ML13343A178

From kanterella
Jump to navigation Jump to search

Report P23-1680-001, Rev. 0, Site-Specific Decommissioning Cost Estimate for Crystal River Unit 3 Nuclear Generating Plant.
ML13343A178
Person / Time
Site: Crystal River Duke Energy icon.png
Issue date: 12/31/2013
From:
TLG Services
To:
Duke Energy Florida, Office of Nuclear Reactor Regulation
Shared Package
ML13343A183 List:
References
P23-1680-001, Rev 0
Download: ML13343A178 (101)


Text

DUKE ENERGY FLORIDA, INC.

CRYSTAL RIVER UNIT 3 DOCKET NUMBER 50-302 / LICENSE NUMBER DPR-72 ATTACHMENT 1 SITE-SPECIFIC DECOMMISSIONING COST ESTIMATE FOR THE CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT

Document No. P23-1680-001, Rev. 0 SITE-SPECIFIC DECOMMISSIONING COST EWRMATE for the CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT preparedfor Duke Energy Florida, Inc.

prepared by TLG Services, Inc.

Bridgewater, Connecticut December 2013

Crystal River Unit 3 Nuclear Generating Plant Document No. P23-1680-01,Rev. 0 Site-Specific Decommissioning Cost Estimate Page ii of xx APPROVALS Project Manager 1*24~ cZAl William A. Cloutier, Jr./ Date Project Engineer D,e" Zt JoIn A. Carlson Date Technical Manager Dat/e/

Francis f.Sy6A TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Page iii of xx TABLE OF CONTENTS SECTION PAGE SU M MARY ............................................................. vi-xx

1. IN TRO D U CTIO N ........................................................ 1-1 1.1 O bjectives of Study .................................................... 1-1 1.2 Site Description ....................................................... 1-1 1.3 Regulatory Guidance ................................................... 1-2 1.3.1 N uclear W aste Policy Act ............................................

1-4 1.3.2 Low -Level Radioactive W aste Acts .....................................

1-6 1.3.3 Radiological Criteria for License Term ination .............................

1-8

2. SAFSTOR DECOMMISSIONING ALTERNATIVE .................................. 2-1 2.1 Period 1 - Preparations .................................................. 2-1 2.2 Period 2 - D orm ancy ................................................... 2-2 2.3 Period 3 - Preparations for D ecom missioning ..................................

2-3 2.4 Period 4 - D ecom missioning .............................................. 2-4 2.5 Period 5 - Site Restoration ............................................... 2-7

3. CO ST ESTIMATE ........................................................ 3-1 3.1 Basis of Estim ate ...................................................... 3-1 3.2 M ethodology ......................................................... 3-1 3.3 Financial Com ponents of the Cost Model .....................................3-3 3.3.1 Contingency .................................................... 3-3 3.3.2 Financial Risk ................................................... 3-5 3.4 Site-Specific Considerations .............................................. 3-6 3.4.1 Spent Fuel M anagem ent ............................................ 3-6 3.4.2 Reactor Vessel and Internal Com ponents ................................

3-9 3.4.3 Prim ary System Com ponents .........................................

3-10 3.4.4 Retired Com ponents ............................................... 3-11 3.4.5 M ain Turbine and Condenser .........................................

3-11 3.4.6 Transportation M ethods ............................................3-11 3.4.7 Low -Level Radioactive W aste Disposal ..................................

3-12 3.4.8 Site Conditions Following Decommissioning ..............................

3-13 3.5 Assum ptions ......................................................... 3-14 3.5.1 Estim ating Basis ................................................. 3-14 3.5.2 Labor Costs ..................................................... 3-14 3.5.3 D esign Conditions .................................................3-15 3.5.4 General ........................................................ 3-16 3.6 Cost Estim ate Sum m ary ................................................ 3-18 TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Page iv of xx TABLE OF CONTENTS (continued)

SECTION PAGE

4. SCHEDULE ESTIMATE ................................................... 4-1 4.1 Schedule Estimate Assumptions ........................................... 4-1 4.2 Project Schedule ...................................................... 4-2
5. RADIOACTIVE WASTES ................................................... 5-1
6. RESULTS .................................................................................. 6-1
7. REFERENCES .............................................................................. 7-1 TABLES
1. Decommissioning Schedule ............................................................................ xvii
2. Decommissioning Cost Summary .................................................................. xviii
3. Schedule of License Termination Expenditures ............................................. xix:

3.1 Total Annual Expenditures ........................................................................... 3-19 3.2 License Termination Expenditures ............................................................... 3-21 3.3 Spent Fuel M anagement Expenditures ........................................................ 3-23 3.4 Site Restoration Expenditures ...................................................................... 3-24 4.1 Decommissioning Schedule ............................................................................. 4-3 5.1 Decommissioning W aste Summary ................................................................. 5-4 6.1 Decommissioning Cost Summary .................................................................... 6-4 6.2 Decommissioning Cost Element Contribution ................................................ 6-5 FIGURES 4.1 Deferred Decommissioning Activity Schedule ................................................. 4-4 4.2 Decommissioning Timeline .............................................................................. 4-5 5.1 Decommissioning W aste Disposition .............................................................. 5-3 APPENDICES A. Unit Cost Factor Development .............................................................. A-1 B. Unit Cost Factor Listing ................................................................... B-1 C. Detailed Cost Analysis ...................................................................... C-1 D. ISFSI Decommissioning Cost Analysis ....................................................... D-1 TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001,Rev. 0 Site-Specific DecommissioningCost Estimate Page v of xx REVISION LOG No. Date Item Revised Reason for Revision 0 12-02-2013 Original Issue TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Page vi of xx

SUMMARY

This report presents an estimate of the cost to decommission the Crystal River Unit 3 Nuclear Generating Plant (CR-3). The analysis relies upon site-specific, technical information from an earlier evaluation prepared in 2011,11] updated to reflect current assumptions pertaining to the disposition of the nuclear unit and relevant industry experience in undertaking such projects. This estimate has been prepared for Duke Energy Florida, Inc. (DEF), formerly known as Florida Power Corporation, to comply with the requirements of 10 CFR 50.82(a)(4)(i).

The current estimate is designed to provide DEF with sufficient information to assess its financial obligations, as they pertain to the decommissioning of the nuclear station.

It is not a detailed engineering document, but a financial analysis prepared in advance of the detailed engineering that will be required to carry out the decommissioning.

CR-3 has been safely shutdown since September 26, 2009, when the plant entered the Cycle 16 refueling outage to replace the steam generators. As of May 28, 2011, all fuel assemblies were removed from the reactor vessel and placed in the spent fuel pool for temporary storage. Certification of the permanent cessation of power operations and defueling was submitted to the Nuclear Regulatory Commission (NRC) on February 20, 2013.[21 DEF has announced its intention to decommission under the SAFSTOR alternative.

The currently projected total cost to decommission the nuclear unit, assuming the SAFSTOR alternative, is estimated at $1,180 million, as reported in 2013 dollars (DEF's share, as well as that of the nine minority owners). The cost includes the monies anticipated to be spent for operating license termination (radiological remediation), interim spent fuel storage and site restoration activities. The cost is based on several key assumptions in areas of regulation, component characterization, high-level radioactive waste management, low-level radioactive waste disposal, performance uncertainties (contingency) and site remediation and restoration requirements. The assumptions are discussed in more detail in this document.

"Preliminary Decommissioning Cost Estimate for the Crystal River Unit 3 Nuclear Generating Plant," Document No. P23-1651-001, Rev. 0, TLG Services, Inc., November 2011 2 FPC to NRC letter dated February 20, 2013, "Crystal River Unit 3 - Certificate of Permanent Cessation of Power Operations and that Fuel Has Been Permanently Removed from the Reactor" (ADAMS Accession No. ML13056A005)

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Page vii of xx Decommissioning Alternatives and Regulations The ultimate objective of the decommissioning process is to reduce the inventory of contaminated and activated material to levels at or below the site release criteria so that the license can be terminated. The NRC (or Commission) provided initial decommissioning requirements in its rule adopted on June 27, 1988.[13 In this rule, the NRC set forth financial criteria for decommissioning licensed nuclear power facilities.

The regulations addressed planning needs, timing, funding methods, and environmental review requirements for decommissioning. The decommissioning rulemaking also defined three decommissioning alternatives as being acceptable to the NRC: DECON, SAFSTOR, and ENTOMB.

DECON is defined as "the alternative in which the equipment, structures, and portions of a facility and site containing radioactive contaminants are removed or decontaminated to a level that permits the property to be released for unrestricted use shortly after cessation of operations."1 4]

SAFSTOR is defined as "the alternative in which the nuclear facility is placed and maintained in a condition that allows the nuclear facility to be safely stored and subsequently decontaminated (deferred decontamination) to levels that permit release for unrestricted use."[15 Decommissioning is to be completed within 60 years, although longer time periods will be considered when necessary to protect public health and safety.

ENTOMB is defined as "the alternative in which radioactive contaminants are encased in a structurally long-lived material, such as concrete; the entombed structure is appropriately maintained and continued surveillance is carried out until the radioactive material decays to a level permitting unrestricted release of the property."[61 As with the SAFSTOR alternative, decommissioning is currently required to be completed within 60 years, although longer time periods will also be considered when necessary to protect public health and safety.

The 60-year restriction has limited the practicality for the ENTOMB alternative at commercial reactors that generate significant amounts of long-lived radioactive 3 U.S. Code of Federal Regulations, Title 10, Parts 30, 40, 50, 51, 70 and 72 "General Requirements for Decommissioning Nuclear Facilities," Nuclear Regulatory Commission, Federal Register Volume 53, Number 123 (p 24018 et seq.), June 27, 1988.

4 Ibid. Page FR24022, Column 3.

5 Ibid.

6 Ibid. Page FR24023, Column 2.

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Page viii of xx material. In 1997, the Commission directed its staff to re-evaluate this alternative and identify the technical requirements and regulatory actions that would be necessary for entombment to become a viable option. The resulting evaluation provided several recommendations, however, rulemaking has been deferred pending the completion of additional research studies (e.g., on engineered barriers).

In 1996, the NRC published revisions to the general requirements for decommissioning nuclear power plants to clarify ambiguities and codify procedures and terminology as a means of enhancing efficiency and uniformity in the decommissioning process.[71 The amendments allow for greater public participation and better define the transition process from operations to decommissioning.

Regulatory Guide 1.184, issued in July 2000, further described the methods and procedures acceptable to the NRC staff for implementing the requirements of the 1996 revised rule relating to the initial activities and major phases of the decommissioning process. The costs and schedules presented in this analysis follow the general guidance and processes described in the amended regulations. The format and content of the estimate is also consistent with the recommendations of Regulatory Guide 1.202, issued in February 2005.[81 Basis of the Cost Estimate The decommissioning approach that has been selected by DEF for CR-3 is the SAFSTOR method. The primary objectives of the CR-3 decommissioning project are to remove the facility from service, reduce residual radioactivity to levels permitting unrestricted release, restore the site, perform this work safely, and complete the work in a cost effective manner. The selection of a preferred decommissioning alternative is influenced by a number of factors. These factors include the cost of each decommissioning alternative, minimization of occupational radiation exposure, availability of low-level waste disposal facilities, availability of a high-level waste (spent fuel) repository or Department of Energy (DOE) interim storage facility, regulatory requirements, and public concerns. In addition, 10 CFR 50.82(a)(3) requires decommissioning to be completed within 60 years of permanent cessation of operations.

Under the SAFSTOR methodology, the facility is placed in a safe and stable condition and maintained in that state, allowing levels of radioactivity to decrease through radioactive decay, followed by decontamination and dismantlement. After the safe 7 U.S. Code of Federal Regulations, Title 10, Parts 2, 50, and 51, "Decommissioning of Nuclear Power Reactors," Nuclear Regulatory Commission, Federal Register Volume 61, (P 39278 et seq.), July 29, 1996.

8 "Standard Format and Content of Decommissioning Cost Estimates for Nuclear Power Reactors,"

Regulatory Guide 1.202, U.S. Nuclear Regulatory Commission, February 2005 TLG Services, Inc.

CrystalRiver Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Page ix of xx storage period, the facility will be decontaminated and dismantled to levels that permit license termination. In accordance with 10 CFR 50.82(a)(9), a license termination plan (LTP) will be developed and submitted for NRC approval at least two years prior to termination of the license.

An Independent Spent Fuel Storage Installation (ISFSI) will be constructed adjacent to the power block. The spent fuel will be relocated from the auxiliary building to the ISFSI to await transfer to a DOE facility. Assuming priority pickup for the spent fuel from shutdown reactors, and based upon a 2032 start date, DEF anticipates that the removal of spent fuel from the site could be completed by the end of year 2036.

For purposes of this analysis, the plant remains in safe-storage until 2067, at which time it will be decommissioned and the site released for alternative use without restriction, i.e., the license is terminated within the required 60-year time period.

Methodology The primary goal of the decommissioning is the removal and disposal of the contaminated systems and structures so that the plant's operating license can be terminated. The analysis recognizes that spent fuel will be stored at the site in the plant's storage pool and/or in an ISFSI until such time that it can be transferred to the DOE. Consequently, the estimate includes those costs to manage and subsequently decommission the interim storage facilities.

The estimate is based on numerous fundamental assumptions, including regulatory requirements, low-level radioactive waste disposal practices, high-level radioactive waste management options, project contingencies, and site restoration requirements.

The methodology used to develop the estimate followed the basic approach originally presented in the AIF/NESP-036 study report, "Guidelines for Producing Commercial Nuclear Power Plant Decommissioning Cost Estimates,"1 91 and the DOE "Decommissioning Handbook."[' 01 These documents present a unit cost factor method for estimating decommissioning activity costs that simplifies the calculations. Unit factors for concrete removal ($/cubic yard), steel removal ($/ton),

and cutting costs ($/inch) were developed using local labor rates. The activity-dependent costs were then estimated with the item quantities (cubic yards and tons), developed from plant drawings and inventory documents. Removal rates and 9 T.S. LaGuardia et al., "Guidelines for Producing Commercial Nuclear Power Plant Decommissioning Cost Estimates," AIF/NESP-036, May 1986.

10 W.J. Manion and T.S. LaGuardia, "Decommissioning Handbook," U.S. Department of Energy, DOE/EV/10128-I, November 1980.

TLG Services, Inc.

CrystalRiver Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Page x of xx material costs for the conventional disposition of components and structures relied upon information available in the industry publication, "Building Construction Cost Data," published by R.S. Means.[I"]

The unit factor method provides a demonstrable basis for establishing reliable cost estimates. The detail provided in the unit factors, including activity duration, labor costs (by craft), and equipment and consumable costs, ensures that essential elements have not been omitted.

An activity duration critical path is used to determine the total decommissioning program schedule. The schedule is relied upon in calculating the carrying costs, which include program management, administration, field engineering, equipment rental, and support services, such as quality control and security.

This analysis reflected lessons learned from TLG's involvement in the Shippingport Station decommissioning, completed in 1989, as well as the decommissioning of the Cintichem reactor, hot cells, and associated facilities, completed in 1997. In addition, the planning and engineering for the Pathfinder, Shoreham, Rancho Seco, Trojan, Yankee Rowe, Big Rock Point, Maine Yankee, Humboldt Bay-3, Connecticut Yankee, and San Onofre-1 nuclear units have provided additional insight into the process, the regulatory aspects, and the technical challenges of decommissioning commercial nuclear units.

Contingency Consistent with cost estimating practice, contingencies are applied to the decontamination and dismantling costs developed as "specific provision for unforeseeable elements of cost within the defined project scope, particularly important where previous experience relating estimates and actual costs has shown that unforeseeable events which will increase costs are likely to occur."[12] The cost elements in the estimate are based on ideal conditions; therefore, the types of unforeseeable events that are almost certain to occur in decommissioning, based on industry experience, are addressed through a percentage contingency applied on a line-item basis. This contingency factor is a nearly universal element in all large-scale construction and demolition projects. It should be noted that contingency, as used in this analysis, does not account for price escalation and inflation in the cost of decommissioning over the life of the project.

11 "Building Construction Cost Data 2013," Robert Snow Means Company, Inc., Kingston, Massachusetts.

12 Project and Cost Engineers' Handbook, Second Edition, American Association of Cost Engineers, Marcel Dekker, Inc., New York, New York, p. 239.

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Page xi of xx Contingency funds are expected to be fully expended throughout the program. As such, inclusion of contingency is necessary to provide assurance that sufficient funding will be available to accomplish the intended tasks.

Low-Level Radioactive Waste Disposal The contaminated and activated material generated in the decontamination and dismantling of a commercial nuclear reactor is generally classified as low-level radioactive waste, although not all of the material is suitable for shallow-land disposal.

With the passage of the "Low-Level Radioactive Waste Disposal Act" in 1980 and its Amendments of 1985, [131 the states became ultimately responsible for the disposition of low-level radioactive waste generated within their own borders.

With the exception of Texas, no new compact facilities have been successfully sited, licensed, and constructed. Construction of the Texas Compact disposal facility is now essentially complete and the facility was declared operational by the operator, Waste Control Specialists (WCS), in November 2011. The facility will be able to accept limited quantities of non-Compact waste; however, at this time the cost for non-Compact generators is being negotiated on an individual basis.

Disposition of the various waste streams produced by the decommissioning process considered all options and services currently available to DEF. The majority of the low-level radioactive waste designated for direct disposal (Class A[1 41) can be sent to EnergySolutions' facility in Clive, Utah. Therefore, disposal costs for Class A waste were based upon DEF's Life of Plant Agreement with EnergySolutions. This facility is not licensed to receive higher activity waste (Class B and C).

The WCS facility is able to receive the Class B and C waste. As such, for this analysis, Class B and C waste is assumed to be shipped to the WCS facility and disposal costs for the waste were based upon preliminary and indicative information on the cost for such from WCS (and intermediary processors such as Studsvik).

The dismantling of the components residing closest to the reactor core generates radioactive waste that may be considered unsuitable for shallow-land disposal (i.e.,

low-level radioactive waste with concentrations of radionuclides that exceed the limits established by the NRC for Class C radioactive waste (GTCC)). The Low-Level Radioactive Waste Policy Amendments Act of 1985 assigned the federal 13 "Low-Level Radioactive Waste Policy Amendments Act of 1985," Public Law 99-240, January 15, 1986 14 Waste is classified in accordance with U.S. Code of Federal Regulations, Title 10, Part 61.55, "Licensing Requirements for Land Disposal of Radioactive Waste" TLG Services, Inc.

Crystal River Unit 3 Nuclear Generating Plant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Pagexii of xx government the responsibility for the disposal of this material. The Act also stated that the beneficiaries of the activities resulting in the generation of such radioactive waste bear all reasonable costs of disposing of such waste. However, to date, the federal government has not identified a cost for disposing of GTCC or a schedule for acceptance.

For purposes of this study, components that must be disposed of as GTCC waste would be packaged in the same canisters used for spent fuel. Because dismantlement would occur after the projected date for DOE acceptance of spent fuel and high level waste, for purposes of this study it is assumed that the canisters would be shipped directly to a DOE facility.

A significant portion of the waste material generated during decommissioning may only be potentially contaminated by radioactive materials. This waste can be analyzed on site or shipped off site to licensed facilities for further analysis, for processing and/or for conditioning/recovery. Reduction in the volume of low-level radioactive waste requiring disposal in a licensed low-level radioactive waste disposal facility can be accomplished through a variety of methods, including analyses and surveys or decontamination to eliminate the portion of waste that does not require disposal as radioactive waste, compaction, incineration or metal melt.

The estimate reflects the savings from waste recovery/volume reduction.

High-Level Radioactive Waste Manaement Congress passed the "Nuclear Waste Policy Act" (NWPA) in 1982, assigning the federal government's long-standing responsibility for disposal of the spent nuclear fuel created by the commercial nuclear generating plants to the DOE. The DOE was to begin accepting spent fuel and high-level waste by January 31, 1998; however, to date no progress in the removal of spent fuel from commercial generating sites has been made.

Today, the country is at an impasse on high-level waste disposal, even with the iUcense Application for a geologic repository submitted by the DOE to the NRC in 2008. The current administration has cut the budget for the repository program while promising to "conduct a comprehensive review of policies for managing the back end of the nuclear fuel cycle ... and make recommendations for a new plan."[' 5 ]

Towards this goal, the administration appointed a Blue Ribbon Commission on America's Nuclear Future (Blue Ribbon Commission) to make recommendations for a new plan for nuclear waste disposal. The Blue Ribbon Commission's charter 15 Blue Ribbon Commission on America's Nuclear Future's Charter, http://cvbercemeterv.unt.edu/archive/brc/20120620215336/httR://brc.gov/index.php)?o=page/charter TLG Services, Inc.

Crystal River Unit 3 Nuclear Generating Plant Document No. P23-1"0-01,Rev. 0 Site-Specific Decommissioning Cost Estimate Page xiii of xx includes a requirement that it consider "jolptiona for safe storage of used nuclear fuel while final disposition pathways are selected and deployed."t6 On January 26, 2012, the Blue Ribbon Commission issued its "Report to the Secretary of Energy" containing a number of recommendations on nuclear waste disposal. Two of the recommendations that may impact decommissioning planning are:

S"[The United States [should] establish a program that leads to the timely development of one or more consolidated storage facilities"9 1 71 S"IT]he United States should undertake an integrated nuclear waste management program that leads to the timely development of one or more permanent deep geological facilities for the safe disposal of spent fuel and high-level nuclear waste."[Ns]

In January 2013, the DOE issued the "Strategy for the Management and Disposal of Used Nuclear Fuel and High-Level Radioactive Waste," in response to the recommendations made by the Blue Ribbon Commission and as "a framework for moving toward a sustainable program to deploy an integrated system capable of transporting, storing, and disposing of used nuclear fuel..."l'91 "With the appropriate authorizations from Congress, the Administration currently plans to implement a program over the next 10 years that:

" Sites, designs and licenses, constructs and begins operations of a pilot interim storage facility by 2021 with an initial focus on accepting used nuclear fuel from shut-down reactor sites;

" Advances toward the siting and licensing of a larger interim storage facility to be available by 2025 that will have sufficient capacity to provide flexibility in the waste management system and allows for acceptance of enough used nuclear fuel to reduce expected government liabilities; and 16 Ibid.

17 "Blue Ribbon Commission on America's Nuclear Future, Report to the Secretary of Energy,"

http://www.brc.gov/sites/default/files/documents/brc finalrevort ian2012.udf p. 32, January 2012 18 Ibid., p. 2 7 19 "Strategy for the Management and Disposal of Used Nuclear Fuel and High-Level Radioactive Waste," U.S. DOE, January 11, 2013 TLG Services,Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Page xiv of xx

  • Makes demonstrable progress on the siting and characterization of repository sites to facilitate the availability of a geologic repository by 2048."[201 In 2010, the government discontinued work on the review of the application to construct a geologic repository for spent nuclear fuel and high-level waste at Yucca Mountain. However, the US Court of Appeals for the District of Columbia Circuit recently issued a writ of mandamus (in August 2013) ordering NRC to comply with federal law and restart its review of DOE's Yucca Mountain repository license application.

Even with a favorable review, there is considerable uncertainty as to DOE's future actions on the growing backlog of spent fuel, even with the additional direction provided by the Blue Ribbon Commission. For purposes of this analysis, Duke Energy evaluated the feasibility of several spent fuel disposition scenarios, both near-term (e.g., 2021) and long-term (e.g., 2048), as well as a more moderate scenario.

For purposes of this estimate, the spent fuel management plan for the CR-3 spent fuel is based in general upon: 1) a 2032 start date for DOE initiating transfer of commercial spent fuel to a federal facility, 2) priority pickup for shutdown reactors, and 3) pickup based on the permanent shutdown date of the plant (oldest fuel first).

Assuming a maximum rate of transfer of 3,000 metric tons of uranium (MTU)/year, [211 and the aforementioned assumptions on spent fuel management, transfer of spent fuel from CR-3 to DOE would begin in 2035 and the spent fuel from CR-3 would be completely removed from the site by the end of 2036.

The NRC requires that licensees establish a program to manage and provide funding for the caretaking of all irradiated fuel at the reactor site until title of the fuel is transferred to the DOE. [221 Interim storage of the fuel, until the DOE has completed the transfer, will be in the auxiliary building's storage pool, as well as at an ISFSI to be constructed on the site. Once the wet storage pool is emptied, the auxiliary building can be prepared for long-term storage.

DEF's position is that the DOE has a contractual obligation to accept the spent fuel earlier than the projections set out above consistent with its contract commitments. No assumption made in this study should be interpreted to be inconsistent with this claim.

20 Ibid., p.2 21 "Acceptance Priority Ranking & Annual Capacity Report," DOE/RW-0567, July 2004 22 U.S. Code of Federal Regulations, Title 10, Part 50- Domestic Licensing of Production and Utilization Facilities, Subpart 54 (bb), "Conditions of Licenses" TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Page xv of xx Site Restoration The efficient removal of the contaminated materials at the site may result in damage to many of the site structures. Blasting, coring, drilling, and the other decontamination activities can substantially damage power block structures, potentially weakening the footings and structural supports. It is unreasonable to anticipate that these structures would be repaired and preserved after the radiological contamination is removed. Dismantling site structures with a work force already mobilized is more efficient and less costly than if the process is deferred. Consequently, this study assumes that site structures addressed by this analysis are removed to a nominal depth of three feet below the top grade of the embankment, wherever possible.

The cost for the site restoration of decontaminated and/or non-contaminated structures has been calculated and is separately presented as "Site Restoration" expenditures in this report.

Summary The cost to decommission CR-3 assumes the removal of all contaminated and activated plant components and structural materials such that DEF may then have unrestricted use of the site with no further requirements for an operating license. Low-level radioactive waste, other than GTCC waste, is sent to a commercial processor for treatment/conditioning or to a controlled disposal facility.

Decommissioning is accomplished within the 60-year period required by current NRC regulations. In the interim, the spent fuel remains in storage at the site until such time that the transfer to a DOE facility is complete. Once emptied, the storage facilities are also decommissioned.

The decommissioning scenario is described in Section 2. The assumptions are presented in Section 3, along with schedules of annual expenditures. The major cost contributors are identified in Section 6, with detailed activity costs, waste volumes, and associated manpower requirements delineated in Appendix C.

The cost elements in the estimate are assigned to one of three subcategories: NRC License Termination, Spent Fuel Management, and Site Restoration. The subcategory "NRC License Termination" is used to accumulate costs that are consistent with "decommissioning" as defined by the NRC in its financial assurance regulations (i.e.,

10 CFR Part 50.75). In situations where the long-term management of spent fuel is not an issue, the cost reported for this subcategory is generally sufficient to terminate the unit's operating license.

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Page xvi of xx The "Spent Fuel Management" subcategory contains costs associated with the containerization and transfer of spent fuel from the wet storage pool to the ISFSI, as well as the eventual transfer of the spent fuel at the ISFSI to the DOE. Costs are included for the operation of the storage pool and the management of the ISFSI until such time that the transfer is complete. It does not include any spent fuel management expenses incurred prior to June 3, 2013, cost to construct the ISFSI, purchase the horizontal storage modules, nor does it include any costs related to the final disposal of the spent fuel.

"Site Restoration" is used to capture costs associated with the dismantling and demolition of buildings and facilities demonstrated to be free from contamination. This includes structures never exposed to radioactive materials, as well as those facilities that have been decontaminated to appropriate levels.

It should be noted that the costs assigned to these subcategories are allocations.

Delegation of cost elements is for the purposes of comparison (e.g., with NRC financial guidelines) or to permit specific financial treatment (e.g., Asset Retirement Obligation determinations). In reality, there can be considerable interaction between the activities in the three subcategories. For example, DEF may decide to remove non-contaminated structures early in the project to improve access to highly contaminated facilities or plant components. In these instances, the non-contaminated removal costs could be reassigned from Site Restoration to an NRC License Termination support activity. However, in general, the allocations represent a reasonable accounting of those costs that can be expected to be incurred for the specific subcomponents of the total estimated program cost, if executed as described.

As noted within this document, the estimate is developed and costs are presented in 2013 dollars. As such, the estimate does not reflect the escalation of costs (due to inflationary and market forces) during the decommissioning project. The decommissioning periods and milestone dates for the analyzed SAFSTOR decommissioning scenario are identified in Table 1. The cost projected for license termination (in accordance with 10 CFR 50.75) is shown at the bottom of Table 2 along with the costs for spent fuel management and site restoration. The schedule of expenditures for license termination activities is provided in Table 3.

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Page xvii of xx TABLE 1 DECOMMISSIONING SCHEDULE Start End Duration Decommissioning Periods (years)

Period 1: Planning and Preparations [11 03 Jun 2013 01 Jul 2015 2.08 Period 2a: Dormancy w/Wet Fuel Storage 01 Jul 2015 13 Aug 2019 4.12 Period 2b: Dormancy w/Dry Fuel Storage 13 Aug 2019 31 Dec 2036 17.39 Period 2c: Dormancy w/No Fuel Storage 31 Dec 2036 23 May 2067 30.39 Period 3a: Site Reactivation 23 May 2067 22 May 2068 1.00 Period 3b: Decommissioning Prep 22 May 2068 21 Nov 2068 0.50 Period 4a: Large Component Removal 21 Nov 2068 03 May 2070 1.45 Period 4b: Plant Systems Removal and Building Remediation 03 May 2070 22 May 2072 2.05 Period 4f: License Termination 22 May 2072 20 Feb 2073 0.75 Period 5b: Site Restoration 20 Feb 2073 21 Aug 2074 1.50 Total [21 61.22

[1] While permanent cessation of operations was declared on February 20, 2013, decommissioning costs are accumulated as of June 2013

[21 Columns may not add due to rounding TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Page xviii of xx TABLE 2 DECOMMISSIONING COST

SUMMARY

[1]

(thousands of 2013 dollars)

License Spent Fuel Site Decommissioning Periods Termination Management Restoration Period 1: Planning and Preparations [21 145,653 33,638 Period 2a: Dormancy w/Wet Fuel Storage [31 28,071 147,032 Period 2b: Dormancy w/Dry Fuel Storage 94,344 84,835 Period 2c: Dormancy w/No Fuel Storage 163,892 Period 3a: Site Reactivation 43,152 667 Period 3b: Decommissioning Prep 34,626 - 876 Period 4a: Large Component Removal 170,798 - 2,356 Period 4b: Plant Systems Removal and Building Remediation 155,222 - 1,397 Period 4f: License Termination 25,926 -

Period 5b: Site Restoration 219 - 47,424 Total [41 861,902 265,505 [5] 52,721

[1] Represents the total cost of decommissioning: DEF's share (91.8%), as well as that of the nine minority owners: City of Alachua, City of Bushnell, City of Gainesville, City of Kissimmee, City of Leesburg, City of Ocala, Orlando Utilities Commission, Seminole Electric Cooperative, and City of New Smyrna Beach

[21 Includes site costs (budgets for 2013, 2014 and the first half of 2015), installation of the alternative spent fuel cooling system, shutdown electrical line-up, and removal of legacy waste from the site

[31 Includes site costs to off-load the spent fuel pool to the ISFSI (completed in 2019)

[41 Columns may not add due to rounding

[51 $93.8M in ISFSI construction costs funded from sources outside the DTF are not included in the total TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Page xix of xx TABLE3 SCHEDULE OF LICENSE TERMINATION EXPENDITURES (thousands, 2013 dollars)

Equipment & LLRW Year Labor Materials Energy Disposal Other Total 2013 30,458 1,554 0 0 1,640 33,652 2014 52,440 2,675 0 6,000 6,385 67,500 2015 27,196 1,567 56 14,007 5,109 47,935 2016 2,371 479 ill 15 3,855 6,831 2017 2,364 477 ill 15 3,845 6,812 2018 2,364 477 ill 15 3,845 6,812 2019 2,364 418 ill 12 3,370 6,275 2020 2,370 326 ill 7 2,623 5,437 2021 2,364 325 ill 7 2,616 5,422 2022 2,364 325 ill 7 2,616 5,422 2023 2,364 325 ill 7 2,616 5,422 2024 2,370 326 ill 7 2,623 5,437 2025 2,364 325 ill 7 2,616 5,422 2026 2,364 325 ill 7 2,616 5,422 2027 2,364 325 ill 7 2,616 5,422 2028 2,370 326 ill 7 2,623 5,437 2029 2,364 325 ill 7 2,616 5,422 2030 2,364 325 ill 7 2,616 5,422 2031 2,364 325 ill 7 2,616 5,422 2032 2,370 326 ill 7 2,623 5,437 2033 2,364 325 ill 7 2,616 5,422 2034 2,364 325 ill 7 2,616 5,422 2035 2,364 325 ill 7 2,616 5,422 2036 2,370 326 ill 7 2,623 5,437 2037 2,364 317 ill 6 2,592 5,390 2038 2,364 317 ill 6 2,592 5,390 2039 2,364 317 ill 6 2,592 5,390 2040 2,370 318 ill 6 2,599 5,404 2041 2,364 317 ill 6 2,592 5,390 2042 2,364 317 ill 6 2,592 5,390 2043 2,364 317 ill 6 2,592 5,390 2044 2,370 318 ill 6 2,599 5,404 2045 2,364 317 ill 6 2,592 5,390 2046 2,364 317 ill 6 2,592 5,390 2047 2,364 317 ill 6 2,592 5,390 2048 2,370 318 ill 6 2,599 5,404 TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Page xx of xx TABLE 3 (continued)

SCHEDULE OF LICENSE TERMINATION EXPENDITURES (thousands, 2013 dollars)

Equipment & LLRW Year Labor Materials Energy Disposal Other Total 2049 2,364 317 ill 6 2,592 5,390 2050 2,364 317 ill 6 2,592 5,390 2051 2,364 317 ill 6 2,592 5,390 2052 2,370 318 ill 6 2,599 5,404 2053 2,364 317 ill 6 2,592 5,390 2054 2,364 317 ill 6 2,592 5,390 2055 2,364 317 ill 6 2,592 5,390 2056 2,370 318 ill 6 2,599 5,404 2057 2,364 317 ill 6 2,592 5,390 2058 2,364 317 ill 6 2,592 5,390 2059 2,364 317 ill 6 2,592 5,390 2060 2,370 318 ill 6 2,599 5,404 2061 2,364 317 ill 6 2,592 5,390 2062 2,364 317 ill 6 2,592 5,390 2063 2,364 317 ill 6 2,592 5,390 2064 2,370 318 ill 6 2,599 5,404 2065 2,364 317 ill 6 2,592 5,390 2066 2,364 317 ill 6 2,592 5,390 2067 23,365 1,272 722 22 3,080 28,461 2068 45,542 9,911 1,108 3,235 4,880 64,677 2069 47,629 24,558 1,055 28,524 16,304 118,071 2070 44,857 14,448 907 18,276 11,268 89,757 2071 43,465 9,372 833 13,130 8,740 75,541 2072 35,266 4,691 461 5,126 5,040 50,584 2073 4,223 233 30 4 366 4,857 2074 93 0 0 0 93 Total 475,185, 87,166 10,843 88,687, 200,021 861,902 Note: Total costs reported (i.e., there is no cost allocation by ownership share)

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 1, Page I of 9

1. INTRODUCTION This report presents an estimate of the cost to decommission the Crystal River Unit 3 Nuclear Generating Plant (CR-3). The analysis relies upon site-specific, technical information from an earlier evaluation prepared in 2011,[11 updated to reflect current assumptions pertaining to the disposition of the nuclear unit and relevant industry experience in undertaking such projects. This estimate has been prepared for Duke Energy Florida, Inc. (DEF), formerly known as Florida Power Corporation, to comply with the requirements of 10 CFR 50.82(a)(4)(i).

The current estimate is designed to provide DEF with sufficient information to assess its financial obligations, as they pertain to the decommissioning of the nuclear station.

It is not a detailed engineering document, but a financial analysis prepared in advance of the detailed engineering that will be required to carry out the decommissioning.

1.1 OBJECTIVES OF STUDY The objectives of this study were to prepare a comprehensive estimate of the costs to decommission CR-3, to provide a sequence or schedule for the associated activities, and to develop waste stream projections from the decontamination and dismantling activities.

CR-3 has been safely shutdown since September 26, 2009, when the plant entered the Cycle 16 refueling outage to replace the steam generators. As of May 28, 2011, all fuel assemblies were removed from the reactor vessel and placed in the spent fuel pool for temporary storage. Certification of the permanent cessation of power operations and defueling was submitted to the NRC on February 20, 2013.[21 DEF has announced its intention to decommission under the SAFSTOR alternative.

1.2 SITE DESCRIPTION The CR-3 site is located in Citrus County, Florida, approximately 70 miles north of Tampa on the shore of the Gulf of Mexico. The generating site is comprised of four fossil-fired units and one nuclear unit. The Gulf of Mexico provides the heat sink for both Units 1 and 2 fossil-fired units, and the nuclear unit (natural draft towers provide the cooling for Units 4 and 5).

The nuclear steam supply system (NSSS) consists of a pressurized water reactor and a two-loop reactor coolant system, designed by Babcock & Wilcox.

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 1, Page 2 of 9 The generating unit had a reference core design of 2609 MWt (thermal), with a corresponding net dependable capability electrical rating of 860 megawatts (electric) with the reactor at rated power.

The reactor coolant system is comprised of the reactor vessel and two heat transfer loops, each loop containing a vertical once-through type steam generator, and two single speed centrifugal reactor coolant pumps. In addition, the system includes an electrically heated pressurizer, a reactor coolant drain tank and interconnected piping. The system is housed within the reactor containment building or reactor building, a seismic Category I reinforced concrete structure. The reactor building is a reinforced concrete structure composed of a vertical cylinder with a shallow dome and flat circular foundation slab. The cylinder wall is prestressed with a post-tensioning system in the vertical and horizontal directions. The dome roof is prestressed utilizing a three-way post-tensioning system. The foundation slab is reinforced with conventional mild steel. The inside surface of the reactor building is lined with a carbon steel liner to ensure a high degree of leak tightness during operating and accident conditions.

Heat produced in the reactor was converted to electrical energy by the steam and power conversion system. A turbine -generator system converted the thermal energy of steam produced in the steam generators into mechanical shaft power and then into electrical energy. The unit's turbine generator consists of high-pressure and low-pressure turbine sections driving a direct-coupled generator at 1800 rpm. The turbines were operated in a closed feedwater cycle, which condensed the steam; the heated feedwater was returned to the steam generators. Heat rejected in the main condensers was removed by the circulating water system. The condenser circulating water was taken from and returned to the Gulf of Mexico through the intake and discharge canals, respectively.

1.3 REGULATORY GUIDANCE The NRC provided initial decommissioning requirements in its rule "General Requirements for Decommissioning Nuclear Facilities," issued in June 1988.[31 This rule set forth financial criteria for decommissioning licensed nuclear power facilities. The regulation addressed decommissioning planning needs, timing, funding methods, and environmental review requirements. The intent of the rule was to ensure that decommissioning would be accomplished in a safe and timely manner and that adequate funds would be available for this purpose. Subsequent to the rule, the NRC issued Regulatory Guide 1.159, "Assuring the Availability of Funds for Decommissioning Nuclear Reactors,"[41 which provided additional guidance to the licensees of nuclear facilities on the TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Section 1, Page 3 of 9 financial methods acceptable to the NRC staff for complying with the requirements of the rule. The regulatory guide addressed the funding requirements and provided guidance on the content and form of the financial assurance mechanisms indicated in the rule.

The decommissioning rulemaking defined three decommissioning alternatives as being acceptable to the NRC: DECON, SAFSTOR, and ENTOMB. The DECON alternative assumes that any contaminated or activated portion of the plant's systems, structures and facilities are removed or decontaminated to levels that permit the site to be released for unrestricted use shortly after the cessation of plant operations. The rule also placed limits on the time allowed to complete the decommissioning process. For SAFSTOR, the process is restricted in overall duration to 60 years, unless it can be shown that a longer duration is necessary to protect public health and safety. The guidelines for ENTOMB are similar, providing the NRC with both sufficient leverage and flexibility to ensure that these deferred options are only used in situations where it is reasonable and consistent with the definition of decommissioning. At the conclusion of a 60-year dormancy period (or longer for ENTOMB if the NRC approves such a case), the site would still require significant remediation to meet the unrestricted release limits for license termination.

The ENTOMB alternative has not been viewed as a viable option for power reactors due to the significant time required to isolate the long-lived radionuclides for decay to permissible levels. With rulemaking permitting the controlled release of a site,[5] the NRC has re-evaluated this alternative. The resulting feasibility study, based upon an assessment by Pacific Northwest National Laboratory, concluded that the method did have conditional merit for some, if not most reactors. The staff also found that additional rulemaking would be needed before this option could be treated as a generic alternative.

The NRC had considered rulemaking to alter the 60-year time for completing decommissioning and to clarify the use of engineered barriers for reactor entombments.[6 ] However, the NRC's staff has recommended that rulemaking be deferred, based upon several factors, e.g., no licensee has committed to pursuing the entombment option, the unresolved issues associated with the disposition of greater-than-Class C material (GTCC), and the NRC's current priorities, at least until after the additional research studies are complete. The Commission concurred with the staffs recommendation.

In 1996, the NRC published revisions to the general requirements for decommissioning nuclear power plants.[71 When the decommissioning regulations were adopted in 1988, it was assumed that the majority of licensees would decommission at the end of the facility's operating licensed life.

Since that time, several licensees permanently and prematurely ceased TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Section 1, Page 4 of 9 operations. Exemptions from certain operating requirements were required once the reactor was defueled to facilitate the decommissioning. Each case was handled individually, without clearly defined generic requirements. The NRC amended the decommissioning regulations in 1996 to clarify ambiguities and codify procedures and terminology as a means of enhancing efficiency and uniformity in the decommissioning process. The amendments allow for greater public participation and better define the transition process from operations to decommissioning.

Under the revised regulations, licensees will submit written certification to the NRC within 30 days after the decision to cease operations. Certification will also be required once the fuel is permanently removed from the reactor vessel.

Submittal of these notices will entitle the licensee to a fee reduction and eliminate the obligation to follow certain requirements needed only during operation of the reactor. Within two years of submitting notice of permanent cessation of operations, the licensee is required to submit a Post-Shutdown Decommissioning Activities Report (PSDAR) to the NRC. The PSDAR describes the planned decommissioning activities, the associated sequence and schedule, and an estimate of expected costs. Prior to completing decommissioning, the licensee is required to submit an application to the NRC to terminate the license, which will include a license termination plan (LTP).

1.3.1 Nuclear Waste Policy Act Congress passed the "Nuclear Waste Policy Act"[8 ] (NWPA) in 1982, assigning the federal government's long-standing responsibility for disposal of the spent nuclear fuel created by the commercial nuclear generating plants to the DOE. The DOE was to begin accepting spent fuel and high-level waste by January 31, 1998; however, to date no progress in the removal of spent fuel from commercial generating sites has been made.

Today, the country is at an impasse on high-level waste disposal, even with the License Application for a geologic repository submitted by the DOE to the NRC in 2008. The current administration has cut the budget for the repository program while promising to "conduct a comprehensive review of policies for managing the back end of the nuclear fuel cycle ...

and make recommendations for a new plan."[a9 Towards this goal, the administration appointed a Blue Ribbon Commission on America's Nuclear Future (Blue Ribbon Commission) to make recommendations for a new plan for nuclear waste disposal. The Blue Ribbon Commission's charter includes a requirement that it consider "[o]ptions TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 1, Page 5 of 9 for safe storage of used nuclear fuel while final disposition pathways are selected and deployed."

On January 26, 2012, the Blue Ribbon Commission issued its "Report to the Secretary of Energy"1101 containing a number of recommendations on nuclear waste disposal. Two of the recommendations that may impact decommissioning planning are:

" "[T]he United States [should] establish a program that leads to the timely development of one or more consolidated storage facilities"

" "[Tjhe United States should undertake an integrated nuclear waste management program that leads to the timely development of one or more permanent deep geological facilities for the safe disposal of spent fuel and high-level nuclear waste."

In January 2013, the DOE issued the "Strategy for the Management and Disposal of Used Nuclear Fuel and High-Level Radioactive Waste," in response to the recommendations made by the Blue Ribbon Commission and as "a framework for moving toward a sustainable program to deploy an integrated system capable of transporting, storing, and disposing of used nuclear fuel..."W]

"With the appropriate authorizations from Congress, the Administration currently plans to implement a program over the next 10 years that:

" Sites, designs and licenses, constructs and begins operations of a pilot interim storage facility by 2021 with an initial focus on accepting used nuclear fuel from shut-down reactor sites;

" Advances toward the siting and licensing of a larger interim storage facility to be available by 2025 that will have sufficient capacity to provide flexibility in the waste management system and allows for acceptance of enough used nuclear fuel to reduce expected government liabilities; and

" Makes demonstrable progress on the siting and characterization of repository sites to facilitate the availability of a geologic repository by 2048."

In 2010, the government discontinued work on the review of the application to construct a geologic repository for spent nuclear fuel and high-level waste at Yucca Mountain. However, the US Court of Appeals for the District of Columbia Circuit recently issued a writ of mandamus TLG Services,Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Section 1, Page 6 of 9 (in August 2013) ordering NRC to comply with federal law and restart its review of DOE's Yucca Mountain repository license application.

Even with a favorable review, there is considerable uncertainty as to DOE's future actions on the growing backlog of spent fuel, even with the additional direction provided by the Blue Ribbon Commission. For purposes of this analysis, Duke Energy evaluated the feasibility of several spent fuel disposition scenarios, both near (e.g., 2021) and long-term (e.g., 2048), as well as a more moderate scenario.

For purposes of this estimate, the spent fuel management plan for the CR-3 spent fuel is based in general upon: 1) a 2032 start date for DOE initiating transfer of commercial spent fuel to a federal facility, 2) priority pickup for shutdown reactors, and 3) pickup based on the permanent shutdown date of the plant (oldest fuel first). Assuming a maximum rate of transfer of 3,000 metric tons of uranium (MTU)/year, [121 and the aforementioned assumptions on spent fuel management, transfer of spent fuel from CR-3 to DOE would begin in 2035 and the spent fuel from CR-3 would be completely removed from the site by the end of 2036.

The NRC requires that licensees establish a program to manage and provide funding for the caretaking of all irradiated fuel at the reactor site until title of the fuel is transferred to the DOE. 1131 Interim storage of the fuel, until the DOE has completed the transfer, will be in the auxiliary building's storage pool, as well as at an Independent Spent Fuel Storage Facility (ISFSI) to be constructed on the site. Once the wet storage pool is emptied, the auxiliary building can be prepared for long-term storage.

DEF's position is that the DOE has a contractual obligation to accept the spent fuel earlier than the projections set out above consistent with its contract commitments. No assumption made in this study should be interpreted to be inconsistent with this claim.

1.3.2 Low-Level Radioactive Waste Acts The contaminated and activated material generated in the decontamination and dismantling of a commercial nuclear reactor is classified as low-level (radioactive) waste, although not all of the material is suitable for "shallow-land" disposal. With the passage of the "Low-Level Radioactive Waste Policy Act" in 1980,[141 and its Amendments of 1985,[15] the states became ultimately responsible for the disposition of low-level radioactive waste generated within their own borders.

TLG Services, Inc.

CrystalRiver Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Section 1, Page 7 of 9 With the exception of Texas, no new compact facilities have been successfully sited, licensed, and constructed. Construction of the Texas Compact disposal facility is now essentially complete and the facility was declared operational by the operator, Waste Control Specialists (WCS), in November 2011. The facility will be able to accept limited quantities of non-Compact waste; however, at this time the cost for non-Compact generators is being negotiated on an individual basis.

Disposition of the various waste streams produced by the decommissioning process considered all options and services currently available to DEF. The majority of the low-level radioactive waste designated for direct disposal (Class A[11]) can be sent to EnergySolutions' facility in Clive, Utah. Therefore, disposal costs for Class A waste were based upon DEF's Life of Plant Agreement with EnergySolutions. This facility is not licensed to receive higher activity waste (Class B and C).

The WCS facility is able to receive the Class B and C waste. As such, for this analysis, Class B and C waste is assumed to be shipped to the WCS facility and disposal costs for the waste were based upon preliminary and indicative information on the cost for such from WCS (and intermediary processors such as Studsvik).

The dismantling of the components residing closest to the reactor core generates radioactive waste that may be considered unsuitable for shallow-land disposal (i.e., low-level radioactive waste with concentrations of radionuclides that exceed the limits established by the NRC for Class C radioactive waste (GTCC)). The Low-Level Radioactive Waste Policy Amendments Act of 1985 assigned the federal government the responsibility for the disposal of this material. The Act also stated that the beneficiaries of the activities resulting in the generation of such radioactive waste bear all reasonable costs of disposing of such waste.

However, to date, the federal government has not identified a cost for disposing of GTCC or a schedule for acceptance.

For purposes of this study, components that must be disposed of as GTCC waste would be packaged in the same canisters used for spent fuel. Because dismantlement would occur after the projected date for DOE acceptance of spent fuel and high level waste, for purposes of this study it is assumed that the canisters would be shipped directly to a DOE facility.

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Section 1, Page 8 of 9 A significant portion of the waste material generated during decommissioning may only be potentially contaminated by radioactive materials. This waste can be analyzed on site or shipped off site to licensed facilities for further analysis, for processing and/or for conditioning/recovery. Reduction in the volume of low-level radioactive waste requiring disposal in a licensed low-level radioactive waste disposal facility can be accomplished through a variety of methods, including analyses and surveys or decontamination to eliminate the portion of waste that does not require disposal as radioactive waste, compaction, incineration or metal melt. The estimate reflects the savings from waste recovery/volume reduction.

1.3.3 Radiological Criteria for License Termination In 1997, the NRC published Subpart E, "Radiological Criteria for License Termination,"[171 amending 10 CFR Part 20. This subpart provides radiological criteria for releasing a facility for unrestricted use.

The regulation states that the site can be released for unrestricted use if radioactivity levels are such that the average member of a critical group would not receive a Total Effective Dose Equivalent (TEDE) in excess of 25 millirem per year, and provided that residual radioactivity has been reduced to levels that are As Low As Reasonably Achievable (ALARA).

The decommissioning estimate assumes that the CR-3 site will be remediated to the levels specified in 10 CFR 20.1402, "Radiological criteria for unrestricted use," although the remediation measures included in this estimate are believed to be sufficient to result in substantially lower levels than required by the foregoing regulation.

It should be noted that the NRC and the Environmental Protection Agency (EPA) differ on the amount of residual radioactivity considered acceptable in site remediation. The EPA has two limits that apply to radioactive materials. An EPA limit of 15 millirem per year is derived from criteria established by the Comprehensive Environmental Response, Compensation, and Liability Act (CERCLA or Superfund).[1 8 1 An additional and separate limit of 4 millirem per year, as defined in 40 CFR §141.16, is applied to drinking water.1 191 On October 9, 2002, the NRC signed an agreement with the EPA on the radiological decommissioning and decontamination of NRC-licensed sites. The Memorandum of Understanding (MOU)[201 provides that EPA will defer exercise of authority under CERCLA for the majority of facilities decommissioned under NRC authority. The MOU also includes TLG Services, Inc.

CrystalRiver Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Section 1, Page 9 of 9 provisions for NRC and EPA consultation for certain sites when, at the time of license termination, (1) groundwater contamination exceeds EPA-permitted levels; (2) NRC contemplates restricted release of the site; and/or (3) residual radioactive soil concentrations exceed levels defined in the MOU.

The MOU does not impose any new requirements on NRC licensees and should reduce the involvement of the EPA with NRC licensees who are decommissioning. Most sites are expected to meet the NRC criteria for unrestricted use, and the NRC believes that only a few sites will have groundwater or soil contamination in excess of the levels specified in the MOU that trigger consultation with the EPA. However, if there are other hazardous materials on the site, the EPA may be involved in the cleanup. As such, the possibility of dual regulation remains for certain licensees. The present study does not include any costs for this occurrence.

TLG Services, Inc.

CrystalRiver Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 2, Page I of 7

2. SAFSTOR DECOMMISSIONING ALTERNATIVE A detailed cost estimate was developed to decommission the CR-3 nuclear unit for the SAFSTOR decommissioning alternative. The following narrative describes the basic activities associated with the alternative. Although detailed procedures for each activity identified are not provided, and the actual sequence of work may vary, the activity descriptions provide a basis not only for estimating but also for the expected scope of work, i.e., engineering and planning at the time of decommissioning.

The conceptual approach that the NRC has described in its regulations divides decommissioning into three phases. The initial phase commences with the effective date of permanent cessation of operations and involves the transition of both plant and licensee from reactor operations (i.e., power production) to facility de-activation and closure. During the first phase, notification is to be provided to the NRC certifying the permanent cessation of operations and the removal of fuel from the reactor vessel. The licensee is then prohibited from reactor operation.

The second phase encompasses activities during the storage period or during major decommissioning activities, or a combination of the two. The third phase pertains to the activities involved in license termination. The decommissioning estimate developed for CR-3 is also divided into phases or periods; however, demarcation of the periods is based upon major milestones within the project or significant changes in the projected expenditures.

2.1 PERIOD 1 - PREPARATIONS The NRC defines SAFSTOR as "the alternative in which the nuclear facility is placed and maintained in a condition that allows the nuclear facility to be safely stored and subsequently decontaminated (deferred decontamination) to levels that permit release for unrestricted use." The facility is left intact (during the dormancy period), with structures maintained in a sound condition. Systems that are not required to support the spent fuel pool or site surveillance and security are drained, de-energized, and secured. Minimal cleaning/removal of loose contamination and/or fixation and sealing of remaining contamination are performed. Access to contaminated areas is secured to provide controlled access for inspection and maintenance.

Preparations for long-term storage include the revision of technical specifications appropriate to the operating conditions and requirements (i.e.,

permanently shutdown technical specifications), a characterization of the facility and major components, and the development of the PSDAR.

TLG Services,Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 2, Page 2 of 7 The process of placing the plant in safe-storage includes, but is not limited to, the following activities:

" Creation of an organizational structure to support the decommissioning plan and evolving emergency planning and site security requirements.

" Design and installation of an alternate spent fuel cooling system, including air-cooled heat exchangers to be located on the control complex roof and piped into the existing service water system.

" Isolation of the spent fuel pool and fuel handling systems so that safe-storage operations may commence on the balance of the plant.

" Construction of the ISFSI pad and acquisition of the dry fuel storage modules for off-load of the spent fuel pool.

" Removal of systems from service that are no longer required to support site operations or maintenance.

" Processing and disposal of water and filter and treatment media that is not required to support dormancy operations.

" Disposition of legacy waste, including the retired steam generators, reactor vessel closure head and hot leg piping.

" Reconfiguration of ventilation, fire protection, electric power, lighting, and other plant systems needed to support long-term storage and periodic plant surveillance and maintenance.

" Cleaning or fixing loose surface contamination to facilitate future building access and plant maintenance.

" Performing an interim radiation survey of plant, posting caution signs and establishing access requirements, where appropriate.

Posting and/or cordoning off high contamination / high radiation areas.

Reconfiguring security boundaries and surveillance systems, as required.

2.2 PERIOD 2 - DORMANCY The second phase identified by the NRC in its rule addresses licensed activities during a storage period and is applicable to the dormancy phases of the deferred decommissioning alternatives. Dormancy activities include a 24-hour security force, preventive and corrective maintenance on security systems, area lighting, general building maintenance, heating and ventilation of buildings, routine radiological inspections of contaminated structures, maintenance of structural integrity, and a site environmental and radiation monitoring program. Resident maintenance personnel perform equipment maintenance, TLG Services, Inc.

CrystalRiver Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Section 2, Page 3 of 7 inspection activities, routine services to maintain safe conditions, adequate lighting, heating, and ventilation, and periodic preventive maintenance on essential site services.

An environmental surveillance program is carried out during the dormancy period to monitor and control releases of radioactive material to the environment. Appropriate emergency procedures are established and initiated for potential releases that exceed prescribed limits. The environmental surveillance program constitutes an abbreviated version of the program in effect during normal plant operations.

Security during the dormancy period is conducted primarily to safe-guard the spent fuel while on site and prevent unauthorized entry. The security fence, sensors, alarms, and other surveillance equipment provide security. Fire and radiation alarms are also monitored and maintained.

Once the ISFSI has been constructed (estimated in late 2016), the spent fuel will be transferred from the spent fuel pool to horizontal storage modules located on the ISFSI pad. Spent fuel transfer is expected to be complete by January 2019. The pool will be drained and readied for long-term storage once the fuel transfer is completed. The spent fuel pool will be maintained in a recoverable condition until all fuel has been removed from the site unless contingency plans are put in place for offload of DSCs if needed.

For purposes of planning and this cost estimate, the transfer of the spent fuel from the ISFSI to a DOE facility is projected to begin in 2035 and be completed a year later (end of 2036), although transfer could occur earlier if DOE is successful in implementing its current strategy for the management and disposal of spent fuel.. The ISFSI will then be secured for long-term storage and decommissioned along with the power block structures in Period 4.

2.3 PERIOD 3 - PREPARATIONS FOR DECOMMISSIONING CR-3 is currently expected to remain in safe storage until 2067, at which time preparations for decommissioning would commence. The period of storage was based upon, and considered, the available financial resources, projected fund growth and the cost to complete decommissioning and plant dismantlement.

Prior to the commencement of decommissioning operations, preparations are undertaken to reactivate site services and prepare for decommissioning.

Preparations include engineering and planning, a detailed site characterization, and the assembly of a decommissioning management TLG Services, Inc.

CrystalRiver Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 2, Page 4 of 7 organization. Final planning for activities and the writing of activity specifications and detailed procedures are also initiated at this time.

At least two years prior to the anticipated date of license termination, an LTP is required. Submitted as a supplement to the Final Safety Analysis Report (FSAR) or its equivalent, the plan must include: a site characterization, description of the remaining dismantling activities, plans for site remediation, procedures for the final radiation survey, designation of the end use of the site, an updated cost estimate to complete the decommissioning, and any associated environmental concerns. The NRC will notice the receipt of the plan, make the plan available for public comment, and schedule a local hearing. LTP approval will be subject to any conditions and limitations as deemed appropriate by the Commission.

2.4 PERIOD 4 - DECOMMISSIONING This period includes the physical decommissioning activities associated with the removal and disposal of contaminated and activated components and structures, including the successful termination of the 10 CFR §50 operating license. Although the initial radiation levels due to 6 0Co will decrease during the dormancy period, the internal components of the reactor vessel will still exhibit sufficiently high radiation dose rates to require remote sectioning under water due to the presence of long-lived radionuclides such as 94Nb, 59Ni, and 63Ni. Portions of the biological shield will also be radioactive due to the presence of activated trace elements with long half-lives (l5 2 Eu and 15 4Eu).

Decontamination will require controlled removal and disposal. It is assumed that radioactive corrosion products on inner surfaces of piping and components will not have decayed to levels that will permit unrestricted use or allow conventional removal. These systems and components will be surveyed as they are removed and disposed of in accordance with the existing radioactive release criteria.

Significant decommissioning activities in this phase include:

Reconfiguration and modification of site structures and facilities, as needed to support decommissioning operations. This may include establishing a centralized processing area to facilitate equipment removal and component preparation for off-site disposal. Modifications may also be required to the reactor building to facilitate access of de-construction equipment, support the segmentation of the reactor vessel internals, and for large component extraction.

" Design and fabrication of temporary and permanent shielding to support removal and transportation activities, construction of contamination control envelopes, and the procurement of specialty tooling.

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 2, Page 5 of 7

" Procurement (lease or purchase) of shipping canisters, cask liners, and industrial packages for the disposition of low-level radioactive waste.

" Decontamination of components and piping systems as required to control (minimize) worker exposure.

" Removal of piping and components no longer essential to support decommissioning operations.

" Removal of control rod drive housings and the head service structure from the reactor vessel head.

" Removal and segmentation of the plenum assembly. Segmentation will maximize the loading of the shielded transport casks, (i.e., by weight and activity). The operations will be conducted under water using remotely operated tooling and contamination controls.

" Disassembly and segmentation, if necessary, of the remaining reactor internals, including the core former and baffles and lower core support assembly. Depending on packaging, some material may exceed Class C disposal requirements. Any such material will be packaged in modified fuel storage canisters for transfer to DOE.

" Segmentation / removal of the reactor vessel. If segmented, a shielded platform will be installed for segmentation as cutting operations will be performed in-air using remotely operated equipment within a contamination control envelope. The water level will be maintained just below the cut to minimize the working area dose rates. Segments will be transferred in-air to containers that are stored under water, for example, in an isolated area of the refueling canal.

" Removal of the activated and contaminated portions of the concrete biological shield and accessible contaminated concrete surfaces. If dictated by the steam generator and pressurizer removal scenarios, those portions of the associated D-rings necessary for access and component extraction will be removed.

" Removal of the steam generators for processing and pressurizer for controlled disposal. The generators will be moved to an on-site processing center and prepared for transport to the waste processor. To facilitate transport, the generators will be cut in half, across the tube bundle. The exposed ends will be capped and sealed. The pressurizer will be disposed of intact.

" Removal of remaining plant systems and associated components as they become nonessential to the decommissioning program or worker health and safety (e.g., waste collection and treatment systems, electrical power and ventilation systems).

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 2, Page 6 of 7 Removal of the steel liners from refueling canal, disposing of the activated and contaminated sections as radioactive waste. Removal of any activated/contaminated concrete.

  • Surveys of the decontaminated areas of the reactor building.
  • Remediation and removal of the contaminated equipment and material from the auxiliary building and any other contaminated area. Radiation and contamination controls will be utilized until residual levels indicate that the structures and equipment can be released for unrestricted access and conventional demolition. This activity may necessitate the dismantling and disposition of most of the systems and components (both clean and contaminated) located within these areas. This activity facilitates surface decontamination and subsequent verification surveys required prior to obtaining release for demolition.
  • Routing of material removed in the decontamination and dismantling to a central processing area. Material certified to be free of contamination will be released for unrestricted disposition, e.g., as scrap, recycle, or general disposal. Contaminated material will be characterized and segregated for additional off-site processing (disassembly, chemical cleaning, volume reduction, and waste treatment), and/or packaged for controlled disposal at a low-level radioactive waste disposal facility.
  • Remediation of the west settling pond (approximately 500 cubic yards), and the excavation and removal of the station drain tank line, as well as the underground portions of the nitrogen line.

Incorporated into the LTP is the Final Survey Plan. This plan identifies the radiological surveys to be performed once the decontamination activities are completed and is developed using the guidance provided in the "Multi-Agency Radiation Survey and Site Investigation Manual (MARSSIM)."[21] This document incorporates the statistical approaches to survey design and data interpretation used by the EPA. It also identifies commercially available instrumentation and procedures for conducting radiological surveys. Use of this guidance ensures that the surveys are conducted in a manner that provides a high degree of confidence that applicable NRC criteria are satisfied.

Once the survey is complete, the results are provided to the NRC in a format that can be verified. The NRC then reviews and evaluates the information, performs an independent confirmation of radiological site conditions, and makes a determination on release of the property for unrestricted use and license termination.

The NRC will terminate the operating license if it determines that site remediation has been performed in accordance with the LTP, and that the TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 2, Page 7 of 7 terminal radiation survey and associated documentation demonstrate that the facility is suitable for release.

2.5 PERIOD 5 - SITE RESTORATION The efficient removal of the contaminated materials at the site may result in damage to many of the site structures. Blasting, coring, drilling, and the other decontamination activities can substantially damage power block structures, potentially weakening the footings and structural supports. It is unreasonable to anticipate that these structures would be repaired and preserved after the radiological contamination is removed. Dismantling site structures with a work force already mobilized is more efficient and less costly than if the process is deferred. Consequently, this study assumes that site structures addressed by this analysis are removed to a nominal depth of three feet below the top grade of the embankment, wherever possible.

The three-foot depth allows for the placement of gravel for drainage, as well as topsoil, so that vegetation can be established for erosion control. Site areas affected by the dismantling activities are restored and the plant area graded as required to prevent ponding and inhibit the refloating of subsurface materials.

Non-contaminated concrete rubble produced by demolition activities is processed to remove reinforcing steel and miscellaneous embedments. The processed material is then used on site to backfill foundation voids. Excess non-contaminated materials are trucked to an off-site area for disposal as construction debris.

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Section 3, Page I of 24

3. COST ESTIMATE The cost estimate prepared for decommissioning CR-3 considers the unique features of the site, including the NSSS, power generation systems, support services, site buildings, and ancillary facilities. The basis of the estimate, including the sources of information relied upon, the estimating methodology employed, site-specific considerations, and other pertinent assumptions, is described in this section.

3.1 BASIS OF ESTIMATE The estimate was developed using the site-specific, technical information from the 2011 analysis. This information was reviewed for the current analysis and updated as deemed appropriate. The site-specific considerations and assumptions used in the previous evaluation were also revisited. Modifications were incorporated where new information was available or experience from ongoing decommissioning programs provided viable alternatives or improved processes.

3.2 METHODOLOGY The methodology used to develop the estimate follows the basic approach originally presented in the AIF/NESP-036 study report, "Guidelines for Producing Commercial Nuclear Power Plant Decommissioning Cost Estimates," [22] and the DOE "Decommissioning Handbook."[23] These documents present a unit factor method for estimating decommissioning activity costs, which simplifies the estimating calculations. Unit factors for concrete removal ($/cubic yard), steel removal ($/ton), and cutting costs ($/inch) are developed using local labor rates. The activity-dependent costs are estimated with the item quantities (cubic yards and tons), developed from plant drawings and inventory documents. Removal rates and material costs for the conventional disposition of components and structures rely upon information available in the industry publication, "Building Construction Cost Data," published by R.S. Means.[241 The unit factor method provides a demonstrable basis for establishing reliable cost estimates. The detail provided in the unit factors, including activity duration, labor costs (by craft), and equipment and consumable costs, ensures that essential elements have not been omitted. Appendix A presents the detailed development of a typical unit factor. Appendix B provides the values contained within one set of factors developed for this analysis.

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Section 3, Page 2 of 24 This analysis reflects lessons learned from TLG's involvement in the Shippingport Station Decommissioning Project, completed in 1989, as well as the decommissioning of the Cintichem reactor, hot cells, and associated facilities, completed in 1997. In addition, the planning and engineering for the Pathfinder, Shoreham, Rancho Seco, Trojan, Yankee Rowe, Big Rock Point, Maine Yankee, Humboldt Bay-3, Oyster Creek, Connecticut Yankee, and San Onofre-1 nuclear units have provided additional insight into the process, the regulatory aspects, and the technical challenges of decommissioning commercial nuclear units.

Work Difficulty Factors TLG has historically applied work difficulty adjustment factors (WDFs) to account for the inefficiencies in working in a power plant environment. WDFs are assigned to each unique set of unit factors, commensurate with the inefficiencies associated with working in confined, hazardous environments.

The ranges used for the WDFs are as follows:

  • Access Factor 10% to 20%
  • Respiratory Protection Factor 0% to 50%
  • Radiation/ALARA Factor 0% to 15%
  • Protective Clothing Factor 0% to 30%
  • Work Break Factor 8.33%

The factors and their associated range of values were developed in conjunction with the AIF/NESP-036 study. The application of the factors is discussed in more detail in that publication.

Scheduling Program Durations The unit factors, adjusted by the WDFs as described above, are applied against the inventory of materials to be removed in the radiological controlled areas.

The resulting man-hours, or crew-hours, are used in the development of the decommissioning program schedule, using resource loading and event sequencing considerations. The scheduling of conventional removal and dismantling activities is based upon productivity information available from the "Building Construction Cost Data" publication.

An activity duration critical path is used to determine the total decommissioning program schedule. The schedule is relied upon in calculating the carrying costs, which include program management, administration, field TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Section 3, Page 3 of 24 engineering, equipment rental, and support services such as quality control and security. This systematic approach for assembling decommissioning estimates ensures a high degree of confidence in the reliability of the resulting costs.

3.3 FINANCIAL COMPONENTS OF THE COST MODEL TLG's proprietary decommissioning cost model, DECCER, produces a number of distinct cost elements. These direct expenditures, however, do not comprise the total cost to accomplish the project goal, i.e., license termination and site restoration.

3.3.1 Contingency Inherent in any cost estimate that does not rely on historical data is the inability to specify the precise source of costs imposed by factors such as tool breakage, accidents, illnesses, weather delays, and labor stoppages.

In the DECCER cost model, contingency fulfills this role. Contingency is added to each line item to account for costs that are difficult or impossible to develop analytically. Such costs are historically inevitable over the duration of a job of this magnitude; therefore, this cost analysis includes funds to cover these types of expenses.

The activity- and period-dependent costs are combined to develop the total decommissioning cost. A contingency is then applied on a line-item basis, using one or more of the contingency types listed in the AIF/NESP-036 study. "Contingencies" are defined in the American Association of Cost Engineers "Project and Cost Engineers' Handbook"[25] as "specific provision for unforeseeable elements of cost within the defined project scope; particularly important where previous experience relating estimates and actual costs has shown that unforeseeable events which will increase costs are likely to occur." The cost elements in this analysis are based upon ideal conditions and maximum efficiency; therefore, consistent with industry practice, contingency is included. In the AIF/NESP-036 study, the types of unforeseeable events that are likely to occur in decommissioning are discussed and guidelines are provided for percentage contingency in each category. It should be noted that contingency, as used in this analysis, does not account for price escalation and inflation in the cost of decommissioning over the remaining operating life of the station.

Contingency funds are an integral part of the total cost to complete the decommissioning process. Exclusion of this component puts at risk a TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 3, Page 4 of 24 successful completion of the intended tasks and, potentially, subsequent related activities. For this study, TLG examined the major activity-related problems (decontamination, segmentation, equipment handling, packaging, transport, and waste disposal) that necessitate a contingency. Individual activity contingencies ranged from 10% to 75%,

depending on the degree of difficulty judged to be appropriate from TLG's actual decommissioning experience. The contingency values used in this study are as follows:

" Decontamination 50%

  • Contaminated Component Removal 25%

" Contaminated Component Packaging 10%

" Contaminated Component Transport 15%

  • Low-Level Radioactive Waste Disposal 25%
  • Low-Level Radioactive Waste Processing 15%
  • Reactor Segmentation 75%
  • NSSS Component Removal 25%
  • Reactor Waste Packaging 25%
  • Reactor Waste Transport 25%

" Reactor Vessel Component Disposal 50%

" Non-Radioactive Component Removal 15%

" Heavy Equipment and Tooling 15%

  • Construction 15%
  • Supplies 25%
  • Engineering 15%

" Energy 15%

  • Characterization and Termination Surveys 30%
  • Spent Fuel Transfer 15%
  • ISFSI Decommissioning 25%

" Operations and Maintenance 15%

  • Taxes and Fees 10%

" Insurance 10%

  • Staffing (plant, contractor and security) 15%

The contingency values are applied to the appropriate components of the estimate on a line item basis, except where actual budgets were provided or estimates for activities provided by DEF assume to include contingency.

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 3, Page 5 of 24 3.3.2 Financial Risk In addition to the routine uncertainties addressed by contingency, another cost element that is sometimes necessary to consider when bounding decommissioning costs relates to uncertainty, or risk.

Examples can include changes in work scope, pricing, job performance, and other variations that could conceivably, but not necessarily, occur.

Consideration is sometimes necessary to generate a level of confidence in the estimate, within a range of probabilities. TLG considers these types of costs under the broad term "financial risk." Included within the category of financial risk are:

" Delays in approval of the decommissioning plan due to intervention, public participation in local community meetings, legal challenges, and national and local hearings.

" Changes in the project work scope from the baseline estimate, involving the discovery of unexpected levels of contaminants, contamination in places not previously expected, contaminated soil previously undiscovered (either radioactive or hazardous material contamination), variations in plant inventory or configuration not indicated by the as-built drawings.

" Regulatory changes, for example, affecting worker health and safety, site release criteria, waste transportation, and disposal.

" Policy decisions altering national commitments (e.g., in the ability to accommodate certain waste forms for disposition), or in the timetable for such, for example, the start and rate of acceptance of spent fuel by the DOE.

" Pricing changes for basic inputs such as labor, energy, materials, and disposal. Items subject to widespread price competition (such as materials) may not show significant variation; however, others such as waste disposal could exhibit large pricing uncertainties, particularly in markets where limited access to services is available.

This cost study does not add any additional costs to the estimate for financial risk, since there is insufficient historical data from which to project future liabilities. Consequently, the areas of uncertainty or risk should be revisited periodically and addressed through revisions or updates of the base estimate.

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Section 3, Page 6 of 24 3.4 SITE-SPECIFIC CONSIDERATIONS There are a number of site-specific considerations that affect the method for dismantling and removal of equipment from the site and the degree of restoration required. The cost impact of the considerations identified below is included in this cost study.

3.4.1 Spent Fuel Management The cost to dispose the spent fuel generated from plant operations is not reflected within the estimate to decommission CR-3. Ultimate disposition of the spent fuel is within the province of the DOE's Waste Management System, as defined by the Nuclear Waste Policy Act. As such, the disposal cost is financed by a 1 mill/kW-hr surcharge paid into the DOE's waste fund during operations. However, the NRC requires licensees to establish a program to manage and provide funding for the management of all irradiated fuel at the reactor until title of the fuel is transferred to the Secretary of Energy. This funding requirement is fulfilled through inclusion of certain high-level waste cost elements within the estimate, as described below.

Completion of the decommissioning process is highly dependent upon the DOE's ability to remove spent fuel from the site. The timing for removal of spent fuel from the site is based upon an internal DEF probability assessment and the most recent information from the DOE on likely future actions regarding interim and long-term solutions to spent fuel disposition.

For purposes of this estimate, the spent fuel management plan for the CR-3 spent fuel is based in general upon: 1) a 2032 start date for DOE initiating transfer of commercial spent fuel to a federal facility, 2) priority pickup for shutdown reactors, and 3) pickup based on the permanent shutdown date of the plant (oldest fuel first). Assuming a maximum rate of transfer of 3,000 metric tons of uranium (MTU)/year,[26] and the aforementioned assumptions on spent fuel management, the spent fuel from CR-3 would be completely removed from the site by the end of 2036.

ISFSI An ISFSI will be constructed adjacent to the power block and used to off-load the spent fuel pool. The ISFSI is assumed to be available by the end of 2016 with the majority of spent fuel transferred to the facility in 2017 TLG Services, Inc.

CrystalRiver Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 3, Page 7 of 24 and 2018. The estimate includes the costs to purchase, load, and transfer the dry shielded canisters (DSCs), as well as operations and maintenance costs (e.g., staffing, security, insurance, and licensing fees, etc.). It does not include the cost to construct the ISFSI and purchase the horizontal storage modules (HSMs).

Assuming that DOE begin accepting spent fuel in 2032 (from shutdown units), CR-3 fuel is projected to be first removed from the site in 2035.

The process is expected to be completed by the end of the following year.

Once emptied, the ISFSI will be secured for storage. Decommissioning of the ISFSI will be deferred and synchronized with the power block structures.

Storage Canister Design DOE has not identified any cask systems it may use. As such, for the purpose of this analysis, the design and capacity of the ISFSI is based upon the NUHOMS system, with a 32 fuel assembly internal DSC and a concrete HSM.

Canister Loading and Transfer The cost for the labor and equipment to seal each spent fuel canister once it is loaded and to load/transport the spent fuel from the pool to the ISFSI pad was provided by DEF based upon current vendor-supplied information. For estimating purposes, an allowance was used for the transfer of the fuel from the ISFSI into a DOE transport cask.

Operations and Maintenance The estimate includes the cost for operation and maintenance of the spent fuel pool and the ISFSI. Pool operations are expected to continue through January of 2019, as which time it will be emptied and secured for storage. ISFSI operations are expected to continue through December 2036, based upon the previously outlined assumptions on DOE performance.

ISFSI Decommissioning In accordance with 10 CFR §72.30, licensees must have a proposed decommissioning plan for the ISFSI site and facilities that includes a cost estimate to implement. The plan should contain sufficient information on the proposed practices and procedures for the TLG Services, Inc.

CrystalRiver Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 3, Page 8 of 24 decontamination of the ISFSI and for the disposal of residual radioactive materials after all spent fuel, high-level radioactive waste, and reactor-related GTCC waste have been removed.

A multi-purpose (storage and transport) dry shielded storage canister with a horizontal, reinforced concrete storage module is used as a basis for the cost analysis. As an allowance for module remediation, 6 modules are assumed to have some level of neutron-induced activation after approximately 20 years of storage (i.e., to levels exceeding free-release limits), equivalent to the number of modules required to accommodate the final core off load. The steel support structure is assumed to be removed from these modules and sent, along with the concrete, for controlled disposal. The cost of the disposition of this material, as well as the demolition of the ISFSI facility, is included in the estimate.

The cost estimate for decommissioning the ISFSI reflects: 1) the cost of an independent contractor performing the decommissioning activities; 2) an adequate contingency factor; and 3) the cost of meeting the criteria for unrestricted use. The cost summary for decommissioning the ISFSI is presented in Appendix D.

GTCC The dismantling of the reactor internals generates radioactive waste considered unsuitable for shallow land disposal (i.e., low-level radioactive waste with concentrations of radionuclides that exceed the limits established by the NRC for Class C radioactive waste (GTCC)).

The Low-Level Radioactive Waste Policy Amendments Act of 1985 assigned the Federal Government the responsibility for the disposal of this material. The Act also stated that the beneficiaries of the activities resulting in the generation of such radioactive waste bear all reasonable costs of disposing of such waste. However, to date, the Federal Government has not identified a cost for disposing of GTCC or a schedule for acceptance. For purposes of this estimate, the GTCC radioactive waste has been assumed to be packaged in the same canisters used to store spent fuel and disposed of as high-level waste, at a cost equivalent to that envisioned for the spent fuel.

The GTCC material is assumed to be shipped directly to a DOE facility as it is generated from the segmentation of the reactor vessel internals.

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 3, Page 9 of 24 3.4.2 Reactor Vessel and Internal Components The reactor pressure vessel and internal components are segmented for disposal in shielded, reusable transportation casks. Segmentation is performed in the refueling canal, where a turntable and remote cutter are installed. The vessel is segmented in place, using a mast-mounted cutter supported off the lower head and directed from a shielded work platform installed overhead in the reactor cavity. Transportation cask specifications and transportation regulations dictate the segmentation and packaging methodology.

Intact disposal of reactor vessel shells has been successfully demonstrated at several of the sites currently being decommissioned.

Access to navigable waterways has allowed these large packages to be transported to the Barnwell disposal site with minimal overland travel.

Intact disposal of the reactor vessel and internal components can provide savings in cost and worker exposure by eliminating the complex segmentation requirements, isolation of the GTCC material, and transport/storage of the resulting waste packages. Portland General Electric (PGE) was able to dispose of the Trojan reactor as an intact package (including the internals). However, its location on the Columbia River simplified the transportation analysis since:

  • the reactor package could be secured to the transport vehicle for the entire journey, i.e., the package was not lifted during transport, 0 there were no man-made or natural terrain features between the plant site and the disposal location that could produce a large drop, and 0 transport speeds were very low, limited by the overland transport vehicle and the river barge.

As a member of the Northwest Compact, PGE had a site available for disposal of the package - the US Ecology facility in Washington State.

The characteristics of this and site proved favorable in demonstrating compliance with land disposal regulations.

It is not known whether this option will be available to CR-3. Future viability of this option will depend upon the ultimate location of the disposal site, as well as the disposal site licensee's ability to accept highly radioactive packages and effectively isolate them from the environment. Consequently, the study assumes the reactor vessel will TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Section 3, Page 10 of 24 require segmentation, as a bounding condition. With lower levels of activation, the vessel shell can be packaged more efficiently than the curie-limited internal components. This will allow the use of more conventional waste packages rather than shielded casks for transport.

3.4.3 Primary System Components Due to the natural decay of radionuclides over the dormancy period, a chemical decontamination of the primary coolant system is not included.

The following discussion deals with the removal and disposition of the steam generators, but the techniques involved are also applicable to other large components, such as heat exchangers, component coolers, and the pressurizer. The steam generators' size and weight, as well as their location within the reactor building, will ultimately determine the removal strategy.

A trolley crane is set up for the removal of the generators. It can also be used to move portions of the steam generator cubicle walls and floor slabs from the reactor building to a location where they can be decontaminated and transported to the material handling area.

Interferences within the work area, such as grating, piping, and other components are removed to create sufficient laydown space for processing these large components.

The generators are rigged for removal, disconnected from the surrounding piping and supports, and maneuvered into the open area where they are lowered onto a dolly. Each generator is rotated into the horizontal position for extraction from the reactor building and placed onto a multi-wheeled vehicle for transport to an on-site processing and storage area.

The generators are segmented on-site to facilitate transportation. Each unit is cut in half, across the tube bundle. The exposed ends are capped and sealed. Each component is then loaded onto a rail car for transport to the waste processing facility.

Reactor coolant piping is cut from the reactor vessel once the water level in the vessel (used for personnel shielding during dismantling and cutting operations in and around the vessel) is dropped below the nozzle zone. The piping is boxed and transported by shielded van. The reactor coolant pumps and motors are lifted out intact, packaged, and transported for processing and/or disposal.

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Section 3, Page 11 of 24 3.4.4 Retired Components The estimate includes the cost to dispose of the retired steam generators, reactor closure head and hot leg piping. Disposition is currently scheduled to occur in 2014 and 2015, prior to the plant entering dormancy.

3.4.5 Main Turbine and Condenser The main turbine is dismantled using conventional maintenance procedures. The turbine rotors and shafts are removed to a laydown area. The lower turbine casings are removed from their anchors by controlled demolition. The main condensers are also disassembled and moved to a laydown area. Material is then prepared for transportation to an off-site recycling facility where it is surveyed and designated for either decontamination or volume reduction, conventional disposal, or controlled disposal. Components are packaged and readied for transport in accordance with the intended disposition.

3.4.6 Transportation Methods Contaminated piping, components, and structural material other than the highly activated reactor vessel and internal components will qualify as LSA-I, II or III or Surface Contaminated Object, SCO-I or II, as described in Title 49.[271 The contaminated material will be packaged in Industrial Packages (IP-1, IP-2, or IP-3, as defined in subpart 173.411) for transport unless demonstrated to qualify as their own shipping containers. The reactor vessel and internal components are expected to be transported in accordance with Part 71, as Type B. It is conceivable that the reactor, due to its limited specific activity, could qualify as LSA II or III. However, the high radiation levels on the outer surface would require that additional shielding be incorporated within the packaging so as to attenuate the dose to levels acceptable for transport.

Any fuel cladding failure that occurred during the lifetime of the plant is assumed to have released fission products at sufficiently low levels that the buildup of quantities of long-lived isotopes (e.g., 13 7Cs, 90 Sr, or transuranics) has been prevented from reaching levels exceeding those that permit the major reactor components to be shipped under current transportation regulations and disposal requirements.

Transport of the highly activated metal, produced in the segmentation of the reactor vessel and internal components, will be by shielded truck TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-00.1, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 3, Page 12 of 24 cask. Cask shipments may exceed 95,000 pounds, including vessel segment(s), supplementary shielding, cask tie-downs, and tractor-trailer. The maximum level of activity per shipment assumed permissible was based upon the license limits of the available shielded transport casks. The segmentation scheme for the vessel and internal segments is designed to meet these limits.

The transport of large intact components (e.g., large heat exchangers and other oversized components) will be by a combination of truck, rail, and/or multi-wheeled transporter.

Transportation costs for material requiring controlled disposal are based upon the mileage to the EnergySolutions facility in Clive, Utah and the Waste Control Specialist facility in Andrews County, Texas.

Transportation costs for off-site waste processing are based upon the mileage to Memphis, Tennessee. Truck transport costs are estimated using published tariffs from Tri-State Motor Transit.[281 The transportation cost for the GTCC material is assumed to be included in the disposal cost.

3.4.7 Low-Level Radioactive Waste Disposal To the greatest extent practical, metallic material generated in the decontamination and dismantling processes is processed to reduce the total cost of controlled disposal. Material meeting the regulatory and/or site release criterion, is released as scrap, requiring no further cost consideration. Conditioning (preparing the material to meet the waste acceptance criteria of the disposal site) and recovery of the waste stream is performed off site at a licensed processing center. Any material leaving the site is subject to a survey and release charge, at a minimum.

The mass of radioactive waste generated during the various decommissioning activities at the site is shown on a line-item basis in Appendix C, and summarized in Section 5. The quantified waste summaries shown in these tables are consistent with 10 CFR Part 61 classifications. Commercially available steel containers are presumed to be used for the disposal of piping, small components, and concrete.

Larger components can serve as their own containers, with proper closure of all openings, access ways, and penetrations. The volumes are calculated based on the exterior package dimensions for containerized material or a specific calculation for components serving as their own waste containers.

TLG Services, Inc.

Crystal River Unit 3 Nuclear-GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 3, Page 13 of 24 The more highly activated reactor components will be shipped in reusable, shielded truck casks with disposable liners. In calculating disposal costs, the burial fees are applied against the liner volume, as well as the special handling requirements of the payload.

Disposal fees are based upon estimated charges, with higher rates applying for the highly activated components, for example, generated in the segmentation of the reactor vessel. The cost to dispose of the lowest level and majority of the material generated from the decontamination and dismantling activities is based upon the current cost for disposal at E nergySolut tons facility in Clive, Utah. Disposal costs for the higher activity waste (Class B and Q are based upon preliminary and indicative information on the cost for such from WCS.

The estimate includes a Florida Department of Health inspection fee; applied to the volume of low-level radioactive waste shipped to commercial low-level radioactive waste management facilities for treatment, storage, or disposal (Florida Radiation Protection Act, s.

404.131(3)(a)).

Material exceeding Class C limits (limited to material closest to the reactor core and comprising less than 1% of the total waste volume) is generally not suitable for shallow-land disposal. This material is packaged in the same multi-purpose canisters used for spent fuel transport.

3.4.8 Site Conditions Following Decommissioning The NRC will terminate the site license if it determines that site remediation has been performed in accordance with the license termination plan, and that the terminal radiation survey and associated documentation demonstrate that the facility is suitable for release. The NRC's involvement in the decommissioning process will end at this point. Local building codes and state environmental regulations will dictate the next step in the decommissioning process, as well as the owner's own future plans for the site.

Non-essential structures or buildings severely damaged in decontamination process are removed to a nominal depth of three feet below the top grade of the embankment (i.e., 118'-6"), wherever possible.

The embankment and the foundations of buildings located on the embankment, below this elevation, will be abandoned in place. Below grade voids will be filled with clean concrete rubble (processed to TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 3, Page 14 of 24 removed rebar), generated from demolition activities. Excess construction debris is trucked off site as an alternative to onsite disposal. Certain facilities, which have continued use or value (e.g., the switchyard) are left intact.

The intake and discharge canals are abandoned. No remediation is anticipated.

Costs are included for the remediation of minor quantities of asbestos containing materials (e.g., gaskets, insulation, construction materials) and for the remediation of the firing range (i.e., removal of soil containing lead residue).

3.5 ASSUMPTIONS The following are the major assumptions made in the development of the estimate for decommissioning the site.

3.5.1 Estimating Basis The study follows the principles of ALARA through the use of work duration adjustment factors. These factors address the impact of activities such as radiological protection instruction, mock-up training, and the use of respiratory protection and protective clothing. The factors lengthen a task's duration, increasing costs and lengthening the overall schedule. ALARA planning is considered in the costs for engineering and planning, and in the development of activity specifications and detailed procedures. Changes to worker exposure limits may impact the decommissioning cost and project schedule.

3.5.2 Labor Costs DEF, as the licensee, will continue to provide site operations support, including decommissioning program management, licensing, radiological protection, and site security. A Decommissioning Operations Contractor (DOC) will provide the supervisory staff needed to oversee the labor subcontractors, consultants, and specialty contractors needed to perform the work required for the decontamination and dismantling effort. The DOC will also provide the engineering services needed to develop activity specifications, detailed procedures, detailed activation analyses, and support field activities such as structural modifications.

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 3, Page 15 of 24 Site personnel costs are based upon average salary information provided by DEF. Overhead costs are included for site and corporate support, reduced commensurate with the staffing of the project.

The craft labor required to decontaminate and dismantle the nuclear unit is acquired through standard site contracting practices. The current cost of labor at the site is used as an estimating basis.

Security, while reduced from operating levels, is maintained throughout the decommissioning for access control, material control, and to safeguard the spent fuel. Once the spent fuel is removed from the site, the organization is converted from a "nuclear" to an industrial security force.

3.5.3 Design Conditions Any fuel cladding failure that occurred during the lifetime of the plant is assumed to have released fission products at sufficiently low levels that the buildup of quantities of long-lived isotopes (e.g., 137Cs, 90Sr, or transuranics) has been prevented from reaching levels exceeding those that permit the major NSSS components to be shipped under current transportation regulations and disposal requirements.

The curie contents of the vessel and internals at final shutdown are derived from those listed in NUREG/CR-3474.[291 Actual estimates are derived from the curie/gram values contained therein and adjusted for the different mass of the CR-3 components, operating life, and period of decay. Additional short-lived isotopes were derived from NUREG/CR-0130[301 and NUREG/CR-0672,[31] and benchmarked to the long-lived values from NUREG/CR-3474.

The control elements are disposed of along with the spent fuel, i.e., there is no additional cost provided for their disposal. The estimate does include an allowance for the legacy waste currently stored in the spent fuel pool. The $3 million dollars allocated for its disposal is expected to be spent in 2014.

Neutron activation of the containment building structure is assumed to be confined to the biological shield.

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 3, Page 16 of 24 3.5.4 General Transition Activities Existing warehouses are cleared of non-essential material and remain for use by DEF and its subcontractors. The plant's operating staff performs the following activities at no additional cost or credit to the project during the transition period:

" Drain and collect fuel oils, lubricating oils, and transformer oils for recycle and/or sale.

" Drain and collect acids, caustics, and other chemical stores for recycle and/or sale.

" Process operating waste inventories, i.e., the estimate does not address the disposition of any legacy wastes; the disposal of operating wastes during this initial period is not considered a decommissioning expense.

Scrap and Salvage The existing plant equipment is considered obsolete and suitable for scrap as deadweight quantities only. DEF will make economically reasonable efforts to salvage equipment. However, dismantling techniques assumed by TLG for equipment in this analysis are not consistent with removal techniques required for salvage (resale) of equipment. Experience has indicated that some buyers wanted equipment stripped down to very specific requirements before they would consider purchase. This required expensive rework after the equipment had been removed from its installed location. Since placing a salvage value on this machinery and equipment would be speculative, and the value would be small in comparison to the overall decommissioning expenses, this analysis does not attempt to quantify the value that an owner may realize based upon those efforts.

It is assumed, for purposes of this analysis, that any value received from the sale of scrap generated in the dismantling process would be more than offset by the on-site processing costs. The dismantling techniques assumed in the decommissioning estimate do not include the additional cost for size reduction and preparation to meet "furnace ready" conditions. For example, the recovery of copper from electrical cabling may require the removal and disposition of any contaminated insulation, an added expense. With a volatile market, the potential profit margin in scrap recovery is highly speculative, regardless of the ability to free TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 3, Page 17 of 24 release this material. This assumption is an implicit recognition of scrap value in the disposal of clean metallic waste at no additional cost to the project.

Furniture, tools, mobile equipment such as forklifts, trucks, bulldozers, and other property is removed at no cost or credit to the decommissioning project. Disposition may include relocation to other facilities. Spare parts are also made available for alternative use.

Equipment and materials acquired for the power uprate, and not installed, are assumed to be dispositioned at no net cost or credit to the project.

Energy For estimating purposes, the plant is assumed to be de-energized, with the exception of those facilities associated with spent fuel storage.

Replacement power costs are used to calculate the cost of energy consumed during decommissioning for tooling, lighting, ventilation, and essential services.

Insurance Costs for continuing coverage (nuclear liability and property insurance) during decommissioning are included and based upon operating premiums. Reductions in premiums, upon entering dormancy and beyond, are based upon the guidance provided in SECY-00-0145, "Integrated Rulemaking Plan for Nuclear Power Plant Decommissioning." 1 321 The NRC's financial protection requirements are based on various reactor (and spent fuel) configurations.

Taxes The estimate includes an allowance for property taxes (or payments in lieu of taxes).

Site Modifications The perimeter fence and in-plant security barriers will be moved, as appropriate, to conform to the Site Security Plan in force during the various stages of the project.

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 3, Page 18 of 24 3.6 COST ESTIMATE

SUMMARY

Schedules of expenditures are provided in Tables 3.1 through 3.4. The tables delineate the cost contributors by year of expenditures as well as cost contributor (e.g., labor, materials, and waste disposal).

The cost elements are also assigned to one of three subcategories: "License Termination," "Spent Fuel Management," and "Site Restoration." The subcategory "License Termination" is used to accumulate costs that are consistent with "decommissioning" as defined by the NRC in its financial assurance regulations (i.e., 10 CFR §50.75). In situations where the long-term management of spent fuel is not an issue, the cost reported for this subcategory is generally sufficient to terminate the unit's operating license.

The "Spent Fuel Management" subcategory contains costs associated with the containerization and transfer of spent fuel from the wet storage pool to the ISFSI, as well as the eventual transfer of the spent fuel at the ISFSI to the DOE. Costs are included for the operation of the storage pool and the management of the ISFSI until such time that the transfer is complete. It does not include any spent fuel management expenses incurred prior to June 3, 2013, cost to construct the ISFSI, purchase the horizontal storage modules, nor does it include any costs related to the final disposal of the spent fuel.

"Site Restoration" is used to capture costs associated with the dismantling and demolition of buildings and facilities demonstrated to be free from contamination. This includes structures never exposed to radioactive materials, as well as those facilities that have been decontaminated to appropriate levels.

As noted within this document, the estimate is developed and costs are presented in 2013 dollars. As such, the estimate does not reflect the escalation of costs (due to inflationary and market forces) during the decommissioning project. Schedules of expenditures are based upon the detailed activity costs reported in Appendix C, along with the schedule presented in Section 4.

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Section 3, Page 19 of 24 TABLE 3.1 TOTAL ANNUAL EXPENDITURES (thousands, 2013 dollars)

Equipment & LLRW Year Labor Materials Energy Disposal Other Total 2013 37,138 4,281 0 0 1,640 43,060 2014 63,941 7,371 0 6,000 6,385 83,698 2015 45,819 7,267 112 14,007 6,749 73,955 2016 28,070 7,185 223 15 7,119 42,612 2017 27,993 7,165 222 15 7,099 42,495 2018 27,993 7,165 222 15 7,099 42,495 2019 19,555 4,603 179 12 5,601 29,950 2020 6,166 534 ill 7 3,229 10,048 2021 6,150 533 ill 7 3,220 10,020 2022 6,150 533 ill 7 3,220 10,020 2023 1 6,150 533 ill 7 3,220 10,020 2024 6,166 534 ill 7 3,229 10,048 2025 6,150 533 ill 7 3,220 10,020 2026 6,150 533 ill 7 3,220 10,020 2027 6,150 533 ill 7 3,220 10,020 2028 6,166 534 ill 7 3,229 10,048 2029 6,150 533 ill 7 3,220 10,020 2030 6,150 533 ill 7 3,220 10,020 2031 6,150 533 ill 7 3,220 10,020 2032 1 6,166 534 ill 7 3,229 10,048 2033 6,150 533 ill 7 3,220 10,020 2034 6,150 533 ill 7 3,220 10,020 2035 8,910 533 ill 7 3,220 12,780 2036 8,236 534 ill 7 3,229 12,118 2037 2,364 317 ill 6 2,592 5,390 2038 2,364 317 ill 6 2,592 5,390 2039 2,364 317 ill 6 2,592 5,390 2040 2,370 318 ill 6 2,599 5,404 2041 2,364 317 111 6 2,592 5,390 2042 2,364 317 ill 6 2,592 5,390 2043 2,364 317 ill 6 2,592 5,390 2044 2,370 318 ill 6 2,599 5,404 2045 2,364 317 ill 6 2,592 5,390 2046 2,364 317 ill 6 2,592 5,390 2047 2,364 317 ill 6 2,592 5,390 TLG Services,Inc.

CrystalRiver Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 3, Page 20 of 24 TABLE 3.1 (continued)

TOTAL ANNUAL EXPENDITURES (thousands, 2013 dollars)

Equipment & LLRW Year Labor Materials Energy Disposal Other Total 2048 2,370 318 ill 6 2,599 5,404 2049 2,364 317 ill 6 2,592 5,390 2050 2,364 317 ill 6 2,592 5,390 2051 2,364 317 111 6 2,592 5,390 2052 2,370 318 ill 6 2,599 5,404 2053 2,364 317 ill 6 2,592 5,390 2054 2,364 317 ill 6 2,592 5,390 2055 2,364 317 ill 6 2,592 5,390 2056 2,370 318 ill 6 2,599 5,404 2057 2,364 317 ill 6 2,592 5,390 2058 2,364 317 ill 6 2,592 5,390 2059 2,364 317 ill 6 2,592 5,390 2060 2,370 318 ill 6 2,599 5,404 2061 2,364 317 ill 6 2,592 5,390 2062 2,364 317 ill 6 2,592 5,390 2063 2,364 317 ill 6 2,592 5,390 2064 2,370 318 ill 6 2,599 5,404 2065 2,364 317 ill 6 2,592 5,390 2066 2,364 317 ill 6 2,592 5,390 2067 23,773 1,272 722 22 3,080 28,868 2068 46,849 9,921 1,108 3,235 4,883 65,995 2069 49,154 24,639 1,055 28,524 16,327 119,700 2070 45,805 14,489 907 18,276 11,276 90,754 2071 44,124 9,394 833 13,130 8,740 76,221 2072 35,523 4,699 461 5,126 5,040 50,848 2073 19,103 10,550 126 4 2,333 32,117 2074 11,100 7,631 71 1,455 Total 706,364, 146,208, 11,467, 88,687 227,402, 1,180,128 Note: Columns may not add due to rounding TLG Services,Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 3, Page 21 of 24 TABLE 3.2 LICENSE TERMINATION EXPENDITURES (thousands, 2013 dollars)

Equipment & LLRW Year Labor Materials Energy Disposal Other Total 2013 30,458 1,554 0 0 1,640 33,652 2014 52,440 2,675 0 6,000 6,385 67,500 2015 27,196 1,567 56 14,007 5,109 47,935 2016 2,371 479 ill 15 3,855 6,831 2017 2,364 477 ill 15 3,845 6,812 2018 2,364 477 ill 15 3,845 6,812 2019 2,364 418 ill 12 3,370 6,275 2020 2,370 326 ill 7 2,623 5,437 2021 2,364 325 ill 7 2,616 5,422 2022 2,364 325 ill 7 2,616 5,422 2023 2,364 325 ill 7 2,616 5,422 2024 2,370 326 ill 7 2,623 5,437 2025 2,364 325 ill 7 2,616 5,422 2026 2,364 325 ill 7 2,616 5,422 2027 2,364 325 ill 7 2,616 5,422 2028 2,370 326 ill 7 2,623 5,437 2029 2,364 325 ill 7 2,616 5,422 2030 2,364 325 ill 7 2,616 5,422 2031 2,364 325 ill 7 2,616 5,422 2032 2,370 326 ill 7 2,623 5,437 2033 2,364 325 ill 7 2,616 5,422 2034 2,364 325 ill 7 2,616 5,422 2035 2,364 325 ill 7 2,616 5,422 2036 2,370 326 ill 7 2,623 5,437 2037 2,364 317 ill 6 2,592 5,390 2038 2,364 317 ill 6 2,592 5,390 2039 2,364 317 ill 6 2,592 5,390 2040 2,370 318 ill 6 2,599 5,404 2041 2,364 317 ill 6 2,592 5,390 2042 2,364 317 ill 6 2,592 5,390 2043 2,364 317 ill 6 2,592 5,390 2044 2,370 318 ill 6 2,599 5,404 2045 2,364 317 ill 6 2,592 5,390 2046 2,364 317 ill 6 2,592 5,390 2047 2,364 317 ill 6 2,592 5,390 TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 3, Page 22 of 24 TABLE 3.2 (continued)

LICENSE TERMINATION EXPENDITURES (thousands, 2013 dollars)

Equipment & LLRW Year Labor Materials Energy Disposal Other Total 2048 2,370 318 ill 6 2,599 5,404 2049 2,364 317 ill 6 2,592 5,390 2050 2,364 317 ill 6 2,592 5,390 2051 2,364 317 ill 6 2,592 5,390 2052 2,370 318 ill 6 2,599 5,404 2053 2,364 317 ill 6 2,592 5,390 2054 2,364 317 ill 6 2,592 5,390 2055 2,364 317 ill 6 2,592 5,390 2056 2,370 318 ill 6 2,599 5,404 2057 2,364 317 ill 6 2,592 5,390 2058 2,364 317 ill 6 2,592 5,390 2059 2,364 317 ill 6 2,592 5,390 2060 2,370 318 ill 6 2,599 5,404 2061 2,364 317 ill 6 2,592 5,390 2062 2,364 317 ill 6 2,592 5,390 2063 2,364 317 ill 6 2,592 5,390 2064 2,370 318 ill 6 2,599 5,404 2065 2,364 317 ill 6 2,592 5,390 2066 2,364 317 ill 6 2,592 5,390 2067 23,365 1,272 722 22 3,080 28,461 2068 1 45,542 9,911 1,108 3,235 4,880 64,677 2069 47,629 24,558 1,055 28,524 16,304 118,071 2070 44,857 14,448 907 18,276 11,268 89,757 2071 43,465 9,372 833 13,130 8,740 75,541 2072 35,266 4,691 461 5,126 5,040 50,584 2073 4,223 233 30 4 366 4,857 2074 0 0 0 93 Total 475,1851 87,1661 10,843, 88,687 200,021 861,902 Note: Columns may not add due to rounding TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 3, Page 23 of 24 TABLE 3.3 SPENT FUEL MANAGEMENT EXPENDITURES (thousands, 2013 dollars)

Equipment & LLRW Year Labor Materials Energy Disposal Other Total 2013 6,680 2,728 0 0 0 9,408 2014 11,502 4,696 0 0 0 16,198 2015 18,623 5,700 56 0 1,641 26,020 2016 25,699 6,706 ill 0 3,264 35,780 2017 25,629 6,688 ill 0 3,255 35,683 2018 1 25,629 6,688 ill 0 3,255 35,683 2019 17,191 4,185 68 0 2,231 23,675 2020 3,796 209 0 0 606 4,611 2021 3,786 208 0 0 604 4,598 2022 3,786 208 0 0 604 4,598 2023 3,786 208 0 0 604 4,598 2024 3,796 209 0 0 606 4,611 2025 3,786 208 0 0 604 4,598 2026 3,786 208 0 0 604 4,598 2027 3,786 208 0 0 604 4,598 2028 3,796 209 0 0 606 4,611 2029 3,786 208 0 0 604 4,598 2030 3,786 208 0 0 604 4,598 2031 3,786 208 0 0 604 4,598 2032 3,796 209 0 0 606 4,611 2033 3,786 208 0 0 604 4,598 2034 3,786 208 0 0 604 4,598 2035 6,546 208 0 0 604 7,358 2036 5,866 209 0 0 606 6,681 Total Ill 200,189 40,933 458 0 23,926 265,505[21 Notes:

Ill Columns may not add due to rounding

[21 $93.8M in ISFSI construction costs funded from sources outside the DTF are not included in the total TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 3, Page 24 of 24 TABLE 3.4 SITE RESTORATION EXPENDITURES (thousands, 2013 dollars)

Equipment & LLRW Year Labor Materials Energy Disposal Other Total 2013-66 0 0 0 0 0 0 2067 408 0 0 0 0 408 2068 1,307 9 0 0 3 1,319 2069 1,525 81 0 0 23 1,629 2070 948 41 0 0 8 997 2071 659 21 0 0 0 680 2072 256 8 0 0 0 265 2073 14,880 10,317 96 0 1,967 27,260 2074 11,007 7,631 71 0 1,455 20,164 Total 30,9901 18,10911. 167 0 3,4551 5 Note: Columns may not add due to rounding TLG Services,Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 4, Page I of 5

4. SCHEDULE ESTIMATE The schedule for the decommissioning scenario considered in this study follows the sequences presented in the AIF/NESP-036 study, with minor changes to reflect recent experience and site-specific constraints. In addition, the scheduling has been revised to reflect the spent fuel management plan described in Section 3.4.1.

The start and end dates of the decommissioning subperiods are shown in Table 4.1. A schedule or sequence of activities for the deferred decommissioning portion of the SAFSTOR alternative is presented in Figure 4.1. The scheduling sequence assumes that fuel has been removed from the site prior to the start of decontamination and dismantling activities. The key activities listed in the schedule do not reflect a one-to-one correspondence with those activities in the cost tables, but reflect dividing some activities for clarity and combining others for convenience. The schedule was 33 prepared using the "Microsoft Project Professional 2010" computer software.[ 1 4.1 SCHEDULE ESTIMATE ASSUMPTIONS The schedule reflects the results of a precedence network developed for the site decommissioning activities, i.e., a PERT (Program Evaluation and Review Technique) Software Package. The work activity durations used in the precedence network reflect the actual person-hour estimates from the cost table, adjusted by stretching certain activities over their slack range and shifting the start and end dates of others. The following assumptions were made in the development of the decommissioning schedule:

  • The spent fuel handling area in the auxiliary building is isolated until such time that all spent fuel has been discharged from the spent fuel pool to the ISFSI.

" All work (except vessel and internals removal) is performed during an 8-hour workday, 5 days per week, with no overtime. There are eleven paid holidays per year.

" Reactor and internals removal activities are performed by using separate crews for different activities working on different shifts, with a corresponding backshift charge for the second shift.

" Multiple crews work parallel activities to the maximum extent possible, consistent with optimum efficiency, adequate access for cutting, removal and laydown space, and with the stringent safety measures necessary during demolition of heavy components and structures.

TLG Services, Inc.

Crystal River-Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 4, Page 2 of 5 For plant systems removal, the systems with the longest removal durations in areas on the critical path are considered to determine the duration of the activity.

4.2 PROJECT SCHEDULE The period-dependent costs presented in the detailed cost tables are based upon the durations developed in the schedules for decommissioning. Durations are established between several milestones in each project period; these durations are used to establish a critical path for the entire project. In turn, the critical path duration for each period is used as the basis for determining the period-dependent costs.

The project timeline is provided in Figure 4.2 with milestone dates based on the 2013 declaration of permanent cessations of operations. The fuel pool is emptied by January 2019, while ISFSI operations continue until the DOE can complete the transfer of assemblies to its repository. Deferred decommissioning is assumed to commence in 2067 with the operating license is terminated within a 60-year period from the declared cessation of plant operations.

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 4, Page 3 of 5 TABLE 4.1 DECOMMISSIONING SCHEDULE Start End Duration Decommissioning Periods (years)

Period 1: Planning and Preparations [P] 03 Jun 2013 01 Jul 2015 2.08 Period 2a: Dormancy w/Wet Fuel Storage 01 Jul 2015 13 Aug 2019 4.12 Period 2b: Dormancy w/Dry Fuel Storage 13 Aug 2019 31 Dec 2036 17.39 Period 2c: Dormancy w/No Fuel Storage 31 Dec 2036 23 May 2067 30.39 Period 3a: Site Reactivation 23 May 2067 22 May 2068 1.00 Period 3b: Decommissioning Prep 22 May 2068 21 Nov 2068 0.50 Period 4a: Large Component Removal 21 Nov 2068 03 May 2070 1.45 Period 4b: Plant Systems Removal and Building Remediation 03 May 2070 22 May 2072 2.05 Period 4f: License Termination 22 May 2072 20 Feb 2073 0.75 Period 5b: Site Restoration 20 Feb 2073 21 Aug 2074 1.50 Total [21 1 61.22 11] While permanent cessation of operations was declared on February 20, 2013, decommissioning costs are accumulated as of June 2013

[2] Columns may not add due to rounding TLG Services, Inc.

CrystalRiver Unit 3 Nuclear Generating Plant Document No. P23-1680-001,Rev. 0 Site-Specific Decommissioning Cost Estimate Section 4, Page 4 of 5 FIGURE 4.1 DEFERRED DECOMMISSIONING AC7TIVTY SCHEDULE MD Task Name

__________________________2067 2068 2069 2070 2071 2072 2073 2074 1 CR3 SA.STOR Schedule 2 Period 3a Start 3 PERIOD 3a - Reactivate Site Following SAFSTOR Dormancy 4 Reconaure, plant 6 Prepare activity specifcations 6 Perform site characterzation 7 PERIOD 3b - Decommisioning Preparations S DOC staff mobilized 9 Reconfigure plant (continued) 10 Prepare detailed work procedures 11 PERIOD 4a - Large Component Removal 12 Preparation for reactor vessel removal 13 Reactor vessel & internals 14 Remamnig large NSSS components dispositon 15 Non-easential systems 1C Main turbine/generator 17 Main condenser 18 Reactor Building Systems Removal 19 Systems removal not supporting vessel removal 20 Building decon not supporting vessel removal 21 License ternination plan submitted 22 PERIOD 4b - Decontamination 23 Reactor Building Systems Removal 24 Reactor Building Decon 25 Remaining Decorum Activities IC Removal of remaining systems 27 Decontamination of remaining buildings 18 License termination plan approved Final Site Survey NRC review & approval Part 50 license terminated PERIOD b.- Site Restoration C,*cal Path Tas - slieuyuai w----- wpwkffd Dia Pald TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Section 4, Page 5 of 5 FIGURE 4.2 DECOMMISSIONING TIMELINE (not to scale)

Declaration of Permanent Cessation of Operating License Operations Terminated I 7- 7 7P I

'A, "a Period 2 Period 3 Dormancy Decommissioning Preparations 02/2013 07/2015 05/2067 11/2068 02/2073 08/2074 Wet Transfer Complete T

Transfer of Irradiated Fuel from Pool to ISFSl Dry Transfer 01/2019 Complete I

Transfer of Irradiated Fuel from ISFSI to DOE 12/2036 TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 5, Page I of 4

5. RADIOACTIVE WASTES The objectives of the decommissioning process are the removal of all radioactive material from the site that would restrict its future use and the termination of the NRC license. This currently requires the remediation of all radioactive material at the site in excess of applicable legal limits. Under the Atomic Energy Act,[3 4] the NRC is responsible for protecting the public from sources of ionizing radiation. Title 10 of the Code of Federal Regulations delineates the production, utilization, and disposal of radioactive materials and processes. In particular, Part 71 defines radioactive material as it pertains to transportation and Part 61 specifies its disposition.

Most of the materials being transported for controlled burial are categorized as Low Specific Activity (LSA) or Surface Contaminated Object (SCO) materials containing Type A quantities, as defined in 49 CFR Parts 173-178. Shipping containers are required to be Industrial Packages (IP-1, IP-2 or IP-3, as defined in 10 CFR

§173.411). For this study, commercially available steel containers are presumed to be used for the disposal of piping, small components, and concrete. Larger components can serve as their own containers, with proper closure of all openings, access ways, and penetrations.

The destinations for the various waste streams from decommissioning are identified in Figure 5.1. The volumes are shown on a line-item basis in Appendix C and summarized in Table 5.1. The volumes are calculated based on the exterior dimensions for containerized material and on the displaced volume of components serving as their own waste containers.

The reactor vessel and internals are categorized as large quantity shipments and, accordingly, will be shipped in reusable, shielded truck casks with disposable liners.

In calculating disposal costs, the burial fees are applied against the liner volume, as well as the special handling requirements of the payload. Packaging efficiencies are lower for the highly activated materials (greater than Type A quantity waste),

where high concentrations of gamma-emitting radionuclides limit the capacity of the shipping casks.

No process system containing/handling radioactive substances at shutdown is presumed to meet material release criteria by decay alone (i.e., systems radioactive at shutdown will still be radioactive over the time period during which the decommissioning is accomplished, due to the presence of long-lived radionuclides).

13 7 While the dose rates decrease with time, radionuclides such as Cs will still control the disposition requirements.

TLG Services, Inc.

COystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Section 5, Page 2 of 4 The waste material produced in the decontamination and dismantling of the nuclear plant is primarily generated during Period 4 of SAFSTOR. Material that is considered potentially contaminated when removed from the radiological controlled area (e.g., concrete and dry active waste) and metal with low levels of contamination are sent to processing facilities in Tennessee for conditioning and disposal. The disposal volumes reported in the tables reflect the savings resulting from reprocessing and recycling. Heavily contaminated components and activated materials are routed for direct, controlled disposal.

Disposal costs for Class A waste were based upon DEF's Life of Plant Agreement with EnergySolutions. Separate rates were used for containerized waste and large components, including the pressurizer and reactor coolant pumps. Demolition debris including miscellaneous steel, scaffolding, and concrete was disposed of at a bulk rate. The decommissioning waste stream also includes resins and dry active waste.

Since EnergySolutions is not currently able to receive the more highly radioactive components generated in the decontamination and dismantling of the reactor, disposal costs for the Class B and C material were based upon preliminary and indicative information on the cost for such waste from WCS.

The estimate includes a Florida Department of Health inspection fee; applied to the volume of low-level radioactive waste shipped to commercial low-level radioactive waste management facilities for treatment, storage, or disposal (Florida Radiation Protection Act, s. 404.131(3)(a)).

A small quantity of material will be generated during the decommissioning will not be considered suitable for near-surface disposal, and is assumed to be disposed of in a geologic repository, in a manner similar to that envisioned for spent fuel disposal.

This material, known as GTCC material, is estimated to require five spent fuel storage canisters (or the equivalent) to dispose of the most radioactive portions of the reactor vessel internals. The volume and weight reported in Table 5.1 represents the packaged weight and volume of the spent fuel storage canisters.

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001,Rev. 0 Site-Specific DecommissioningCost Estimate Section 5, Page 3 of 4 FIGURE 5.1 DECOMMISSIONING WASTE DISPOSITION Direct Burial EnergySolutions Containerized Clive, Utah Waste Waste Control Reactor Waute Specialists (Classes B/C) Andrews County, Texas Reactor Waste Geologic Disposal (Class GTCC) Federal Facility TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 5, Page 4 of 4 TABLE 5.1 DECOMMISSIONING WASTE

SUMMARY

Waste Volume Weight Waste Cost Basis Class [1] Waste Form (cubic feet) (pounds)

Low-Level Radioactive Waste EnergySolutions (near-surface disposal) A Containerized 69,040 6,000,659 A Bulk 67,818 6,480,244 WCS B Shielded Cask 876 92,900 WCS C Shielded Cask 462 59,891 GTCC (geologic repository or federal Spent Fuel facility) Equivalent GTCC DSC 1,785 353,095 Processed/Conditioned Recycling (off-site recycling center) Vendors A Bulk 269,051 12,459,830 Total [2] 409,032 25,446,619

[1] Waste is classified according to the requirements as delineated in Title 10 CFR, Part 61.55

[2] Columns may not add due to rounding.

TLG Services,Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 6, Page I of 5 6.RESULTS The analysis to estimate the cost to decommission CR-3 relied upon the site-specific, technical information developed for a previous analysis prepared in 2011. While not an engineering study, the estimate provides DEF with sufficient information to assess their financial obligations, as they pertain to the decommissioning of the nuclear station.

The estimate described in this report is based on numerous fundamental assumptions, including regulatory requirements, project contingencies, low-level radioactive waste disposal practices, high-level radioactive waste management options, and site restoration requirements. The decommissioning scenarios assume continued operation of the station's spent fuel pool until the spent fuel can be off-loaded to the ISFSI. The ISFSI will be used to safeguard the spent fuel until such time that the DOE can complete the transfer of the assemblies to its facility.

The cost projected for deferred decommissioning (SAFSTOR) is estimated to be

$1,180.1 million. The majority of this cost (approximately 73.0%) is associated with placing the unit in storage, ongoing caretaking of the unit during dormancy, and the eventual physical decontamination and dismantling of the nuclear unit so that the operating license can be terminated. Another 22.5% is associated with the management, interim storage, and eventual transfer of the spent fuel. The remaining 4.5% is for the demolition of the designated structures and limited restoration of the site. The costs are allocated, by subperiod, into the categories of License Termination, Spent Fuel Management and Site Restoration in Table 6. 1.

The primary cost contributors, identified in Table 6.2, are either labor-related or associated with the management and disposition of the radioactive waste. Program management is the largest single contributor to the overall cost. The magnitude of the expense is a function of both the size of the organization required to manage the decommissioning, as well as the duration of the program. It is assumed, for purposes of this analysis, that DEF will oversee the decommissioning program, using a DOC to manage the decommissioning labor force and the associated subcontractors. The size and composition of the management organization varies with the decommissioning phase and associated site activities. However, once the operating license is terminated, the staff is substantially reduced for the conventional demolition and restoration of the site.

As described in this report, the spent fuel pool will be isolated and an independent spent fuel island created. Once the ISFSI is constructed, the spent fuel will be packaged into transportable steel canisters for interim storage. Dry storage of the fuel provides additional flexibility in the event the DOE is not able to meet the TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Section 6, Page 2 of 5 current timetable for completing the transfer of assemblies to an off-site facility and minimizes the associated caretaking expenses.

The cost for waste disposal includes only those costs associated with the controlled disposition of the low-level radioactive waste generated from decontamination and dismantling activities, including plant equipment and components, structural material, filters, resins and dry-active waste. As described in Section 5, the EnergySolutions facility in Utah is the assumed destination for the majority of the low-level radioactive material required controlled disposal, with the remaining high-activity waste destined for Waste Control Specialists' facility in Texas.

Components, requiring additional isolation from the environment (i.e., GTCC), are packaged for geologic disposal. The cost of geologic disposal is based upon a cost equivalent to spent fuel.

A significant portion of the metallic waste is designated for additional processing and treatment at an off-site facility. Processing reduces the volume of material requiring controlled disposal through such techniques and processes as survey and sorting, decontamination, and volume reduction. The material that cannot be unconditionally released is packaged for controlled disposal at one of the currently operating facilities. The cost identified in the summary tables for processing is all-inclusive, incorporating the ultimate disposition of the material.

Removal costs reflect the labor-intensive nature of the decommissioning process, as well as the management controls required to ensure a safe and successful program.

Decontamination and packaging costs also have a large labor component that is based upon prevailing wages. Non- radiological demolition is a natural extension of the decommissioning process. The methods employed in decontamination and dismantling are generally destructive and indiscriminate in inflicting collateral damage. With a work force mobilized to support decommissioning operations, non-radiological demolition can be an integrated activity and a logical expansion of the work being performed in the process of terminating the operating license.

The reported cost for transport includes the tariffs and surcharges associated with moving large components and/or overweight shielded casks overland, as well as the general expense, e.g., labor and fuel, of transporting material to the destinations identified in this report. For purposes of this analysis, material is primarily moved overland by truck.

Decontamination is used to reduce the plant's radiation fields and minimiz e worker exposure. Slightly contaminated material or material located within a contaminated area is sent to an off-site processing center, i.e., this analysis does not assume that contaminated plant components and equipment can be decontaminated for uncontrolled release in-situ. Centralized processing centers have proven to be a TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 6, Page 3 of 5 more economical means of handling the large volumes of material produced in the dismantling of a nuclear unit.

License termination survey costs are associated with the labor intensive and complex activity of verifying that contamination has been removed from the site to the levels specified by the regulating agency. This process involves a systematic survey of all remaining plant surface areas and surrounding environs, sampling, isotopic analysis, and documentation of the findings. The status of any plant components and materials not removed in the decommissioning process will also require confirmation and will add to the expense of surveying the facilities alone.

The remaining costs include allocations for heavy equipment and temporary services, as well as for other expenses such as regulatory fees and the premiums for nuclear insurance. While site operating costs have been greatly reduced following the final cessation of plant operations, certain administrative functions do need to be maintained either at a basic functional or regulatory level.

TLG Services,Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Section 6, Page 4 of 5 TABLE 6.1 DECOMMISSIONING COST

SUMMARY

[1]

(thousands of 2013 dollars)

License Spent Fuel Site Decommissioning Periods Termination Management Restoration Period 1: Planning and Preparations [21 145,653 33,638 Period 2a: Dormancy w/Wet Fuel Storage [31 28,071 147,032 Period 2b: Dormancy w/Dry Fuel Storage 94,344 84,835 Period 2c: Dormancy w/No Fuel Storage 163,892 - _

Period 3a: Site Reactivation 43,152 - 667 Period 3b: Decommissioning Prep 34,626 - 876 Period 4a: Large Component Removal 170,798 - 2,356 Period 4b: Plant Systems Removal and Building Remediation 155,222 - 1,397 Period 4f: License Termination 25,926 Period 5b: Site Restoration 219 - 47,424 Total [4] 861,902 265,505 [51 52,721 P'] Represents the total cost of decommissioning: DEF's share (91.8%), as well as that of the nine minority owners: City of Alachua, City of Bushnell, City of Gainesville, City of Kissimmee, City of Leesburg, City of Ocala, Orlando Utilities Commission, Seminole Electric Cooperative, and City of New Smyrna Beach

[21 Includes site costs (budgets for 2013, 2014 and the first half of 2015), installation of the alternative spent fuel cooling system, shutdown electrical line-up, and removal of legacy waste from the site

[11 Includes site costs to off-load the spent fuel pool to the ISFSI (completed in 2019)

[41 Columns may not add due to rounding

[51 $93.8M in ISFSI construction costs funded from sources outside the DTF are not included in the total TLG Services, Inc.

CrystalRiver Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Section 6, Page 5 of 5 TABLE 6.2 DECOMMISSIONING COST ELEMENT CONTRIBUTION (thousands of 2013 dollars)

Cost Element Total  %

Preparations for Safe-Storage (2013 - 2015) - Excluding Security 116,090 9.8 Preparations for Safe-Storage (2013 - 2015) - Security 17,845 1.5 Spent Fuel Pool Off-load Preparations (2013 - 2015) 17,577 1.5 Alternate Spent Fuel Cooling System 2,931 0.3 Reduction of Electrical System 2,675 0.2 Decontamination 6,919 0.6 Removal 112,629 9.5 Packaging 16,347 1.4 Transportation 11,163 1.0 Waste Disposal 64,646 5.5 Off-site Waste Processing 32,610 2.8 Program Management [1] 325,212 27.6 Security 142,622 12.1 Spent Fuel Management - Direct Costs [21 68,091 5.8 Insurance and Regulatory Fees 49,349 4.2 Energy 11,467 1.0 Characterization and Licensing Surveys 28,600 2.4 Property Taxes 20,642 1.8 Miscellaneous Equipment 21,378 1.8 Site O&M 110,397 9.4 Other 938 0.1 Total [31 1,180,128 100.0 Cost Allocation Total  %

License Termination 861,903 73.0 Spent Fuel Management 265,505 22.5 Site Restoration 52,721 4.5 Total [31 1,180,128 100.0

[N1 Includes engineering 121 Excludes program management costs (staffing) and ISFSI construction, but includes costs for ISFSI O&M, EP fees, and spent fuel transfer costs to DOE

[3] Columns may not add due to rounding TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Section 7, Page 1 of 3

7. REFERENCES
1. "Preliminary Decommissioning Cost Estimate for the Crystal River Unit 3 Nuclear Generating Plant," Document No. P23-1651-001, Rev. 0, TLG Services, Inc., November 2011
2. FPC to NRC letter dated February 20, 2013, "Crystal River Unit 3 - Certificate of Permanent Cessation of Power Operations and that Fuel Has Been Permanently Removed from the Reactor" (ADAMS Accession No. ML13056A005)
3. U.S. Code of Federal Regulations, Title 10, Parts 30, 40, 50, 51, 70 and 72, "General Requirements for Decommissioning Nuclear Facilities," Nuclear Regulatory Commission, Federal Register Volume 53, Number 123 (p 24018 et seq.), June 27, 1988
4. U.S. Nuclear Regulatory Commission, Regulatory Guide 1.159, "Assuring the Availability of Funds for Decommissioning Nuclear Reactors," October 2003
5. U.S. Code of Federal Regulations, Title 10, Part 20, Subpart E, "Radiological Criteria for License Termination"
6. U.S. Code of Federal Regulations, Title 10, Parts 20 and 50, "Entombment Options for Power Reactors," Advanced Notice of Proposed Rulemaking, Federal Register Volume 66, Number 200, October 16, 2001
7. U.S. Code of Federal Regulations, Title 10, Parts 2, 50 and 51, "Decommissioning of Nuclear Power Reactors," Nuclear Regulatory Commission, Federal Register Volume 61 (p 39278 et seq.), July 29, 1996.
8. "Nuclear Waste Policy Act of 1982 and Amendments," U.S. Department of Energy's Office of Civilian Radioactive Management, 1982
9. Blue Ribbon Commission on America's Nuclear Future's Charter, http://cybercemetery.unt.edu/archive/brc/20120620215336/httl,:/ibrc.gov/index.p hp?q=p3age/charter
10. "Blue Ribbon Commission on America's Nuclear Future, Report to the Secretary of Energy," http://www.brc.gov/sites/default/files/documents/brc finalreport jan2012.pdf, January 2012 TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Section 7, Page 2 of 3

7. REFERENCES (continued)
11. "Strategy for the Management and Disposal of Used Nuclear Fuel and High-Level Radioactive Waste," U.S. DOE, January 11, 2013
12. "Acceptance Priority Ranking & Annual Capacity Report," DOE/RW-0567, July 2004
13. U.S. Code of Federal Regulations, Title 10, Part 50, "Domestic Licensing of Production and Utilization Facilities," Subpart 54 (bb), "Conditions of Licenses"
14. "Low Level Radioactive Waste Policy Act," Public Law 96-573, 1980
15. "Low-Level Radioactive Waste Policy Amendments Act of 1985," Public Law 99-240, 1986
16. Waste is classified in accordance with U.S. Code of Federal Regulations, Title 10, Part 61.55
17. U.S. Code of Federal Regulations, Title 10, Part 20, Subpart E, "Radiological Criteria for License Termination," Federal Register, Volume 62, Number 139 (p 39058 et seq.), July 21, 1997
18. "Establishment of Cleanup Levels for CERCLA Sites with Radioactive Contamination," EPA Memorandum OSWER No. 9200.4-18, August 22, 1997.
19. U.S. Code of Federal Regulations, Title 40, Part 141.16, "Maximum contaminant levels for beta particle and photon radioactivity from man-made radionuclides in community water systems"
20. "Memorandum of Understanding Between the Environmental Protection Agency and the Nuclear Regulatory Commission: Consultation and Finality on Decommissioning and Decontamination of Contaminated Sites," OSWER 9295.8-06a, October 9, 2002
21. "Multi-Agency Radiation Survey and Site Investigation Manual (MARSSIM),"

NUREG/CR-1575, Rev. 1, EPA 402-R-97-016, Rev. 1, August 2000

22. T.S. LaGuardia et al., "Guidelines for Producing Commercial Nuclear Power Plant Decommissioning Cost Estimates," AIF/NESP-036, May 1986 TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Section 7, Page 3 of 3

7. REFERENCES (continued)
23. W.J. Manion and T.S. LaGuardia, "Decommissioning Handbook," U.S.

Department of Energy, DOE/EV/10128-1, November 1980

24. "Building Construction Cost Data 2013," Robert Snow Means Company, Inc.,

Kingston, Massachusetts

25. Project and Cost Engineers' Handbook, Second Edition, p. 239, American Association of Cost Engineers, Marcel Dekker, Inc., New York, New York, 1984
26. Civilian Radioactive Waste Management System Waste Acceptance System Requirements Document, Revision 5" (DOE/RW-0351) issued May 31, 2007
27. U.S. Department of Transportation, Section 49 of the Code of Federal Regulations, "Transportation," Parts 173 through 178
28. Tri-State Motor Transit Company, published tariffs, Interstate Commerce Commission (ICC), Docket No. MC-427719 Rules Tariff, March 2004, Radioactive Materials Tariff, August 2011
29. J.C. Evans et al., "Long-Lived Activation Products in Reactor Materials" NUREG/CR-3474, Pacific Northwest Laboratory for the Nuclear Regulatory Commission. August 1984
30. R.I. Smith, G.J. Konzek, W.E. Kennedy, Jr., "Technology, Safety and Costs of Decommissioning a Reference Pressurized Water Reactor Power Station,"

NUREG/CR-0130 and addenda, Pacific Northwest Laboratory for the Nuclear Regulatory Commission. June 1978

31. H.D. Oak, et al., "Technology, Safety and Costs of Decommissioning a Reference Boiling Water Reactor Power Station," NUREG/CR-0672 and addenda, Pacific Northwest Laboratory for the Nuclear Regulatory Commission. June 1980
32. SECY-00-0145, "Integrated Rulemaking Plan for Nuclear Power Plant Decommissioning," June 2000
33. "Microsoft Project Professional 2010," Microsoft Corporation, Redmond, WA.
34. "Atomic Energy Act of 1954," (68 Stat. 919)

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001,Rev. 0 Site-Specific Decommissioning Cost Estimate Appendix A, Page I of 4 APPENDIX A UNIT COST FACTOR DEVELOPMENT TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Appendix A, Page 2 of 4 APPENDIX A UNIT COST FACTOR DEVELOPMENT Example: Unit Factor for Removal of Contaminated Heat Exchanger < 3,000 lbs.

1. SCOPE Heat exchangers weighing < 3,000 lbs. will be removed in one piece using a crane or small hoist. They will be disconnected from the inlet and outlet piping. The heat exchanger will be sent to the waste processing area.
2. CALCULATIONS Activity Critical Act Activity Duration Duration ID Description (minutes) (minutes)*

a Remove insulation 60 (b) b Mount pipe cutters 60 60 c Install contamination controls 20 (b) d Disconnect inlet and outlet lines 60 60 e Cap openings 20 (d) f Rig for removal 30 30 g Unbolt from mounts 30 30 h Remove contamination controls 15 15 i Remove, wrap, send to waste processing area 60 60 Totals (Activity/Critical) 355 255 Duration adjustment(s):

+ Respiratory protection adjustment (50% of critical duration) 128

+ Radiation/ALARA adjustment (15% of critical duration) 38 Adjusted work duration 421

+ Protective clothing adjustment (30% of adjusted duration) 126 Productive work duration 547

+ Work break adjustment (8.33 % of productive duration) 46 Total work duration (minutes) 593

      • Total duration = 9.883 hours0.0102 days <br />0.245 hours <br />0.00146 weeks <br />3.359815e-4 months <br /> ***
  • alpha designators indicate activities that can be performed in parallel TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Appendix A, Page 3 of 4 APPENDIX A (continued)

3. LABOR REQUIRED Duration Rate Crew Number (hours) ($/hr) Cost Laborers 3.00 9.883 $33.47 $992.35 Craftsmen 2.00 9.883 $44.63 $882.16 Foreman 1.00 9.883 $53.20 $525.78 General Foreman 0.25 9.883 $61.78 $152.64 Fire Watch 0.05 9.883 $33.47 $16.54 Health Physics Technician 1.00 9.883 $51.92 $513.13 Total Labor Cost $3,082.60
4. EQUIPMENT & CONSUMABLES COSTS Equipment Costs none Consumables/Materials Costs

-Universal Sorbent 50 @ $0.69 sq ft *11 $34.50

-Tarpaulins (oil resistant/fire retardant) 50 @ $0.31/sq ft (2) $15.50

-Gas torch consumables 1 @ $19.21/hr x 1 hr (3} $19.21 Subtotal cost of equipment and materials $69.21 Overhead & profit on equipment and materials @ 16.00 % $11.07 Total costs, equipment & material $80.28 TOTAL COST:

Removal of contaminated heat exchanger <3000 pounds: $3,162.88 Total labor cost: $3,082.60 Total equipment/material costs: $80.28 Total craft labor man-hours required per unit: 72.15 TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Appendix A, Page 4 of 4

5. NOTES AND REFERENCES
  • Work difficulty factors were developed in conjunction with the Atomic Industrial Forum's (now NEI) program to standardize nuclear decommissioning cost estimates and are delineated in Volume 1, Chapter 5 of the "Guidelines for Producing Commercial Nuclear Power Plant Decommissioning Cost Estimates," AIF/NESP-036, May 1986.

" References for equipment & consumables costs:

1. www.mcmaster.com online catalog, McMaster Carr Spill Control (7193T88)
2. R.S. Means (2013) Division 01 56, Section 13.60-0600, page 22
3. R.S. Means (2013) Division 01 54 33, Section 40-6360, page 688
  • Material and consumable costs were adjusted using the regional indices for Tampa, Florida.

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001,Rev. 0 Site-Specific Decommissioning Cost Estimate Appendix B, Page 1 of 7 APPENDIX B UNIT COST FACTOR LISTING (SAFSTOR: Power Block Structures Only)

TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Appendix B, Page 2 of 7 APPENDIX B UNIT COST FACTOR LISTING (Power Block Structures Only)

Unit Cost Factor CostlUnit($)

Removal of clean instrument and sampling tubing, $/linear foot 0.39 Removal of clean pipe 0.25 to 2 inches diameter, $/linear foot 4.08 Removal of clean pipe >2 to 4 inches diameter, $/linear foot 5.95 Removal of clean pipe >4 to 8 inches diameter, $/linear foot 11.47 Removal of clean pipe >8 to 14 inches diameter, $/linear foot 21.91 Removal of clean pipe >14 to 20 inches diameter, $/linear foot 28.62 Removal of clean pipe >20 to 36 inches diameter, $/linear foot 42.07 Removal of clean pipe >36 inches diameter, $/linear foot 49.93 Removal of clean valve >2 to 4 inches 78.93 Removal of clean valve >4 to 8 inches 114.67 Removal of clean valve >8 to 14 inches 219.09 Removal of clean valve >14 to 20 inches 286.18 Removal of clean valve >20 to 36 inches 420.73 Removal of clean valve >36 inches 499.29 Removal of clean pipe hanger for small bore piping 28.21 Removal of clean pipe hanger for large bore piping 95.46 Removal of clean pump, <300 pound 196.25 Removal of clean pump, 300-1000 pound 537.06 Removal of clean pump, 1000-10,000 pound 2,112.69 Removal of clean pump, >10,000 pound 4,095.85 Removal of clean pump motor, 300-1000 pound 222.34 Removal of clean pump motor, 1000-10,000 pound 874.68 Removal of clean pump motor, >10,000 pound 1,968.03 Removal of clean heat exchanger <3000 pound 1,148.81 Removal of clean heat exchanger >3000 pound 2,905.59 Removal of clean feedwater heater/deaerator 8,089.54 Removal of clean moisture separator/reheater 16,498.75 Removal of clean tank, <300 gallons 252.11 Removal of clean tank, 300-3000 gallon 789.63 Removal of clean tank, >3000 gallons, $/square foot surface area 6.63 TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Appendix B, Page 3 of 7 APPENDIX B UNIT COST FACTOR LISTING (Power Block Structures Only)

Unit Cost Factor Cost[Unit($)

Removal of clean electrical equipment, <300 pound 104.61 Removal of clean electrical equipment, 300-1000 pound 361.99 Removal of clean electrical equipment, 1000- 10,000 pound 723.99 Removal of clean electrical equipment, >10,000 pound 1,753.79 Removal of clean electrical transformer < 30 tons 1,217.98 Removal of clean electrical transformer > 30 tons 3,507.58 Removal of clean standby diesel generator, <100 kW 1,244.08 Removal of clean standby diesel generator, 100 kW to 1 MW 2,776.84 Removal of clean standby diesel generator, >1 MW 5,748.61 Removal of clean electrical cable tray, $/linear foot 9.96 Removal of clean electrical conduit, $/linear foot 4.36 Removal of clean mechanical equipment, <300 pound 104.61 Removal of clean mechanical equipment, 300-1000 pound 361.99 Removal of clean mechanical equipment, 1000-10,000 pound 723.99 Removal of clean mechanical equipment, >10,000 pound 1,753.79 Removal of clean HVAC equipment, <300 pound 126.49 Removal of clean HVAC equipment, 300-1000 pound 434.96 Removal of clean HVAC equipment, 1000-10,000 pound 866.88 Removal of clean HVAC equipment, >10,000 pound 1,753.79 Removal of clean HVAC ductwork, $/pound 0.41 Removal of contaminated instrument and sampling tubing, $/linear foot 1.17 Removal of contaminated pipe 0.25 to 2 inches diameter, $/linear foot 17.97 Removal of contaminated pipe >2 to 4 inches diameter, $/linear foot 29.11 Removal of contaminated pipe >4 to 8 inches diameter, $/linear foot 45.75 Removal of contaminated pipe >8 to 14 inches diameter, $/linear foot 87.89 Removal of contaminated pipe >14 to 20 inches diameter, $/linear foot 104.94 Removal of contaminated pipe >20 to 36 inches diameter, $/linear foot 143.96 Removal of contaminated pipe >36 inches diameter, $/linear foot 169.19 Removal of contaminated valve >2 to 4 inches 354.93 Removal of contaminated valve >4 to 8 inches 406.14 TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Appendix B, Page 4 of 7 APPENDIX B UNIT COST FACTOR LISTING (Power Block Structures Only)

Unit Cost Factor CostlUnit($)

Removal of contaminated valve >8 to 14 inches 820.91 Removal of contaminated valve >14 to 20 inches 1,041.98 Removal of contaminated valve >20 to 36 inches 1,381.63 Removal of contaminated valve >36 inches 1,633.92 Removal of contaminated pipe hanger for small bore piping 114.40 Removal of contaminated pipe hanger for large bore piping 361.86 Removal of contaminated pump, <300 pound 722.19 Removal of contaminated pump, 300-1000 pound 1,644.38 Removal of contaminated pump, 1000-10,000 pound 5,221.26 Removal of contaminated pump, >10,000 pound 12,691.12 Removal of contaminated pump motor, 300-1000 pound 726.23 Removal of contaminated pump motor, 1000-10,000 pound 2,141.94 Removal of contaminated pump motor, >10,000 pound 4,817.34 Removal of contaminated heat exchanger <3000 pound 3,162.88 Removal of contaminated heat exchanger >3000 pound 9,264.14 Removal of contaminated tank, <300 gallons 1,207.75 Removal of contaminated tank, >300 gallons, $/square foot 23.04 Removal of contaminated electrical equipment, <300 pound 549.62 Removal of contaminated electrical equipment, 300-1000 pound 1,304.67 Removal of contaminated electrical equipment, 1000-10,000 pound 2,516.48 Removal of contaminated electrical equipment, >10,000 pound 5,046.17 Removal of contaminated electrical cable tray, $/linear foot 26.73 Removal of contaminated electrical conduit, $/linear foot 13.29 Removal of contaminated mechanical equipment, <300 pound 612.32 Removal of contaminated mechanical equipment, 300-1000 pound 1,458.37 Removal of contaminated mechanical equipment, 1000-10,000 pound 2,807.39 Removal of contaminated mechanical equipment, >10,000 pound 5,046.17 Removal of contaminated HVAC equipment, <300 pound 612.32 Removal of contaminated HVAC equipment, 300-1000 pound 1,458.37 Removal of contaminated HVAC equipment, 1000-10,000 pound 2,807.39 TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific DecommissioningCost Estimate Appendix B, Page 5 of 7 APPENDIX B UNIT COST FACTOR LISTING (Power Block Structures Only)

Unit Cost Factor CostlUnit($)

Removal of contaminated HVAC equipment, >10,000 pound 5,046.17 Removal of contaminated HVAC ductwork, $/pound 1.82 Removal/plasma arc cut of contaminated thin metal components, $/linear in. 2.90 Additional decontamination of surface by washing, $/square foot 6.44 Additional decontamination of surfaces by hydrolasing, $/square foot 26.13 Decontamination rig hook up and flush, $/ 250 foot length 5,153.02 Chemical flush of components/systems, $/gallon 21.48 Removal of clean standard reinforced concrete, $/cubic yard 134.93 Removal of grade slab concrete, $/cubic yard 171.08 Removal of clean concrete floors, $/cubic yard 368.58 Removal of sections of clean concrete floors, $/cubic yard 1,043.46 Removal of clean heavily rein concrete w/#9 rebar, $/cubic yard 243.04 Removal of contaminated heavily rein concrete w/#9 rebar, $/cubic yard 1,798.06 Removal of clean heavily rein concrete w/#18 rebar, $/cubic yard 307.24 Removal of contaminated heavily rein concrete w/#18 rebar, $/cubic yard 2,375.29 Removal heavily rein concrete w/#18 rebar & steel embedments, $/cubic yard 438.28 Removal of below-grade suspended floors, $/cubic yard 368.58 Removal of clean monolithic concrete structures, $/cubic yard 852.65 Removal of contaminated monolithic concrete structures, $/cubic yard 1,787.88 Removal of clean foundation concrete, $/cubic yard 673.83 Removal of contaminated foundation concrete, $/cubic yard 1,665.07 Explosive demolition of bulk concrete, $/cubic yard 30.03 Removal of clean hollow masonry block wall, $/cubic yard 93.44 Removal of contaminated hollow masonry block wall, $/cubic yard 280.67 Removal of clean solid masonry block wall, $/cubic yard 93.44 Removal of contaminated solid masonry block wall, $/cubic yard 280.67 Backfill of below-grade voids, $/cubic yard 37.43 Removal of subterranean tunnels/voids, $/linear foot 106.85 Placement of concrete for below-grade voids, $/cubic yard 138.88 Excavation of clean material, $/cubic yard 3.60 TLG Services, Inc.

CrystalRiver Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Appendix B, Page 6 of 7 APPENDIX B UNIT COST FACTOR LISTING (Power Block Structures Only)

Unit Cost Factor Cost/Unit($)

Excavation of contaminated material, $/cubic yard 36.57 Removal of clean concrete rubble (tipping fee included), $/cubic yard 26.59 Removal of contaminated concrete rubble, $/cubic yard 22.87 Removal of building by volume, $/cubic foot 0.31 Removal of clean building metal siding, $/square foot 1.15 Removal of contaminated building metal siding, $/square foot 3.58 Removal of standard asphalt roofing, $/square foot 1.82 Removal of transite panels, $/square foot 1.93 Scarifying contaminated concrete surfaces (drill & spall), $/square foot 11.08 Scabbling contaminated concrete floors, $/square foot 6.48 Scabbling contaminated concrete walls, $/square foot 16.94 Scabbling contaminated ceilings, $/square foot 57.69 Scabbling structural steel, $/square foot 5.17 Removal of clean overhead crane/monorail < 10 ton capacity 510.43 Removal of contaminated overhead crane/monorail < 10 ton capacity 1,361.87 Removal of clean overhead crane/monorail >10-50 ton capacity 1,225.02 Removal of contaminated overhead crane/monorail >10-50 ton capacity 3,266.88 Removal of polar crane > 50 ton capacity 5,224.54 Removal of gantry crane > 50 ton capacity 21,922.39 Removal of structural steel, $/pound 0.18 Removal of clean steel floor grating, $/square foot 3.91 Removal of contaminated steel floor grating, $/square foot 10.33 Removal of clean free standing steel liner, $/square foot 9.94 Removal of contaminated free standing steel liner, $/square foot 26.62 Removal of clean concrete-anchored steel liner, $/square foot 4.97 Removal of contaminated concrete-anchored steel liner, $/square foot 30.94 Placement of scaffolding in clean areas, $/square foot 14.84 Placement of scaffolding in contaminated areas, $/square foot 22.26 Landscaping with topsoil, $/acre 27,452.06 Cost of CPC B-88 LSA box & preparation for use 2,323.32 TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Appendix B, Page 7 of 7 APPENDIX B UNIT COST FACTOR LISTING (Power Block Structures Only)

Unit Cost Factor Cost/Unit($)

Cost of CPC B-25 LSA box & preparation for use 2,119.84 Cost of CPC B-12V 12 gauge LSA box & preparation for use 1,716.34 Cost of CPC B-144 LSA box & preparation for use 12,107.07 Cost of LSA drum & preparation for use 209.65 Cost of cask liner for CNSI 8 120A cask (resins) 9,210.20 Cost of cask liner for CNSI 8 120A cask (filters) 9,042.46 Decontamination of surfaces with vacuuming, $/square foot 0.76 TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001,Rev. 0 Site-Specific DecommissioningCost Estimate Appendix C, Page I of 10 APPENDIX C DETAILED COST ANALYSIS TLG Services, Inc.

CrtQaol RiMe. Unit 3 N aclear e1e-atis-t Plant Document P23-1680-001, Rle. 0 Site-Specifi DecaeisinningCost Eati-aae Appendix C, Page 2a1I0 Table C Crystal River Unit 3 Nuclear Generating Plant SAFSTOR Decommissioning Cost Estimate with Dry Fuel Storage (thousands of 2012 dollars)

Off-Site LLRW NRC Spent Fuel Site P essed BSrial V.l..-e B.6aia I utility nd I D-ea R.inea Pakaging Tenspuet FeaessIg Diipnsal Other Tatal Teed Lic.Tee- Magement Hestnation Valae Class A Class B CIa.. C GTCC Pe-emsed Craft Contractnr I I At1xi-y Cast I i*acx *II*XV v*cr]pK[o* Casot Casts Casts Casts Casts Casts Catttln=enco Coats Casts Casts Caste Ca. Feet Ca. Feet Ca. Feet C. Feet C. Feet Wt..Ubs. = nanhou Nannou PERIOD 5- Prepaesratis Peiod I Additinoo] Coals 1.2.1 21OttOu&0I Sudget qEoodln SEerity. 07.0

  • 0.710 0 702 .

I22 2012tO&NI Sudnot No PleotoiveSerolos (Soooty) 1.,500 - .5m1 1.0 1.32S 1.2.3 2012Co*rpotteAltoatioon - 2.400 2.403 I 2.4 2014-&.%1odMet(ExcudodgS-eoty) 542,591 5e-51 1.2. 201406NJ uu*deNo-. PeoleetitoSeritt tSoeoeitt) W0.905 10,095 1.010 9086

.2.t 2004tO&9ISodgel orpuraic .. Alleatnes - 10.202 - 1.265 18,265 I 27 20150C Ind

  • `: (Et .lod.ngSeturo1y)
  • 250*8 -05,5807 2.585 1.2.0 2012tO&StSodcst Nor. trotecttto Sorotes l.¢ccrltt) '-250 r,25 11r21 29 Scent F-1IPool Oload Prepoaltons 17.177 S .571 - 17.S7 1.0 IS Seserancootttonoocr) ,1102 2 5 5, 109 5.1S, Il S11 o*-dOo ef Elteorl S-st-t 24!0 187 2,675 2675 1.2.12 Alilcate Spoo. Fuot Cthno Slstom 2 27 205 2,931 2.931 1.2.12 Dispooltof IRetiedNSSSComponent. 15,000 - 2,0M 17,002 17,000 29:386 2.370,w9 1.2.14 Sapoonofr-..1'1 adwoste 1.2 Subtol-[ Period I AddilionalCosts 2,391 127,119 143.481 03G38 29,386 i.370.069 Pcriod I Prriod-DcpcndoolCosts 1.4.2 ProPertytotes 2 1728 21%2 2,172 2172 I 4 Subtotal Period I PFrod-DopendetoCosis 2.172 2.172 PERIOD t TOTALS 18 M. 15t.9o* 20I01 12,291 1t5.G6t ý3380 29 MG -70 .9 PERIOD2s - SA0STO1 Do -ney with WetSpent Fuel Stneage Pcrtodinatirot Derto misoooMton tlttee 2o.l.t ooQu orlrlynspceklto 2o.l1.2

~

.2a Semto-nnatcottnootorstalsouosy Propos recorte 2n.1. ` 1antotnaor. s7upplis It2 710 710 2a. Subtolna Pod 2in.olitq Coas - - . . . - 912 104 1,111 1].1 Perood2. Addltiona]Co.-

2o.2.1 ISFS1Conelrolnon&Pool&IOmeod

  • 55,116 55,116 55,110 Oo.2 Subtotot Period2a Addgtnal .. tsl - - 5011 -I 50.1 16 55.116 Pertod2t Period.DOeopdettCosts 214 2358 .1.15 242 n.t.2 Poropelytotes - 5,1-0 5.4 2nat 2 Hal11t phys sopplirs 229 1,14. 1.145 t

t.tIa. Dlsrpal of DAW - -eneted 2t 16 95 95 S0,10 2O.W2f2 3 2a.-.5 Polrnterg" bndnrt 1I- W6 15,8 I.M, tot NOO

] rf eet 1.214 121 1,03M 1.3w0 2a...7 tmer-e,-t PIl.ot F-e I2 1,1 1,3 8o.40 FloridaLL W anspoionFer 1

.2u.4. Spool Foe,]Pool 0&1 401 7M509 4,729 to 4.10U SF21

's" (pintlo

,, Costs U*4 SS M 442 t4 I Ste It&M No-Labor 1,957 14,90 6067 0r121 2o4 13 1a:.2 Securiy SI.T C-1Letht1StafTCo Le C.9110 49,200 3.2-5 171;5 W.2M'o 1,5*7 2,t610 0.202 01."089

,3712 n.2a Subtota Period2OPertod-Dopeodtt Costs 916 24 I1619 118.877 26.M-t 91.917 L. 10 21'202 00 1.4 630 t2.0 TO-TALPER109I SoCO-ýST ,30 159,265 11S-3 175,103 28.071 147.032 1i.OO 2O.202 30 i,09,t463 PERIOD21,- SAPSTOR Do3 et e with DflySpent Fast Slege Pertod2O, Stet -e.iestoong A,1-1-c 21, Q1ooerlylnsp.tioo 2b51.2 Soot-aoooal eottnomsetlasotuex 2b tI Ps.! reports ob.l.o Stl~totlous t -f plsoeot * - - 1171 221 1,692 69M 21 t 5 I.- .tteno. opplier 1Ot 2.6 211.991 21 I Sub-toal Period21 Atistly CoAst * , - .71' .21 4,691 *1,9 TLG S-ei.-, I.n.

Cnytot Rit'e Unit 3 Nulear Generating Plant Doco.enl P23-1680-001, Re.. 0 Site-Specific Deo..oning Coat Fofitae Appendiý C, Page 3 f 10 Table C Crystal River Unit 3 Nuclear Generating Plant SAFSTOR Decommissioning Cost Estimate with Dry Fuel Storage (thousands of 2013 doll..e)

Off-Site LLRW NRC Spent Font Site Penedoo BurialS'oloum. Burial Itilityo Actinity Doon R .l Packagio. TaoAtot Pmcesing Dinptots G Other Total Total Lie. Teo M a-eet tRestocrtion V.ot..e Clan.A Clo.. B Clan. C TCC P-oened Ccft Contractor loden Actimity Dreiptin Co.t Cost Coot. Costs Conts Co-ts Cost. COntinencc Cost. Cost. Costs Cont. Cu. IFet Cu. Font Cu. Feet Cu. Feel Cu. Feet Wt.. Lb.. Manho.un Mahou-Pceriod 2b C llart eral Cests 21,0 I S"en Ful Captlat-nd Tra.nser I 2M* G' 8* 4.830 I 1<30 2b.3 Subtoota Perod 2b Ccllaterat Cool.

Poeod 2b Peod-Ocerndnt CdaL.

2b.4.1 I-a 83ý1 4 -,16'1 8,52 52.

21,1.2 pcctcerylance 4062 - 4..12 4,062 2b4.3 Health pbyn':nu-pphe - 1.757 447 2234 2.234 2b.4.4 [Ditpena] ofDA%generated 95 *, 101 181 1.525 18.422 12 -

21.4.5 Plant t.c.fM budýe 0I.2 25:2 1,93:1 21,4, NRC .. es 4 901 4, 0391 5 509.1 2b4.7 E-mrcencyPl.--nn Fe- 1.521 152 1.674 1.1174 2hA4 se FIoda LTRWInspeetton Fee 2bA.u ISFS1Operas Cost. I.G3 43 18s 1.861.

214.10 S-rn I1&MN-bo.- 29241 13* M r27 2..888 ,.7"8 2b.4.11 Snot Stuffst 51.014 7,787 U,7571 1,725 05.981 - - - - . -1.197.1117 2b4.1 LUtitilp StaI oor 43.120 6.408 49,.818 26.308 23.510 2b4 Subtol.[ Peered2b PC-i.d-IlepcodcutCoarn 1,707 42 11 *5 145.... 21,120 1Iw51528 09568 3 80.0M15 * ,723 - 8.222 113 1.778.285 2b,.0 TOTALPERIOD A21,25)9 1,787 45 1 9 ", 154G71 22.570 179.180 94,344 n4.832 - 1,923 - 8.252 P,3 1.775.285 PERIOD f-SAFSThR Do-oncy without Sp-nt Fel Stoe.ge Ped 2I D-t u-;lclrmtoae M-1 2' , I Scate.ruly necoorn 2ý1 2 Semi-a~a -1 mea -u-'y 2!.. .3 Pe-pat -p-rl 2r"1 Oirciaeu.

,4 ceftplaeoet t2771 W3 8 5 2,95" 2,977 2u.I5 Sarnrtneoc rupphre S74615 548 0242 s,242 2-.I Subtotal Pe1d 21Attietry Cot. - . 1745 1,434 8,199 8,199 Ferrod2rc Per.Od-Depedeo C.ots Sell Ins~nern It 191 1,419 1511I 15611 2t 1.2 FPoperty taiet 7.1IM1 - 7,105 7. IW1 2e 13 Hlearthcpht-ir supplien - 2.030 731 3072 3.r72 2u.44 roralefDAW genratcd .3 17 154 - 48 592 2.2 2e4.5 Plor ewcmo boudect 2,028 441] 3,378 3.378 2'.4 6 NkR.ee-4 1 4 4 2,.4.7 Flbrda&LLRWlnoeehoo Fc 2'.4 Site 1)aMNun-Labuc 40.61 1]29 416,9M 456,50 "D8rOW 1,127 2t9* 37 95 134:14

!,.- Ste-unr Slam-on 1 IS l rurityStaf Cet 1 9M 75 5597 9 47375 5 975 554.9.50 2tht DýdoC.A 3.95 -1 W'15 tIll 1. n3 ec.4 2c A-IOM Feteod Subtotal 0taff 2e Penoe,-Depondnsenot~os 2.938 73 17 1.54 15.24M 12187 Mr. r,93 11 3 155 tctt TTAL PERIOD1 2,eCOST 2.9a8 73 17 154 14054.721 124 718,170 21.2 2. 3.095 .pI W15 1.1 1.5M293 PERIODS2TOTALS 5,142 142 33 2.qs 454.5N* 57,.,W4 518,]715 28m,m307 .8i 6.028 129058 17 4.M94.035 PERIOD 3. - Ranticote SoN Folowiog SAFSTPORDo.n.,

PeriodtDc D.-c Det iaaionmg.let 1t

.1i Precpotrecpltnreao-dteectrntttoungeeot 1 300 ISO 24 1,2 .082 Ia 1.2 Rectewplont dwn.& spcs. 4SO tl Fecfee delorlednd -oey 2t 1.4 End product derept-o 122 3 1.5 Detailcdbrect rclenlt 15,! 24 182 57 - . 1.3011 3,..1. Define maoreework .cquenec 137 01 71ZI 1,053 1,`51 t

4,].7 Perfon SER .ad EA N4 4, 1.8 Peefe. SLIt-SpectrttCet SItudy 1 701 751 Id.

. PteparnlnubmirLireosttn ina-iee plan 75 74 54 3a 1.10 reIlt ,N.'RC app-nvol ottenjeat en pcan

- . 7,155 Aettety Spnefreatrens 3a.t.t .1 tt-oe.1toate plot & teepory foerlten 1IM 1,0o3 9nf 103 7370 3a 1 2 PIanlosyoleou 865 71; 4 2 3,11 t-aolot

... rn.le.1 -18 IN *5 9 7,100 3a.1.[1.4 Re1t heoredd sJ 'ito 1 3a 115 Sioleatcalnshietd maG Se-itea- I-c.

C"rt Ri-er Unit 3 NucLear Generatin Plant Docanment P23-1680-001, Re-. 0 SiteSpecific D-emnisioning Cat Eatinate Appendix C, Page 4 f 10 Table C Crystal River Unit 3 Nuclear Generating Plant SAFSTOR Decommissioning Cost Estimate with Dry Fuel Storage (thousands of 2013 dnllasn)

SActicity

-n1en Act Onsetritin Dteon Cost RetvalD Cost Packaging Cat o

Tc-sunt

-.s Cs t-ie Pcessistg L.LRlW Distposul Costs Other Casts Totel ontiaene Tottl s

NRC Lic. Teuo Costs Spen Fuel Maýasgett Costs Site Restoration Conts Pcneset V.It-e Cu. Feet Class A Cu. Feel BRuti.] V.nI.te Class B Cu. Feet Class C Ca. Feet GTCC Ca. Feet Racia /lt PFnessed Wt.. Lbs.

Craft Manhotrs iiit-da Cntrscto M.utnhn Acltttlty Spcicficatneon (etloocdt 97 817 utS ;3 12.,

3It.I .7 Relfod-exrc-le 112 7 1L2 ulIlI8 Ntat Tuerbin Ia . 11.0 Maincandnnanr 49

,3.l .10 Ptani"1ructu-e & bu.td-nn 3M0 571 43K 211 21lt 3,120 luiilI lWncte noaxeerxent 4.ýO 84 945 045 1.20 1..l.l12. Faeithy& ile cld-u i110 16 126 6w 406 - - -

1aI] Tu.l] 4.14. 27 5571 4.0 Planimnr& Site Peparal.tns In 1.12 Precaet dlsmanithg eqneon*

Ia1.13 Plant ptp & lntp.sr-es 41 1:5 1a3

" 1.14

.a et ter eD. on-u-p tn 171 1.40K

3. 1 15 Riet-ng/Coni.Ceiri E-xlpsAllngti 22M0 -33 2.5w 203 1x1. P- &

.u..oak.Aireacntai- 22 132 172 72.7W7

3. I Subida Perod Ia .-ct ot 7 C7 2.,04 16,052 35'384 Period3a Per...d-Deendeni Cd-ts

-aI 4 e ITurPa", 47, .1 r 51:1 Ia.] 2 Ppeulrryia"tace In iI OnHalih pbxsca suppbne 1 M1 .177 5177 luA.il Heaty eqatpaeontScla 01 704 71t4 InI 5 Dtaponol

. f iAW eerta- d 12 17 3lu6 Pl-tnenrgy budgnf 145 1.111 3.11 l47 NRC Fe-. 38 a19 419 a4 8 Flor-da LLRI 1n-pe-t.on Fe-3-..9 Sic O&MNun-Labur 20 2,221 2221 2Oo 1.'3. 1l :514

-a.4.:0 Security S lff Coa Il.177 4C.170 150.020 3a 4 I ] LTtlltcStTffCutt 2,ta2 23332.0,7.101 40 20 40 I751.

34 S.1,btotalPeriod is Period-.epcndr-l Crete 1.074 12 10.287 111807 122 514 3a.l l1\0u9LPEtiUS:5to 7(ST 1.074 12 11.2a87 ýW9 i.5t" 2G2 PERIOD tb - Dfentssinniug Peptrctieus 122i Period3b Dircrll ro-iaetri Jilxe Dtciled Wurk P rdu.

00.],l,1 Plant reelemt 57 00-I 97, 4.7.3 311.1 2 ltea1 ri.lot nuler 'M -3 05' lb. I. 1.1 Renmantn buiddxngs 29. 189 471 142 3b ll CRD mhng assembly .6 6. 54A) lb.t.I 5 CRD hou=n-s& ICl tubes lb 6.t I-n 2! 18 ,

Ib.lI.L7 Rneatr reasc 1.2M0 lb. 8.1.8 Fac-hty0-lo1uu lb tI 1 S -flteaIhlde I Noo(

lb. 1.3.30 Rtoloeteal s,held IS 14n 144 3.243 L~ow lbI. ].31 Siesto geercaloea

-70 2.73.

t '40 1 733 thbi I3 lb.l.t.ii late Trbine Mute*oendeae

  • '2' lbI : 15 A--la budding lb 6.3.30 Reurtor bulldon 5,Zoa a-

- ,1928 1873 7140 32.243 lb I i TLial

- 1.28 189 4.518 l 70t3 l2 12.241 3l I Sub*l Peer1d3b A.ttity C-otn 189 4,534 1.642 Perd 3b AddittonaL. .t1 55,08 3b . I St- ..arai-Terieatin' - 10000 0875 lb I Subtotal Perindlb Addtlonal . atI - O133 30 '0 572 Peod lb llatnral C.-t

ýb 3.1 De'e equipent 1014

'b 3 2 D'ýe f e~a o e~ 1.2M58 199 I 147 1.017 Ib.3 3 Pipe uelntsnqutpment Il303 - 165 1.261 1.240 lb3 Subtot[ Period3bCtllatneat Cto IOW4 ',]03 - 258 300

.878 3.878 TLG Sertia, 1-c.

Crtal Tis-r Unit 3 Nuclear Oeaerstitg Plant Document P23-1680-001, R.,e. 0 Site-Specific Dectmlfiononp Cat Estimate Apendi- C, Pa.e,5 o 0 Table C Crystal River Unit 3 Nuclear Generating Plant SAFSTOR Decommissioning Cost Estimate with Dry Fuel Storage (thousands of22013 dollarsl Off-Site LLRW NRC Sp-et Font Site Pessed B13i-WVs'oles Burial IUtility .

ad IActivity Index~Ae ~tivt Desription D-oo Cost Re.oovt Costs Psekagitg oo Trestoet Peosalng Dtisposl Other Costs Tot-t Contigeny Tot-l Cot.

Lie. Te-Costs Mtangement Co Restorto Cots o

Co. FPet Cl... A C.. Fent Cs.s B C.. FPet Cl.ss C C.. Fent GTCC C.. rent Preonsed Wt..LUt.

Ceaft Mthot s Contrsetor M-hoto I

P-ed 31, PtrMod-Depottio Cot.

3141I NDccnuppleo 2* 39 3 20 287 287 3b 43 Property torn 117 5 117 117 Sb8.4 H Heoth , hk1e11orches 64 .473 317 04b.40 HRea.teq.pee.,t -. ta1 3b4.4 Dispo olf RAW enteroted 5 ,7 292 5.8 4 1 14 2t, 2b.4.7 Plots e-e-o budgel 3h 48 NDC V-2tt 191 t~t 1.31 4.3 1b4.4 Flotitd LLRWIntoeotionFie 0 344410 Site U&M933n.Labor

,lb 4.11 S:euttiy RtfCot 1445 70 779 b 412 DU.G StalffCoo 675 5,1732 5.173 b.tA.I Ut13 tit Statlcosi 1733 10.231 18.231 12.

  • 3b 4 Subicil Period31Penod-Ocrendint Coot, 7 2 14 1 0,15 -495 19,195, 19.195 292 220.,W 34b.0 WIiTAL PER4100 Sb11107 .045 .6*2 2 14 20,357 5,471 2ý 502 34,622 292 5.834 30,610 264 02 PRIOato TOTALS .047 2730 I op X4,371 11,rl M 93 IMu -,,77. ,.0. 16 121  ;,0,0.6 1,543 8t512 PERIOD 4, - Ler Com. oont R-.1vl Pinnd t.Dir-ct e.mivso.ning

.. Aeicttos NulelorSliea SopplySt.em R-mool 4o I ] I Reoctr C-loot Pipi~n 28 149 27 296 .W4 507 M,,3847 2.774 4u.;1.1.2 P-e-.urioc ReliefTook 4 4 7 29 7495 94 4 - 2,840 360 48.1.1.3 Ococt or C-loot Potpoh& Motot St 67 121 - ,804 - - 6,873 - 37.286 2441I so 4o.-.l.4 tretouroer 2.58. 2,7 25W 1,5X` 1,5A 122 2,624 341.500 4,555 So.I 41.5 SteoamIroeruotoe 2* 4.ý0 2,541 32 415 15,-12 2A.374.46 0.4134 to 4.4.5 CRP3Mell~iotIfe"*ic Steoc'ore Reovtoco XM{;4 2352 4o.I.t1.7 Rect or Vreset Intetoals 7110

.40 6.478 7.404 67. 281t;46 2.: 583 2- 276 6:, 2 3 379 462 90.11 4 'ettel &lItorool~sGTLCCDipo*a 1071 &,2M 8.237 1,785 37:s.605 -

4o.i.i.S ReociorVetoe 3 2003 276 20 4M3 20 IM: - 977.823 2.; M3 i. 19L 4o.,l Totolo 7 178 9.5,21 267 15.073 11-94 M*7 230.52 8A791 86.791 19,039 24,217 U*2 1.785 5.5m?,.01 72220 8.471 So.I1.2 MloioTutbiitel"lerocturo 260 23 5 I -0 8" 159 45S - 43.602 1.470 4u1.t Main Coodcae -Si74 55 43 2577 2911 234 1.310 1.310 104.240 17,2448 Ci.odive Costs e-toClean B uiding Demolition io.t.t.I Reacito 8.1440

-7 24 0

78 to.tI.4.3 PoetHandlit Aeea IAut RldgI 17 -3 3 1,249 4 4.1.0 4 Itin cdi Bldg 19 4

-. t.4.5 tm-,- Shop - Hot 1 4 1 140 Jo..4.4.6 44 Woehoo-4o.t.J iTolol I.2 15ý I,22ý1 1,221 DOipoolof Plfo Sysems 4J t 5.1 Athary Steam 1a.t 52 Aontat3- Steam - RCA I 2 Jo I5.3 o'heCol Addtioo- Cot 2l 19 1 24.217 1,127 4.1 5 4 CbhmicolAdd-.n o-n- Intolated 13 l 3 2044 159 to 4.5.3 Choecul Addtmo - Iolated - RCA 2.' 1 124 2' 147 147 to 744 Chenico. Addition.-RCA 0 - 26,704 503 So1.5. CbeniicotSeedSecooonta* Cy*cle 22 143 143 "31 4St 5 8 Chomico FeedSecoday ycle - RCA 2.W7 259 "71 SoI 0.0 Chiled Wotc- - - 4,020 515 4S If 10 Chilled W.t-r- RCA N 67 672 27.273 1.220 JoI40.11 C-vult.e - W.-er 2t 143 143 Renrat m 1 - 812 U318 4.

Jo 15 13 1 C-ontdDetai

- -bdes 67 tal1.1 e Coodent.e &1DvWateer Suppl to 45.45 Goodene & De-.. Wtter Supp" - C-o '48 116 - 19.60 4.244 4J 1.5.167 Godeotote& RemitWoir Soppy . RCA 2I 12 W413 143I - 3573 1.773 4o..1 tondenot *?ont - - 4

=25 .8 21 2 -131.41 3,560 4Jo15.1 i'oodteeotDcmtoerolhzer - 2.482 So.l.t.lS CondeonoteDemioerahoer-Cootl 1.604 675.134 28M0 TLG Serice, I-e.

Cr"n.alRi-er unit 3 N-clear .. enet iegPlant Dtcnnet P23-1680-001. Rev. 0 Site-Specific DeLt lmiosiein Coat Estimate Appendix C. Page 6 of 10 Table C Crystal River Unit 3 Nuclear Generating Plant SAFSTOR Decommissioning Cost Estimate with Dry Fuel Storage (thousands of 2013 dollars)

=Ot-Site LLRW NRC Spent Fuee Site Prcessed Borint Voaumes Vureea I Utilily and Actitity Deee Rete- nv PFackaging Trlseote Peoesiog Disosal Other Tatl Tatal Lie. Teo Metgettet Re.-ratlin Vo.I-e CIa.. A Class B Class C CTCC Poessed Craft Coat1ra=ter toden Rottots-oea Detýptine Cent Casts ntCo tnoencl Cet Casts Casts Cast. Ce. Feet C.. Feet Ce. Feet Ca. Feet Cu. Feet Wt.. Lb.. Mahote Manhote

.tspotalotftlart Stme teootrttueed)

a. 1.5.20 Condn- Ar r-etooal & P itng 94 62 71 M7* 2 {18 Ia 1.5.21 0.le Makeup DemtoWet,, 71 1.472 Ia 1.5.22 t0.la Makeup eert Water - RCA
  • 12 3 21 M4 141 - 513 20841 1.125 4a 15.M3 t0', Startup 1 1o 10 222 4...5.24 tale Startup - RCA 21 2 2 43 12 4 1 7-.510 4201 O 1.5.25 Diem]Jdket Ciooe 26 30 613 4a '.5.20 Dlesot-Aae Cto, Cane 4 6 WO Ox 5 SOCFO& Cxmprd3Air & Ehau-t E.25 4.1 It. 1.5E28 RD LubeOil S 20 Ilt 4a 1.5.259 COP-i eomptseandsd Stttn Atr 10 5 I

Iu I 5.10 EpP. Fuee IWTransfer 18 M 31 2 3 414 atI 5.1 EFPPRumpDthae - 30 5.8 -- - -- -- - 180- 1.0 .82 Ia.t.5.32 OmerenryFeedmater ta 1.5.33 tmoreno"oFe-dwaer - RCA 127- 3 a M 205 -- W,-51 2.30 4a 1.5.31 Ettraoro th'm 517 134 - - 2,1.W 4O.t.5.1S FR Reaer,ReliefVents & Dran - .121 43/4 ].5.3 t6 t SeaterReFiH t Vents & Drain -.. ,nt I I I --

1- 31 Ol 300 4a.t.0.:t7 Feedatter 1-- 0 2 11.2 4a.t.5.35 Pedatero Iotetatad- 3RUA 2.o 2.9393 IM 10.1 4I I 540 FPdwater - RCA 57 -8 0ot 1107 10031 92 5U -1 572 23 2431 426 I 5.1t HVAtOttt OutSlde.

4I 5.42 LP & HP Feedate Drain & Ve=t 2-0 tI.l.5.Io LP & HP Fedmater D- & Vente-ot 2 19 02 2.5 -S 0 -- - 5N.14 Gl 4.9. 4.94 4O 15.44 LiquidSampln - C- 01 t12721 1.398

1.5.45 LtqeidSamplite - RCA
  • 336 - - 141830 M.655 l,1,187 IN' 4a .5.4s LubeOtt 58 "8 7 12 256 40.1.5.47 SMai& teheat Stesam 102 -- 2.23;0 I 71 54 -

15.8 4a ;ai. & thleat Steam -C- 34.811.4W¢ l7. 12031 92 544 544 4, ,

5: lai9 & Reheat Steam - RCA - 29 182 279 lIe tt- Turbine Rba S-oom Se DR.mn 22 1,3 3 1.35

t. 51t1teno tseTurbtneR5om Draitns- 0t-1 21{14 2 7 .014 114 la t 552 NtteenltHdm-eatCnrb.a D-m&od 011 - - - 1=20 t..: 5.53 NueSe" &fDeoay eatSeaWate. 54 == 1.172 a.1 554 Nu SeI & De..y Hea: SeaWa.er - Coat - - --- - 1,107 4.t.O 51 Nu, Se- & D-ea Hea Sa ater - RCA 5 19 S 47 t .t.5.50 RC & Mie Want, E .aporatur .,07.5 454 276 26; 7,957 4u.] 57 RC & M.,- Wa-st EaporaTor- Insulated 41 4 - 62 135 ] L."0 636
  • 79 tu. .5.58 S.rren
Wsh Wat.e 47 98M 4O u 55 Seal& Spry WRater 4 - - I3 225 - 5 - - 99 a.t.5 GW eal & S"pr Water-. on INo 1 4 143
10'44 1.ý77 al t Set & Spray Water.- RCA 79 I - 7M:  :*1 11 ý,79 tu.].5 02 Se..ndary CycloSapmott 24 - - 4 27/ 27 U22 5a.t53 S.ndat" CyoleSamplinn-Coet t 1at4 Se1m-,1 d 76et,Sampht C-Cotrt - to 2 Is 8 .7O 4a. .0.05 See1-t*a CyctoS.amtph - Ineulated 4 .500 S1mndxey t Se, C'lod 'Nte CIlit, 201
4. 1.5.07 T-b Bide SR p & O+/-5Water Ieparat.r 31 4,97 4a. 1.5tCA Turbire ,enerator Reel1i. 20 22 Ia.t.5.05 Turob-e1laxd Steam &DralDn 57 4 2 ;9 4a.t 570 Tutbteb ubeItd 7 54 It. .571 W.aste- D - ,t 3 ']1 7 Wo 16 2a 2 4a.1.5 72 W"e- G.e Disposat 141 829 11 - ,374 6,4 1 .50 5,.3 Ia 1.5 Txtatt 7 027 2,12 2297 15.314 1,.049 2M3* 70,051 IX2 2.0317ý1 114,fl1 43/4 1.0 Seaffoldhne toseppornte udemnt isnte.tr 875 20 6 805 M - 23M 1239 1.23.J 784 - .1 22.21t 4..l Sable41 Period4t.o,- i I U-1 24l,1. 12.In. t.797 10837 2.,525 552 20.000 104.304 t ýt 2.295 04,076 25.6308 870 462 1.785 8020.504 4.251 0.451 P-.:* 4, AdfTIfia-] *l-l.2.3 Reinedat A iort Surreys - - l,5;i 4O8 2 0:O 2.030 ta 23 Sa.bestos Abatement 25 125 125 Ia 0.3 Remaep(teetamtttated Otutdoor Prprot -t ,039 37.050 7031 224 1.2 -- 37* 12001 4I.2 Stuo a. Perrod 4. Addat.onaI Cotta 141 2. 49 224 1.-61 i9 &1. 5,,

Peipod4a 4On.at Cosl 4.5I PrSxedeomm. sexnrnrraHerrear-e 33 2.707 4a.3.3 Small tootaltiowano 36 215 247, -27 - -

TLG Senhia, I-

Cytal Rit'e, Unit 3 Ntltar Ge-erating PIant Docu-ent P23-1680-001, fe-. 0 SitSpecific Decmeisinnin Coat Fsti-tt Appendix C, Pae 7of 10 Table C Crystal River Unit 3 Nuclear Generating Plant SAFSTOR Decommissioning Cost Estimate with Dry Fuel Storage (thousands oft2013 dollars)

SAatetity tnden Actlclv Dripnto Danon Cant Sesonal Cnt Packaging Costs Tcrspnsor CtssCntin Of-iter Pcncegl nP 1+/-4W Disposal Cs Other Total ence Total Casts NSC

[Ac.Tes Cnts Spentrat longenet os t RSite SentSra-tion Csts Prne...ed Vniame nC.

rent Class A Co. Fent SocialVoncesSois]

Cltss S Clas C Cn. Feet Cn. Feet GTCC Cn. Feet Peossed W.. LUs.

Ceait Manhon Utilt o Conter-tne Monhon 1-:' Si ola Ptro .la olateral C-a I 2319 1S 19 4s 328 300 27 15 2 707 9 Pend loPtnad-ependtto Casts la .1 Dteoi supplics 22 112 H12

,.42 Insutantto 752 75 024 824 04 43 Fp-party Itart 34 4a.4.4 Heath phyo.. upplies - 1,055 489 2.444 2,444

4. 45 Heat.yetquipen -1nat1 - 3.304 3W03 j00 3.903 4.4.0 Otrpo~. l ofDAW -ra-ed 21 .1 3. 360 3,.22 76.441l 4- 7 Plant .eergo bude.l 13M8 tM9 1.527 1.52?

laý KRC F... ý7 95s ý.%

a 409 Flrtda LLRWIlnspcttn F-e 21 Ms 184

4. 4 14 LtqoidRad.aslr Pt sinmOqutptntlSettcs 3, 344 574
  • 1.02 125

.l it S~ttS e &MNon-Lhbort 42 4 4261 3221 3.221 tIl OIeeutity Otat Co$t 289 2,218 2201 94.244 4,.4.13 D~lt StslTfot 2,245 17.212 17,212 20M.183 4u.4.14 Ulihty StuffCoo 25,915 4887 2M.AN0 20003 377,140 4-.4 Subtotal Fet Ia Pcrtod-DrpetdeatCo-s

4. 21 1W0 40.6A 8,393 3.70 63 7a32 34 - 822 76.441

-~0 IN.TAL CEROI1(E 4. 'XIST oo 29.812 1 12.13 .800 1t037 26.957 s1.84W 35002 173.1.5 1707,8 2.3.S 90074 3.2744 824 462 1.785 8.7C0.518 274,077 4M4082 PERIOD4k - SiteDantciotn Pcttodth[ltrret 4 l*eotnlsstob g.t1iltt ib I.1 Stmte spcnt - fuel r ko 190 1.5 71. 420 1..73 1.873 389M 257.713 1,1174 Dtposalof Pl1nt S st-,,

4b.1.2.I 1 XC t-l JCn. 15 -2 18 -

41 1.2.2 Cbhmt.al Clotting Steam lin -Coot 24 o 1 412 44 2.9 Chem:al Cleuta- Ste- teo6 RCA 19 - 7.442 bt...4 Cantaentcul hlonitorire a5 2. 114 114 ib I 2.5 Cor Fl-dto1 415 I-M 286 21 55.74:3 41

,26 Do-at Heal Cloed cOlr Cmling I1 43 219 1,068 lm 40 .651 tb.1.7 2 e-v Stat Sonata!

5u 48 76 203 1,670 1.670 - 7.317 I.,W - 91.471 A4 28 Dt-o FuolO,1TanktiUSTs 3 25 25

  • 01..320 Nus 41, 2.0 Dtuestti. W.ter 44.1.2 10 DomnstteWace- RCA 279 1 3 24 14W 145 21,339 1.1(6
4. 1.2.11 Elcril.] - Cleao 615 41 4b. 2 2 - a-t1 t-oed

.lertrvr 7 2a 114 1.100 W 1,10 178 l'5.'

44.1.213 Cleelnr, oI.* tnootatmatod 441.0.14 FleEr',c Wa1rtor 1.524 0420 ,429 -.693 054 25* 1.727 2412 21 Us-1:

h1.22 15 tn n-lWatr.-RCA 12  :*

  • 21:7 I1 21 1,521 7. 12G 9 742 44.:.2.16 Once& tutop Otatn-An-& RaeaBldg IM: 79:1 79:1 2G14 8*t 164879 I 482 lb.l.2 ,? IV.AC - Att-litat '"d, 7 21 M12 795 075 4.174 1695..( 4279 44.1.2.18 HVlAC.Cloea hlohicShop 2793 1 9 t4.l1.2.19 19'A12.- Canttl tiomplet Wl 43 911 5,102 44.I 2.2!

4b. 2.2 lIAC.-

11'.\C Sics.l - Dle-l Cmo S-d Bide 171 23 43 8 1ý8 I 705 44.1.2.-1 HVAC- F-c Pup Iot 72 4412.22I IHAC- Fuol HandltneAaca 1.tOt 63. 634 121.2M4 3 _*

4b.1.2.43 HVAC. OatMaohiacShup 127 17 107 107 20 7.1.

4b I 224 HVA00- ICtletedtato Bido 220 1'1;2 7J.028 4A.1.3.20 HlX'AC. -l .t..anm Suoport 202 -U I 7 7%

1 4112 2 IIVAC-Offl B14 6 77 17b'

=1 LA I-lb 12.27 lILAC. RneatorBldg -314.71 17 1.4 I 7751 i4 120 lIVAC - Turbtoe Blde iA I 2.20 IC e I 93 227 227 731 4b 1.230 4 12.31 W ndsit,.l Io-Wotc-Iadtatriol Co-IorWtor.- CA 7a 1,2 35 1.*4222 3.708

ý7 4b1.2.32 1-r- .1a& S..,on Se i-o Ai W27 441.2.39 I S tal Se*air.Atr - .Co..

Asteotncl&

  • 5 322 342 17.115 3. 11 441.234 &tst ceot&Siattaa S-rin A -.k*A 04 1.2i35 L[a RateTc- - Cant 29.3:5 177.1 53175 517 4 1.4 l.at. Rae Tes. - RCA 5 73.2 . 1 1b 2 37 Lqd tutd.astc[.sp.ol M54 147 4C'J 2 2.24 2 234 17.119 9 45 b 1.2.3M MaLkeup & P-1fiti.on 1 220 .2.0 1.28S 17-.76 A412339 okeup& Punfietion - Isu-at1-d 70 83 M.,212 4b.12.40 Nitognnflldo1enoCorb., Dionde - 2J 6..28 4C9 4b.1.2.4 1 Nitetren00ydtoecoltorbonDi-ed. - HCA 84 I 26.153 1,4012 4b.1.2.42 NIobleG-s fMlna M--ot riap- tan- 20 8 4 41 152 G.r2 TL2G Scri, Inhc.

Cýyalal Alter Unlf 3 Nuclear tonerains Planf Docan-est P23-1680-001, Iet. 0 Silo-Sp*,ifc Daomoi~aionini Cast Lalietato Appendi C, Page.8of 10 Table C Crystal River Unit 3 Nuclear Generating Plant SAFSTOR Decommissioning Cost Estimate with Dry Fuel Storage (thousands of2013 dollars)

Off-Site LLRW NRC Spest Fue Site PFneaand Burial Volum.es Burial Utility ad I Decoa Re=oae Packaging Tsgsn Pes isg Di.posal Other Totl ToJtl Lie. Tee. Maagenet Re.toratio Voluse Cla.. A Class 5 Cla.. C GTCC Peosed Crsgt Co.teactod I Aeltelly I I*u* *LlVlLy*lc[I pLIOn Coat Cost Costa Colts Coal. Casts Cosat Csntisaency Cstl Costa Coats Coal. Cu. Fee Cu. Feel . t C. feet Co. Feet Wt... Ls. M onue Manhours Diopoal of Pluot Sye-oalee emued) lb. 1.2.43 NobleCuaEffutenl nleoen - RCA 15 - - 7 37 37

.1 2 30 2 ýW 12,31 152 5W, .. 172 3

M* 132ý 5ý1 lb .24 NS " ClCoaede*.-leCelsg-Ceet lb. 1.2.45 Noe Re" CboedCt-oleCeooin.RCfCý -53 27 78 Itn 2 2-49519 H.61 Wd I98, 1132j lb I 2.I PASSContainment Moonlooo.C.ol 8 D 0 3 15 15 It 1,727 147 4b.l.2.47 PASSl00ltoetl blonitojiog- RCA 17 0 I 128 5,207 396 lb. .2.48 Pool.Zdeot Ssplig - Col 21 SIl 63 205 It-a r.79 lb. .2.4W PontA.-.rldv n atptdog-rC- -n 0 0 24 2117 9.629 520 4b.t.2.50 PoetAn-'tedenVenllog.-Coni ,11 1. t17f .8.

lb 12 51 1-o Atidoet Veolhtg.RCA I12 G.Z.581 234 lb.l..5I2 B Peenetratio ooh .5RCA I 15 2 5 f1 2.4 2(64 9M *.WX5 2 178 lb I2.53 RCPLub 0t -,o- 4 0 1 2 '.' l M8 2.361 01 lb. 1.2.51 RCPLube tI - RCA 2 12 f1f lb ] 2 55 R*dwanteflcmtnratse 1"- 7, 12.440 58W t 4 -

lb.1.2. Ror BB Feenoure Rroino & Tfoa 3 ]3 lb.f.2.57 ec Bid,Pe-,ue S--tloe TotI .RCA 2- 15 N6 86 '93 -11.9%5 673 4b.t.2.58 Re-celo utldteropray 27ý 2.752 -- 111.74. 4,454 b.1.2.59 Rfueling Eqluipmen 1 1 1. 16 ] 42 .2 31,41 7 -56 4 3.o,.

lb.t.f.u5 Rooage 53243 I 61 2 14 '14 282 lb 1.2.61 Spool FuelCooling 482 41 42 `I5 2. 3.9. 1.445 255.1 10. IM6.

3 1 1f wd 1 2 25 1.4 137 lb. 1.2A2 Wue- G.a SR pling -1.5 11 -- 1 21 lb.1.263 Rot LayuptNS2 Blafkottn l4 lb.1.26 "WetLupNIR2 RBlenketn- S 0 ' 2 1 - 14 14 V.t 1626 102 lb.l.2G5 1,t L..up.N2 BRankeng-RCA S7 - 24 -978 6I lb. 1.2 T-o1u 12.8.* 424 923 14-917 1-215 7818 3M.128 36472 1.397 18,7Mf 66303 6.476.f2 258.055 4b 3 3 Snuffeldtoein uploul ofdemoiaonoo - 17 1. I04 - 59,I 33.321 DR nloiatoion of RifeRuildtoee 4b.1.4.1 RIot-o 1,12 437 IS 61 2-286 1.2;.3 205.1:8 28.526 2.4083 25 2.48 ib.1. 2 Aulolbo Ruifdteg 3l 1.5 4 4* lo -7 221 12 125 1.1f- 114.'44 8773 4b I u- Fuel (loedllooAeaolAu-Bldg) 1.,9 74 - .76 9ft0- 292 M43 27,179 4bll 44 nte--d-t Bldg r.9 II1 19 258 ff0 - 0S8 266 - ofSi 10-32 lb 4 5 Mb hlo Shbp- Hot 1 12 184 1814 1 181 15.753 1201 4b.I G OIS-3 S--ag Buddin Io I I 1 2.I 21 1261 12f1 112 .- ,322 t77 4bl4. B Ma Iennt Bid, .. d HP --ff- 35 21 21 49 4260 199 4b 68 RM SAu*h ot 39 M I1 23i 2518 LAM1 1.11M - 421 36510 1.382 4b.I 4.9 RI\CH Sto.er BRuildto 74 2.2 S 114 14 '7, 13 2.]8 1 4b I I10 I R-,or BuildiogInterolr rons-le I"6 93 .2 ,22 4.,18 4,M8 - 32.437 2.818.700 2.465 4b.1.4 Tutule 2.141 1,394 13 ],0 2,:U5 1..4*.1 10.4.1 - 7, 37.115 S.5f8.512 72.785 1 .4 .'qL 50ý 1 48.D45 lb I SRbtloluPot lb Aetot Co-tt 2,W I I 770 2,F41 2., 1,91 - 1,397 1.97 '-ti4 4,72.1 - :101 MR46 3: 035 Perod lbAdddhloal Coo.

1b.2.1 LI, u T--e-5na100Sue- Planeng- - 4% 2. 1* 2,1IW 12.410 h 22 deesmeeaoongol ISPST 271 3 667 M8 ;1.912 3,912 1..12 2.11.4,229 7509 17.059I 16.2.3 WRoSelltto f'nd 23 2 68 218 I,35 1.115 - - ,.950o 1.515396oo 339 4b.2.4 L'2d:rgeoundSeolE-loo -n I.,85 6 63n 4.35 4b.2. RemediallooOuee'ca - - 2218 25,ýS 2,S8" -- - 12.712 4b.2. Ofperlill T.1i & E"oucsc'l - 3 49 77. 124 952 952 H-1.710 - 290730 II 4b2 S.1,1-1 P.e..od 4bAddilion.l Coals 2 28 7 784 771j 1.0' 7.1-~ "'N:9 if, 1ý8 15,6.M 11-110 15,1U 3449979 5,5734 Peed 4b .ollateal 1b.3.1 P-s.eadCOmflsslnortonwaer ale 9 - 12 02 12 1!1 181 154 92 33 16.35 Soalt bola-llowa- 324 '9 3~ M7 4b.3 4 e- .... Equ,.1entD-spositon ilon... 155 155 14. 1.122 1.122 - ,o0 1529 3- 4..8 88 4b.5.9 OO-.it nu.ey and ,eleo of 134.94 1toceanlmeth ate .. . 1- 208 2os, 4b.3 SubtoealPeetoflb41,5.11-0A1 Cool 9 324 1AS 117 247 1.884 1.1384 6000 68,3 314.224 118 Peetod4b Per-d-DRpendontCools lb 4.1 DRo- supplies 1.098 2-15 1 37.ý 1 1-13 1w7 1. 1,171, 4b 1.2 1n--une 4b IS Peopory lut, b.t.1 Health phy* supplies 3.014 751 376 ý1.71, s

Ib 4 5 Heu'equelp eelln - 4 773 - '7 5 4. 5,t8M 4.b .6 Ditposalof DAWgoenead 10 33 29o - 5975 - 19. I51' 191 4b.l.7 Plunte7eeg" b-d-e.e .2.171 1,7.12 I.M1 124 1,359 1,359 4b.48 NRC Fee, 4b.4.9 Florid, LLHW nsecon Fo 4 ' 51 351 TLG Serice, I*.

Crystal irer Uflil 3 Nclear . e.erati. Plant Document P23-1680-001. Rev. 0 Site-Speeift Deotstiasiotiog Coat Fstinaste Appendix C, PaJe o9f 10 Table C Crystal River Unit 3 Nuclear Generating Plant SAFSTOR Decommissioning Cost Estimate with Dry Fuel Storage (thousands of 2013 dollars)

B I I

,Mft_

.. ... ... .i . .-. .r ....

D-ou Cost Raaul Cost Packaging Cost.

Traseoet Cost.

.C Psoesang Costs n '....

Diseosal Cost.

Othes Coat.

1...

otal l

Coohlnoesoet

. .I..--

Total Coats

-C-..I.F...C.......

Lie. Tee Costs M.dage Costs It Retoaioo Costs Vola-Ca. Pset Class A Co. reet Cl-. B Co. reet Cia.. C Co. Peet GTCC Cs. reet Poessetd Wi..130..

Craft Mdaahoous Co-t1atorI Mtstoa h I

PeNod4hbPeod.Ccpendot Coste nttneedt ib.AIO Liqid Rodoaste P-es-g Eqoipteco/Se-,rs 122 9:,8 93 4b 4 I Site o&M Not-Labor 2.74M 550 4.191 4.491 4b.4.12 Set-o SttiTCoa 411 3.14I4 3 141 4b4 13 D4C2S9iffC0t S-20,9 3040 23.077 23.677 287,143 4h.4.14 ttilityStafYCast- 5,242 40.181 40.48M - - - 50 t714 4b.4 Subtotal Plriod4b Pe-td-Depcodent Coot, 1.098 7.717 440 33 292 G7.,

573 I 4.780 M4,712 88,712 1]3004

. 14,9 926.786 4b.9 TOTAL45331370 41,COST 3.647 25993 1.092 1.479 17_-330 732 75,43 4 24,021 153.00 155,222 1.397 174,.74 69,544 PERIODr.fU- Tssenlttsltote TLe*ss Ptoodt(irec n - rtt~s~r~~

-- Act-rtc 4f,..1

,IoRISE noatory sur'ey - .i 19 211 211 tf.4.2 Toe~matle tenst-4f.I Sbtotet1 Periotd4fA-t-tvoy 163 49 213 211 Perod 4fAdditioa.l Coots 4f62. L.-T-o* tioStro-ey iTrm

.t, - 6,752 2,026 8,7"*. ,777 '6.56 6240 43.2 Subtotal Ptriod 4fAdditoatI Cost .7-M 20872.711 87.77, 12GT*,.G G M4 Pe-nodIl Cotlceotr]Costs 413.1 t tareloaiio-sýpent-siT 1.258 189 1,447 4.407 4f3 Subitot Pt-cud c.-llatertl-iosts 1.2M8 487 1,447 1.447 Period43" Prod-DNepetdet Coat 4(4 Ptopety telet- - 175 472 464.4. Heath pbyhe"supplie- 1-. 873 873 145 34444 Oiepol of DS.W ge.erated S7 414.5 'ln ea-,eU bodel 22 307 407 144 NBC Fec 15 427 427 4(47 FloridaLLRWIntpectton Fe 0 174 31 1 .3 1 4r4.8 S!t J&M N.o.Labor 1 54.4 474 4.ý3:4 :4 4(4 9 S-co-ity StaffCOat 09 153 477 - - - - - - - 1t.709 4f4.10 12'C& StlffCt 682 5.226 5.22G 57,140 4(4.1 Ctd1tyStaffT-st 5.855 878 6,733 6,733 74373 464 Subtoal] Period4f Pot-d-Deprod-et Co1o 2 1-7 12.724 2,040 15,4.0 35490 - 0 - 6--90 9 1 3 O'O9 460 TO.TALPE0309 43.COST 137 2,89-7 S - 47 - 99 3120.,77 15d544 PERIOD4 TOTALS 4W07 5654 13413 270-7 32707 148.139 3.757 279,051 14039 876 462 1.785 22 9:.4G0 M35: 570 1,80098" PERIOD 5b- Sts Reataetlt Pe-tod5b i*-ct DeimmasicotgA-tiea .ct eNoltiion o3tt-maittne Site Boildin-51, 1 1.1 11- -o 6343 4.839 4,M3 47,433 tb.i 1.2 AACDt-t 1-nerator Suildin 24 27 493 -

Sb I..3 AS'S Ready Se-reboot 5b 4t4 Atibaryi Hilding o 242 1,857 r9a 19,l11 IGo 4,;

51 I.4. Ct-ott-at Aiat* St orloS Sit1 I.G Ctiheo Stoere 5b. 1.1.7 Cont.-1 r Mpleo 126 917 ob 1.1.8 DStI FPI Oil Tacit LIST. 2 19 19 Sb.l.1.S D-t1ie -enert Btdo 4.335 Sb31.40 EFS Pop Building 20 M hb.i.i.it Pir PumpFoute 5b 134.42 PoetlHandtiogAweatAcoBtdgt 9b.t.i.13 trnLt- ke O oborr't-geSteort.rtus 14'7 67 51.1 5b 11.41 lote-ge-diat A dbide Sb.3.4.49 Met-ite Shop.- Cold 12,42M Sb.3.4I.4 Slot-bins Shop - Sot :5 I.B 5b.1.1.17 %a- Yard St--t-or & Foondoitoo. M2 1,712 1.712 5 1.1.18 M5 aott... w Yard S-1tttou 1 923 288 2,211 2.211 273.7 Sb3.i.19 O7S13S -ot Reiiding 77 59 Sb.1.-.20 40B M--.t-eoa Bide -ndHP Off-5b.1.1.21 R %%orhoue 4U 45 445 5b.1.41.22 61VCH Stor.e Huddite 7. 1. 91.

TLG Sen'iee, I-.

Crystal River Unit 3 Nulear Gene.atl. Plant Document P23-l680-001, Rc. 0 Site-Spe-ifrw DommisioningCost ERtinote Appendix C, Page I0 f 10 Table C Crystal River Unit 3 Nuclear Generating Plant SAFSTOR Decommissioning Cost Estimate with Dry Fuel Storage (thousands of 2013 dollars)

CI-Site LLRW NBC SpeotFuel. Site Poesd Barisl Volu-es BOoial Utility "d Actieity Dman arutaval Packaging Trasport P= ieslig Disposal Other Tats1 Toesl Lic. Ter Mauagrment R -torstino Vnlume Close A Ctas B Clas C GTCC Pessed Croft Contractor t1den Actiittlr Denrrtion Cost Cost Costs Costs Costs Costs Costs Co0sin cur- Costs Conts Costs Costs Co. Feet Cn. Feet C.. Feet Cu. Feet Ca. Feet We.. Lbs. MTaonnhr Maouns Denhtltt flSomtg 1 Site Bldtnt, leIlto.ued) 5b.1.1.23 R-st B dg 227 2.1 3.770 5b I.I.24 Ttrbtte Buddmno 2,07G 11 2* 2..Wa 27.7S5 Sb1.1.25 Turbine Pedcotal 5W7 5.121 5b 1.1 Totals 18,705 2.70t 19.211 19.211 19.401 S- it loeo t tit 51 I 2 bakFill Site 61 467 467 5b.1.3 'r-d, & taodoi-,ere 494 -S 74 509 - 047 5b 1.4 Fixl tepot to NBC 1WI 29 2 19 219 I.-

5b I Subtotal Peed SbSetityt lotts 190 2.1* 204. 219 - 45246 - - -- 2. W12 LzkX)

Poe-od5b Addtit.l.C.ot.

5b 2.l1 CosrhtCr Mbt 9 ItS 792 792 Sb2.2 Doemhttooof ISFS1 93 711 711 5b.2.3 Inoke .od Ditoheee- Cofftedoms 141 610 ,10 4,43.

5b 2.4 Fir~t R-,S Cl-ue 179 122 93a 938W

- ,777 - 160 5b.2 Subtoa] Period 5b.Additeoalloott 1*7 398 3.0R0 I-.502 Per.od5b CoSotral Coet bI Stmll 11 "allon-a' - IS 27 206 20G Sb.:t S1b8ototPetted 5b Colltatea Cot -7 2W*

Pettod 5b PotMd.Depondool-- os Sb4 3cela- Seto" equttment - .982 -- 747 72 5 729 Sb.4.41 loo torsy bodet . 145 22 147 1.7 Sb.4I Silt O&MNon-Labot 210 3,15 2.41 2- 14 Sb.4 6 S,-et-t ItotfftO 7-2 119

' l1 -I0 37577 Sb41 C D'tc Staff Coot 8 i - 1.217 128 .. 2 -16 tS16 56.49 Utilitly Sinal"tCott

- -4t;72 Sul1 5372 5.372 .6163

,b.i Subltoal terid 5b PeCod.tttedennt lotte 4983 15', W _--,

22:tt 92L3. - -- 210109 Sb.S ' -TItLPEPRin-S51,JST 24 113 1 A. 5219

.211 t7 3 2t 47,.4 N-.21u.7 2' 829 PERIOD0 TOTALS 20 54 .74..4 1t3 .2t t7O Tt*.2819 1244.004 201429 TOTAL COSTTO DECOMM2ISSION 5.052 89.473 1.54 9.0 28,0N7 51.046 8ý42.M,1 140.661 1.180.128 "*1.902 26,0 52,721 269.051 136.830 87 462 1.783 25.446.620 1.094.804 7.362,363l TOTALCOST TO DECOMMISSION: 12.110,1 thousands of 2Il3 do&lsrs TOTALNRC LICENSE TERMINATION COSTIS 73.0. OR: 91.902 ltthousndsof tOt1 delisn SPENTFUEL MANAGEMENT COST IS 2o.5". OR: $2t5.503 thtoutsndsnf 2003 dolise NON-NUCLEARDEMOLITIONCOST IS 4.47% OR: $52,72t thoassds of 2010 doUan TOTALLOW-LEVELRADIOACTIVEWASTEVOLUME BURIED (EXCLUDINGGTCCj: 138.196 -obib free TOTALGREATERTHAN CLASSC RIADWASTE VOLUMEGENERATED: 1.7, table feet TAL SCRAP METAL R OVE:D3esee teons TALCRAFTLABORREQUIREMENTS 1.094.304 -o-h.ort Eod Nole, sl - iodcale rbut rbit atttty n. obhared to deetoteiooofn esprom.

a

  • iodiatoe- tbot perfooed bydetsmmttisioeineetot

-Nta1t3iety 9 -idat-e thbt this IaloeIt es thas 0.5but 0000-m a ef11 totatng.'o" dcatesaeetotalue TLG Stei-e, I-.

Crystal River Unit 3 Nuclear GeneratingPlant Document No. P23-1680-001,Rev. 0 Site-Specific Decommissioning Cost Estimate Appendix D, Page 1 of 2 APPENDIX D ISFSI DECOMMISSIONING COST ANALYSIS TLG Services, Inc.

Crystal River Unit 3 Nuclear GeneratingPlant Document P23-1680-001, Rev. 0 Site-Specific Decommissioning Cost Estimate Appendix D, Page 2 of 2 Table D Crystal River Unit 3 Nuclear Generating Plant ISFSI Decommissioning Cost Estimate (thousands of 2013 dollars)

Burial Oversight LLRW Removal Packaging Transport Other Total Volume Craft and Costs Costs Costs Disposal Costs Costs Class A Manhours Contractor Activity Description (cubic feet) Manhours Decommissioning Contractor Planning (characterization, specs and procedures) - - 146.6 146.6 1.024 Decontamination (activated HSM disposition) 46.2 3.5 667.4 295.6 1.012.7 1.682 475 License Termination (radiological surveys) 805.9 805.9 7,034 Subtotal 46.2 3.5 667.4 295.6 952.5 1,965.2 1,682 7.509 1.024 Supporting Costs NRC and NRC Contractor Fees and Costs - 398.3 398.3 776 Insurance 72.3 72.3 Property taxes _

Heavy equipment rental 225.2 225.2 Plant energy budget 31.8 31.8 Corporate A&G Site O&M Security Staff Cost 173.3 173.3 11,520 Oversight Staff Cost 287.2 287.2 3,771 Subtotal 225.2 - - - 962.9 1,188.1 - - 16,067 Total (w/o contingency) 271.4 3.5 667.4 295.6 1.915.4 3,153.3 1,682 7,509 17,091 Total (w/25% contingency) 339.2 4.4 834.3 369.5 2,394.3 3,941.6 1 The application of contingency (25%) is consistent with the evaluation criteria referenced by the NRC in NUREG-1757 ("Consolidated Decommissioning Guidance, Financial Assurance, Recordkeeping, and Timeliness." U.S. NRC's Office of Nuclear Material Safety and Safeguards. NUREG-1757, Vol. 3, Rev. 1, February 2012)

TLG Services, Inc.