later date.
The enclosed inspection plan lists the inspections scheduled through December 31, 2017.
Routine inspections performed by resident inspectors are not included in the inspection plan.
The inspections listed during the last 9 months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence.
The NRC inspection schedule includes a triennial inspection conducted in accordance with Inspection Procedure 71111.21, Component Design Bases Inspection, and several infrequently performed inspection activities related to the operation of the Independent Spent Fuel Storage Installation (ISFSI) using IP 60856, Review of 10 CFR 72.212(b) Evaluations, IP 60854.1, Preoperational Testing of an Independent Spent Fuel Storage Facility Installations at Operating Plants, and IP 60855.1, Operation of an ISFSI Independent Spent Fuel Storage Installation at Operating Plants.
The NRC notified you in our 2014 annual assessment letter, Annual Assessment Letter for Clinton Power Station, Unit 1, dated March 4, 2015 (ML15062A577), that the NRC would perform IP 92723, Follow-up Inspection for Three or More Severity Level IV Traditional Enforcement Violations in the Same Area in a 12-Month Period, to follow-up on three Severity Level IV violations. On December 28, 2015, your staff notified us of your readiness for us to conduct the follow-up inspection to review the actions taken to address the performance issues.
From January 1 to December 31, 2015, the NRC issued three additional Severity Level IV traditional enforcement violations associated with impeding the regulatory process. Therefore, the NRC plans to conduct an inspection to follow-up on these six Severity Level IV violations.
The NRC staff received the Clinton Power Station Final Compliance letter for Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events and Order EA-12-051, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation. The NRC staff issued the Clinton Power Station Final Safety Evaluation on December 23, 2015 (ML15324A238), and will confirm full implementation of the orders mentioned above by performing Temporary Instruction 191, Inspection of the Licensee's Responses to Mitigation Strategies Order EA-12-049, Spent Fuel Pool Instrumentation Order EA-12-051 and Emergency Preparedness Information, dated December 1, 2015.
In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room). Please contact Karla Stoedter at 630-829-9731 with any questions you have regarding this letter.
Sincerely,
/RA/
Patrick L. Louden, Director Division of Reactor Projects Docket Nos. 50-461 License Nos. NPF-62 Enclosure:
Inspection Plan cc: Distribution via LISTSERV