Letter Sequence RAI |
---|
|
|
MONTHYEAR3F1213-02, Post-Shutdown Decommissioning Activities Report2013-12-0202 December 2013 Post-Shutdown Decommissioning Activities Report Project stage: Request 3F1213-01, Update to Irradiated Fuel Management Program Pursuant to 10 CFR 50.54(bb)2013-12-0303 December 2013 Update to Irradiated Fuel Management Program Pursuant to 10 CFR 50.54(bb) Project stage: Request ML13343A1782013-12-31031 December 2013 Report P23-1680-001, Rev. 0, Site-Specific Decommissioning Cost Estimate for Crystal River Unit 3 Nuclear Generating Plant. Project stage: Request ML14034A0242014-01-16016 January 2014 Edit - Transcript of Discussion of the Crystal River, Unit 3 Post-Shutdown Decommissioning Activities Report, 01/16/214 Project stage: Request ML14024A2632014-01-16016 January 2014 Handouts for Post-Shutdown Decommissioning Activities Report Public Meeting, January 16, 2014 Project stage: Request ML14034A0232014-01-16016 January 2014 Transcript of Discussion of the Crystal River, Unit 3 Post-Shutdown Decommissioning Activities Report, 01/16/2014 Project stage: Other ML14034A0262014-04-0303 April 2014 1/16/2014 Summary of Meeting in Crystal River, Fl, to Discuss and Accept Public Comments Related to the Crystal River, Unit 3 Nuclear Generating Station Post-Shutdown Decommissioning Activities Report Project stage: Meeting ML14104A0392014-04-28028 April 2014 Request for Additional Information on the Post Shutdown Decommissioning Activities Report Project stage: RAI ML14133A5032014-05-14014 May 2014 Correction, Request for Additional Information on the Post Shutdown Decommissioning Activities Report Project stage: RAI 3F0614-02, Post-Shutdown Decommissioning Activities Report - Response to Request for Additional Information2014-06-17017 June 2014 Post-Shutdown Decommissioning Activities Report - Response to Request for Additional Information Project stage: Response to RAI ML14321A7512015-03-11011 March 2015 Post-Shutdown Decommissioning Activities Report Project stage: Other 2014-04-28
[Table View] |
|
---|
Category:Letter
MONTHYEARIR 05000302/20240012024-09-23023 September 2024 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3, NRC Inspection Report No. 05000302/2024001 ML24240A1692024-09-18018 September 2024 Cy 2023 Summary of Decommissioning Trust Fund Status ML24226B2392024-08-27027 August 2024 Application for License Amendment Request to Add License Condition to Include License Termination Plan Requirements – Acknowledgement of Withdrawal ML24179A0702024-07-26026 July 2024 SHPO S106 Completion Crystal River Unit 3 ML24205A2192024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Muscogee Nation ML24205A2182024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Seminole Nation of Oklahoma ML24179A0912024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3: Seminole Tribe of Florida ML24205A2202024-07-24024 July 2024 Tribal S106 Completion Crystal River Unit 3_Miccosukee Tribe of Florida ML24190A1912024-07-0808 July 2024 Fws Concurrence for Crystal River Unit 3 ML24172A2552024-06-20020 June 2024 Fws to NRC Species List: Florida Ecological Services Field Office 06/20/2024 ML24170A9242024-06-18018 June 2024 024-0023697 Crystal River License Termination Plan Unit 3 ML24151A6482024-06-0303 June 2024 Changes in Reactor Decommissioning Branch Project Management Assignments for Some Decommissioning Facilities ML24114A2262024-04-24024 April 2024 Amended Special Package Authorization for the Cr3 Middle Package (Crystal River 3 Middle Package - Docket No. 71-9393) IR 05000302/20230022024-04-17017 April 2024 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2023002 ML24054A0612024-04-0202 April 2024 Request to Initiate Section 106 Consultation Regarding the License Termination Plan for Crystal River Unit 3 in Citrus County, Florida ML24079A2492024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Johnson, Lewis Johnson ML24054A0582024-04-0202 April 2024 Achp S106 Initiation Crystal River Unit 3 - Letter 1 ML24079A2472024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Cypress, Talbert ML24079A2482024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Hill, David Hill ML24054A0812024-04-0202 April 2024 Tribal S106 Initiation Crystal River Unit 3-Osceola, Marcellus ML24089A0362024-03-29029 March 2024 Response to Audit Plan in Support of Accelerated Decommissioning Partners and Request to Add License Condition to Include License Termination Plan Requirements. W/Enclosures 1 to 5 ML24073A1922024-03-11011 March 2024 Fws to NRC, List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML24054A6452024-02-29029 February 2024 Letter - Reply to Request for RAI Extension Related to the Crystal River License Termination Plan ML24030A7482024-02-12012 February 2024 Audit Report Cover Letter and Report - Crystal River Unit 3 Nuclear Generating Plant LTP ML23342A0942024-01-0909 January 2024 – Independent Spent Fuel Storage Installation Security Inspection Plan ML23354A0632023-12-22022 December 2023 Cover Letter - Crystal River License Termination Plan Request for Additional Information ML23345A1882023-12-0606 December 2023 Fws to NRC Crystal River Species List of Threatened and Endangered Species That May Occur in Your Proposed Project Location or May Be Affected by Your Proposed Project ML23320A2592023-11-17017 November 2023 STC-23 077 Notification of the Crystal River Unit 3 Generating Plant License Termination Plan Public Meeting and Federal Register Notice ML23313A1322023-11-15015 November 2023 Request for Additional Information for the Environmental Assessment of the License Termination Plan for Crystal River Unit 3 Nuclear Generating Plant ML23310A0712023-11-0707 November 2023 Audit Plan Cover Letter - Crystal River Unit 3 Nuclear Generating Plant LTP ML23187A1112023-07-25025 July 2023 Acceptance of Requested Licensing Action License Request to Add License Condition to Include License Termination Plan Requirements ML23107A2722023-06-13013 June 2023 Letter Transmitting NRC Survey Results for East Settling Pond ML23160A2962023-06-0909 June 2023 Response to Crystal River, Unit 3 – Supplemental Information Needed for Acceptance on the Application for a License Amendment Regarding Approval of the License Termination Plan ML23107A2732023-06-0707 June 2023 Orise Independent Survey Report Dcn 5366-SR-01-0 IR 05000302/20220032023-05-25025 May 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2022003 ML23103A1902023-04-19019 April 2023 Request for Supplemental Information Cover Letter ML23058A2532023-03-22022 March 2023 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River, Unit 3 - NRC Inspection Report No. 05000302/2022003 ML22361A1022023-02-24024 February 2023 Reactor Decommissioning Branch Project Management Changes for Some Decommissioning Facilities and Establishment of Backup Project Manager for All Decommissioning Facilities ML22265A0192022-09-26026 September 2022 Nuclear Generating Plant - U.S. Nuclear Regulatory Commissions Analysis of ADP CR3, LLCs Decommissioning Funding Status Report (License No. DPR-72, Docket Nos. 50-302 and 72-1035) IR 05000302/20220022022-08-0909 August 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022002 IR 05000302/20220012022-05-0303 May 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report 05000302/2022001 ML22116A1752022-04-27027 April 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3- Independent Spent Fuel Storage Installation Security Inspection Report 07201035/2022401 ML22105A3992022-04-18018 April 2022 Nuclear Generating Plant - Change in NRC Project Manager ML22011A1362022-01-31031 January 2022 Independent Spent Fuel Storage Installation Security Inspection Plan ML22024A2142022-01-24024 January 2022 Nuclear Generating Plant - NMFS NRC Letter - Crystal River Energy Complex Biological Opinion Status (License No. DPR-72, Docket Nos. 50-302 and 72-1035) IR 05000302/20210042022-01-24024 January 2022 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report No. 05000302/2021004 ML21351A0052021-12-20020 December 2021 NRC Analysis of ADP CR3, LLC Decommissioning Funding Status Report for the Crystal River Unit 3 Nuclear Generating Plant (License No. DPR-72, Docket Nos. 50-302 and 72-1035) ML21322A2702021-11-24024 November 2021 Nuclear Generating Plant - Issuance of Amendment No. 260 Approving the Independent Spent Fuel Storage Installation Only Security Plan, Rev 3 IR 05000302/20210032021-11-0909 November 2021 Accelerated Decommissioning Partners (ADP) CR3, LLC, Crystal River Unit 3 - NRC Inspection Report Nos. 05000302/2021003 and 07201035/2021001 ML21288A4292021-10-18018 October 2021 Letter - Crystal River Unit 3 Nuclear Generating Plant - Correction to Safety Evaluation Related to the Issuance of Amendment No. 259 Approving the Independent Spent Fuel Storage Installation Only Emergency Plan 2024-09-23
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML23354A0632023-12-22022 December 2023 Cover Letter - Crystal River License Termination Plan Request for Additional Information ML23354A0642023-12-22022 December 2023 Enclosure - Crystal River License Termination Plan Request for Additional Information ML23313A1322023-11-15015 November 2023 Request for Additional Information for the Environmental Assessment of the License Termination Plan for Crystal River Unit 3 Nuclear Generating Plant ML23103A1922023-04-19019 April 2023 Request for Supplemental Information Enclosure ML21182A1032021-07-0606 July 2021 Request for Additional Information (RAI) Related to the ISFSI-Only Emergency Plan ML16032A1772016-02-0404 February 2016 J. Hickman, NRC, Letter to T. Hobbs, Crystal River 3, Request for Additional Information for Emergency Plan Change ML15026A4162015-02-0202 February 2015 Request for Additional Information Regarding the 10 CFR 50.54(p) Changes to the Security Plans ML14274A1392015-01-0808 January 2015 Request for Additional Information, License Amendment Request to Revise Technical Specifications and License Conditions to Create Permanently Defueled Technical Specifications ML14133A5032014-05-14014 May 2014 Correction, Request for Additional Information on the Post Shutdown Decommissioning Activities Report ML14104A0392014-04-28028 April 2014 Request for Additional Information on the Post Shutdown Decommissioning Activities Report ML13175A2152013-06-28028 June 2013 Request for Additional Information Regarding Request to Rescind Fukushima-Related Orders ML13018A3072013-02-0101 February 2013 Request for Additional Information for Extended Power Uprate License Amendment Request ML12355A6592012-12-21021 December 2012 Nuclear Generating Plant - RAI 9.3 of the Near-Term Task Force Fukushima Dai-ichi.. ML12333A0892012-12-19019 December 2012 Request for Additional Information for Extended Power Uprate License Amendment Request ML12310A2912012-11-15015 November 2012 Request for Additional Information for Changes to Security Plan ML12240A0152012-08-28028 August 2012 Request for Additional Information for Extended Power Uprate License Amendment Request ML12219A1912012-08-16016 August 2012 Request for Additional Information for Extended Power Uprate License Amendment Request ML12213A3032012-08-0303 August 2012 Request for Additional Information for Extended Power Uprate License Amendment Request (Srxb) ML12202A0602012-08-0202 August 2012 Request for Additional Information for Extended Power Uprate License Amendment Request ML12125A1622012-08-0101 August 2012 Nuclear Generating Plant - Request for Additional Information for Extended Power Uprate License Amendment Request ML12194A4172012-07-17017 July 2012 Generating Plant - Request for Additional Information for Extended Power Uprate License Amendment Request ML12174A2922012-07-0505 July 2012 Request for Additional Information for Extended Power Uprate License Amendment Request ML12171A3472012-07-0505 July 2012 Request for Additional Information for Extended Power Uprate License Amendment Request ML12102A0442012-05-0404 May 2012 Request for Additional Information for Extended Power Uprate License Amendment Request ML12056A0492012-03-12012 March 2012 Enclosure 3 - Recommendation 2.3: Seismic ML12056A0512012-03-12012 March 2012 Enclosure 5 - Recommendation 9.3: Emergency Preparedness ML12056A0502012-03-12012 March 2012 Enclosure 4 - Recommendation 2.3: Flooding ML12056A0482012-03-12012 March 2012 Enclosure 2 - Recommendation 2.1: Flooding ML12056A0472012-03-12012 March 2012 Enclosure 1 - Recommendation 2.1: Seismic ML12052A1302012-03-0202 March 2012 Request for Additional Information for Extended Power Uprate License Amendment Request ML12003A2172012-02-0808 February 2012 Nuclear Generating Plant - Request for Additional Information for Extended Power Uprate License Amendment Request ML11326A2312011-12-0707 December 2011 Request for Additional Information for Extended Power Uprate License Amendment Request ML11308A6592011-11-17017 November 2011 Generating Plant - Request for Additional Information Regarding 60-Day Response to Bulletin 2011-01, Mitigating Strategies ML11301A1142011-11-0808 November 2011 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application ML1128602942011-10-12012 October 2011 IR 05000302-11-005; 11/14-18/2011; Crystal River Unit 3, Notification of Inspection and Request for Information ML11175A1512011-06-30030 June 2011 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application ML11137A1742011-06-22022 June 2011 Nuclear Generating Plant; H. B. Robinson Steam Electric Plant, 2; and Shearon Harris Nuclear Power Plant, Unit 1 Request for Additional Information Regarding 2011 Decommissioning Funds ML1115403412011-06-0202 June 2011 Nuclear Generating Plant - Notification of Inspection and Request for Information 05000302/2011501 ML11122A0002011-05-26026 May 2011 Request for Additional Information for the Review of the Crystal River, Unit 3, License Renewal Application ML1112501592011-05-0505 May 2011 Notice of Inspection and Request for Information 05000302/2011003 ML1108202262011-03-31031 March 2011 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application ML1031402722010-11-16016 November 2010 Request for Additional Information for the Review of the Crystal Review Unit 3 Nuclear Generating Plant, License Renewal Application ML1029503292010-11-0808 November 2010 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant License Renewal Application ML1030202942010-10-28028 October 2010 Nuclear Generating Plant - Notification of Inspection and Request for Information IR 05000302-10-005 ML1027100652010-10-19019 October 2010 09/27/10 Summary of Telephone Conference Call Held Between NRC and Florida Power Corp., Concerning Draft Request for Information Related to Crystal River, Unit 3, License Renewal Application ML1026002432010-10-14014 October 2010 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application ML1022800102010-08-11011 August 2010 Nuclear Generating Plant - Draft RAIs Regarding Crystal River Unit 3 Part 26 Exemption Request ML1017404972010-07-0808 July 2010 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application ML1015303972010-07-0808 July 2010 RAI for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application ML1014105122010-06-0202 June 2010 Request for Additional Information for the Review of the Crystal River Unit 3 Nuclear Generating Plant, License Renewal Application 2023-04-19
[Table view] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 April 28, 2014 Mr. Terry D. Hobbs Decommissioning Director Crystal River Nuclear Plant (NA2C) 15760 W. Power Line Street Crystal River, FL 34428-6708
SUBJECT:
CRYSTAL RIVER UNIT 3- REQUEST FOR ADDITIONAL INFORMATION ON THE POST-SHUTDOWN DECOMMISSIONING ACTIVITIES REPORT (TAC NO. MF3210)
Dear Mr. Hobbs:
The U.S. Nuclear Regulatory Commission (NRC) staff is reviewing Duke Energy Florida, Inc.'s Post-Shutdown Decommissioning Activities Report, dated December 2, 2013, including the Site-Specific Decommissioning Cost Estimate, pursuant to Title 10 of the Code of Federal Regulations (10 CFR), Part 50, Sections 50.82(a)(4)(i) and 50.82(a)(8)(iii) for Crystal River Unit 3 (CR-3). The staff is also reviewing the Updated Irradiated Fuel Management Program per 10 CFR 50.54(bb), dated December 3, 2013, for CR-3.
The NRC staff determined that additional information is needed to complete our review.
Attached is our list of information requests. The NRC staff requests that you respond to them within 30 days of the date of this letter.
If you have any questions, please contact me at 301-415-1055 or via e-mail at Christopher. Gratton@ nrc.gov.
Sincerely, Christopher Gratton, Senior Project Manager Plant Licensing IV-2 and Decommissioning Transition Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No. 50-302
Enclosure:
As stated cc w/enclosure: Distribution via Listserv
REQUESTS FOR ADDITIONAL INFORMATION DUKE ENERGY FLORIDA INC.
CRYSTAL RIVER UNIT 3 DOCKET NO. 50-302 The U.S. Nuclear Regulatory Commission (NRC) staff is reviewing Duke Energy Florida's (DEF's) Post-Shutdown Decommissioning Activities Report (PSDAR) dated December 2, 2013 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML13340A009), and attached Site-Specific Decommissioning Cost Estimate (DCE) (ADAMS Accession No. ML13343A178) pursuant to Title 10 of the Code of Federal Regulations ( 10 CFR)
Part 50, Sections 50.82(a)(4)(i) and 50.82(a)(8)(iii) for Crystal River Unit 3 (CR-3). The staff is also reviewing the Updated Irradiated Fuel Management Program for CR-3 per 10 CFR 50.54(bb), dated December 3, 2013 (ADAMS Accession No. ML13340A008).
The NRC received comments from the public, which were used by the staff in the development of the following information request.
RAI#1:
Per 10 CFR 50.82(a)(4)(i), licensees must submit a PSDAR that has a Site-Specific DCE.
Regulatory Guide 1.185 Revision 1, "Standard Format and Content for Post-Shutdown Decommissioning Activities Report," indicates that the amount in the cost estimate cannot be less than the minimum amount calculated from 10 CFR 50.75(c). DEF did not provide the minimum amount from 10 CFR 50.75(c). Provide the minimum formula amount per 10 CFR 50.75(c)(1) for CR-3 in 2013 dollars. The staff requires assurance that the Site-Specific DCE for radiological decommissioning is not less than the minimum formula amount.
RAI#2:
Per 10 CFR 50.82(a)(4)(i), licensees must include in their Site-Specific DCEs costs for managing spent fuel. Section 50.54(bb) of 10 CFR requires licensees to provide a plan for management of spent fuel within 2 years of permanent cessation of operations. Provide additional information on "internal probability assessment" related to the dates when the Department of Energy (DOE) will assume control of spent nuclear fuel. Why did DEF assume 2032 as the first year that DOE will assume control of spent nuclear fuel in the country as discussed in Section 1 of the Site-Specific DCE?
RAI#3:
Per 10 CFR 50.82(a)(8)(iii), licensees must submit a Site-Specific DC E. Guidance for providing DCEs is provided in Regulatory Guide 1.202, "Standard Format and Content of Decommissioning Cost Estimates for Nuclear Power Reactors" (ADAMS Accession No. ML050230008).
Enclosure
Since information provided in the Site-Specific DCE is needed for reasonable assurance of availability of funds for decommissioning, the staff requests that DEF address the difference in Class 8 and C waste volume compared to the reference Pressurized-Water Reactor (PWR) in NUREG-1713, "Standard Review Plan for Decommissioning Cost Estimates for Nuclear Power Reactors" (ADAMS Accession No. ML043510113). The staff noted an 83-percent difference between combined Class 8 and C waste volume from Table 5.1 in the CR-3 Site-Specific DCE (1338 cubic feet) compared to those for the reference PWR in NUREG-1713, Table 20 (9900 cubic feet).
RAI#4:
Per 10 CFR 50.82(a)(8)(iii), licensees must submit a Site-Specific DC E. Guidance for providing DCEs is provided in Regulatory Guide 1.202, "Standard Format and Content of Decommissioning Cost Estimates for Nuclear Power Reactors" (ADAMS Accession No. ML050230008).
The staff requests that DEF address the difference in cost between Period 1, Planning and Preparation from NUREG-1713, Table 6, and the Site-Specific DCE Planning and Preparation amount from Table 2. In Table 2 of the Site-Specific DCE, DEF assumed approximately
$145 million in 2013 dollars. Table 6 of NUREG-1713 assumes $14.5 million, in 2000 dollars.
Assuming an adjustment per the Consumer Price Index, from 2000 dollars to 2013 dollars, NUREG-1713 Planning and Preparation costs would be approximately $20 million.
RAI#5:
Florida Public Service Commission (FPSC) Order No. PSC-13-0452-FOF-EI permits DEF to allocate its decommissioning trust fund among the three categories of license termination, spent fuel management, and site restoration. However, when requested by the licensee, the FPSC did not issue a declaratory statement prohibiting spent fuel management and site restoration funds to be used for license termination costs without FPSC approval. According to 10 CFR 50.82(8)(i)(A), "Decommissioning trust funds may be used by licensees if the withdrawals are for expenses for legitimate decommissioning activities consistent with the definition of decommissioning in §50.2." It is not clear to the NRC staff what portion of the nuclear decommissioning trust fund is meant for decommissioning as defined in 10 CFR 50.2.
DEF should provide documentation from the FPSC authorizing collections for decommissioning that describe the flow of funds into each of the three categories listed above, and the growth of those funds to their current amount. Information needed by the staff includes contributions by fund category, FPSC orders, and rates of returns on each of the funds.
RAI#6:
Section 50.82(a)(8)(vi) of 10 CFR states: "If the sum of the balance of any remaining decommissioning funds, plus earnings on such funds calculated at not greater than a 2-percent real rate of return, together with the amount provided by other financial assurance methods being relied upon, does not cover the estimated cost to complete the decommissioning, the
financial assurance status report must include additional financial assurance to cover the estimated cost of completion."
In the 2011 Preliminary DCE for CR-3 (ADAMS Accession No. ML113390139), a 2-percent real rate of return was assumed in Table 3. In the PSDAR Table 4, the real rate of return was lowered to 1.65 percent. The staff requests that DEF provide the FPSC Order authorizing DEF to use a real rate of return of 1.65 percent.
- .. ML14104A039 *Memo dated OFFICE NRRIDORULPL4-2/PM NRR!DORULPL4-2/LA NRR/DIRS/IFIB/BC NRRIDORULPL4-2/bc NAME CGratton BCiayton AKock* DBroaddus DATE 4/14/14 4/14/14 3/11/2014 4/28/14