Letter Sequence Other |
|---|
TAC:ME1044, Clarify Application of Setpoint Methodology for LSSS Functions (Approved, Closed) TAC:ME1045, Clarify Application of Setpoint Methodology for LSSS Functions (Approved, Closed) |
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance, Acceptance, Acceptance
- Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement, Supplement
|
MONTHYEAR05000255/LER-2008-007-01, Potential Loss of a Safety Function Due to Non-Conservative Auxiliary Feedwater Trip Setpoints2009-01-21021 January 2009 Potential Loss of a Safety Function Due to Non-Conservative Auxiliary Feedwater Trip Setpoints Project stage: Request NRC 2009-0030, License Amendment Request 261, Extended Power Uprate2009-04-0707 April 2009 License Amendment Request 261, Extended Power Uprate Project stage: Request ML0912505692009-04-0707 April 2009 Attachment 5 - Point Beach, Units 1 and 2, License Amendment Request 261, Extended Power Uprate, Licensing Report, Chapter 2, Section 2.5.8 Through Appendices Project stage: Request ML0910006472009-04-0808 April 2009 Transmittal of Background Information to Support License Amendment Request 261 Interconnection System Impact Study Project stage: Request NRC 2009-0058, Response to Request for Additional Information License Amendment Request 241 Alternative Source Term2009-06-0101 June 2009 Response to Request for Additional Information License Amendment Request 241 Alternative Source Term Project stage: Response to RAI NRC 2009-0066, License Amendment Request 261 Supplement 1 Extended Power Uprate2009-06-17017 June 2009 License Amendment Request 261 Supplement 1 Extended Power Uprate Project stage: Supplement NRC 2009-0068, License Amendment Request 261 Supplement 2 Extended Power Uprate2009-06-17017 June 2009 License Amendment Request 261 Supplement 2 Extended Power Uprate Project stage: Supplement ML0917603382009-06-29029 June 2009 Deferral of the Extended Power Uprate Acceptance Review and Acceptance Review of the Auxiliary Feedwater Modifications and Non Conservative Setpoint Technical Specifications Project stage: Acceptance Review ML0921905632009-08-0606 August 2009 Extended Power Uprate and Alternate Source Term Review Planning Meeting Presentation Project stage: Request ML0922402982009-08-0606 August 2009 Extended Power Uprate and Alternate Source Term Review Planning Meeting Presentation (Handout 2) Project stage: Request ML0922500082009-08-25025 August 2009 Extended Power Uprate (EPU) Acceptance Review Project stage: Acceptance Review ML0923104542009-08-26026 August 2009 Request for Additional Information from Electrical Engineering Branch Regarding Auxiliary Feedwater Project stage: RAI ML0924305172009-08-31031 August 2009 Notice of Meeting on AFW Modifications, Questions to Be Discussed Project stage: Meeting L-2009-207, Units 1 & 2, Update to Decommissioning Funding Status and Financial Assurance Plan2009-09-11011 September 2009 Units 1 & 2, Update to Decommissioning Funding Status and Financial Assurance Plan Project stage: Request NRC 2009-0094, License Amendment Request 261 Extended Power Uprate Expedited Review Request2009-09-11011 September 2009 License Amendment Request 261 Extended Power Uprate Expedited Review Request Project stage: Request ML0923211842009-09-14014 September 2009 Meeting Summary, Meeting with FPL Energy Point Beach, LLC, on the Extended Power Uprate and Alternate Source Term Amendments Project stage: Meeting NRC 2009-0098, License Amendment Request 261, Extended Power Uprate, Response to Request for Additional Information2009-09-25025 September 2009 License Amendment Request 261, Extended Power Uprate, Response to Request for Additional Information Project stage: Response to RAI NRC 2009-0108, License Amendment Request 261, Extended Power Uprate Response to Acceptance Review Questions2009-10-0909 October 2009 License Amendment Request 261, Extended Power Uprate Response to Acceptance Review Questions Project stage: Request ML0928005432009-10-19019 October 2009 Nonacceptance with the Opportunity to Supplement Letter for Extended Power Uprate Project stage: Other ML0929305162009-10-22022 October 2009 Request for Additional Information from Mechanical and Civil Engineering Branch Auxiliary Feedwater Modification Project stage: RAI ML0929308342009-10-22022 October 2009 Request for Additional Information from Balance of Plant Branch Auxiliary Feedwater Modification Project stage: RAI ML0929201272009-10-28028 October 2009 Summary of Meeting with FPL Energy Point Beach, LLC on the Auxiliary Feedwater Modification Amendment Project stage: Meeting ML0930205422009-11-0404 November 2009 Acceptance Review of Requested Licensing Action Regarding Extended Power Uprate Project stage: Acceptance Review ML0930603312009-11-0505 November 2009 Request for Additional Information from Technical Specification Branch Non-conservative Setpoint Changes (TAC Nos. ME1083 & ME1084) Project stage: RAI ML0930603012009-11-0606 November 2009 Request for Additional Information from Technical Specifications Branch Regarding Auxiliary Feedwater Project stage: RAI NRC 2009-0114, Transmittal of Background Information to Support License Amendment Request 261 Final Interconnection System Impact Study2009-11-13013 November 2009 Transmittal of Background Information to Support License Amendment Request 261 Final Interconnection System Impact Study Project stage: Request ML0931402312009-11-16016 November 2009 Request for Additional Information from Balance of Plant Branch Regarding Main Feedwater Isolation Valves Project stage: RAI NRC 2009-0125, License Amendment Request 261 Re Extended Power Uprate, Response to Request for Additional Information on Auxiliary Feedwater System2009-11-20020 November 2009 License Amendment Request 261 Re Extended Power Uprate, Response to Request for Additional Information on Auxiliary Feedwater System Project stage: Response to RAI NRC 2009-0123, License Amendment Request 261, Extended Power Uprate, Response to Request for Additional Information for Calculation of the Auxiliary Feedwater Pump Low Suction Pressure Setpoint2009-11-20020 November 2009 License Amendment Request 261, Extended Power Uprate, Response to Request for Additional Information for Calculation of the Auxiliary Feedwater Pump Low Suction Pressure Setpoint Project stage: Response to RAI NRC 2009-0116, License Amendment Request 261, Extended Power Uprate, Response to Request for Additional Information2009-11-21021 November 2009 License Amendment Request 261, Extended Power Uprate, Response to Request for Additional Information Project stage: Response to RAI NRC 2009-0115, License Amendment Request 261, Extended Power Uprate, Response to Request for Additional Information2009-11-21021 November 2009 License Amendment Request 261, Extended Power Uprate, Response to Request for Additional Information Project stage: Response to RAI ML0932400282009-11-24024 November 2009 Request for Additional Information from Reactor Systems Branch Regarding Extended Power Uprate Project stage: RAI NRC 2009-0124, License Amendment Request 261 Extended Power Uprate Response to Request for Additional Information2009-11-30030 November 2009 License Amendment Request 261 Extended Power Uprate Response to Request for Additional Information Project stage: Response to RAI NRC 2009-0120, License Amendment Request 261, Supplement 3 Extended Power Uprate2009-12-0808 December 2009 License Amendment Request 261, Supplement 3 Extended Power Uprate Project stage: Supplement NRC 2009-0122, License Amendment Request 261, Extended Power Uprate, Response to Request for Additional Information2009-12-16016 December 2009 License Amendment Request 261, Extended Power Uprate, Response to Request for Additional Information Project stage: Response to RAI NRC 2009-0128, License Amendment Request 261, Extended Power Uprate, Response to Request for Additional Information2009-12-21021 December 2009 License Amendment Request 261, Extended Power Uprate, Response to Request for Additional Information Project stage: Response to RAI ML0935002032009-12-22022 December 2009 Request for Additional Information from Reactor Systems Branch EPU Expedited Portions Project stage: RAI NRC 2010-0003, License Amendment Request 261, Extended Power Uprate Auxiliary Feedwater System Pipe Stress Analysis Information2010-01-0808 January 2010 License Amendment Request 261, Extended Power Uprate Auxiliary Feedwater System Pipe Stress Analysis Information Project stage: Request ML1000800812010-01-13013 January 2010 Request for Additional Information from Balance of Plant Branch Extended Power Uprate Project stage: RAI NRC 2010-0005, License Amendment Request 261 Extended Power Uprate Response to Request for Additional Information2010-01-13013 January 2010 License Amendment Request 261 Extended Power Uprate Response to Request for Additional Information Project stage: Response to RAI ML1002500112010-01-22022 January 2010 Response Request for Additional Information License Amendment Request 261 Extended Power Uprate Project stage: Request NRC 2010-0013, License Amendment Request 264 - Diesel Fuel Oil Storage Requirements2010-01-27027 January 2010 License Amendment Request 264 - Diesel Fuel Oil Storage Requirements Project stage: Request ML1001203312010-02-0101 February 2010 Request for Additional Information from Electrical Engineering Branch Auxiliary Feedwater - Round 2 Project stage: RAI NRC 2010-0022, License Amendment Request 261, Extended Power Uprate & Transmittal of Proposed Technical Specifications for Reactor Protection System & Engineered Safety Features Setpoints Not Associated with Extended Power Uprate2010-02-25025 February 2010 License Amendment Request 261, Extended Power Uprate & Transmittal of Proposed Technical Specifications for Reactor Protection System & Engineered Safety Features Setpoints Not Associated with Extended Power Uprate Project stage: Request NRC 2010-0012, License Amendment Request 261, Extended Power Uprate, Response to Request for Additional Lnformation2010-03-0303 March 2010 License Amendment Request 261, Extended Power Uprate, Response to Request for Additional Lnformation Project stage: Request ML1006803682010-03-10010 March 2010 Notice of Meeting with FPL Energy Point Beach, LLC, to Discuss the Alternative Source Term, Auxiliary Feedwater, and Extended Power Uprate Amendments Project stage: Meeting ML1007806102010-03-25025 March 2010 Request for Additional Information, Extended Power Uprate Project stage: RAI ML1007506852010-03-25025 March 2010 Request for Additional Information, Extended Power Uprate Project stage: RAI ML1008103682010-03-25025 March 2010 Request for Additional Information, Extended Power Uprate Project stage: RAI ML1007804772010-03-31031 March 2010 Request for Additional Information, Extended Power Uprate Project stage: RAI 2009-04-08
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 October 19, 2009 Mr. Larry Meyer Site Vice President NextEra Point Beach, LLC 6610 Nuclear Road Two Rivers, WI 54241-9516 SUB~IECT:
POINT BEACH NUCLEAR PLANT, UNITS 1 AND 2 - NONACCEPTANCE WITH THE OPPORTUNITY TO SUPPLEMENT REGARDING ACCEPTANCE REVIEW FOR EXTENDED POWER UPRATE (TAC NOS. ME1044 AND ME1045)
Dear Mr. Meyer:
By letter dated April 7, 2009 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML091250564), as supplemented by letter dated September 11,2009 (ADAMS Accession No. ML092570205), FPL Energy Point Beach, LLC (the licensee),
submitted a license amendment request for Point Beach Nuclear Plant, Units 1 and 2. The proposed amendment would increase each unit's licensed core power level from 1540 megawatts thermal (MWt) to 1800 MWt reactor core power, and revise the technical specifications (TS) to support operation at this increased core thermal power level.
In a letter dated August 25,2009 (ADAMS Accession No. ML092250008), the U.S. Nuclear Regulatory Commission (NRC) staff notified the licensee that the acceptance review for the Extended Power Uprate (EPU) would be contingent on: 1) the EPU submittal contains sufficient information in scope and depth to allow the NRC staff to complete its technical review per Office Instruction L1C-109; and 2) the responses to the outstanding request for additional information questions at the time the letter was issued for the Alternate Source Term (AST) amendment adequately address the NRC staff's concerns with the AST submittal. The purpose of this letter is to provide acceptance review results relating to the first contingency item. The NRC staff is still evaluating the second contingency item.
The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to complete its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
Consistent with Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), an amendment to the license (including the technical specifications) must fully describe the changes requested, and following as far as applicable, the form prescribed for original applications. Section 50.34 of 10 CFR addresses the content of technical information required.
This section stipulates that the submittal address the design and operating characteristics, unusual or novel design features, and principal safety considerations.
The NRC staff has reviewed your application and concluded that the information delineated in the enclosure to this letter is necessary to enable the NRC staff to make an independent
L. Meyer
- 2 assessment regarding the acceptability of the proposed amendment request in terms of regulatory requirements and the protection of public health and safety and the environment.
In order to make the application complete, the NRC staff requests that the licensee supplement the application to address the information requested in the enclosure by October 22, 2009. This will enable the NRC staff to complete its detailed technical review. If the information responsive to the NRC staff's request is not received by the above date, the application will not be accepted for review pursuant to 10 CFR 2.101, and the NRC staff will cease its review activities associated with the application. If the application is subsequently accepted for review, you will be advised of any further information needed to support the NRC staff's detailed technical review by separate correspondence.
The information requested and associated time frame in this letter was discussed with Steve Hale of your staff on October 2, 2009.
If you have any questions, please contact me at (301) 415-2048.
Sincerely,
/ /
/
7:j2
~--
Justin C. Poole, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301
Enclosure:
As stated cc w/encl:
Distribution via Listserv
SUPPLEMENTAL INFORMATION NEEDED AMENDMENT REQUEST FPL ENERGY POINT BEACH, LLC POINT BEACH NUCLEAR PLANT. UNITS 1 AND 2 DOCKET NOS. 50-266 AND 50-301 Question 1 - Balance of Plant Branch In Section 2.5.1.2 of Attachment 5 to the license amendment request (LAR), the licensee states:
Evaluation of the effects of these plant modifications (e.g., feedwater and condensate pump capacity increases) on internal flooding will be performed as part of the modification process.
We consider this unacceptable because the feedwater and condensate flow increase is an inherent part of the Extended Power Uprate (EPU). If the licensee is unsure of the bounding values for peak flow, the licensee can specify the regulatory process (i.e.. Title 10 of the Code of Federal Regulations (10 CFR) Section 50.59 change evaluation), the methodology for the flooding evaluation that could be used without prior Nuclear Regulatory Commission review and approval pursuant to 10 CFR 50.59, and the associated acceptance criteria. Otherwise, the licensee should provide a complete evaluation for internal flooding.
Question 2 - Mechanical and Civil Engineering Branch Pipe evaluations for main feedwater, steam lines and auxiliary feedwater piping at EPU conditions need to have been completed (at EPU application submittal) and pipe stress summaries need to be submitted including high-energy line break (HELB) evaluations to support the licensee's statements that there are no changes in the existing HELB evaluations, and that these lines are structurally acceptable for EPU conditions. In addition, detailed descriptions of affected piping and supports are also required to be completed (at EPU application submittal) and affected summaries of results of pipe support evaluations to be available for staff review.
If these items (above) are not available at time of EPU staff review, the staff finds the proposed EPU LAR unacceptable with opportunity to supplement. Confirm that the analyses for all piping systems and supports for the above systems are now complete.
Question 3 - Reactor System Branch The technical specification (TS) has no loading curves so the staff assumes that the licensee's current analysis is based on fresh fuel assumption (i.e., no burnup credit). Please confirm this assumption with the licensee.
Question 4 - Reactor System Branch Will EPU operation conform to the integral fuel burnable absorber requirements or use fuel enrichment less than 4.6 wlo per the current TS?
Enclosure
L. Meyer
- 2 assessment regarding the acceptability of the proposed amendment request in terms of regulatory requirements and the protection of public health and safety and the environment.
In order to make the application complete, the NRC staff requests that the licensee supplement the application to address the information requested in the enclosure by October 22, 2009. This will enable the NRC staff to complete its detailed technical review. If the information responsive to the NRC staff's request is not received by the above date, the application will not be accepted for review pursuant to 10 CFR 2.101, and the NRC staff will cease its review activities associated with the application. If the application is subsequently accepted for review, you will be advised of any further information needed to support the NRC staff's detailed technical review by separate correspondence.
The information requested and associated time frame in this letter was discussed with Steve Hale of your staff on October 2, 2009.
If you have any questions, please contact me at (301) 415-2048.
Sincerely, Ira!
Justin C. Poole, Project Manager Plant Licensing Branch 111-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-266 and 50-301
Enclosure:
As stated cc w/encl: Distribution via Listserv DISTRIBUTION:
PUBLIC RidsNrrDorlDpr Resource LPL3-1 rlf RidsNrrDorlLpl3-1 Resource RidsAcrsAcnw_MailCTR Resource RidsNrrLATHarris Resource RidsNrrDeEmcb Resource RidsNrrPMPointBeach Resource RidsNrrDssSbpb Resource RidsOgcRp Resource RidsNrrDssSrxb Resource RidsRgn3MailCenter Resource RidsNrrDorl Resource ADAMS Accession No. ML092800543 OFFICE NRR/LPL3-1/PM NRR/LPL3-1/LA NRR/EMCB/BC NRRISPBP/BC NRRISRXB/BC NRR/LPL3-1/BC NAME JPoole THarris MKhanna GCasto GCranston RPascarelli DATE 10/19/09 10/15/09 10/16/09 10/19/09 10/16/09 10/19/09 Official Record Copy