ML090200064

From kanterella
Jump to navigation Jump to search
IR 05000424-08-005 & 05000425-08-005; on 10/1/2008 - 12/31/2008; Vogtle Electric Generating Plant, Units 1 and 2; Access Control to Radiologically Significant Areas
ML090200064
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 01/20/2009
From: Scott Shaeffer
NRC/RGN-II/DRP/RPB2
To: Tynan T
Southern Nuclear Operating Co
References
IR-08-005
Download: ML090200064 (43)


See also: IR 05000424/2008005

Text

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION II

SAM NUNN ATLANTA FEDERAL CENTER

61 FORSYTH STREET, SW, SUITE 23T85

ATLANTA, GEORGIA 30303-8931

January 20, 2009

Mr. Tom E. Tynan

Vice President - Vogtle

Southern Nuclear Operating Company, Inc.

Vogtle Electric Generating Plant

7821 River Road

Waynesboro, GA 30830

SUBJECT: VOGTLE ELECTRIC GENERATING PLANT - NRC INTEGRATED INSPECTION

REPORT 05000424/2008005 AND 05000425/2008005

Dear Mr. Tynan:

On December 31, 2008, the U.S. Nuclear Regulatory Commission (NRC) completed an

inspection at your Vogtle Electric Generating Plant, Units 1 and 2. The enclosed integrated

inspection report documents the inspection findings, which were discussed on January 15, 2009,

with you and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel.

This report documents one self-revealing finding of very low safety significance (Green) which

was determined to be a violation of NRC requirements. The NRC is treating this violation as a

non-cited violation (NCV) consistent with Section VI.A.1 of the NRC Enforcement Policy because

of the very low safety significance and because it was entered into your corrective action

program. If you contest this NCV, you should provide a response within 30 days of the date of

this inspection report, with the basis for your denial, to the Nuclear Regulatory Commission,

ATTN.: Document Control Desk, Washington DC 20555-0001; with copies to the Regional

Administrator, Region II; the Director, Office of Enforcement, United States Nuclear Regulatory

Commission, Washington, DC 20555-0001; and the NRC resident inspector at the Vogtle

Electric Generating Plant.

SNC, Inc. 2

In accordance with the Code of Federal Regulations 10 CFR 2.390 of the NRCs Rules of

Practice, a copy of this letter, its enclosures, and your response (if any) will be available

electronically for public inspection in the NRC Public Document Room or from the Publicly

Available Records (PARS) component of the NRCs document system (ADAMS). ADAMS is

accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public

Electronic Reading Room).

Sincerely,

/RA/

Scott M. Shaeffer, Chief

Reactor Projects Branch 2

Division of Reactor Projects

Docket Nos.: 50-424, 50-425

License Nos.: NPF-68 and NPF-81

Enclosures: Inspection Report 05000424/2008005 and 05000425/2008005

w/Attachment: Supplemental Information

cc w/encl: (See next page)

_________________________ G SUNSI REVIEW COMPLETE

OFFICE RII:DRP RII:DRP RII:DRP RII:DRP RII:DRP RII:DRP RII:DRS

SIGNATURE /RA/ /RA/ /RA/ /RA/ /RA/ /RA/ /RA/

NAME CRapp SShaeffer E. Crowe E. Morris T. Chandler G. McCoy B. Caballero

DATE 1/ /2009 1/ /2009 1/ /2009 1/ /2009 1/ /2009 1/ /2009 1/ /2009

E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

OFFICE RII:DRS RII:DRS RII:DRS RII:DRS RII:DRS RII:DRS RII:DRS

SIGNATURE /RA/ /RA/ /RA/ /RA/ /RA/ /RA/ /RA/

NAME C. Fletcher E. Michel D. Mas-Penaranda J. Hamman C. Peabody R. Lewis R. Berryman

DATE 1/ /2009 1/ /2009 1/ /2009 1/ /2009 1/ /2009 1/ /2009 1/ /2009

E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

OFFICE RII:DRS RII:DRS RII:DRS RII:DRS RII:DRS RII:DRS RII:DRS

SIGNATURE /RA/ /RA/ /RA/ /RA/ /RA/

NAME R. Patterson R. Williams G. Kuzo A. Nielsen J. Rivera-Ortiz

DATE 1/ /2009 1/ /2009 1/ /2009 1/ /2009 1/ /2009 1/ /2009 1/ /2009

E-MAIL COPY? YES NO YES NO YES NO YES NO YES NO YES NO YES NO

SNC, Inc. 3

cc w/encl: Mr. N. Holcomb, Commissioner

Angela Thornhill Department of Natural Resources

Managing Attorney and Compliance Officer Electronic Mail Distribution

Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Dr. Carol Couch, Director

Environmental Protection

N. J. Stringfellow, Manager Department of Natural Resources

Licensing Electronic Mail Distribution

Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Cynthia Sanders, Program Manager

Radioactive Materials Program

Jeffrey T. Gasser Department of Natural Resources

Executive Vice President Electronic Mail Distribution

Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Jim Sommerville, (Acting) Chief

Environmental Protection Division

L. Mike Stinson, Vice President Department of Natural Resources

Fleet Operations Support Electronic Mail Distribution

Southern Nuclear Operating Company, Inc.

Electronic Mail Distribution Mr. Steven M. Jackson

Senior Engineer - Power Supply

Michael A. MacFarlane Municipal Electric Authority of Georgia

Southern Nuclear Operating Company, Inc. Electronic Mail Distribution

40 Inverness Center Parkway

P.O. Box 1295 Mr. Reece McAlister, Executive Secretary

Birmingham, AL 35201-1295 Georgia Public Service Commission

Electronic Mail Distribution

David H. Jones, Vice President

Engineering Office of the Attorney General

Southern Nuclear Operating Company, Inc. Electronic Mail Distribution

Electronic Mail Distribution

Office of the County Commissioner

Bob Masse, Resident Manager Burke County Commission

Vogtle Electric Generating Plant Electronic Mail Distribution

Oglethorpe Power Corporation

Electronic Mail Distribution Arthur H. Domby, Esq.

Troutman Sanders

Moanica Caston Electronic Mail Distribution

Vice President and General Counsel

Southern Nuclear Operating Company, Inc. Director

Electronic Mail Distribution Consumers' Utility Counsel Division

Govenor's Office of Consumer Affairs

Laurence Bergen 2 M. L. King, Jr. Drive

Oglethorpe Power Corporation Plaza Level East; Suite 356

Electronic Mail Distribution Atlanta, GA 30334-4600

(cc w/encl. cont: See next page)

SNC, Inc. 4

Senior Resident Inspector

Southern Nuclear Operating Company, Inc.

Vogtle Electric Generating Plant

U.S. NRC

7821 River Road

Waynesboro, GA 30830

Susan E. Jenkins

Director, Division of Waste Management

Bureau of Land and Waste Management

S.C. Department of Health and Environmental Control

Electronic Mail Distribution

SNC, Inc. 5

Letter to Tom E. Tynan from Scott M.Shaeffer dated January 20, 2009

SUBJECT: VOGTLE ELECTRIC GENERATING PLANT - NRC INTEGRATED INSPECTION

REPORT 05000424/2008005 AND 05000425/2008005

Distribution w/encl:

C. Evans, RII EICS (Part 72 Only)

L. Slack, RII EICS (Linda Slack)

OE Mail (email address if applicable)

RIDSNRRDIRS

PUBLIC

R. Martin, NRR

U. S. NUCLEAR REGULATORY COMMISSION

REGION II

Docket Nos.: 50-424, 50-425

License Nos.: NPF-68, NPF-81

Report Nos.: 05000424/2008005 and 05000425/2008005

Licensee: Southern Nuclear Operating Company, Inc.

Facility: Vogtle Electric Generating Plant, Units 1 and 2

Location: Waynesboro, GA 30830

Dates: October 1, 2008 through December 31, 2008

Inspectors: G. McCoy, Senior Resident Inspector (SRI)

E. Crowe, SRI, Farley Nuclear Plant

E. Morris, Acting SRI

T. Chandler, Resident Inspector

C. Fletcher, Reactor Inspector (Section 1R08)

E. Michel, Senior Reactor Inspector (Section 1R08)

B. Caballero, Operations Engineer (Section 1R11)

D. Mas-Penaranda, Reactor Inspector (Section 1R17)

J. Hamman, Reactor Inspector (Section 1R17)

C. Peabody, Reactor Inspector (Section 1R17)

R. Lewis, Senior Reactor Inspector (Section 1R17)

R. Berryman, P.E., Senior Reactor Inspector (Section 1R17)

R. Patterson, Reactor Inspector (Section 1R17)

R. Williams, Reactor Inspector (Section 1R17)

G. Kuzo, Sr. Health Physicist (Sections 2OS2, 4OA1)

A. Nielsen. Health Physicist (Sections 2OS1, 2PS1, 2PS2)

J. Rivera-Ortiz, Sr. Project Inspector (Section 4OA5.2)

Approved by: Scott M. Shaeffer, Chief

Reactor Projects Branch 2

Division of Reactor Projects

Enclosure

SUMMARY OF FINDINGS

IR 05000424/2008-005, 05000425/2008-005; 10/1/2008 - 12/31/2008; Vogtle Electric

Generating Plant, Units 1 and 2; Access Control to Radiologically Significant Areas

The report covered a three-month period of inspection by four resident inspectors, nine reactor

inspectors, two health physicists, and a project engineer. One Green non-cited violation (NCV)

was identified. The significance of most findings is indicated by their color (Green, White,

Yellow, or Red) using Inspection Manual Chapter 0609, Significance Determination Process

(SDP). Findings for which the SDP does not apply may be Green or be assigned a severity level

after management review. The NRC's program for overseeing the safe operation of commercial

nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Rev 4 dated

December 2006.

A. NRC-Identified and Self-Revealing Findings

Cornerstone: Occupational Radiation Safety

Green. Two examples of a self-revealing non-cited violation of Technical Specification 5.7.1, High Radiation Area, was identified for unauthorized entry into High Radiation

Areas (HRAs). Inadequate communication between workers and Health Physics

department resulted in licensee personnel breaching HRA boundaries without prior

knowledge of the radiological conditions. The licensee had entered these issues into the

corrective action program as Condition Reports 2007105476 and 2007108830.

This finding is greater than minor because it is associated with the Occupational

Radiation Safety Cornerstone attribute of Human Performance and adversely affects the

cornerstone objective of ensuring adequate protection of worker health and safety from

exposure to radiation from radioactive material during routine civilian nuclear reactor

operation. The finding was evaluated using the Occupational Radiation Safety

Significance Determination Process and was determined to be of very low safety

significance because it not related to As Low As Reasonably Achievable (ALARA)

planning, did not involve an overexposure or substantial potential for overexposure, and

the ability to assess dose was not compromised. This finding involved the cross-cutting

aspect of Human Performance, Work Practices H.4.a] because the HRA events were a

direct result of poor communications during pre-job briefings and a willingness on the

part of licensee personnel to proceed in the face of uncertainty. (Section 2OS1).

B. Licensee-Identified Violations

None.

Enclosure

REPORT DETAILS

Summary of Plant Status

Unit 1 operated at full rated thermal power for the entire inspection period.

Unit 2 started the report period shutdown for a planned refueling outage. The unit was

restarted on October 19 and attained full power on October 29. The unit was shutdown

on November 16 to replace a reactor coolant pump seal. The unit was restarted on

November 21 and reached full power on November 25. The unit operated at full rated

thermal power for the remainder of the inspection period.

1. REACTOR SAFETY

Cornerstones: Initiating Events, Mitigating Systems, Barrier Integrity

1R01 Adverse Weather Protection

a. Inspection Scope

Seasonal Readiness Review. The inspectors performed a walkdown of the following two

systems to verify they would remain functional during low temperature conditions. The

inspectors reviewed preventive maintenance activities associated with heat tracing and

freeze protection systems to verify they were appropriately scheduled and completed

prior to the onset of cold weather. The inspectors reviewed compensatory actions to

verify they were implemented for degraded or inoperable heat trace and freeze protection

equipment. Additionally, the inspectors reviewed the condition report (CR) database to

verify that adverse weather related items were being identified and appropriately

resolved. Documents reviewed are listed in the Attachment.

C Unit 1 nuclear service cooling water (NSCW) tower instrumentation rooms (both

trains)

C Unit 1 and 2 refueling water storage tank instrumentation rooms

Impending Adverse Weather Condition Review. On November 25, the inspectors

reviewed licensee procedure 11877-1 and 11877-2, Cold Weather Checklist, to verify the

licensee had implemented actions to prepare the plant site for predicted severe weather

conditions of sub-freezing temperatures. The inspectors walked down various safety-

significant areas of the plant to verify the licensees ability to respond to the predicted

adverse weather conditions.

b. Findings

No findings of significance were identified.

4

1R04 Equipment Alignment

a. Inspection Scope

Partial System Walkdown. The inspectors performed partial walkdowns of the following

two systems to verify correct system alignment. The inspectors checked for correct valve

and electrical power alignments by comparing positions of valves, switches, and

breakers to the documents listed in the Attachment. Additionally, the inspectors

reviewed the condition report database to verify that equipment alignment problems were

being identified and appropriately resolved.

C Unit 2 train A auxiliary feedwater (AFW) system when the train B auxiliary feedwater

pump was out of service for maintenance

C Unit 1 train B emergency diesel generator (EDG) and fuel oil transfer system

following maintenance activities

Complete System Walkdown. The inspectors performed a complete walkdown of the

Unit 1 train B NSCW system. The inspectors performed a detailed check of valve

positions, electrical breaker positions, and operating switch positions to evaluate the

operability of the redundant trains or components by comparing the required position in

the system operating procedure to the actual position. The inspectors also reviewed

control room logs, condition reports, and system health reports to verify that alignment

and equipment discrepancies were being identified and appropriately resolved.

Documents reviewed are listed in the Attachment.

b. Findings

No findings of significance were identified.

1R05 Fire Protection

a. Inspection Scope

Fire Area Tours. The inspectors walked down the following four plant areas to verify the

licensee was controlling combustible materials and ignition sources as required by

procedures 92015-C, Use, Control, and Storage of Flammable/Combustible Materials,

and 92020-C, Control of Ignition Sources. The inspectors assessed the observable

condition of fire detection, suppression, and protection systems and reviewed the

licensees fire protection Limiting Condition for Operation log and CR database to verify

that the corrective actions for degraded equipment were identified and appropriately

prioritized. The inspectors also reviewed the licensees fire protection program to verify

the requirements of Updated Final Safety Analysis Report (UFSAR) Section 9.5.1, Fire

Protection Program, and Appendix 9A, Fire Hazards Analysis, were met. Documents

reviewed are listed in the Attachment.

Enclosure

5

C Unit 2 EDG fuel oil storage pumps and tanks

C Unit 1 and 2 spent fuel pools

C Unit 1 safety injection pump rooms

C Unit 2 auxiliary component cooling water (ACCW) pump rooms

b. Findings

No findings of significance were identified.

1R06 Flood Protection Measures

a. Inspection Scope

Internal Flood Review. The inspectors walked down the following two areas which

contained risk-significant structures, systems, and components below flood level to verify

flood barriers were in place. Motor controllers and terminal boxes that could become

potentially submerged were inspected to ensure that the sealing gasket material was

intact and undamaged. The inspectors reviewed selected licensee alarm response

procedures to verify alarm setpoints and setpoints for sump pump operation were

consistent with the UFSAR, the setpoint index, and Technical Specifications.

C Unit 1 residual heat removal pump rooms (both trains)

C Unit 1 containment spray pump rooms (both trains)

b. Findings

No findings of significance were identified.

1R07 Heat Sink Performance

a. Inspection Scope

Annual Review. The inspectors reviewed the licensees records of the performance tests

conducted on the Unit 2 A train component cooling water (CCW) and ACCW heat

exchangers. The inspectors reviewed EPRI NP-7552, Heat Exchanger Performance

Monitoring Guidelines to ensure that the licensees testing procedures were appropriate.

Additionally, the inspectors reviewed the licensees corrective action program for heat

exchanger performance issues to ensure that discrepancies were being identified and

appropriately resolved. Documents reviewed are listed in the Attachment.

b. Findings

No findings of significance were identified.

1R08 In-service Inspection (ISI) Activities

.1 Non-Destructive Examination (NDE) Activities and Welding Activities

Enclosure

6

a. Inspection Scope

The inspectors reviewed the implementation of the licensees ISI program for monitoring

degradation of the reactor coolant system (RCS) boundary and risk significant piping

boundaries. The inspectors activities consisted of an on-site review of NDE and welding

activities to evaluate compliance with the applicable edition of the American Society of

Mechanical Engineers (ASME) Boiler and Pressure Vessel Code,Section XI (Code of

record: 2001 Edition with 2003 Addenda), and to verify that indications and defects (if

present) were appropriately evaluated and dispositioned in accordance with the

requirements of the ASME Code,Section XI acceptance standards.

The inspectors review of NDE activities specifically covered examination procedures,

NDE reports, equipment and consumables certification records, personnel qualification

records, and calibration reports (as applicable) for the following examinations:

C UT examination of weld 21204-023-21, ASME Class 2, Safety Injection System, 6-

inch diameter pipe-to-tee (Section XI ISI)-Direct Observation.

C UT examination of weld 21204-243-31-RI, ASME Class 2, Safety Injection System,

1.5-inch diameter pipe-to-elbow (Risk Informed ISI)-Direct Observation

C Radiography (RT) examination film of welds associated with Q.I.S. Work Order No.

08-70-0658 (ASME Section III and V NDE)

The inspectors also reviewed documentation for the following indications, which were

accepted for continuous service:

C CN-RIDA-07-40, Westinghouse Thermal Sleeve Wear Criteria Analysis, Rev 0.

The inspectors review of welding activities specifically covered the welding activity listed

below in order to evaluate compliance with procedures and the ASME Code. The

inspectors reviewed the work order, repair and replacement plan, weld data sheets,

welding procedures, procedure qualification records, welder qualification records, and

NDE reports.

  • Welding Package for ACCW NCP Motor Cooler Outlet Pressure Test Point (Class 2)

associated with Work Order 2081126401, Pipe to Flange Weld.

b. Findings

No findings of significance were identified.

.2 PWR Vessel Upper Head Penetration Inspection Activities

a. Inspection Scope

The inspectors reviewed the licensees activities relative to the Bare Metal Visual

examination of the reactor pressure vessel upper head (RPVUH) nozzles and the visual

examination to identify potential boric acid leaks from pressure-retaining components

above the RPVUH. These activities were reviewed to verify licensee compliance with the

Enclosure

7

regulatory requirements of NRC Order EA-03-009 Modifying Licenses dated February 20,

2004. The inspectors specifically reviewed BMV examination procedures, final BMV

examination report and disposition of indications, personnel training and qualification

records, final image electronic report, a sample of examination videos, and reports for

the visual inspection of pressure retaining components above the head performed every

outage. In addition, the inspectors reviewed the licensees RPVUH Effective

Degradation Years calculation to ensure it had been performed and updated in

accordance with the NRC Order.

b. Findings

No findings of significance were identified.

.3 Boric Acid Corrosion Control (BACC) Inspection Activities

a. Inspection Scope

The inspectors reviewed the licensees BACC program activities to ensure

implementation with commitments made in response to NRC Generic Letter 88-05, Boric

Acid Corrosion of Carbon Steel Reactor Pressure Boundary, and applicable industry

guidance documents. Specifically, the inspectors performed an on-site record review of

procedures and the results of the licensees containment walk-down inspections

performed during the Unit 2 fall 2008 outage. The inspectors also interviewed the BACC

program owner and conducted an independent walk-down of the reactor building to

evaluate compliance with licensees BACC program requirements and verify that

degraded or non-conforming conditions, such as boric acid leaks identified during the

containment walk-down, were properly identified and corrected in accordance with the

licensees BACC and corrective action programs. The inspectors reviewed the following

four engineering evaluations completed for evidence of boric acid found on systems

containing borated water to verify that the minimum design code required section

thickness had been maintained for the affected components.

  • CR 2008102122 - Boric Acid Containment Recovery Project.
  • CR 2007106211 - Boric Acid Containment Recovery Project.
  • CR 2007110612 - Boric Acid Containment Recovery Project.
  • CR 2008108419 - Boric Acid Containment Recovery Project.

b. Findings

No findings of significance were identified.

.4 Steam Generator (SG) Tube Inspection Activities

a. Inspection Scope

The inspectors reviewed the eddy current testing (ECT) activities of Unit 2 SGs 1 and 4

to ensure compliance with Technical Specifications, applicable industry standards, SG

Program Procedures, and ASME Code Section XI requirements. The inspectors

Enclosure

8

reviewed the latest Degradation Assessment (DA) report to identify the scope of the

inspection and verify it addressed existing and potential degradation mechanisms, plant

specific degradation history, and applicable operating experience. The inspectors

reviewed portions of the tube inspection plan to verify it complied with the inspections

cited in the DA. The inspectors reviewed the licensees SG Program Strategic Plan to

ensure SG tube inspection intervals were in accordance with EPRI Pressurized Water

Reactor Steam Generator Examination Guidelines, Revision 7. The inspectors selected

a sample of site-specific acquisition and analysis Examination Technique Specification

Sheets (ETSS) to ensure that equivalency was maintained with the associated qualified

ETSSs per the EPRI Pressurized Water Reactor Steam Generator Examination

Guidelines, Revision 7. The inspectors discussed in-situ pressure testing requirements

and monitoring with engineering personnel associated with the sites ECT vendor. None

of the SG tubes met the criteria for in-situ pressure testing. The inspectors also reviewed

the last Condition Monitoring and Operational Assessment report in conjunction with the

inspection status reports to assess the licensees prediction capability for expected tube

degradation. The inspectors reviewed licensee criteria for tube repair to verify they were

consistent with EPRI guidelines. Additionally, the inspectors reviewed documentation to

ensure that resolution analysts, ECT probes, and equipment configurations were certified

to detect the expected types of SG tube degradation, including performance of a site

specific performance demonstration. The inspectors also directly observed acquisition

for a sample of tubes, and directly observed a qualified resolution analyst perform

calibration and resolution of tubes from calibration group 66. The inspectors discussed

the status of foreign objects, and associated foreign object search and recovery for

objects discovered as a result of Digital Metal Impact Monitoring System alarms received

during shutdown. The inspectors reviewed the licensees Secondary Side Integrity plan,

and interviewed plant personnel to ensure compliance with EPRI SG Integrity

Assessment Guidelines, Revision 2.

b. Findings

No findings of significance were identified.

.5 Identification and Resolution of Problems

a. Inspection Scope

The inspectors performed a review of ISI-related problems, including welding, BACC,

and SG inspections that were identified by the licensee and entered into the corrective

action program as CRs. The inspectors reviewed the CRs to confirm that the licensee

had appropriately described the scope of the problem and had initiated corrective

actions. The review also included the licensees consideration and assessment of

operating experience events applicable to the plant. The inspectors performed this

review to ensure compliance with 10CFR Part 50, Appendix B, Criterion XVI, Corrective

Action, requirements. The corrective action documents reviewed by the inspectors are

listed in the report attachment.

Enclosure

9

b. Findings

No findings of significance were identified.

1R11 Licensed Operator Requalification

a. Inspection Scope

Resident Quarterly Observation. The inspectors observed operator performance on

October 21, during licensed operator simulator training described in Operating Test

Dynamic Simulator Scenario DS#9, Rev. 21. The simulator scenarios covered operator

actions resulting from NSCW pump shaft shear, main turbine trip below P-9, loss of the

running main feed pump and subsequent loss of all feed water, anticipated transient

without trip, rod control failure, and emergency boration. Documents reviewed are listed

in the Attachment. The inspectors specifically assessed the following areas:

C Correct use of the abnormal and emergency operating procedures

C Ability to identify and implement appropriate actions in accordance with the

requirements of the Technical Specifications

C Clarity and formality of communications in accordance with procedure 10000-C,

Conduct of Operations

C Proper control board manipulations including critical operator actions

C Quality of supervisory command and control

C Effectiveness of the post-evaluation critique

Annual Review of Licensee Requalification Examination Results. On January 08, 2009,

the licensee completed administering the 2008 biennial written examinations and annual

requalification operating tests, which are required to be given to all licensed operators in

accordance with 10 CFR 55.59(a) (2). The inspectors performed an in-office review of

the overall pass/fail results of the written examinations, individual operating tests, and the

crew simulator operating tests. These results were compared to the thresholds

established in Manual Chapter 609 Appendix I, Operator Requalification Human

Performance Significance Determination Process.

b. Findings

No findings of significance were identified.

1R12 Maintenance Effectiveness

a. Inspection Scope

The inspectors reviewed the following three CRs to evaluate the effectiveness of the

licensees handling of equipment performance problems and to verify the licensees

maintenance efforts met the requirements of 10 CFR 50.65 (the Maintenance Rule) and

licensee procedure 50028-C, Engineering Maintenance Rule Implementation. The

inspector also reviewed the safety-significant system to verify that the licensees

maintenance efforts met the requirements of 10 CFR 50.65 (the Maintenance Rule) and

Enclosure

10

licensee procedure 50028-C, Engineering Maintenance Rule Implementation. The

reviews included adequacy of the licensees failure characterization, establishment of

performance criteria or 50.65(a)(1) performance goals, and adequacy of corrective

actions. Other documents reviewed during this inspection included control room logs,

system health reports, the maintenance rule database, and maintenance work orders

(WO). Also, the inspectors interviewed system engineers and the maintenance rule

coordinator to assess the accuracy of identified performance deficiencies and extent of

condition.

C CR 2008107271, Containment cooling fan number 7 did not start in fast speed

C CR 2008107662, NSCW pump number 3 Agastat timing relay out of tolerance

C CR 2008112205, Unit 2 first bank steam dumps; 2PV-0507A, B, and C; control signal

not properly connected

b. Findings

No findings of significance were identified.

1R13 Maintenance Risk Assessments and Emergent Work Evaluation

a. Inspection Scope

The inspectors reviewed the following two work activities to verify plant risk was properly

assessed by the licensee prior to conducting the activities. The inspectors reviewed risk

assessments and risk management controls implemented for these activities to verify

they were completed in accordance with procedure 00354-C, Maintenance Scheduling,

and 10 CFR 50.65(a)(4). The inspectors also reviewed the CR database to verify that

maintenance risk assessment problems were being identified at the appropriate level,

entered into the corrective action program, and appropriately resolved.

C November 10, planned maintenance for Unit 1 train B NSCW pump #4

C December 18, planned maintenance for Unit 1 train B CCW pump

b. Findings

No findings of significance were identified.

1R15 Operability Evaluations

a. Inspection Scope

The inspectors reviewed the following four evaluations to verify they met the

requirements of procedure NMP-GM-002, Corrective Action Program, and NMP-GM-002-

001, Corrective Action Program Instructions. The scope of this inspection included a

review of the technical adequacy of the evaluations, the adequacy of compensatory

measures, and the impact on continued plant operation.

Enclosure

11

C CR 2008111760, Unit 2 train B AFW check valve, 2-1302-U4-116, failed surveillance

testing

C CR 2008111970, Unit 2 turbine driven AFW steam inlet valve, 2-HV-5106, stroke

time out of specification

C CR 2008110669, Unit 2 train B containment spray pump low differential pressure

C CR 2008112035, Unit 1 train B missed surveillances on NSCW pumps 2 and 6

b. Findings

No findings of significance were identified.

1R17 Evaluations of Changes, Tests, or Experiments and Permanent Plant Modifications

a. Inspection Scope

The inspectors reviewed selected 10 CFR 50.59 evaluations to confirm that the licensee

had appropriately considered the conditions under which changes to the facility, UFSAR,

or procedures may be made and tests can be conducted without prior NRC approval.

The inspectors reviewed the nine evaluations for changes listed in the Attachment and

reviewed additional information, such as drawings, calculations, supporting analyses, the

UFSAR, and Technical Specifications (TS) to confirm that the licensee had appropriately

concluded the changes could be accomplished without prior NRC approval. The

inspectors also reviewed the nineteen changes listed in the Attachment which the

licensee had determined that 10 CFR 50.59 evaluations were not required to confirm that

the licensees conclusions to screen out these changes were correct and consistent

with 10 CFR 50.59.

The inspectors evaluated the engineering design change packages for the following

eleven modifications to verify there were no adverse effects on system availability,

reliability, and functional capability. The inspectors review also verified that all details

were incorporated in licensing and design basis documents and associated plant

procedures. Additionally, the inspectors reviewed test documentation to ensure

adequacy in scope and conclusion. Documents reviewed are listed in the Attachment.

The inspectors also reviewed selected CRs and the licensees recent self-assessment

associated with modifications and screening/evaluation issues to confirm that problems

were identified at an appropriate threshold, were entered into the corrective action

process, and appropriate corrective actions had been initiated and tracked to completion.

C 1049501701, Containment Spray Pump Overcurrent Relay Setpoint Change

(Mitigating Systems)

Attributes: Control Signals, Equipment Protection, Process Medium, Failure Modes,

Licensing Basis, Post Modification Testing

C 1060607901, Mitigating Actions on Alloy 600 Materials in Pressurizer Nozzle Welds

(Barrier Integrity)

Attributes: Materials/Replacement Components, Pressure Boundary, Licensing

Basis, Failure Modes

Enclosure

12

C 1070824101 Replace Electrical and Mechanical Lockout Valve Solenoids,

(Mitigating Systems)

Attributes: Energy Needs, Material/Replacement Components, Post Modification

Test, Vendor Information, Walkdown

C 1071579101, Valve 1HV-11817 Internals Removal (Mitigating Systems)

Attributes: Operations, Flowpaths, Pressure Boundary, Process Medium, Failure

Modes, Licensing Basis, Post Modification Testing

C 2049000601, Snubber Reduction (Mitigating Systems)

Attributes: Materials/Replacement Components, Structural

C 2060336901, 480V Switchgear Transformer and Breaker Replacements (Mitigating

Systems)

Attributes: Materials/Replacement Components, Control Signals, Operations, Failure

Modes

C 2060609501, Mitigating Actions on Alloy 600 Materials in Pressurizer Nozzle Welds

(Barrier Integrity)

Attributes: Materials/Replacement Components, Pressure Boundary, Licensing Basis,

Failure Modes

C 2061287901, TDAFW Governor Valve Bonnet Gasket (Mitigating Systems)

Attributes: Materials/Replacement Components, Flowpath, Pressure Boundary

C 2071073601, Installation of Manual Valves on the SIS Test Header (Unit 2), (Barrier

Integrity)

Attributes: Flowpaths, Process Medium

C 2081590101/2, Addition of Vent Valve to CCP Suction Line (Unit 2), (Barrier Integrity)

Attributes: Equipment Protection, Flowpaths, Process Medium

C 2081605401, Replace Motor 2HV8103C with New Motor in Stock, (Mitigating Systems)

Attributes: Materials Replacement Components, Operations, Post Modification

Testing, Energy Needs, Control Signals, Licensing Basis

b. Findings

No findings of significance were identified.

1R18 Plant Modifications

a. Inspection Scope

Temporary Modifications. The inspectors reviewed temporary modification TM

2081803801 and associated 10CFR50.59 screening criteria against the system design

bases documentation and procedure 00307-C, Temporary Modifications. This temporary

modification installed a camera inside containment to allow operators to observe the leak

Enclosure

13

rate of the number 2 seal on reactor coolant pump 3 on local flow indicator, 2FIS0192.

The inspectors reviewed implementation, configuration control, post-installation test

activities, drawing and procedure updates, and operator awareness for this temporary

modification.

Permanent Modifications. The inspectors reviewed minor design change MDC

2081590101 and associated 10CFR50.59 screening criteria against the system design

bases documentation and procedure 58007-C, Design Change Packages. This design

change installed a high-point vent valve, 2-1208-X4-054, on the common coolant

charging pump suction line, 2-1208-L4-139-6. The inspectors conducted a visual

walkdown to verify the installed vent valve was consistent with specifications and

drawings provided in the design change package. The inspectors verified that the

modification did not degrade the system design bases, licensing bases, or equipment

performance capability. Additionally, the inspectors verified that plant risk was not

increased unnecessarily during implementation of the modification.

b. Findings

No findings of significance were identified.

1R19 Post-Maintenance Testing

a. Inspection Scope

The inspectors either observed post-maintenance testing or reviewed the test results for

the following seven maintenance activities to verify that the testing met the requirements

of procedure 29401-C, Work Order Functional Tests, for ensuring equipment operability

and functional capability was restored. The inspectors also reviewed the test procedures

to verify the acceptance criteria were sufficient to meet the Technical Specifications

operability requirements.

C WO 2071889201 and 2061382201, Unit 2 train B motor-driven AFW pump outage

C WO 1081701001, Unit 1 train A control building control room filter

C WO 1081751501, Unit 1 train A EDG vibration switch

C WO 2080253001, Unit 2 train B NSCW transfer pump motor (located in A tower)

C WO A081808201, Technical Support Center air handling unit

C WO 1080381901, Unit 1 train B NSCW pump #4

C WO 1081073801 and 1081073601, Unit 1 train B CCW pump #6 outage

b. Findings

No findings of significance were identified.

Enclosure

14

1R20 Refueling and Other Outage Activities

a. Inspection Scope

The inspectors performed the following inspection activities described below for the Unit

2 refueling outage that began on September 17 and for the Unit 2 maintenance outage to

replace a reactor coolant pump seal that began on November 16. The inspectors

confirmed that the licensee maintained defense-in-depth commensurate with the outage

risk control plan for key safety functions and applicable technical specifications and that

configuration changes due to emergent work and unexpected conditions were controlled

in accordance with the outage risk control plan. Documents reviewed are listed in the

Attachment.

C Reviewed RCS pressure, level, and temperature instruments to verify that the

instruments provided accurate indication and that allowances were made for

instrumentation errors.

C Verified that outage work did not impact the operation of the spent fuel cooling

system during and after core load..

C Reviewed the status and configuration of electrical systems to verify that those

systems met technical specification requirements and the licensees outage risk

control plan.

C Observed decay heat removal parameters to verify that the system was properly

functioning and providing cooling to the core.

C Reviewed system alignments to verify that the flow paths, configurations and

alternative means for inventory addition were consistent with the outage risk plan

C Reviewed selected control room operations to verify that the licensee was controlling

reactivity in accordance with the TSs.

C Observed the licensees control of containment penetrations to verify that the

requirements of the TSs were met.

C Reviewed the licensees plans for changing plant configuration to verify that technical

specifications, license conditions, and other requirements, commitments, and

administrative procedure prerequisites were met prior to changing plant configuration.

C Observed refueling activities for compliance with TSs, to verify proper tracking of fuel

assemblies from the spent fuel pool to the core, and to verify foreign material

exclusion was maintained.

C Performed containment closure activities, including a detailed containment walkdown

prior to startup, to verify no evidence of leakage and that debris had not been left

which could affect the performance of the containment sump.

C Observed heatup and startup activities to verify that TSs, license conditions, and

other requirements, commitments, and administrative procedure prerequisites for

mode changes were met prior to changing modes.

C RCS integrity was verified by reviewing RCS leakage calculations and containment

integrity was verified by reviewing the status of containment penetrations and

containment isolation valves.

b. Findings

No findings of significance were identified.

Enclosure

15

1R22 Surveillance Testing

a. Inspection Scope

The inspectors reviewed the following four surveillance test procedures and either

observed the testing or reviewed test results to verify that testing was conducted in

accordance with the procedures and that the acceptance criteria adequately

demonstrated that the equipment was operable. Additionally, the inspectors reviewed

the CR database to verify that the licensee had adequately identified and implemented

appropriate corrective actions for surveillance test problems.

Surveillance Tests

C 14905-2, Unit 2 RCS Leakage Calculation (Inventory Balance)

C 14666-2, Unit 2 Train A Diesel Generator and ESFAS Test

In-Service Tests

C 14545-2, Unit 2 Motor Driven Auxiliary Feedwater Pump Operability Test

Containment Isolation Valve

C 14313-A-2, Unit 2 Containment Penetration 13A Local Leakrate Test

b. Findings

No findings of significance were identified.

1EP6 Drill Evaluation

a. Inspection Scope

The inspectors reviewed the facility activation exercise guide and observed the following

emergency response activity to verify the licensee was properly classifying emergency

events, making the required notifications, and making appropriate protective action

recommendations in accordance with procedures 91001-C, Emergency Classifications,

and 91305-C, Protective Action Guidelines.

C On November 5, the licensee conducted an emergency preparedness drill involving a

steam generator tube rupture and loss of AC power to emergency buses, 1AA02 and

1BA03. The technical support center was activated and the site participated in the

exercise.

b. Findings

No findings of significance were identified.

Enclosure

16

2. RADIATION SAFETY

Cornerstone: Occupational Radiation Safety

2OS1 Access Control To Radiologically Significant Areas

a. Inspection Scope

Access Controls The inspectors evaluated control of worker access to radiologically

significant areas and monitoring jobs in-progress associated with the Unit 2 refueling

outage. The inspectors directly observed implementation of administrative and physical

radiological controls; evaluated radiation worker (radworker) and health physics

technician (HPT) knowledge of and proficiency in implementing radiation protection

requirements; and assessed worker exposures to radiation and radioactive material.

During facility tours, the inspectors directly observed postings and physical controls for

radiation areas, HRAs, and potential airborne radioactivity areas established within the

radiation control area (RCA) of the Unit 2 containment, Unit 1 and Unit 2 auxiliary

buildings, and radioactive waste (radwaste) processing and storage locations. The

inspectors independently measured radiation dose rates or directly observed licensee

radiation surveys for selected RCA areas. Results were compared to current licensee

surveys and assessed against established postings and Radiation Work Permit (RWP)

controls. Licensee key control and access barrier effectiveness were evaluated for

selected Unit 1 and Unit 2 Locked High Radiation Area (LHRA) and Very High Radiation

Area (VHRA) locations. Changes to procedural guidance for LHRA and VHRA controls

were discussed with health physics (HP) supervisors. Controls for storage of irradiated

material within the spent fuel pool were observed and evaluated. Established

radiological controls were observed for selected HRA tasks including SG eddy current

work and movement of a spent resin container. In addition, licensee controls for areas

where dose rates could change significantly as a result of plant shutdown, refueling

operations, and resin sluicing activities were reviewed and discussed.

For selected tasks, the inspectors attended pre-job briefings and reviewed RWP details

to assess communication of radiological control requirements to workers. Occupational

workers adherence to selected RWPs and HPT proficiency in providing job coverage

were evaluated through direct observations and interviews with licensee staff. Electronic

dosimeter (ED) alarm set points were evaluated against area radiation survey results for

selected 2R13 outage tasks.

The inspectors evaluated the effectiveness of radiation exposure controls, including air

sampling, barrier integrity, engineering controls, and postings through a review of both

internal and external exposure results. Worker exposure as measured by ED and by

licensee evaluations of skin doses resulting from discrete radioactive particle or

dispersed skin contamination events were reviewed and assessed. Licensee activities

for monitoring and controlling alpha-emitting radio-nuclides were evaluated. For HRA

tasks involving significant dose rate gradients, e.g. SG work, the inspectors evaluated the

use and placement of whole body and extremity dosimetry to monitor worker exposure.

Radiation protection activities were evaluated against the requirements of UFSAR

Enclosure

17

Section 12; TS Sections 5.4 and 5.7; 10 CFR Parts 19 and 20; and approved licensee

procedures. Documents reviewed are listed in the report Attachment. The inspectors

completed 21 of the required line-item samples described in Inspection Procedure (IP)

71121.01.

Problem Identification and Resolution The inspectors reviewed corrective action

program (CAP) documents associated with access control to radiologically significant

areas. This included review of selected CRs related to radworker and HPT performance.

The inspectors evaluated the licensees ability to identify, characterize, prioritize, and

resolve the identified issues in accordance with procedure NMP-GM-002. The

inspectors also evaluated the scope of the licensees internal audit program and

reviewed recent assessment results. Documents reviewed are listed in the Attachment.

b. Findings

Introduction. Two examples of a Green, self-revealing, non-cited violation (NCV) of TS 5.7.1, High Radiation Area, was identified for unauthorized entries into HRAs.

Inadequate communication between workers and HP resulted in licensee personnel

breaching HRA boundaries without prior knowledge of the radiological condition.

Description On May 9, 2007, a Shift Operator (SO) performed a visual inspection in the

Unit 2 Residual Heat Removal Pump Room A. This room contained both a Radiation

Area (RA) and a posted and barricaded HRA. The SO contacted HP prior to entering the

room, but failed to communicate that entry into the HRA might be required. As a result,

HP briefed the SO on current RA radiological conditions. The assigned RWP did not

allow entry into HRAs without first obtaining a briefing on the HRA radiological conditions.

Typically, this inspection does not require the SO to pass the HRA boundary; however,

insulation obstructed the SOs view from outside the HRA. Without knowledge of dose

rates in the HRA, the SO proceeded past the HRA boundary and subsequently received

an ED dose rate alarm.

On August 16, 2007, two Facilities personnel entered the Unit 2 Fuel Handling Building

room 2-FHB-A-01 to perform cleaning duties and replace light bulbs. This area

contained a Contaminated Area (CA), RA, and a posted and barricaded HRA. Prior to

starting work, the personnel were briefed by HP on radiological conditions in the CA and

RA. There was no clear understanding between the two groups that a HRA entry would

be required. The assigned RWP did not allow entry into HRAs without first obtaining a

briefing on the HRA conditions. Without knowledge of dose rates in the HRA, one

worker proceeded past the HRA boundary in room 2-FHB-A-01 to continue the

housekeeping activities and received an ED dose rate alarm.

Analysis The inspectors determined that the unauthorized entries into HRAs were

performance deficiencies. This finding is greater than minor because it is associated

with the Occupational Radiation Safety Cornerstone attribute of Human Performance and

adversely affects the cornerstone objective in that workers who enter HRAs without prior

knowledge of current radiological conditions could receive unintended occupational

exposures. The finding was evaluated using the Occupational Radiation Safety SDP and

determined to be of very low safety significance (Green). The finding was not related to

Enclosure

18

ALARA planning, nor did it involve an overexposure or substantial potential for

overexposure, and the ability to assess dose was not compromised. This finding

involved the cross-cutting aspect of Human Performance, Work Practices H.4.a]

because the HRA events were a direct result of poor communications during pre-job

briefings and a willingness on the part of licensee personnel to proceed in the face of

uncertainty.

Enforcement TS 5.7.1, High Radiation Area, requires individuals entering HRAs to meet

one or more of the following criteria: 1) carry a survey meter; 2) wear an ED and be made

aware of radiological conditions in the area; or 3) be escorted by a HP technician.

Contrary to the above, on May 9, 2007, and on August 16, 2007, plant personnel entered

HRAs without a survey meter, without being aware of radiological conditions in the area,

or without HP technician escort. Because the violation is of very low safety significance

and has been entered into the licensees CAP (CR 2007105476 and CR 2007108830),

this violation is being treated as an NCV, consistent with Section VI.A of the NRC

Enforcement Policy: NCV 05000424/425, 2008005-01, Unauthorized Entries Into High

Radiation Areas.

2OS2 ALARA Planning and Controls

a. Inspection Scope

The inspectors reviewed ALARA program guidance and its implementation for ongoing

2R13 job tasks. The inspectors evaluated the accuracy of ALARA work planning and

dose budgeting, observed implementation of ALARA initiatives and radiation controls for

selected jobs in-progress, assessed the effectiveness of source-term reduction efforts,

and reviewed historical dose information.

ALARA planning documents and procedural guidance were reviewed and projected dose

estimates were compared to actual dose expenditures for the following high dose jobs:

scaffolding installation/removal, reactor vessel head work, steam generator maintenance

activities, motor operated valve (MOV) testing and maintenance, and installation of the

external neutron monitoring system inside containment. Differences between budgeted

dose and actual exposure received were discussed with cognizant ALARA staff.

Changes to dose budgets relative to changes in radiation source term and/or job scope

were also discussed. The inspectors attended pre-job briefings and evaluated the

communication of ALARA goals, RWP requirements, and industry lessons-learned to job

crew personnel.

The inspectors made direct field or closed-circuit-video observations of outage job tasks

involving work inside Unit 2 containment. For the selected tasks, the inspectors

evaluated radworker and HPT job performance, individual and collective dose

expenditure versus percentage of job completion, surveys of the work areas,

appropriateness of RWP requirements, and adequacy of implemented administrative and

physical controls.

Implementation and effectiveness of selected program initiatives with respect to source-

term reduction were evaluated. Chemistry program ALARA initiatives and their effect on

Enclosure

19

containment and auxiliary building dose rate trends were reviewed.

Plant exposure history for 2005 through 2008 year-too-date, and data reported to the

NRC pursuant to 10 CFR 20.2206 were reviewed, as were established goals for reducing

collective exposure during the current 2R13 outage. The inspectors reviewed procedural

guidance for dosimetry issuance and exposure tracking. The inspectors also examined

dose records of declared pregnant workers to evaluate assignment of gestation dose.

ALARA program activities and their implementation were reviewed against 10 CFR Part

20, and approved licensee procedures. In addition, licensee performance was evaluated

against guidance contained in Regulatory Guide (RG) 8.8, Information Relevant to

Ensuring that Occupational Radiation Exposures at Nuclear Power Stations will be As

Low As Reasonably Achievable, and RG 8.13, Instruction Concerning Prenatal Radiation

Exposure. Documents reviewed are listed in of the Attachment. The inspectors

completed 20 samples of specified line-items in IP 71121.02 to close the procedure.

Problem Identification and Resolution. The inspectors reviewed selected CR and Action

Item (AI) data in the area of exposure control. The inspectors evaluated the licensees

ability to identify, characterize, prioritize, and resolve the identified issues in accordance

with NMP-GM-002. The inspectors also evaluated the scope of the licensees internal

audit program and reviewed recent assessment results. Documents reviewed are listed

in the Attachment.

b. Findings

No findings of significance were identified.

Cornerstone: Public Radiation Safety

2PS1 Radioactive Gaseous and Liquid Effluent Treatment and Monitoring Systems

a. Inspection Scope

Groundwater Monitoring. The inspectors discussed current and future programs for

onsite groundwater monitoring with chemistry specialists and corporate staff, including

number and placement of monitoring wells and identification of plant systems with the

greatest potential for contaminated leakage. The inspectors also reviewed procedural

guidance for identifying and assessing onsite spills and leaks of contaminated fluids. In

addition, the inspectors reviewed records of historical and recent contaminated spills

retained for decommissioning purposes as required by 10 CFR Part 50.75(g).

The licensee has installed a number of onsite groundwater monitoring wells; optimally

located to detect contamination based on recent hydrological studies. The sample

results from these wells were included in the Annual Radiological Environmental

Monitoring Program Report. For the period reviewed, all monitoring well results were

below reporting limits (20,000 pCi/L for drinking water and 30,000 pCi/L for non-drinking

water).

Enclosure

20

b. Findings

No findings of significance were identified.

2PS2 Radioactive Material Processing and Transportation

a. Inspection Scope

Waste Processing and Characterization During inspector walk-downs, accessible

sections of the liquid and solid radwaste processing systems were assessed for material

condition and conformance with system design diagrams. Inspected equipment included

floor drain tanks; resin transfer piping; resin and filter packaging components; and

abandoned evaporator equipment. The inspectors discussed component function,

processing system changes, and radwaste program implementation with licensee staff.

The 2007 Effluent Report and radionuclide characterizations from 2007 - 2008 for each

major waste stream were reviewed and discussed with radwaste staff. For primary filters

and Dry Active Waste (DAW) the inspectors evaluated analyses for hard-to-detect

nuclides, reviewed the use of scaling factors, and examined comparison results between

licensee waste stream characterizations and outside laboratory data. Waste stream

mixing and concentration averaging methodology for spent resin and primary filters were

evaluated and discussed with radwaste operators. The inspectors also reviewed the

licensees procedural guidance for monitoring changes in waste stream isotopic

mixtures.

Radwaste processing activities and equipment configuration were reviewed for

compliance with the licensees Process Control Program and UFSAR, Chapter 11.

Waste stream characterization analyses were reviewed against regulations detailed in 10

CFR Part 20, 10 CFR Part 61, and guidance provided in the Branch Technical Position

on Waste Classification and Waste Form. Reviewed documents are listed in Section

2PS2 of the report Attachment.

Transportation The inspectors directly observed preparation activities for a shipment of

contaminated laundry. The inspectors noted package markings and placarding,

observed dose rate measurements, and interviewed shipping technicians regarding

Department of Transportation (DOT) regulations.

Five shipping records were reviewed for consistency with licensee procedures and

compliance with NRC and DOT regulations. The inspectors reviewed emergency

response information, DOT shipping package classification, radiation survey results, and

evaluated whether licensees in receiving were authorized to accept the packages.

Procedures for opening and closing Type B shipping casks were compared to Certificate

of Compliance requirements. In addition, training records for selected individuals

currently qualified to facilitate the shipment of radioactive material were reviewed.

Transportation program implementation was reviewed against regulations detailed in 10

CFR Part 20, 10 CFR Part 71, 49 CFR Parts 172-178; as well as the guidance provided

in NUREG-1608, Categorizing and Transporting Low Specific Activity Materials and

Enclosure

21

Surface Contaminated Objects. Training activities were assessed against 49 CFR Part

172 Subpart H. Documents reviewed are listed in the Attachment. The inspectors

completed 6 of 6 samples as required by IP 71122.02.

Problem Identification and Resolution Selected CRs in the area of radwaste processing

and transportation were reviewed in detail and discussed with licensee personnel. The

inspectors assessed the licensees ability to characterize, prioritize, and resolve the

identified issues in accordance with licensee procedure NMP-GM-002. The inspectors

also evaluated the scope of the licensees internal audit program and reviewed recent

assessment results. Licensee CAP documents reviewed are listed in Section 2PS2 of

the report Attachment.

b. Findings

No findings of significance were identified.

4. OTHER ACTIVITIES

4OA1 Performance Indicator (PI) Verification

a. Inspection Scope

The inspectors sampled licensee submittals for the listed PIs during the period from

July 1, 2007 through June 30, 2008, for Unit 1 and Unit 2. The inspectors verified the

licensees basis in reporting each data element using the PI definitions and guidance

contained in procedure 00163-C, NRC Performance Indicator and Monthly Operating

Report Preparation and Submittal, and Nuclear Energy Institute document NEI 99-02,

Regulatory Assessment Indicator Guideline.

Cornerstone: Mitigating Systems

C Mitigating Systems Performance Index (MSPI), Cooling Water Systems

C MSPI, Emergency AC Power Systems

C Safety System Functional Failures

The inspectors reviewed Unit 1 and Unit 2 operator log entries, the Vogtle Electric

Generating Plant Unit 1 and Unit 2 NRC Mitigating System Performance Index Basis

Document, the monthly operating reports and monthly PI summary reports to verify that

the licensee had accurately submitted the PI data.

Cornerstone: Occupational Radiation Safety

  • Occupational Exposure Control Effectiveness

The inspectors reviewed PI data collected from January 1, 2007, through September 30,

2008. For the reviewed period, the inspectors assessed CAP records to determine

whether HRA, VHRA, or unplanned exposures, resulting in TS or 10 CFR 20 non-

conformances, had occurred during the review period. In addition, the inspectors

reviewed selected personnel contamination event data, internal dose assessment

Enclosure

22

results, and ED alarms for cumulative doses and/or dose rates exceeding established

set-points. Documents reviewed are listed in the Attachment.

Cornerstone: Public Radiation Safety

  • Radiological Control Effluent Release Occurrences

The inspectors reviewed the PI results for the period of January 1, 2007, through

September 30, 2008. For the assessment period, the inspectors reviewed cumulative

and projected doses to the public, out-of-service effluent radiation monitors and

compensatory sampling data. The inspectors also reviewed licensee procedural

guidance for collecting and documenting PI data. Documents reviewed are listed in the

Attachment.

b. Findings

No findings of significance were identified.

4OA2 Identification and Resolution of Problems

.1 Daily Condition Report Review. As required by Inspection Procedure 71152,

Identification and Resolution of Problems, and in order to help identify repetitive

equipment failures or specific human performance issues for follow-up, the inspectors

performed a daily screening of items entered into the licensees corrective action

program. This review was accomplished by either attending daily screening meetings

that briefly discussed major CRs, or accessing the licensees computerized corrective

action database and reviewing each CR that was initiated.

.2 Focused Review

a. Inspection Scope

The inspectors performed a detailed review of the work-around lists for Unit 1 and 2 that

were in effect on October 28. The inspectors reviewed the licensees list to determine

whether any items would adversely affect the operators ability to implement abnormal or

emergency operating procedures. The inspectors reviewed proposed corrective actions

and schedule for each item on the work-around list. The inspectors reviewed the

compensatory actions and cumulative effects on plant operation. The inspectors verified

each item was being dispositioned in accordance with plant procedure 10025-C, Work

Around Program. Documents reviewed are listed in the Attachment.

b. Findings and Observations

No findings of significance were identified.

Enclosure

23

.3 Semi-Annual Trend Review

a. Inspection Scope

The inspectors performed a review of the licensees corrective action program and

associated documents to identify trends which could indicate the existence of a more

significant safety issue. The review was focused on repetitive equipment issues, but also

considered the results of inspector daily CR screening and the licensees trending efforts.

The review nominally considered the six month period of July 2008 through December

2008 although some examples extended beyond those dates when the scope of the

trend warranted. The inspectors also reviewed several CRs associated with operability

determinations which occurred during the period. The inspectors compared and

contrasted their results with the results contained in the licensees two latest Integrated

Performance Assessments. Corrective actions associated with a sample of the issues

identified in the licensees trend reports were reviewed for adequacy. The inspectors

also evaluated the trend reports against the requirements of the licensees corrective

action program as specified in licensee procedure NMP-GM-002 and 10 CFR 50,

Appendix B. Documents reviewed are listed in the Attachment.

b. Findings and Observations

No findings of significance were identified. The inspectors compared the licensee

Integrated Performance Assessments with the results of the inspectors daily screening

and did not identify any discrepancies or potential trends in the data that the licensee had

failed to identify.

4OA5 Other Activities

.1 Quarterly Resident Inspector Observations of Security Personnel and Activities

a. Inspection Scope

During the inspection period, the inspectors conducted observations of security force

personnel and activities to ensure that the activities were consistent with licensee

security procedures and regulatory requirements relating to nuclear plant security. These

observations took place during both normal and off-normal plant working hours.

b. Findings and Observations

No findings of significance were identified.

.2 (Closed) Unresolved Item 05000424/2008003-02: Steam Generator (SG) Tube Damage

as a Result of Tube Pulling Activities

The inspectors evaluated additional information regarding SG tube damage caused by

tube pulling activities. Specifically, several tubes adjacent to tube R11C62 in SG

Number 4 suffered damage when the licensee vendor attempted to remove a section of

tube R11C62 assuming that the tube was completely cut. The vendors Root Cause

Enclosure

24

Analysis determined, in part, that the cause of the issue was incorrect setting of cutting

tool rotation in conjunction with insufficient detail of the acceptance criteria of for tube

cutting in the vendors procedure.

The vendor initiated corrective actions to revise the tube pulling procedure in order to

ensure that correct rotation is verified prior to begin tube cutting activities and to enhance

the requirements for confirmation that a tube is severed after a cutting operation. In

addition, the licensee initiated corrective actions to track the implementation of the

vendors corrective actions for future onsite SG work and to improve vendor oversight by

requiring SG vendors to identify and notify the licensee about all critical hold-points for

SG activities.

The damaged tubes were re-inspected with Eddy Current Testing, stabilized, and

repaired by plugging before the Unit returned to normal operation. The licensee

performed an Operational Assessment and determined that the repaired tubes, as well

as the rest of the tubes left in service, would maintain their structural integrity until the

next inspection opportunity. The inspectors concluded that this issue resulted in no

findings of significance based on the results of the Root Cause Analysis and Operational

Assessment, planned corrective actions, discussions with the licensee, and the fact that

the SG tube damage and repairs occurred while the plant was in a safe condition.

4OA6 Meetings, Including Exit

.1 Exit Meeting

On January 15, 2009, the resident inspectors presented the inspection results to Mr. T.

Tynan and other members of his staff, who acknowledged the findings. The inspectors

confirmed that proprietary information was not provided or examined during the

inspection.

ATTACHMENT: SUPPLEMENTAL INFORMATION

Enclosure

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee personnel:

R. Brown, Training and Emergency Preparedness Manager

C. Buck, Chemistry Manager

W. Copeland, Performance Analysis Supervisor

R. Dedrickson, Plant Manager

K. Dyar, Security Manager

I. Kochery, Health Physics Manager

J. Robinson, Work Control Superintendent

T. Tynan, Site Vice-President

D. Vineyard, Operations Manager

J. Williams, Site Support Manager

T. Youngblood, Site Engineering Manager

NRC personnel:

S. Shaeffer, Chief, Region II Reactor Projects Branch 2

LIST OF ITEMS OPENED AND CLOSED

Opened and Closed

05000424, 425/2008005-01 NCV Unauthorized Entries Into High Radiation Areas

(Section 2OS1)

Closed

05000424/2008003-02 URI Steam Generator Tube Damage as a Result of Tube

Pulling Activities (Section 4OA5)

LIST OF DOCUMENTS REVIEWED

Section 1R01: Adverse Weather Protection

Procedures

11901-1, Heat Tracing System Alignment

11901-2, Heat Tracing System Alignment

1877-1, Cold Weather Checklist

1877-2, Cold Weather Checklist

System Health Reports

Heat Tracing System (1817)

Section 1R04: Equipment Alignment

Procedures

11610-2, Auxiliary Feedwater System Alignment

11146-1, Diesel Generator Fuel Oil Transfer System Alignment

11145-1, Diesel Generator Alignment

11150-1, Nuclear Service Cooling Water System Alignment

Attachment

2

Drawings

2X4DB161-1, 2, 3, Auxiliary Feedwater System

1X4DB170-2, P&I Diagram Diesel Generator System Train B

1X4DB133-2, P&I Diagram Nuclear Service Cooling Water System

1X4DB134, P&I Diagram Nuclear Service Cooling Water System

1X4DB135-1, P&I Diagram Nuclear Service Cooling Water System

1X4DB135-2, P&I Diagram Nuclear Service Cooling Water System

System Health Reports

Auxiliary Feedwater System 1302A, Third Quarter 2008

Section 1R05: Fire Protection

Procedures

Procedure 92865-2, Zone 165 - Diesel Generator Tanks and Pumphouse Fire Fighting Preplan

Procedure 92866-2, Zone 166 - Diesel Generator Tanks and Pumphouse Fire Fighting Preplan

Procedure 92839-1, Zone 139 - Fuel Handling Building - Level 1 Fire Fighting Preplan

Procedure 92731-1, Zone 31 - Auxiliary Building - Level B Fire Fighting Preplan

Procedure 92732-1, Zone 32 - Auxiliary Building - Level B Fire Fighting Preplan

Procedure 92730-2, Zone 30 - Auxiliary Building - Level B Fire Fighting Preplan

Procedure 92733-2, Zone 33 - Auxiliary Building - Level B Fire Fighting Preplan

Section 1R08: In-service Inspection Activities

Procedures

Procedure NMP-ES-024-208, Version 1.0, Visual Exam of Reactor Vessel Head Penetrations &

Base Material (Remote & Direct)

Procedure NMP-ES-024-506, Version 1, Manual UT Exam of Non-PDI, Full Penetration Welds.

Procedure Number 00435-C, Revision 5.3, Boric Acid Corrosion Control Program.

Procedure Number 83201-C rev 7.1, Boric Acid Corrosion Assessment.

Westinghouse Procedure Number MRS 2.4.2 GPC-37, Steam Generator Eddy Current Data

Analysis Techniques for Vogtle Units 1&2, Rev 14

Westinghouse Procedure MRS-TRC-1910, Use of Appendix H Qualified Techniques at Vogtle

Unit 2 13th Refueling, Rev 0

Calculations

Vogtle Unit 2 Determination of RPV head Effective Degradation years, June 24, 2008.

CAV-NF-1561, EFPY Operation of Vogtle with Projection to the EOC Burnup for the Current

Operating Cycle on Unit 2, June 4, 2008.

Calculation Note DDM-96-009, Documentation of Appendix H Compliance and Equivalency, Rev

0

Corrective Action Documents

2008104461, 2008102122, 2007106211, 2007110612, 2008108419, 2008110436, 2008110460

Other

Boric Acid Corrosion Assessments: 1204-2007-004, 1204-2008-04, 1204-2008-011,

1204-2008-013.

VGEP Unit 2, Boric Acid Leak Summary report, September 21, 2008.

Work Orders 2070719501, 2070668801, 2070628701, 2070668701, 2053288601, 2053288501,

Attachment

3

UT Calibration/Examination Record for Report Number S08V2U055 and S08V2U056.

Certified Test Report for Ultragel II Couplant Batch: 06225.

RT Film for welds associated with Work Order Number 2070570001.

Radiography (RT) examination film of welds associated with Q.I.S. Work Order No. 08-70-0658

(ASME Section III and V NDE).

Training and qualification records for 4 LMT Test operators and data analysts.

CN-RIDA-07-40, Westinghouse Thermal Sleeve Wear Criteria Analysis, Rev O.

NL-05-0990, Vogtle Unit 2 Response to NRC Request for Additional Information Regarding

relaxation from First Revision of NRC Order EA-03-009, July 1, 2005.

NL-05-1672, Vogtle Unit 1 & 2 Relaxation of Requirements Associated with the First revised

Order EA-03-009, Feb 20, 2004.

NL-07-1260, Vogtle Unit 2 Results of RPV Inspections Required by First Revised Order EA-03-

009, June 21, 2007.

Reactor Vessel Exam Summary Record, Year 2007 for Vogtle Unit 2.

Vogtle Unit 2 Performance Demonstration Initiative Program Procedure: PDI-UT-2, Revision C,

Addenda 3, Generic Procedure for the Ultrasonic Examination of Austenitic Pipe Welds.

Southern Nuclear Study Guide for General Employee Training Topics, January 2008.

NMP-ES-004-GL01, Steam Generator Program Strategic Plan, April 2008.

Vogtle Steam Generator Program Secondary Side Plan, April 2008

SG-CDME-08-31, Steam Generator Degradation Assessment for Vogtle Unit 2 September 2008

Outage (2R13)

Operating License Amendment No. 133 to Facility Operating License NPF-81, Accession No

ML082530044, September 16, 2008

Personnel Qualification Records for various ECT personnel

Certificates of Conformance for various ECT probes

Certificate of Calibration for OMNI-200 ECT testers 221038 and 221041

EPRI ETSS # 20510.1, Rev 6

EPRI ETSS # 20511.1, Rev 8

EPRI ETSS # 21409.1, Rev 5

EPRI ETSS # 21410.1, Rev6

Westinghouse ANTS GBE-A-108, Rev 1

Westinghouse ANTS GBE-B-108, Rev 0

Westinghouse ANTS GBE-C-108, Rev 0

Westinghouse ANTS GBE-D-108, Rev 0

Westinghouse ANTS GBE-E-108, Rev 0

Westinghouse ACTS, GBE-06-108, Rev 0

ASME ECT Calibration Standard Drawing No 1B81101, Rev 0

ASME ECT Calibration Standard Drawing No 1B81102, Rev 1

Various Vogtle 2R13 Refueling Outage Interim Engineering Assessments for SG1 and SG4

Base on Eddy Current Inspection Data

Westinghouse MRS-TRC-1919, Site Specific Performance Demonstration (SSPD) Program,

September 2008

Westinghouse SG-SGDA-05-50, Vogtle Unit 2R11 Refueling Outage Condition Monitoring and

Operational Assessments, November 2005

Attachment

4

Section 1R11: Licensed Operator Requalification Program

Procedures

Operating Test Dynamic Simulator Scenario DS#9, Rev. 21

Section 1R17: Evaluations of Changes, Tests, or Experiments and Permanent Plant

Modifications

Full Evaluations

2054225601, Installation of Freeze Seal to perform work on the bypass line of 2HV8701B, dated

April 7, 2008

DCP 1050351501, 1BB16, 1NB02, 1NB03, 1NB08, 1NB11 and 1NB19 480V Circuit Breaker

and Load Center Transformers 1NB02X, 1NB08X, 1NB09X, and 1NB19X Replacement, Ver. 5.0

DCP 1060336201, 1BB06, 1BB07, 1NB10, 1NB12, and 1NB28 480V Circuit Breaker and Load

Center Transformer 1NB28X Replacement, Ver. 2.0

DCP 1979006101, Safety Features Sequencer Control Logic Upgrade, dated May 17, 2007

DCP 2053320201, 2AB15, 2NB02, 2NB08, 2NB09, 2NB12, and 2NB19 480V Circuit Breaker

and Load Center Transformers 2NB02X, 2NB08X, 2NB09X, 2NB12X and 2NB19X

Replacement, Ver. 7.0

DCP 2061266101, MFRV Air-Gag Instrument Air Supply Line and other MFRV appurtenances

for Reliability Improvement, dated April 5, 2007

DCP 2060336901, 2AB04, 2AB05, 2NB01, and 2NB28 480V Circuit Breaker and Load Center

Transformer 2NB28X Replacement, Ver. 3.0

DCP 2060609501, Mitigation Actions on Alloy 600 Materials in the Pressurizer Nozzle Welds,

dated October 22, 2007

RER A071430001, Interim Onsite Storage for Low Level Radioactive Waste (LLW), dated April

25, 2008

Screened Out Items

2070053701, 207052601, 2070500901, 2070215601, 2070780601, 2071419601, 2080864701,

2081030001, 2081619401,

A080016601

ABN-V00714

DCP 2049000601 Ver. 2.0, DCP C999007101 (DCPT 99-VAN0071-005) Ver. 1.0

MDC 2061287901 Ver. 1.0, MDC 1061785901 Rev. 1, MDC 1061854401 Ver. 2.0

TM 2070053201 Rev. 1, TM 2070053401, TM 2070053601 Rev. 1

Modifications

1049501701, 1060607901, 1070824101, 1071579101, 2049000601, 2060336901 Ver. 3.0,

2060609501, 2061287901 Ver. 1.0, 2071073601, 2081590101/2, 2081605401

Condition Reports

2006102035, 2006102117, 2006105418, 2006113977, 2008110234

Action Items

2006203400, Ensure Pre-Existing Flow Enveloped, dated August 3, 2006

Procedures

11150-1 Rev. 18, 13435-C Rev. 28, 13540-1 Rev. 9.2. 13610-2, 13715A-1 Rev. 4, 14286-1 Rev.

22, 14286-2 Rev. 18, 14546-2 Rev. 27, 14748-2 Rev. 18.1, 14810-2 Rev. 37.1, 17002-1 Rev.

Attachment

5

19.1, 18020-C Rev. 9, 18030-C Rev. 18, 20236-C Rev. 3, 22287-C Revision 3, 22413-C Rev. 1,

23701-1 Rev. 13, 25508-C Rev. 24.1, 25721-C Rev. 15.2, 27572-C Rev. 12.1, Terry Turbine

Type GS2 Governor Valve Maintenance, 27736-C Rev. 9.1, 85052-C Rev. 10, 28480-C Rev. 13,

28909-C Rev. 15, 55020-C Rev. 18.1, 55024-C Rev. 12.3, 58007-C Rev 16, 85052-C Rev. 10

Work Orders

1061785902, Elimination of Pressure Control Circuit 1PT-11741, Rev. 1.0

1061785903, Elimination of Pressure Control Circuit 1PT-11742, Rev. 0

1051650501, Freedom Series Overload Relay Failure Due to Early Trip, Rev. 0

1062213401, Inspection of Aux Contact Assembly Mounting on Freedom Series Starters, Rev. 0

1070247701, Aux Contact Assembly Inspection Found Improperly Seated Block in Cubicle

1BBA22 Supplying 1HV12119, Rev. 0

2060167001, Thermography Indication of Bad Crimp in Starter, Rev. 0

2061284902, Replacement of TDAFW Body-to-bonnet Metallic O-ring with Flexitallic Gasket,

Rev. 0

2070175901, Terry Turbine Governor Valve Inspection, Rev. 1.0

A061353801, Freedom Series Thermal Overload Relays Tripping Early, Rev. 1

MWO1071618401, Contingency MWO to place 1FV0520 MFRV on the Air Gag, dated June 21,

2008

MWO 2081605402, 2HV8103C Motor Replacement, dated October 26, 2006

WO 00567352 01, Rebuild Valve 2-E41-F002, dated February 23, 2005

Calculations

DOEJ-SJ-97-V1N0061-001, Engineering judgment associated with EMI/RFI issues with

Westinghouse supplied sequencer, Rev. 1

EF02712, Nuclear Service Cooling Water System Pipe Stress Analysis, Ver. 5.0

EF02714, Nuclear Service Cooling Water System Pipe Stress Analysis, Ver. 3.0

GL 89-10 Scope of Motor Operated Valves, Ver. 21

MC-V-04-0023, Unit 1 and 2 Containment Spray Pump Relaying, Ver. 1

MC-V-07-0191, Impact Documentation to Base Calculation X3CF12, 1E DC Panel Loading, Due

to Replacement of GE AKR Circuit Breakers with ABB EMAX Breakers per DCP 2060336901,

Ver. 1.0

V2-1202-006-H050, Pipe Support Assembly Evaluation for 2-1202-006-H050, Ver. 5.0

V2-1202-006-H060, Pipe Support Assembly Evaluation for 2-1202-006-H060, Ver. 4.0

X3C18, Voltage Profile for Normal Non-1E Conditions, Rev. 6

X3C22PG, Voltage Profile for Refuel Outage Conditions, dated December 3, 2006

X3CA20, Unit 2 Class 1E 89-10 MOV Starting Voltages, Ver. 6

X4C1000U02, Valve Required Thrust/Torque and Operator Capabilities and Limitations for the

X4C1202S00F1, Failure Modes and Effects (FMEA) - Nuclear Service Cooling Water, Rev. 8

X4C1202S10, NSCW Water Hammer Study, Rev. 2

X4C1202V056, Vogtle NSCW System Water Hammer Analysis, Rev. 2

X4CPS.0075.228, Identification of Components Requiring ECSAs, Rev. 10

X5CP11741, Nuclear Service Cooling Water Train A Pump Discharge Pressure, Rev. 5

X5CP11742, Nuclear Service Cooling Water Train B Pump Discharge Pressure, Rev. 5

X6CDD.46, Dose Rate Versus Distance from Filter Storage HICs, Rev. 0

X6CJH.19, Post LOCA Penetration Streaming - Control Building, Rev. 3

Attachment

6

Drawings

1X3AE13-00056-1, Diesel Generator SFS Card and Chassis Configuration, Sheet 1 of 5, Rev.

21X3AE13-00056-2, Diesel Generator SFS Card and Chassis Configuration, Sheet 2 of 5, Rev.

22X3D-BG-D03B, Piping Penetration Vent System 2-1556-B7-003-M01 Elementary Diagram,

Rev. 4

1X3D-AA-A01A, Main One Line Unit 1, Ver. 26.0

1X3D-AA-E12A, One Line Diagram 480V Switchgear 1NB12 1-1805-S3-B12, Rev. 9

1X3D-AA-E20A, One Line Diagram 480V Switchgear 1NB19 1-1805-S3-B19, Rev. 8

1X3D-AA-E26A, 480V Switchgear 1NB25, Rev. 5

1X3D-AA-E28A, One Line Diagram 480V Switchgear 1NB28 1-1805-S3-B26, Ver. 10

1X3D-AA-E30A, One Line Diagram 480V Switchgear 1NB28 1-1805-S3-B28, Rev. 6

1X3D-AA-M04A, Load Center Transformer Data and Tap Settings, Sheet 20, Ver. 8.0

1X3D-BD-KO4F, Elementary Diagram Nuclear Service Cooling Water System 1-1202-P4-006-

M01, Ver. 21.0

1X3D-BD-KO5W, Elementary Diagram Nuclear Service Cooling Water System 1HV-1669A, Ver.

12.0

1X3D-BD-K05X, Elementary Diagram Nuclear Service Cooling Water System 1HV-1669B, Ver.

9.0

1X3DF512-1, Conduit/Tray Plan Area 1 El 171;-9: to El 185-0 Containment Building Unit 1, Ver.

22.0

1X4DB133-1, P&ID Nuclear Service Cooling Water System (1202), Ver. 51.0

1X4DB133-2, P&ID Nuclear Service Cooling Water System (1202), Ver. 58.0

1X4DB134, P&ID Nuclear Service Cooling Water System (1202), Ver. 31.0

1X4DB135-1, P&ID Nuclear Service Cooling Water System (1202), Ver. 29.0

1X4DB135-2, P&ID Nuclear Service Cooling Water System (1202), Ver. 34.0

1X4DB137, Component Cooling Water System, Ver. 19.0

2K3-1202-036-01, Nuclear Service Cooling Water System Fabrication Isometric Aux Bldg Area

3H Level A1, Rev. 5

2K3-1202-099-01, Nuclear Service Cooling Water System Fabrication Isometric Aux Bldg Area

3H Level B, Ver. 8.0

2K3-1202-406-01, Nuclear Service Cooling Water System Fabrication Isometric Aux Bldg Area

3H and 3F Level 2, Ver. 4.0

2K3-1203-026-01, Component Cooling Water System Fabrication Isometric Aux Bldg Area 3H

Level A1, Rev. 8

2K3-1203-026-02, Component Cooling Water System Fabrication Isometric Aux Bldg Area 3H

Level 2, Rev. 5

2K5-1202-006-01, Nuclear Service Cooling Water System Fabrication Isometric Outside Area

8F Tunnel 2T2B, Rev. 8

2K5-1202-006-02, Nuclear Service Cooling Water System Fabrication Isometric NSCT

Pumphouse Area 8F, Rev. 8

2X3AC03-01732, Connection Diagram for UNITROL Unit 2X3AC03-1732-3, Rev. 4

2X3AC03-02291, Front View Motor Control Center 2ABA, Rev. 6

2X3D-AA-A01A, Vogtle Main One Line for Unit 2, Rev. 19

2X3D-AA-E03A, 480V Switchgear 2NB03 2-1805-S3-B03, Ver. 9.0

2X3D-AA-E04A, One Line Diagram 480V Switchgear 2AB04 2-1805-S3-B04, Ver. 4.0

2X3D-AA-E05A, One Line Diagram 480V Switchgear 2AB05 2-1805-S3-B05, Ver. 6.0

2X3D-AA-E22A, One Line Diagram 480V Switchgear 2NB21 2-1805-S3-B21, Rev. 6

2X3D-AA-F05A, 480V Motor Control Center 2NBE, Rev. 19

Attachment

7

2X3D-AA-F18A, One Line Diagram 480V Motor Control Center 2ABA 2-1805-S3-ABA, Rev. 13

2X3D-AA-F24A, One Line Diagram 480V Motor Control Center 2ABE 2-1805-S3-ABE, Rev. 20

2X3D-AA-F25A, One Line Diagram 480V Motor Control Center 2BBE 2-1805-S3-BBE, Ver. 17

2X3D-AA-F29A, 480V Motor Control Center 2NBT, Ver. 15.0

2X3D-AA-F36A, One Line Diagram 480V Motor Control Center 2ABF 2-1805-S3-ABF, Ver. 12.0

2X3D-AA-F42, 480V Distribution Panels, Rev. 9

2X3D-BC-B05B, Circulating Water System 2HV-7244, Ver. 8.0

2X3D-BC-B06B, Circulating Water System 2HV-7245, Ver. 7.0

2X3D-BC-B08B, Turbine Plant Cooling Water System 2HV-6799, Rev. 4

2X3D-BC-B55B, Cooling Tower Makeup Valve 2-LY-27268B, Rev. 4

2X3D-BC-B55C, Cooling Tower Makeup Valve 2-LY-27268C, Rev. 1

2X3D-BC-B55D, Cooling Tower Makeup Valve 2-LY-27268D, Rev. 1

2X3D-BG-D03C, Piping Penetration Vent System 2-1556-B7-004-M01 Elementary Diagram,

Rev. 4

2X3D-BG-D03D, Piping Penetration Vent System 2-1556-B7-005-M01 Elementary Diagram,

Rev. 5

2X3D-BG-D03E, Piping Penetration Vent System 2-1556-B7-005-M01 Elementary Diagram,

Rev. 4

2X3D-BG-D03K, Piping Penetration Vent System 2-1556-B7-012-M01 Elementary Diagram,

Rev. 5

2X3D-BH-K01B, AC System 480 Volts 2NB0309, Ver. 2.0

2X4DB111, P & I Diagram RCS System No. 1201, Rev. 27

2X4DB122, P & I Diagram RHR System No. 1025, Rev. 52

2X4DB133-2, P&ID Nuclear Service Cooling Water System (1202), Ver. 49.0

2X4DB134, P&ID Nuclear Service Cooling Water System (1202), Ver. 31.0

2X4DB136, P&ID Component Cooling Water System (1203), Ver. 23.0

2X4DB137, P&ID Component Cooling Water System (1203), Ver. 19.0

2X6AN02-00103-3, Unit 2 Refueling Machine Trolley and Mast Assembly, Rev. 8

2X6AN02-023-5, Unit 2 Refueling Machine General Assembly, Rev. 7

AX1D08SA028, Delay Features Fencing Floppy P.A. and Red Zone Sections and Details, Rev.1

AX2D47A469, Concrete Storage Pad for Low Level Radwaste, Ver. 1.0

AX3D-AA-A00V-01, General Notes, Installation Instructions and References for Cable Splices,

Ver. 19.0

AX3D-AA-A00V-02, Notes and Details for In-line Cable Splices, Rev. 15

AX3D-AA-A00V-03, Notes and Details for In-line Bolted Cable Splices, Ver. 7.0

AX3D-AA-F18A, 480V Motor Control Center ANBT, Ver. 12.0

V2-1201-054-H614, Pipe Support Assembly Drawing for 2-1201-054-H614, Ver. 3.0

V2-1201-054-H625, Pipe Support Assembly Drawing for 2-1201-054-H625, Ver. 1.0

V2-1202-004-H071, Pipe Support Assembly Drawing for 2-1202-004-H071, Rev. 2

V2-1202-006-H060, Pipe Support Assembly Drawing for 2-1202-006-H060, Ver. 2.0

V2-1202-006-H050, Pipe Support Assembly Drawing for 2-1202-006-H050, Ver. 3.0

V2-1202-088-H033, Pipe Support Assembly Drawing for 2-1202-088-H033, Ver. 3.0

V2-1202-151-H025, Pipe Support Assembly Drawing for 2-1202-151-H025, Ver. 4.0

V2-1202-405-H031, Pipe Support Assembly Drawing for 2-1202-405-H031, Ver. 4.0

V2-1203-026-H007, Pipe Support Assembly Drawing for 2-1203-026-H007, Ver. 5.0

Attachment

8

Other Documents

2054225601, Installation of Freeze Seal to perform work on the bypass line of 2HV8701B, dated

April 7, 2008

2070500901, Install Vibration Monitoring on RHR Loop 4 Suction Valve 2HV8702B Bypass and

Packing Leakoff Lines, dated April 14,2006

2081619401, Preaccess Purge Exhaust Damper Air Supply, dated October 29,2008

2NB0309-55024, 480 Volt Solid State Trip Breaker Data Sheet, Rev. 1

2NBT08-55025, AC Molder Case Circuit Breaker Data Sheet 2HV-7244, Rev. 4

2NBT11-55025, AC Molder Case Circuit Breaker Data Sheet 2HV-6799, Rev. 1

2NBT12-55025, AC Molder Case Circuit Breaker Data Sheet 2HV-7245, Rev. 4

2X4AF03-00229, Instruction Manual for Terry Steam Turbine, Ver. 13.0

2X4AQ59-00006, Installation, Operation and Maintenance Manual for Lisega Replacement

Struts, Ver. 3

ASME Form NIS-2 for WO1060607902, dated June 19, 2008

ASME Form NIS-2 for WO1060607903, dated June 19, 2008

ASME Form NIS-2 for WO1060607904, dated June 19, 2008

ASME Form NIS-2 for WO1060607905, dated June 19, 2008

ASME Form NIS-2 for WO1060607906, dated June 19, 2008

ASME Form NIS-2 for WO1060607907, dated June 19, 2008

ASME Test Verification Form 08018, dated March 18, 2008

ASME Test Verification Form 08019, dated March 18, 2008

ASME Test Verification Form 08020, dated March 18, 2008

AX3AE13-00030, Diesel Generator SFS -Common Q Qualification Summary Report, Revision 3

AX3AE13-00031, Diesel Generator Safety Features Sequencer Equipment Qualification Report,

Revision 4

AX3AC03-10021, Freedom Series Starters, Contactors and Thermal Overload Relays

Instruction Manual, Ver. 2.0

AX3AC03-10022, Freedom Series Starters, Contactors, and Thermal Overload Relays Seismic

Qualification Report, Ver. 4.0

AX3AC02B-20016, ABB 480V Breakers Installation and Maintenance Manual, Ver. 2.0

AX3AC02B-20017, ABB EMAX ANSI Qualification Reports, Ver. 1.0

Clearance 2-DT-R13; Tagout 2-DT-08-1204-15105(001), Current

DC-1017, Pipe Stress and Pipe Supports Analysis Criteria, Ver. 15

DC-1018, Pipe break Criteria - Interdiscipline, Ver. 7

DC-1202, Nuclear Service Cooling Water (NSCW) System, Rev. 12

DOEJ-SC-1050351501-001, Seismic Evaluation of 480V Replacement ABB Breakers for Plant

Vogtle 1 DCP 1050351501, Ver. 1.0

DOEJ-SC-1060336201-001, Seismic Evaluation of 480V Replacement ABB Breakers for Plant

Vogtle 1 DCP 1060336201, Ver. 1.0

DOEJ-SC-1061854401-001, Addition of Environmental Seals for Barton Transmitters Models

763 and 764 per DCP 1061854401 for Plant Vogtle, Ver. 2.0

DOEJ-SC-2060336901-001, Seismic Evaluation of 480V Replacement ABB Breakers for Plant

Vogtle 1 DCP 2060336901, Ver. 1.0

DOEJ-SC-2053320201-001, Seismic Evaluation of 480V Replacement ABB Breakers for Plant

Vogtle 1 DCP 2053320201, Ver. 1.0

EQDP X5AD07, ITE Barton Level and Pressure Transmitter Equipment Qualification Data

Package, Rev. 21

Attachment

9

EQDP X6AA15, Westinghouse NSSS Safety Related Mechanical and Electric Equipment, Rev.

88

LDCR 2007054, Deletion of NSCW Pressure Loops 1PT11741 and 1PT11742, dated October

15,2007

NL-04-1150, SNC Response to NRC Bulletin 2004-01, dated July 26, 2006

NL-04-1948, SNC Response to NRC Bulletin 2004-01, dated October 21, 2004

NL-05-0923, First Revised NRC Order EA-03-009, dated June 6, 2005

NL-07-0803, Pressurizer Nozzle Full Structural Weld Overlay Evaluation and Nondestructive

Examination results, Spring 2007 Outage (2R12), dated April 13, 2008

NL-07-0837, Pressurizer Nozzle Full Structural Weld Overlay Evaluation, dated April 13, 2007

NL-07-0859, Pressurizer Nozzle Full Structural Weld Overlay Evaluation and Nondestructive

Examination results, Spring 2007 Outage (2R12), dated April 18, 2008

NL-08-0667, Pressurizer Nozzle Full Structural Weld Overlay Evaluation and Nondestructive

Examination results, Spring 2008 Outage (1R14), dated May 2, 2008

NOTS-02722, Potential Substantial Safety Hazard - Defect in Freedom Series Motor Starter

Heater Packs 10 CFR Part 21 Notification, dated January 6, 2005.

PS-03-1393, Vogtle Mid-Year design Change Process Self-Assessment, dated June 20, 2003

PS-03-2319 (RER 2003-V0376), Investigation of Recent Failures of Cutler-Hammer Thermal

Overloads, dated November 7, 2003

PS-04-2134 (RER C049630701), Design Basis Review of Deletion of Pressure Loops

1PT11741 and 1PT11742, dated November 4, 2004

PS-06-0278, (RER C052437601), Review of Failures of Freedom Series Thermal Overloads and

10 CFR Part 21 Reporting Thermal Overloads, dated February 9, 2006

PS-06-2127 (RER C052437601), Suitable Replacement Alternative for Freedom Series Thermal

Overload Relays, dated September 25, 2006

PS-07-1443 (RER C070118501), Verification of RER C049630701 Response Conclusions,

dated July 31, 2007

Safety Evaluation Report related to the Westinghouse Common Q Platform, dated February 24,

2003

SG-15919 (REA 97-VAA621), Evaluation of Snubber 2-1208-123-H007 As-Found Condition,

dated October 2,1997

SG-16580 (REA 97-VAA621), Snubber Deletion - Feasibility/Cost Benefit Study, dated

November 13,1998

SG-17117 (REA 99-VAA629), Replacement Recommendation for Obsolete Cutler-Hammer

Starters and Overload Relays, dated September 1, 1999

SG-18646 (REA 01-VAA615), Review of Application of Lisega E-Bar in Place of Existing

Snubbers, dated August 30, 2001

Technical Specification Section 3.8.6, Battery Parameters

Technical Specification Bases Section 3.8.4, DC Sources - Operating, Revision 1

Technical Specification Bases Section 3.8.5, DC Sources - Shutdown, Revision 1

Technical Specification Bases Section 3.8.6, Battery Parameters, Revision 2

TR 13.8.2, Safety-Related Motor -Operated Valves Thermal Overload Protection and Bypass

devices, Rev. 1

Valve Inservice Testing Program, Revision 12, dated December 6, 2004

V-EL-JP-15001-02.1, Job Performance Measure for EMAX Breaker, dated August 26, 2008

V-EL-JP-15002-1.1, Job Performance Measure for Racking EMAX Breaker, dated August 26,

2008

Attachment

10

V-EL-LP-15001, EMAX Breaker Maintenance Lesson Plan, Rev. 02

Weld Overlay Process Traveler 900757-N6, Rev. 3 with actual data taken on April 4, 2008

X3AR01, Section E9, Cable Installation and Cable Termination, Rev. 28

X4AF03, Specification for Auxiliary Feedwater Pumps and Drivers, Rev. 13

Section 2OS1: Access Control To Radiologically Significant Areas

Procedures, Guidance Documents, and Manuals

43630-C, Calibration, Operation and Use of the Eberline HANDECOUNT Alpha/Beta Counter,

Rev. 10 & Rev.11

43005-C, Establishing and Posting Radiation Controlled Areas and High Radiation Area Access

Control, Rev. 35.2

43000-C, Radiation and Contamination Surveys, Rev. 30

43002-C, Airborne Radioactivity Sampling and Evaluation, Rev. 31

47025-C, Use and Maintenance of the Trends Airshield, Re. 3.3

43018-C, Radiological Controls for Diving Operations, Rev. 2.1

RWPs 07-0105, 07-0104, 08-2304, 08-0112 Rev. 1

HandECount Manual, May 2003

Records and Data

ALARA Briefing Record, RWP 08-2301, Install and Remove Nozzle Dams for U2 S/G 1&4

Surveys 96433, 98589, 94405, 110332

Containment Air Sample log, 9/21/08 - 9/25/08

Personnel Contamination Event Log, 9/22/08 - 10/9/08

Beta/Gamma-to-Alpha comparisons for S/G bowls, 2R10, 2R11, and 2R12

TEDE-ALARA Evaluation Worksheets, RWP Nos. 2311 & 2301, Nozzle Dam Installation, U2

DOP Testing Data Sheet, U2 S/G Negative Pressure HEPAs, 9/24/08

CAP Documents

VQA-2007-023, QA Audit of Health Physics, 7/18/07

CRs 2008102174, 2007105476, 2008110423, 2008110155, 2008104352, 2008103837,

2008109283,

Section 2OS2: As Low As Reasonably Achievable (ALARA)

Procedures, Manuals, and Guidance Documents

Vogtle Electric Generating Plant, Strategic Plan for Radiation Exposure Reduction,

2008-2012, Approved 12/14/07

NMP-HP-001, Radiation Protection Standard Practices, Ver. 3.0

00950-C, Personnel Dosimetry Program, Rev. 17.4

16035-2, Chemistry Operations Interface for Reactor Coolant System (RCS) Chemistry Control

During Scheduled Plant Shutdowns, Rev. 1

41001-C, ALARA Job Review, Rev. 28

41006-C, Temporary Shielding, Rev. 24

45012-C, Individual Radiation Exposure Records and Reports, Rev. 22

Southern Nuclear Study Guide for General Employee Training Topics: Plant Access,

Radiation Worker, Respiratory Protection, Confined Space, January 2008

RWPs 08-2004, 08-2005, 08-2300, 08-2301, 08-2302, 08-2304, 08-2311, 08-2601, 08-2602, 08-

2603, 08-2617

Attachment

11

Records and Data Reviewed

ALARA Briefing Records for RWPs 08-2004, 08-2100, 08-2104, 08-2302, 08-2617

Surveys 109508, 109185, 110056, 109079,

Plant Vogtle Unit 2 Refueling Outage Cycle 13 (2R13) - Reactor Coolant System (RCS)

Shutdown Chemistry Parameters September 08-22, 2008, including: Soluble and total

iron; filtrate iodines; soluble and total nickel; xenon (Xe) -133 and Xe-135; Hard

Gamma- emitting radionuclides including cobalt (Co)-58 and Co-60, manganese (Mn)-

54, and total gamma; RCS filtrate isotopes including Mn-54, C0-58, Co-60, zinc -65,

and cesium (Cs) 134 and Cs-137

RCS Chemistry Shutdown Dosimeter Data, Shutdown 09/15-20/08

Mixed Bed Demineralizer No. 3 Dose Rate Data during Unit 2 Outage

Unit 2 Refueling Outage Cycle 12 (2R12) Steam Generator (S/G) Channel-head Dose

Rates, S/G #1, S/G #2, S/G # 3, S/G #4

2R12, Unit 2 Standard Radiation Survey Data,

2R13, Unit 2 Standard Radiation Survey Data

Secondary S/G Dose Rate Comparison Data, 2R10/11/12/13 S/G #4

Shutdown chemistry electronic dosimetry dose rate date after peroxide addition for chemical

degassing, 09/17/08

Unit 2 Refueling Outage Cycle 13 (2R13) Outage Dose Summary Reports,

September 22 -25, 2008, and October 6-9, 2008

2R13 Radiation Exposure, Cumulative Exposure Data. September 22-25, 2008, and

October 6-9, 2008

Daily Health Physics Summary Reports, September 22-25, 2008, and October 6-9,

2008

Minor Design Change (MDC) Request No. 1081391301/1.0, Unit 1, Tri Nuke permanent

storage in refueling cavity, 08/20/08

Engineering work order No. C071255501, Review of full cycle zinc addition - maximum flow for

reactor coolant letdown, Final response, 07/30/07

Request for Engineering Review (RER) C071255501, Units 1 & 2, Review of full cycle zinc

addition - maximum flow for RCS letdown, 08/30/07

File C.04.01, Vogtle Unit 2 Refueling Outage 12 Reactor Coolant System Shutdown

Chemistry Control Report, 07/14/07

CAP Documents

VQA-2007-023, QA Audit of Health Physics, 7/18/07

CRs 2008110012, 2008105257, 2008102036, 2008100658, 2007110751, 2007109138,

2007108087, 2007102593,

AIs 2008201426, 2008201221, 2008201207, 2008201060, 2008200084, 2007206116,

2007204871, 2007204537, 2007204529, 2007204528, 2007204527, 2007204390, 2007204293,

2007203671, 2007203645, 2007203644, 2007109138

Section 2PS1: Radioactive Gaseous and Liquid Effluent Treatment and Monitoring

Systems

NMP-EN-002, Actions for Potential Groundwater Contamination Events, Ver. 2.0

Current 10 CFR Part 50.75(g) File

Groundwater monitoring well sample results, 12/4/07 - 10/3/08

Section 2PS2: Radioactive Material Processing and Transportation

Attachment

12

Procedures, Instructions, and Guidance Documents

46200-C, Shipment of Radioactive Waste and Radioactive Material, Rev. 1.1

46100-C, 10 CFR 61 Waste Classification Sampling Program, Rev. 5.1

46106-C, Waste Classification Resin Shipments, Rev. 6.1

Vogtle Process Control Program, Rev. 8

Records and Data Reviewed

2007 Annual Radioactive Effluent Release Report

DAW Waste Stream Analyses, 2007 and 2008

RCS Filter Waste Stream Analysis, 2008

Shipments06-007, 07-017,07-019, 07-022,08-008

CAP Documents

VQA-2006-042, QA Audit of Chemistry and Radioactive Waste, 12/6/06

CR 2008110945, 2008107446, 2007105876, 2007105502

Section 1R20: Refueling and Other Outage Activities

Procedures

12005-C, Reactor Shutdown to Hot Standby (Mode 2 to Mode 3)

12006-C, Unit Cooldown to Cold Shutdown

12007-C, Refueling Operations

12001-C, Unit Heatup to Hot Shutdown

12002-C, Unit Heatup to Normal Operating Temperature

12003-C, Reactor Startup (Mode 3 to Mode 2)

14900-C, Containment Exit Inspection

Section 4OA1: Performance Indicator Verification

Procedures

Procedure No. 00163-C, NRC Performance Indicator and Monthly Operating Report

Preparation and Submittal, Rev. 13.2

Procedure No. 34331-C, Management of DRMS Status and Parameters, Rev. 24.1

Procedure No. 34333-C, Gaseous Effluent Monitor Setup For Releases, Rev. 7

Records and Data Reviewed

Access Control Alarms Report, August 2007 - September 2008

Personnel Contamination Event/Records January 1, 2008, through September 31, 2008

Gaseous waste permit 70250.020.048.G, Unit 1, Continuous Gaseous Effluent Permit

Gaseous waste permit 70256.025.098.G, Unit 1, Batch Gaseous Effluent Permit

Gaseous Permit No. G-20081006-298-C, Unit 1, Plant Vent Continuous Release

Gaseous Permit No. G-20081006-297-B, Unit 2 Containment Batch Release

Vogtle Annual Radioactive Effluent Release Report for 2007

CAP Documents

CR 2006111265, CR 2007112260, CR 2008109286

Section 4OA2: Identification and Resolution of Problems

Procedures/Calculations/Engineering Documents

10025-C, Work Around Program, Revision 3

Attachment

13

Unit 1 Operator Burdens and Workarounds List

Unit 2 Operator Burdens and Workarounds List

Condition Reports: 2008100397, 2008101130, 2008101535, 2008101550, 2008101570,

2008101792, 2008101829, 2008101855, 2008101914, 2008101946, 2008102012, 2008102019,

2008102031, 2008102047, 2008102059, 2008102078, 2008102128, 2008102161, 2008102189,

2008103582, 2008105478, 2008105657

Action Items: 2008201942 and 2008203528

Attachment