Environmental Scoping Meeting for V.C. Summer Subsequent License Renewal Application-Virtual Meeting Slides
ML23312A020
Person / Time
Site: Summer South Carolina Electric & Gas Company icon.png
Issue date: 11/08/2023
From: Kimberly Conway
NRC/NMSS/DREFS/ELRB
To:
References
Download: ML23312A020 (23)


Text

Environmental Scoping Meeting Related to the V.C. Summer Nuclear Station Subsequent License Renewal Application The webinar will begin shortly POC: Kimberly.Conway@nrc.gov ADAMS ML23312A020 1

Environmental Scoping Meeting Related to the V.C. Summer Nuclear Station Subsequent License Renewal Application November 9, 2023 Marieliz Johnson, Safety Project Manager Kim Conway, Environmental Project Manager 2

3 Agenda

  • Introduction and Purpose

Overview

  • Safety Review
  • Environmental Review
  • Questions on the NRC Presentation
  • Public Comments on Topics to be Included in the V.C. Summer SLR Environmental Review

4

Introductions

  • Marieliz Johnson, NRC, Office of Nuclear Reactor Regulation (NRR), Safety Review Lead
  • Kim Conway, NRC, Office of Nuclear Material Safety and Safeguards (NMSS), Environmental Review Lead

5 Meeting Logistics

  • The NRC is actively soliciting comments to aid the staffs environmental review
  • Public comments are sought at specific points during the meeting
  • No regulatory decisions will be made at todays meeting

6 V.C. Summer Subsequent License Renewal

  • The current Renewed License expiration date for V.C. Summer Unit 1 is August 6, 2042

Contents of Application

  • General information about the plant owner or operator
  • Technical information about plant structures and components and how the applicant proposes to manage plant aging
  • Environmental Report 7
  • If a Request for Hearing is Granted 8

Process Overview Subsequent License Renewal Application (SLRA) Accepted Safety Review Environmental Review Hearings*

ACRS Recommendation NRC Renewal Decision 10 CFR Part 54 10 CFR Part 51 10 CFR 54.25 10 CFR Part 2 10 CFR 54.29

9 Safety Review Milestones Acceptance Review In-Office Technical Review Audit On-Site Audit Breakout Audit Issue Audit Report Issue Safety Evaluation June 2025 October 2023 SLRA Accepted Safety Review Environmental Review Hearings*

ACRS Recommendation NRC Renewal Decision

Regulations and Guidance Licensing Oversight Operating Experience 10 Regulatory Process Support for Decisions Additional Aging Management

Environmental Review

  • National Environmental Policy Act (NEPA)

- Informs Federal decision making

- Public disclosure of environmental impacts and other considerations

Environmental Review (continued)

Consider, analyze, and disclose environmental impacts of continued plant operation and alternatives to license renewal Identify and asses new and significant information regarding generic conclusions reached in the Generic EIS for License Renewal (LR GEIS)

Staff evaluates site-specific issues in a Supplemental Environmental Impact Statement (SEIS) to the LR GEIS 12

Environmental Impact Statement (EIS)

  • Staff evaluates impacts to resources

- Fish and wildlife

- Water, air, terrestrial resources

- Historical and cultural resources

- Socioeconomics

- Environmental justice

- Human health

- Land use 13

Environmental Impact Statement 14

EIS Agency Coordination and Consultation 15

Scoping and Public Involvement 16

  • What about your community should the NRC consider in the EIS?
  • What local environmental issues should be addressed?
  • What other reasonable alternatives should be considered?

Environmental Review Milestones 17 Application Received August 17, 2023 Notice of Intent to Conduct Scoping November 3, 2023 Environmental Scoping Webinar TODAY In-Person Scoping Meeting (Blair, SC)

November 14, 2023 Scoping Comment Period Ends December 4, 2023 Draft EIS Issued November 2024 Draft EIS Public Meeting TBD Draft EIS Comment Period Ends January 2025 Final EIS Issued June 2025 License Renewal Decision August 2025

Project Manager Contacts

  • Marieliz Johnson, Safety PM

- 301-415-5861

- Marieliz.Johnson@nrc.gov

  • Kim Conway, Environmental PM

- 301-415-1335

- Kimberly.Conway@nrc.gov

- 301-415-2481

- Ed.Miller@nrc.gov 18

Documents NRC Website:

https://www.nrc.gov/reactors/operating/licensing/

renewal/applications/virgil-summer-subsequent.html 19 Fairfield County Library 300 West Washington St Winnsboro, SC 29180

Submitting Comments on the Scope of the Environmental Review

  • Provide written comments:
  • By mail:

Office of Administration Mailstop TWFN7A60M U.S. Nuclear Regulatory Commission Washington, DC 20555-0001

  • Website:

http://www.regulations.gov, Docket ID NRC-2023-0152

  • Email:

SummerEnvironmental@nrc.gov 20 Comments should be submitted by December 4, 2023 (within 30 days from the date of the Notice of Intent to Conduct Scoping Process and Prepare EIS Federal Register Notice [88 FR 75627])

Public Participation 21

  • Raise your hand
  • MS Teams: Raise my hand button
  • On the phone: Press *5
  • Youll still need to unmute:
  • MS Teams: Unmute button
  • On the phone: Press *6

Technical Issues 22

  • Drop off and log back on
  • Call into Bridgeline:
  • 301-576-2978
  • Passcode: 169511100#
  • Conference ID: 169511100#
  • In Teams, check your device settings:
  • Click More
  • Choose Settings
  • Choose Device Settings

Summary and Closeout

  • Comment period ends December 4, 2023
  • Comments will be considered by staff in the scoping summary report
  • Scoping participants will receive scoping summary report, to be issued before the draft EIS 23