ML040090432

From kanterella
Jump to navigation Jump to search
Draft IR 05000335-03-002 and IR 05000389-03-002 on 03-10-28/03, St. Lucie Nuclear Plant, Units 1 and 2. Violations Noted
ML040090432
Person / Time
Site: Saint Lucie  NextEra Energy icon.png
Issue date: 12/22/2003
From: Ogle C
NRC/RGN-II/DRS/EB
To: Stall J
Florida Power & Light Co
References
FOIA/PA-2003-0358 IR-03-002
Download: ML040090432 (25)


See also: IR 05000335/2003002

Text

May XX, 2003

Florida Power and Light Company

ATTN: Mr. J. A. Stall, Senior Vice President

Nuclear and Chief Nuclear Officer

P.O. Box 14000

Juno Beach, FL 33408-0420

SUBJECT: ST. LUCIE NUCLEAR PLANT - NRC TRIENNIAL FIRE PROTECTION

INSPECTION. REPORT 50-335/03-02 AND 50-389/03-02

Dear Mr. Stall:

On March 28, 2003, the U.S. Nuclear Regulatory' Commission (NRC) completed an inspection

at your St. Lucie Nuclear Plant, Units 1 and 2. The enclosed inspection report documents the

inspection findings, which were discussed on March 28, 2003, with Mr. D.Jemigan and other

members of your staff.

The inspection examined activities conducted under your license as they relate to safety and

compliance with the Commission's rules and regulations and with the conditions' of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed

personnel.

r

This report documents a finding concerning silicone oil-filled transformers in the B Switchgear

Room which had not been considered or evaluated in the licensee's fire hazards analysis. X

Additionally, a finding was identified concerning the use of manual operator actions outside the

main control room in lieu of physical protection of cables and equipment relied on to achieve

safe shutdown during a fire, without prior NRC approval, for areas designated as 10 CFR 50

Appendix R,Section III.G.2. These findings involved violations of NRC requirements and,

combined, have potential safety significance greater than very low significance. However, a

safety significance determination has not been completed. These findings did not present an

immediate safety concern.

. . .~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

In addition, the report documents one NRC-identified finding of very low safety significance.

(Green), which was determined to involve a violation of NRC requirements. However, because

of the very low safety significance and because it was entered into your corrective action

program, the NRC is treating this as a non-cited violation (NCV) consistent with Section VL.A of

the NRC Enforcement Policy. If you contest any NCV in this report, you should provide a

response within 30 days of the date of this inspection report, with the basis for your denial, to

the Nuclear Regulatory Commission, ATTN.: Document Control Desk, Washington DC 20555-

0001; with copies to the Regional Administrator Region II; the Director, Office of Enforcement, .'

United States Nuclear Regulatory Commission, Washington, DC 20555-0001; and the NRC

Resident Inspector at St. Lucie Nuclear Plant.

I P

FP&L 2

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and its

enclosure, and your response (if any) will be available electronically for public inspection in the

NRC Public Document Room or from the Publicly Available Records (PARS) component of

NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at

httn://www.nrc.oov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

Charles R. Ogle, Chief

Engineering Branch 1

Division of Reactor Safety

Docket Nos.: 50-335, 50-389

License Nos.: DPR-67, NPF-16

Enclosure: Inspection Report 50-335, 389/03-02

w/Attachment: Supplemental Information

cc w/encl: (See page 3)

I

FP&L 3

cc:

Senior Resident Inspector

St. Lucie Plant Mr. Don Mothena

U.S. Nuclear Regulatory Commission Manager, Nuclear Plant Support Services

P.O. Box 6090 Florida Power & Light Company

Jensen Beach, Florida 34957 P.O. Box 14000

Juno Beach, FL 33408-0420

Craig Fugate, Director

Division of Emergency Preparedness Mr. Rajiv S. Kundalkar

Department of Community Affairs Vice President - Nuclear Engineering

2740 Centerview Drive Florida Power & Light Company

Tallahassee, Florida 32399-2100 P.O. Box 14000

Juno Beach, FL 33408-0420

M. S. Ross, Attorney

Florida Power & Light Company Mr. J. Kammel

P.O. Box 14000 Radiological Emergency

Juno Beach, FL 33408-0420 :Planning Administrator

Department of Public Safety

Mr. Douglas Anderson 6000 SE. Tower Drive

County Administrator Stuart, Florida 34997

St. Lucie County

2300 Virginia Avenue Attorney General

Fort Pierce, Florida 34982 Department of Legal Affairs

The Capitol

Mr. William A. Passetti, Chief Tallahassee, Florida 32304

Department of Health

Bureau of Radiation Control 'Mr. Steve Hale

2020 Capital Circle, SE, Bin #C21 St. Lucie Nuclear Plant

Tallahassee, Florida 32399-1741 Florida Power and Light Company

6351 South Ocean Drive

Mr. Donald E. Jernigan, Site Vice President Jensen Beach, Florida 34957-2000

St. Lucie Nuclear Plant

6501 South Ocean Drive Mr. Alan P. Nelson

Jensen Beach, Florida 34957 Nuclear Energy Institute

-1776 I Street, N.W., Suite 400

Mr. R. E. Rose Washington,- DC 20006-3708

Plant General Manager APN@NEI.ORG

St. Lucie Nuclear Plant

6501 South Ocean Drive David Lewis

Jensen Beach, Florida 34957 Shaw Pittman, LLP

2300 N Street, N.W.

Mr. G. Madden Washington, D.C. 20037

Licensing Manager

St. Lucie Nuclear Plant Mr. Stan Smilan

6501 South Ocean Drive 5866 Bay Hill Cir.

Jensen Beach, Florida 34957 Lake Worth, FL 33463

U. S. NUCLEAR REGULATORY COMMISSION

REGION II

Docket Nos: 50-335, 50-389

License Nos: DPR-67, NPF-16

Report No: 50-335/03-02 and 50-389/03-02

Licensee: Florida Power and Light Company (FPL)

Facility: St. Lucie Nuclear Plant

Location: 6351 South Ocean Drive

Jensen Beach, FL 34957

Dates: March 10- 14, 2003 (Week 1)

March 24 - 28, 2003 (Week 2)

Inspectors: R. Deem, Consultant, Brookhaven National Laboratory

P. Fillion, Reactor Inspector

F. Jape, Senior Project Inspector

M. Thomas, Senior Reactor Inspector (Lead Inspector)

S. Walker, Reactor Inspector

G. Wiseman, Senior Reactor Inspector

Approved by: Charles R. Ogle, Chief

Engineering Branch 1

Division of Reactor Safety

.  ;

.. ..

.

.. 0 . . -. - . . . .. ..

.; S .

SUMMARY OF FINDINGS

IR 05000335/2003-002,0500038912003-002; Florida Power and Light Company; 03/10 -

28/2003; St. Lucie Nuclear Plant, Units ISand 2;Triennial Fire Protection

The report covered a two-week period of inspection by regional inspectors and a consultant.

Three Green non-cited violations (NCVs) and'one unresolved item with potential safety

significance greater than Green were'identified. The significance' of most findings is indicated

by their color (Green, White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609,

"Significance Determination Process" (SDP). Findings for which the SDP does not apply may

be Green or be assigned a severity level after NRC management review. The'NRC's program

for overseeing the safe operation of commercial nuclear power reactors is described in NUREG 1649, Reactor Oversight Process," Revision 3, dated July 2000.

A. NRC-ldentified and Self-Revealing Findings

Cornerstone: Initiating Events

  • TBD. The team identified a violation of 10 CFR 50.48 and the St. Lucie Nuclear

Plant Unit 2 Operating License Condition 2.C.(20), Fire Protection. The fire

' hazards analysis failed to consider and evaluate'the combustibility of 380 gallons

of transformer silicone dielectric insulating fluid in'each of six transformers

(installed in three Unit 2 fire areas) as contributors to fire loading and effects on

safe shutdown (SSD) capability, as required by Fire Protection Program

commitments.

This finding is'unresolved pending completion of a significance determination.

The finding is'greater than minor because'it affected the objective of the initiating

events cornerstone to limit the likelihood of those events that could upset plant

stability and challenge critical safety functions relied upon for SSD during a fire.

<The six previously unidentified silicone oil-filled transformers represented an

increase in the ignition frequency of the associated fire areas/zones. Also, when

assessed with other findings identified in this report, the significance could be

greater than very low significance. (Section 1R05.02.b(1))

Cornerstone: Mitigating Systems

TBD. A violation of 10 CFR 50, Appendix R, Section Ill.G.2, was identified for

failure to ensure that one train of equipment necessary to achieve and maintain

safe shutdown would be free of fire damage. Train A 480V vital load center 2A5

and associated electrical cables were located in the Train B switchgear room

(Fire Area C) without adequate spatial separation or fire barriers. This load

center powered redundant equipment (via motor control center 2A6 which

powered boric acid makeup pumps 2A and 2B) required for safe shutdown

(SSD) in the event of a fire. In lieu of providing adequate physical protection for

load center 2A5 and associated electrical cables, manual operator actions

outside the main control room (MCR) were relied on and credited, without prior

NRC approval, for achieving and maintaining SSD.

2

This finding is unresolved pending completion of a significance determination.

The finding was greater than minor because fire damage to the unprotected

cables could prevent operation of SSD equipment from the MCR and challenge

the operators' ability to maintain adequate reactor coolant system inventory and

reactor coolant pump seal flow during a fire in the B switchgear room. (Section

1R05.02.b(2))

Green. A non-cited violation of 10 CFR 50, Appendix R, Section III.G.2 was

identified concerning a lack of spacial separation or barriers to protect cables

against fire damage in containment could result in spurious opening of the

pressurizer power operated relief valve (PORV).

This finding is greater than minor because it affected the mitigating systems

cornerstone objective of equipment reliability, in that, spurious opening of the

PORV during post-fire safe shutdown would adversely affect systems intended to

maintain hot shutdown. The finding is of very low safety significance because

the initiating event likelihood was low, manual fire suppression capability

remained unaffected and all mitigating systems except for the PORV and block

valve were unaffected. (Section 40A5)

B. Licensee-identified Violations

One violation for which the significance has not been determined and two violations of

very low safety significance, which were identified by the licensee, were reviewed by the

inspection team. Corrective actions taken or planned by the licensee have been

entered into the licensee's corrective action program. These violations and corrective

action tracking numbers are listed in Section 40A7 of this report

... a...;jrr .

REPORT DETAILS

1. REACTOR SAFETY-,

Cornerstones: Initiating Events, Mitigating Systems and Barrier Integrity

1R05 FIRE PROTECTION

01. -Systems Required to Achieve and Maintain Post-Fire Safe Shutdown

a. Inspection Scope

The team evaluated the licensee's fire protection program against applicable

requirements, including Operating License Condition (OLC) 2.C.20, Fire Protection; Title

10 of the Code of Federal Regulations Part 50 (10 CFR 50), Appendix R; 10 CFR 50.48;

AppendixkA to Branch Technical Position (BTP) Auxiliary Systems Branch (ASB) 9.5-1,

Guidelines for Fire Protection for Nuclear Power Plants; related NRC Safety Evaluation

Reports (SERs); the Plant St. Lucie (PSL) Updated Final Safety Analysis Report

(UFSAR); and plant Technical Specifications (TS). The team evaluated all areas of this

inspection, as documented below, against these requirements. The team reviewed the

licensee's Individual Plant Examination for External Events (IPEEE) and performed in-

plant walk downs to choose three risk-significant fire areas for detailed inspection and

review. The three fire areas selected were:

  • Unit 2 Fire Area B - Cable Spreading Room (Fire Zone 52). A fire in this area

would involve alternate shutdown from outside the main control room (MCR).

  • Unit 2 Fire Area C - Train B Switchgear Room (Fire Zone 34) and Electrical

Equipment Supply Fan Room (Fire Zone 48). Fire Area C, including the

essential equipment and cables within, was evaluated by the licensee with

respect to the protection and separation criteria of 10 CFR 50, Appendix R,

Section III.G.2, to assure that the ability to safely shut down the plant was not

adversely affected by a single fire event. Train A equipment would be used to

achieve safe shutdown from the Unit 2 MCR during a fire in this area.

  • ' Unit 2 Fire Area I - Fire Zone 51 West (Cable Loft), Fire Zone 21 (Personnel

Rooms), Fire Zone 32 (PASS and Radiation Monitoring Room), Fire Zone

331 (Instrument Repair Shop), and Fire Zone 23 (Train B Electrical

Penetration Room). Fire Area , including the essential equipment and cables

within, was evaluated by'the licensee with respect to the protection and

separation criteria of 10 CFR 50, Appendix R, Section III.G.2, to assure that the

ability to safely shut down the plant Was'not adversely affected by a single fire

event. Train A equipment would be used to achieve safe shutdown from the Unit

2 MCR during a fire in this area.

The team reviewed the licensee's fire protection program (FPP) documented in the PSL

UFSAR (Appendix 9.5Aj Fire Protection Program Report); safe shutdown analysis

2

(SSA); fire hazards analysis (FHA); safe shutdown (SSD) essential equipment list; and

system flow diagrams to identify the components and systems necessary to achieve and

maintain safe shutdown conditions. The objective of this evaluation was to assure the

SSD equipment and post-fire SSD analytical approach were consistent with and

satisfied the Appendix R reactor performance criteria for SSD. For each of the selected

fire areas, the team focused on the fire protection features, and on the systems and

equipment necessary for the licensee to achieve and maintain SSD in the event of a fire

in those fire areas. 'Systems and/or components selected for review included the

pressurizer power operated relief valves (PORVs); boric acid makeup pumps 2A and

2B; boric acid gravity feed valves V2508 and V2509; auxiliary feedwater (AFW);

charging pumps and volume control tank outlet valve V2501; shutdown cooling; heating,

ventilation, and air conditioning (HVAC); atmospheric dump valves (ADVs); and

component cooling water. The team also reviewed the licensee's maintenance program

to determine if a sample of manual valves used to achieve SSD were included.

b. Findings

No findings of significance were identified.

.02 Fire Protection of Safe Shutdown Capability

a. Inspection Scooe

For the selected fire areas, the team evaluated the frequency of fires or the potential for

fires, the combustible fire load characteristics and potential fire severity, the separation

of systems necessary to achieve SSD, and the separation of electrical components and

circuits located within the same fire area to ensure that at least one train of redundant

safe shutdown systems was free of fire damage. The team also inspected the fire

protection features to confirm they were installed in accordance with the codes of record

to satisfy the applicable separation and design requirements of 10 CFR'50, Appendix R,

Section III.G, and Appendix A of BTP ASB 9.5-1. The team reviewed the'following

documents, which established the controls and practices to prevent fires and to control

combustible fire loads and ignition sources, to verify that the objectives established by

the NRC-approved FPP were satisfied:

  • PSL Individual Plant Examination of External Events (IPEEE)
  • Administrative Procedure 1800022, Fire Protection Plan
  • Administrative Procedure 0010434, Plant Fire Protection Guidelines
  • Electrical Maintenance Procedure 52.01, Periodic Maintenance of 4160 Volt (V)

Switchgear-'-;'

3

The team toured the selected plant fire areas to observe whether the licensee had

properly evaluated in-situ compartment fire loads and limited transient fire hazards in a

manner consistent with the fire prevention and combustible hazards control procedures.

In addition, the team reviewed fire protection inspection reports, corrective action

program condition reports (CRs) resulting from fire, smoke, sparks, arcing, and

equipment overheating incidents for the years 2001-2002, to assess the effectiveness of

the fire prevention program and to identify any maintenance or material condition

problems related to fire incidents. [

The team reviewed the fire brigade response, training, and drill program procedures.

The team reviewed fire brigade initial and continuing training course materials to verify

that appropriate training was being conducted. In addition, the team evaluated fire

brigade drill training records for the operating shifts from August 2001 - February 2003.

The reviews were performed to determine whether fire brigade drills had been

conducted in high fire risk plant areas and whether fire brigade personnel qualifications,

drill response, and performance met the requirements of the licensee's FPP.

The team walked down the fire brigade staging and dress-out areas in the turbine

building and fire brigade house to assess the condition of fire fighting and smoke control

equipment. The team examined the fire brigade's personal protective equipment, self-.

contained breathing apparatuses (SCBAs), portable communications equipment, and

various other fire brigade equipment to determine accessibility, material condition and

operational readiness of equipment. Also, the availability of supplemental fire brigade

SCBA breathing air tanks. and the caDabilitv for refill, was evaluated. In' addition;-the  ;

team' observed whethe'r emerency, exit lihtina was provided forersonnel evacuation

pathwavs tlthe outside exits as ientief inthe' National Fire"Protection Association

(NFPA :101. Life Safetv.Code and Occupational Safety and Heat -Administration

(OSHA)'Part'191O,-Occup a Safety ahd H alth Standards: This review also

tional

included an examination of backup emergency lighting units along pathways to, and.

within, the dress-out and staging areas in support of fire brigade operations during a fire- .

induced power failure.

Team members walked down the selected fire areas to compare the associated fire

fighting pre-fire strategies and drawings with as-built plant conditions. This was done to

verify that fire fighting pre-fire strategies and drawings were consistent with the fire I

protection features and potential fire conditions described in the UFSAR Fire Protection,

Program Report. Also, the team performed a review of drawings and engineering

calculations for fire suppression caused flooding associated with the floor and

equipment drain systems for the Train B switchgear room, the electrical equipment

supply fan room, and the Train B electrical penetration room. The review focused on

ensuring that those actions required for SSD would not be inhibited by fire suppression -.

activities or leakage from fire suppression systems.'

The team reviewed design control procedures to verify that plant changes were

adequately reviewed for the potential impact on the fire protection program, SSD

equipment, and procedures as required by PSL Unit 2 Operating License Condition

4

2.C(20). Additionally, the team performed an independent technical review of the

licensee's plant change documentation completed in support of 2002 temporary system

alteration (TSA) 2-02-006-3, which placed two exhaust fans on a fire damper opening

between the cable spreading room and the Train B switchgear room. This TSA was

evaluated in order to verify that modifications to the plant were performed consistent

with plant design control procedures.

b. Findinas

Fire Area C - Train B Switchgear Room

(1) Inadequate Fire Hazards Analysis

Introduction: A violation was identified concerning failure to meet the FPP requirements.

The team found that six silicone oil-filled transformers installed in three Unit 2 fire zones

[Fire Zone 37, Train A Switchgear Room; Fire Zone 34, Train B Switchgear Room; and

Fire Zone 47, Turbine Building Switchgear Room] were not evaluated in the FHA as

contributors to fire loading, and their effects on SSD capability, as required by the FPP.

Description: During a pre-inspection plant walk down on February 26, 2003, the team

found six Unit 2 indoor medium-voltage power transformers that were cooled and

insulated by a silicone-type fluid. The licensee provided the team with information from

the transformer vendor which indicated that the transformer insulating fluid was Dow

Corning (DC) 561, a dimethyl silicone insulating fluid. The team performed an

independent technical review of the licensee's engineering calculations and

maintenance documentation, transformer vendor technical information manual,

insulating fluid manufacturer information, Underwriters Laboratory (UL) and Factory

Mutual (FM) listing agencies' documentation, and Institute of Electrical and Electronics

Engineers.(IEEE) Standards.

The DC 561 technical manual described the DC 561 fluid as a silicone liquid that would

burn, but was less flammable than paraffin-type insulating oils. The technical manual

also stated that the DC 561 fluid had a flash point of 324 o, a total heat release rate,

'~~~~ 'a:-rii';'~+.i-'-;,.:jA*,- '-. .

- -' i .. '-.-z-I ' .,

in their FHfthe

(HRR) of 140 kw/m_ (ser ASTM E 1354-90). and a fire point of 357 oC.G!;g~;slL  ;~ d _

li6nse 'valuated thadeauaci of their fire areazone-and eectrdI'4rcwaVfire

barier stem (ERFBS encoIsure barrier features ased on the combustible hazard

conten andoverall fire oading, (analyzed fire durati) present' with n the c

area/zone. Based on the above, the team concluded that the transformer insulating fluid

was an in-situ combustible liquid that had not been accounted for nor evaluated in the

PSL FHA. Additionally, the team noted that the licensee had conducted an UFSAR

Combustible Loading Update evaluation in 1997. This evaluation, documented in PSL-

ENG-SEMS-97-070, failed to identify that the transformers in fire zone 37 contained

combustible silicone insulating fluid. Also, a PSL triennial fire protection audit

(documented in QA audit Report QSL-FP-01-07) conducted in 2001, reviewed the FHA

but did not identify any fire loading discrepancies.

5

The team determined that the previously unidentified six silicone oil-filled transformers

represented an increase in the ignition frequency 6f the associated fire areas/zones.

Also, the additional in-situ combustible fire load and fire severity represented by the

combustible transformer insulating fluid increased the likelihood of a sustained fire event

from a catastrophic failure of an effected transformer that may upset plant stability and

challenge critical safety functions during SSD operations.

The -T-E Unit Substation Transformers Instruction Manual recommended that the

dielectric insulating fluid be sampled annually and the dielectric strength of the fluid be

tested to ensure that it is at 26 KV or better. The licensee determined that except for

four tests conducted during the period 1990-1992, there were no records of the

transformers' fluid being sampled and tested. This issue was entered nto the'corrective

action program as CR 2003-0978 and will followed up by the NRC resident inspectors at

PSL.

Analysis: The team determined that this finding was associated with the protection

against external factors" attribute and affected the objective of the initiating events

cornerstone to limit the likelihood of those events that could upset plant stability and

challenge critical safety functions relied upon for SSD from'a fire, and is therefore

greater than minor. The six previously unidentified silicone oil-filled transformers in Unit

2 represented an increase in the ignition frequency of the associated fire areas/zones.

The finding was considered to have very low safety significance (Green) because it did

not involve the impairment or degradation of NRC approved fire protection features and

the overall SSD capabilities for the areas were evaluated by the licensee's SSA as

adequate to ensure SSD capability. However, when assessed in combination with other

findings identified in this report, the significance could be greater than very low

significance.

Enforcement: 10 CFR 50.48 states, in part, "Each operating nuclear power plant must

have a fire protection program that satisfies Criterion 3 of Appendix A to this part." PSL

Unit 2 Operating License NPF-16, Condition 2.C.(4) specifies, in part, that the licensee

implement and maintain in effect all provisions of the approved FPP as described in the

UFSAR for the facility and as approved-by the NRC letter dated July 17, 1984, and

subseq pplements. The approved FPP is maintained and documented in the

PSL UFSAR, Appendix 9.5A, Fire Protection Program Report.

The Fire Protection Program Report stated, in part, that the PSL fire protection program

implements the philosophy of defense-in-depth protection against fire hazards and

effects of fire on safe shutdown equipment. The PSL fire protection program is guided

by plant fire hazard analyses and by credible fire postulations. It further stated that the

FHA performed for PSL Unit 2 considered potential fire hazards and their possible effect

on safe shutdown capability. -,

PSL administrative fire protection procedure, 1800022, Section 8.3 states that the FHA

is an individual study of each plant's'design, potential fire hazards in the plant, potential

of those threats occurring, and the effect of postulated fires on safe shutdown capability.

I

6

Further, Section 8.7.1.A of this procedure stated that in-situ combustible features were

evaluated in the FHA as contributors to fire loading in the respective fire zones.

Contrary to the above, the FHA for fire zones 34, 37, and 47 was not adequate and did

not meet FPP commitments. Specifically, 380 gallons of in-situ combustible transformer

silicone dielectric insulating fluid in each of six transformers located in Unit 2 was not

considered nor evaluated in the FHA as contributors to fire loading and possible effects

on SSD capability. This condition was contrary to the requirements of the PSL FPP as

outlined in UFSAR, Section 9.5A, and therefore did not meet the requirements as set

forth in 10 CFR 50.48 and PSL OLC 2.C.(20).

Failure to evaluate in-situ cobustible'transformer silicoie' dielectric insulatinfljid as-a

contributor tofire ladind in the FHA. when assessed inriobination with other finding

identified inthis reDort. could b'e areatr than very low sicnificance ' This fir'dina has

been entered into the licensee s cective tion roaramr as condition reort (CR) 03-

0637

063 . Howeve~ 'ei' .. 'i't -_- t "'Th--"" " h-- dentified in this

-dI

rfi !dings

reDort. the' si6gificance could be areater tan verv low siificance -,Thlg firdinji Is,

unresolved !t6KURl)_ 50-389103-02-OX. Failud to, Evaluate 1n-sI[u C-6mbu-ibr

Transformer Dlelectrc Insulating Fluid a aContribtuto' Fl oig nh

FHA.

(2) Use of Manual Operator Actions Outside the MCR for 10 CFR 50. Appendix R.

Section III.G.2 Areas

.03 Post-Fire Safe Shutdown Circuit Analysis

a. Inspection Scope

The team reviewed how systems would be used to achieve inventory control, reactor

coolant pump seal protection; core heat removal and reactor coolant system (RCS)

pressure control during and following a postulated fire in the fire areas selected for

review. Portions of the licensee's Appendix R Safe Shutdown Analysis Report which

outlined equipment and components in-the chosen fire areas power sources, and their

respective cable functions and system flow diagrams were reviewed. Controtcircul

schematics were analyzed to identify and evaluate cables important to safe shutdown.

The team traced the routing of cables through fire areas selected for review by using

cable schedule, and conduit and tray drawings. The team walked down these fire areas

to compare the actual plant configuration to the layout indicated on the drawings. The

team evaluated the above information to determine if the requirements for protection of

control and power cables were met. The licensee's circuit breaker and fuse coordination

study was reviewed for adequate electrical scheme protection of equipment necessary

for safe shutdown. The following equipment and components were reviewed during the

inspection:

V1474 and V1475, Pressurizer PORVs

V1476 and V1477, Pressurizer Isolation Block Valves

7

  • MV-09-03 and MV-09-04, Feedwater Bypass Valves
  • V2501, VCT Discharge Outlet Valve
  • HCV-3625, Safety Injection Block Valve
  • P-1107/1108, Pressurizer Pressure for Hot Shutdown Panel
  • LI-1 104/1105, Pressurizer Level for Hot Shutdown Panel

LI-9113 / 9123, Steam Generator Level for Hot Shutdown Panel

SIAS Logic

. MCC 2A5/2A6 and relative feeds, 480 Volt Motor Control Center

. MCC 2B5/2B6 and relative feeds, 480 Volt Motor Control Center

. Load Center 2A5 480 Volt Switchgear

b. Findings

-.No findings of significance were identified.

04. Alternative Post-Fire Safe Shutdown Capabilitv

a. Inspection Scope

The cable spreading room, which was one of two alternate shutdown (ASD) fire areas

listed in the St. Lucie SSA for Unit 2, was selected for detailed inspection of post-fire

SSD capability. -Emphasis was placed on verification that hot and cold shutdown from

outside the control room could be implemented; and that transfer of control from the

main control room to the hot shutdown control panel (HSCP) and other equipment

isolation locations could be accomplished within the performance goals stated in 10.

CFR 50, Appendix R, Section lll.L.3.

-- ~__Electrical

- diagrams of power, control, and instrumentation cables required for ASD were

_-analyzed for fire induced faults that could defeat operation from the MCR or the HSCP.

The team reviewed the electrical isolation and protective fusing in the transfer circuits of

components (e.g., motor operated valves) required for post-fire SSD at the HSCP to

verify that the SSD components were physically and electrically separated from the fire

area. The team also examined the electrical circuits for a sampling of components

operable at the HSCP to ensure that a fire in the B Switchgear Room would not

adversely affect safe shutdown capability from the MCR. The team's review was

performed to verify that adequate isolation capability of equipment used for safe

shutdown implementation was in place, accessible, and that the hot shutdown control

panel was capable of controlling all the required equipment necessary to bring the unit

to a safe shutdown condition. This also included a review to verify that the shutdown

process met the performance goals of 10 CFR 50,Appendix R, Section lll.L.3 and

8

guidance in generic letter (GL) 86-10, by comparing it to the thermal hydraulic time line

analysis provided by the licensee.

b. Findings

No findings of significance were identified.

05. Operational Implementation of Post-Fire Safe Shutdown Capability

a. Inspection Scooe

The team reviewed off normal operating procedure 2-ONP-100.02, Control Room

Inaccessibility, Rev. 13B, the licensee's procedure for alternate safe shutdown, and

procedure 2-ONP-100.01, Response to Fire, Rev. 9, the licensee's operating procedure

for post-fire safe shutdown from the MCR. The review focused on ensuring that all

required functions for post-fire safe shutdown and the corresponding equipment

necessary to perform those functions were included in the procedures. The review also

examined the consistency between the operations shutdown procedures and other

procedure driven activities associated with post-fire safe shutdown (i.e., fire fighting

activities).

b. Findings

The team noted that the licensee had identified that manual operator actions outside the

MCR were credited and used in lieu of physical protection of cables and equipment

relied on for SSD during a fire without obtaining prior NRC approval. Use of manual

operator actions outside the MCR for 10 CFR 50, Appendix R, Section III.G.2 areas

(Fire Area C and Fire Area I for this inspection) without prior NRC approval was not in

accordance with the licensee's approved Fire Protection Program. The licensee

identified this-issue inCR 03-0153 prior to this inspection. This finding is More Than

Minor. This finding will'beUnresolvedpending ompleiion-ofthe SDP to determine the

risk associated with using manual operator actions in lieu physicafprotection 10 CFR -

50, Appendix R, Section IIL.G specified the need to identify equipment to achieve and

maintain safe shutdown functions, and the protection requirements for that equipment.

It also stated that one train of safe shutdown equipment should remain free of fire

damage for non-alternate shutdown (III.G.2) designated fire areas. Two of the three fire

areas inspected were so designated. In these areas, manual operator actions outside

the MCR were being used and credited in the SSA to achieve safe shutdown.

Determination of the licensing basis and required NRC exemption to use manual-

operations in lieu of protection for one shutdown train was addressed by another

inspection team member. The inspection team was also concerned whether all potential

spurious operations were properly accounted for in the shutdown procedures.

Subsequent review of the licensee's procedures for these areas did demonstrate that

manual actions required to mitigate spurious signals on both units were properly

dispositioned.

9

06. Communications -

a. Inspection Scone

The team reviewed plant communications to verify that adequate communications were

available to support unit shutdown and fire brigade duties. This included verifying that

site paging (PA), portable radios, and sound-powered phone systems were available

consistent with the licensing basis. The team reviewed the licensee's communications

features to assess whether they-were properly evaluated in the licensee's SSA

(protected from exposure fire damage) and properly integrated into the post-fire SSD

procedures. The team also walked down sections of the post-fire SSD procedures to

verify that adequate communications equipment would be available to support the SSD

process. The team also reviewed the periodic testing of the site fire alarm and PA

systems; maintenance checklists for the sound-powered phone circuits and amplifiers;

and inventory surveillance of post-fire SSD operator equipment to assess whether the

maintenance/surveillance test program for the communications systems was sufficient

to verify proper operation of the systems.

b. Findings

No findings of significance were identified.

07. Emergencv Lighting

a. Inspection Scope

The team reviewed licensee emergency lighting against the requirements of 10 CFR 50,

Appendix R, Section 1ll.J, to verify that eight hour emergency lighting coverage was

provided in areas where manual operator actions were required during post-fire safe

shutdown operations, including the ingress and egress routes. The team's review also

included verifying that emergency, lighting requirements were evaluated in the licensee's

SSA and properly integrated into the Appendix R safe shutdown procedures as

described in UFSAR Appendix 9.5A, Section 3.7. During plant walk downs of selected

areas where operators performed local manual actions defined in the post-fire SSD

procedures, the team inspected area emergency lighting units (ELUs) for operability and

checked the aiming of lamp heads to determine if adequate illumination was available to

correctly and safely perform the actions required by the procedures. The team also

inspected emergency lighting features along access and egress pathways used during

SSD activities for adequacy and personnel safety. The team checked the ELUs' battery

power supplies to verify that they were rated with at least an 8-hour capacity. In

addition, the team reviewed the manufacturer's information and the licensee's periodic

maintenance tests to verify that the ELUs were being maintained and tested in

accordance with the manufacturer's recommendations.

b. Findings - -

10

No findings of significance were identified.

08. Cold Shutdown Repairs

a. Inspection Scone

The team reviewed the licensee's SSA and existing plant procedures to determine if any

repairs were necessary to achieve cold shutdown, and if needed, the equipment and

procedures required to implement those repairs was available onsite.

b. Findings

No findings of significance were identified.

.09 Fire Barriers and Fire Area/Zone/Room Penetration Seals

a. Inspection Scope

The team walked down the selected fire zones/areas to evaluate the adequacy of the

fire resistance of barrier enclosure walls, ceilings, floors, and cable protection. The

team randomly selected several fire barrier features for detailed evaluation and

inspection to verify proper installation and qualification. This evaluation included fire

barrier penetration fire stop seals, fire doors, fire dampers, fire barrier partitions, and

Thermo-Lag electrical raceway fire barrier system (ERFBS) enclosures to ensure that at

least one train of SSD equipment would be maintained free of fire damage from a single

fire.

The team observed the material condition and configuration of the selected fire barrier

features and also reviewed construction details and supporting fire endurance tests for

the installed fire barrier features. This review was performed to compared the observed

fire barrier penetration seal and ERFBS configurations to the design drawings and

tested configurations. The team also compared the penetration seal and ERFBS ratings

with the ratings of the barriers in which they were installed.

The team reviewed licensing documentation, engineering evaluations of Generic Ltter

86-10 fire barrier features, and NFPA code deviations to verify that the fire barrier

installations met design requirements and license commitments. In addition, the team

reviewed surveillance and maintenance procedures for selected fire barrier features to

verify the fire barriers were being adequately maintained.

b. Findings

No findings of significance were identified.

.10 Fire Protection Systems. Features. and Eauipment

11

a. Inspection Scope

The team reviewed flow diagrams, electrical schematic diagrams, periodic test

procedures, engineering technical evaluations for NFPA code deviatidns,>operational

valve lineup procedures, and cable routing data for the power and'control circuits of the

electric motor-driven fire pumps and the'fire protection water supply system'yard mains.

The review was performed to assess whether the common fire protection water delivery

and supply components could be damaged or inhibited by fire-induced failures of

electrical power supplies or control circuits and subsequent possible loss of fire water

supply to the' plant. Additionally, team members walked down the' fire protection'- water

supply system piping and actuation valves for the selected fire areas to assess' the

adequacy of the system material condition, consistency of the as-built configuration with

engineering drawings, and operability of the system in accordance with applicable

administrative procedures and NFPA standards.

The team walked down accessible portions of the fire detection and alarm systems in

the selected fire areas to evaluate the engineering design and operation of the installed

configurations. The team also reviewed engineering drawings for fire detector spacing

and locations in the four selected fire areas for consistency with the licensee's fire

protection plan, engineering evaluations for NFPA code deviations, and the

requirements in NFPA 72A and 72D.

The team also walked down the selected fire zones/areas with automatic sprinkler

suppression systems installed to verify the-proper type, placement and spacing of the

heads/nozzles and the lack of obstructions. The team examined vendor information,

engineering evaluations for NFPA code deviations, and design calculations to verify that

the required suppression system density for each protected area was available.

The team reviewed the manual suppression standpipe and fire hose system to verify the

-adequacyof their design, installation, and operation for the selected fire areas. 'The

team examined design flow calculations and evaluations to verify that the required fire

hose water flow and sprinkler system density for each protected area were available.

The team checked a sample of manual fire hose lengths to'determine whether they

would reach the SSD equipment. Additionallyjthe team observed placement of the fire

hoses and extinguishers to assess consistency with the fire fighting pre-plan drawings.

b. Findings

No findings of significance were identified.-

4. Other Activities

40A2 Problem Identification and Resolution

a. 'Inspection'Scone -- . .

12

The team reviewed a sample of licensee audits, self-assessments, and plant condition

reports (CRs) to verify that items related to fire protection and safe shutdown were

appropriately entered into the licensee's corrective action program in accordance with

the licensee's quality assurance program and procedural requirements. The items

selected were also reviewed for classification and appropriateness of the corrective

actions taken or initiated to resolve the items.

The team reviewed the licensee's applicability evaluations and corrective actions for

selected industry experience issues related to fire protection. The operating experience

reports were reviewed to verify that the licensee's review and actions were appropriate.

The reports are listed in the List of Documents Reviewed Section.

b. Findings

No findings of significance were identified

40A3 Event Followu2

.1 (Closed) LER 50-335. 389/00-01, Outside Design Bases Appendix R Hi-Lo Pressure

Interface and Separation Issues.

On March 9, 2000, the licensee identified seven cases where the plant was not in

compliance with 10 CFR 50, Appendix R, Sections IlI.G.2.d and III.G.2. f. The first

case, involving the pressurizer PORVs, applied to Units 1 and 2, and is discussed in

Section 4AO5 of this report. The other six cases apply to Unit 2 only, and are discussed

as follows.

Shutdown cooling valves

Shutdown cooling valves V3652 and V3481 could spuriously open due to fire induced

cable-to-cable short circuits. The location of vulnerability was a pull box (JB-2031) in the

annulus region of-containment. The valves are motor operated type valves which are

de-energized by procedure during normal plant operation. The problem however is that

the power cables for both these valves were routed through a pull box together with

other three-phase power cables. Therefore, the potential existed for fire induced cable

to cable short circuiting which could inadvertently energize the motors to open these

valves. Both valves would have to open to have a problem. Opening of these valves

directly connects the RCS to piping that is not rated for RCS normal operating pressure.

Should the valves open when the RCS is at operating pressure, a pressure relief valve

would open and RCS coolant would flow from the RCS to the containment sump. This

situation is essentially a large break LOCA. Valve V3545 is a normally open motor

operated valve in series with V3652 and V3481. Theoretically, V3545 could be closed

by the operator to stop the outflow, but the cables for V3545 could have been damaged

by the same fire. The licensee resolved the problem by installing new power cables

using armored cable. This precluded the possibility of cable to cable short circuits.

13

Inspectors confirmed implementation of the modification through review of plant

modification PCM01028.

The reported condition was a violation of Appendix R requirements of more than minor

significance because it could adversely 'affect the equipment reliability objective of the

cornerstones of mitigating systems arid barrier integrity as described'above. Using

techniques described in NRC Procedure 0609, Appendix F, the inspectors determined

that the finding was of very low safety significance (Green). Specifically the SDP

worksheet for large break LOCA was evaluated. The conclusion was supported

'primarily by the negligible probability of the initiating event occurring and the fact that

cables for mitigating systems for LOCA are located outside containment. The'

enforcement considerations for this violation are given in Section 40A7.

Pressurizer pressure instrumentation affected by tray-conduit interaction'

Lack of 20-foot separation or a radiant heat shield between a cable tray and two

conduits in containment meant that a fire which could start in the cable tray due to cable

self ignition 'could result in damage'to a number of pressurizer'pressure instrumentation

loops.' PT-1105, PT-1106 and PT-1107 are in Cable tray L2224; and PT-I103, PT-1104

and PT-1108 are in conduits 25018Y and 23091A. PT-1107 and PT-1108'were the

instruments specified in the post-fire shutdown procedure. These instruments also

provide input to alarms, automatically initiate'automatic actions, provide permissives,

computer inputs,'input to calculations and indications of pressure at various locations.

The inspector reviewed the consequences and ramifications of instruments failing either

high or low. Also reviewed, was which pressurizer pressure instrumentations remain

unaffected by the fire.' This information was analyzed by the inspector, and it was

concluded that the affected instrumentation would not lead to any transient 'nor to

change in core damage frequency. The finding is therefore of very low safety

significance. As corrective action, conduits 25018Y and 23091Awere protected by a

radiant 'heat shield for twenty feet either side' of the tray L2224 by plant modification

PCM99104, Supplement 1. The licensee reports the fact that both channels of

pressurizer pressure instruments specified in the post-fire shutdown procedure could

have been affected by one fire represents a violation of 10 CFR 50, Appendix R, Section

IlIl, G, 2. Refer to Section 40A7 of this report for enforcement aspects.

Pressurizer level instrumentation affected by tray-conduit interaction

Lack of 20-foot separation or a radiant heat shield between a cable tray and two

conduits in containment meant that a fire which could start in the cable tray'due to cable

self ignition could result in damage toall pressurizer level instrumentation loops. LT-

111OX and LT-1105 are in tray L2213; and LT-111OY and LT-1104 are'in conduits

23320D and 23090A. LT-11I0X &Y were specified in the post-fire shutdown

procedure. It was determined that the failure mode for a short-circuit between the

twisted pair or open circuit caused by fire exposure of the signal wires was level fails

low: Level failing low initiates several automatic actions some of which tend to cause

level to rise and some of which cause level to fall. The de-energization of pressurizer

14

heaters dominates the situation and results in falling level. This leads to a reactor trip

with safety injection on low pressurizer pressure. When the safety injection pumps start,

the level will rise. Since the operator cannot see level, he may not turn off the safety

injection pumps. So it follows that the pressurizer will go solid. The post-fire safe

shutdown procedure directs the operator to place the PORVs in override due to

concerns about spurious opening. Therefore, rising level and concomitant pressure rise

would be relieved by the safety relief valves. To obtain the risk significance of the fire

induced failure of pressurizer level instrumentation, the SDP worksheet for stuck open

relief valve was evaluated. The results indicated the finding was of very low safety

significance (Green) for the same reasons mentioned in Section 4A05.1 which deals

with spurious opening of PORVs. The licensee reports the fact that both channels of

pressurizer level instruments specified in the post-fire shutdown procedure could have

been affected by one fire represents a violation of 10 CFR 50, Appendix R, Section I,

G, 2. Refer to Section 40A7 of this report for enforcement aspects.

Pressurizer level instrumentation affected by conduit to conduit interaction

Lack of 20-foot separation or a radiant heat shield between two conduits in containment

containing cables for redundant channels of pressurizer level instrumentation meant that

the separation requirements of Appendix R were not met. The location of the interaction

is in the annulus area at an elevation where there are no ignition sources other than the

cables themselves. It is not considered credible that low voltage, low energy,.

instrumentation circuits could self-induce cable ignition, and even if such occurred within

a conduit, the fire would not affect another conduit. The reported problem was a

violation of Appendix R requirements with regard to separation of cables. The

inspectors determined that, given the particular configuration at issue, it could not

credibly adversely affect any cornerstone. The licensee corrected the separation

problem by installing a radiant heat shield on one of the conduits per plant modification

PCM99104, Supplement 1. This licensee identified issue constitutes a violation of minor

significance that is not subject to enforcement action in accordance with Section IV of

the NRC's Enforcement Policy.

Circuits related to automatic pressurizer pressure control affected by conduit to conduit

interaction

Lack of separation or a radiant heat shield between certain conduits in containment

related to automatic pressurizer pressure control meant that the separation

requirements of Appendix. R were not met. The circuits involved were for the PORV

and the auxiliary spray isolation valves. The concern was that, if one fire could affect

both these circuits, two diverse subsystems designed to reduce pressure when

necessary may not function. There are other ways to reduce pressure, but the above

mentioned ones were the systems designated in the post-fire shutdown procedure for

this function. The location of the interaction is in the annulus area at an elevation where

there are no ignition sources other than the cables themselves. It is not considered

credible that a fire starting within one conduit would expand to affect other nearby

conduits. The reported problem was a violation of Appendix R requirements with regard

-' 15

to separation of cables. The inspectors determined that, given the particular

configuration at issue, it could not credibly adversely affect any cornerstone. The

licensee corrected the separation problem by installing a radiant heat shield on a

sufficient number of the conduits per plant modification PCM99104, Supplement 2. This

licensee identified issue constitutes a violation of minor significance that is not subject to

enforcement action in accordance with Section IV of the NRC's Enforcement Policy.

Radiant heat shields not installed per Appendix R accepted deviation

Inside containment in the area between the containment wall and the bioshield four

groups of cable trays are installed. There are five trays in each group. These trays run

horizontally along the circumference of the containment to carry cables from the

penetration area to their various ultimate destinations in the containment. Train B

cables are in trays near the containment wall, and Train A cables are in trays near the

bioshield. There is at least seven foot horizontal separation between these two sets of

trays in the area of interest. Both the Train A set and the Train B set consists of a group

running above the 45-foot elevation grating and a group running above the 23-foot

elevation grating. Examples of cable trays involved are instrumentation trays L2223

(Train A) and L2224 (Train B); or control trays C2223 (Train A) and C2224 (Train B).

According to the safety evaluation report each of the four groups should have had a

radiant heat shield installed directly below the group. This is actually an accepted

deviation, or exemption, from the requirement to have a heat shield between the

redundant cables. The licensee reported in the LER that the radiant heat shields below

the groups at the 45-foot elevation were not installed. The missing radiant heat shields

have now been installed per PCM01028.

The inspector evaluated the risk significance of the lack of radiant heat shield below the

-45-foot elevation groups of trays. The conclusion of this evaluation was that the

problem was of very low safety significance (Green). Some of the'dominant factors

considered were:

  • Fire brigade capability for a fire in containment was not impaired.

In-situ ignition sources were negligible, and transient ignition sources and

combustibles are not present during normal plant operation.

  • Only the top tray in each group'contains power cables (480 volt) carrying

sufficient energy capable of self ignition of IEEE 383 flame tested cable. Most of

the power cables in containment are not energized during normal plant

operation. These trays are solid metallic bottom and cover type trays. This

construction inherently limits the spread of internal tray fire, and effectively

provides a shield limiting the radiant heat energy.

  • . The target" cable trays have a minimum spatial separation of 15 feet vertical

and 7 feet horizontal from the potentially burning cable tray. The target trays

have solid metallic bottoms. Radiant energy flowing between source and target

I

16

is blocked to a great extent by intervening HVAC ducts, large pipes, tanks and

building steel. Hot gas layer is not a factor in the part of containment under

consideration.

  • The target cables would be instrumentation cables, and various scenarios

involving damage to these same instrumentation cables discussed in relation to

other findings within this report Section were shown to be of very low safety

significance.

  • A very similar configuration in the Unit 1 containment was analyzed by the

licensee and reviewed by the NRC in great detail, and found to be an acceptable

configuration from the fire protection viewpoint. The Unit 1 study had a safety

factor of at least two, which provides margin to account for geometry and other

unknown differences between the two units.

Failure to adhere to the configuration of cable trays and radiant heat shields described

in an exception to 10 CFR 50, Appendix R, Section Il.G.2 represents a licensee

identified violation. Refer to Section 4AO7 of this report for enforcement aspects.

.2 (Closed) LER 50-335/00-04, Pressurizer Level Instrumentation Conduit Separation

Outside Appendix R Design Bases

Lack of 20-foot separation or a radiant heat shield between a cable tray and a conduit in

Unit 1 containment meant that a fire which could start in the cable tray due to cable self

ignition could result in damage to all pressurizer level instrumentation. The discussion

of risk significance and requirements for this issue would be identical to the discussion

of essentially the same issue on Unit 2 in Section .1 above under the heading:

Pressurizer level instrumentation affected by tray-conduit interaction. Refer to Section

4AO7 of this report for enforcement aspects.

40A5 Other Activities

.1 (Closed) URI 335.389/99-08-03. PORV Cabling May Not be Protected from Hot-Shorts

Inside Containment -

Introduction: A Green NCV was identified for failure to comply with 10 CFR 50,

Appendix R,Section III, G, 2.d and f, related to spurious opening of the pressurizer

PORV.

Description: During conduct of an inspection in the area of fire protection (NRC

Inspection Report 50-335, 389/99-08, dated January 31, 2000) the inspectors identified

the possibility that the PORV cables inside containment were not protected from fire

induced cable to cable short circuits. The issue was identified through review of the

licensee's analysis. However, the analysis referred to a study which showed that the

cable to cable short circuit leading to spurious opening of the PORV was not credible.

Since the study could not be located at the time of the inspection, an unresolved item

17

was initiated to track this issue. Subsequently LER 50-335, 389/00-01 reported that the

pressurizer PORVs coOld open 'due to fire induced short circuits that could occur in a

cable tray in containment. In addition, cables for the associated block valve were routed

in the same cable tray. This meant the block valve may not be available to counter the

spurious opening of the PORV. Cables for one PORV and its block valve were in a tray

near the containment wall and cables for the other set were in a tray near the bioshield.

The condition applied to both units.

The licensee resolved the problem by'installing new PORV cables using armored cable.

This precluded the possibility of cable to cable short circuits. The potential for spurious

opening due to spurious pressure signal had already been offset by having the operator

place the control switch in override in'response to a fire in containment. Inspectors

confirmed the modification was implemented through review of plant modification

package PCM00059 (Unit 1) and PCM99104, Rev 4 (Unit 2).

LER 00-01 mentioned above also reported licensee identified findings in the area of

Appendix R. In addition, Unit 1 LER 00-04 reported similar problems. Refer to Section

40A3 for discussion of these findings.

Analysis: The finding was a performance deficiency because it represented a violation of

Appendix R requirements. It was considered greater than minor because it could

adversely affect the cornerstones of mitigating systems and barrier integrity. It affects

mitigating systems in the sense that systems designated for post-fire shutdown would

be adversely affected by an open PORV during the early stages of post-fire shutdown.

It affects the cornerstone of barrier integrity in the sense that a spuriously open PORV

represents a breach of the RCS pres'sure boundary which is one of the barriers. Using

techniques described in NRC Procedure 0609, Appendix F, the inspectors determined

that the finding was of very low safety significance (Green). Specifically,'the SDP

worksheet for stuck open relief valve was evaluated. A key factor leading to this

conclusion was that the initiating event likelihood was relatively low. It was less likely

than the likelihood for stuck open PORV due to non-fire induced causes. Manual

suppression -offines in the containment was in the normal state because the plant had

fire detectors, a fire plan and there were no-automatic valves in the water source that

could be affected by the fire'. Even though no credit coidbe given for-the block-valve, -'

other mitigating systems were unaffected. This was primarily due to the fact that the

associated cables were'all outside containment.

Enforcement: Because this-violation of 10 CFR 50, Appendix R, Section 1II,G.2.d. and f,

is of very low safety significance, has been entered into the CAP (CROO-0386) and the

problem has been corrected through a plant modification it is being treated as an NCV,

consistent with Section VL.A of the NRC Enforcement Policy. The number and title of

this NCV are: NCV 50-335,'389/03-02-01, Failure to Meet 10 CFR 50, Appendix R,

Section II, G, 2, for Protection of the PORV Cables in Containment.

40A6 Meetings

18

On March 28, 2003, the team presented the inspection results to Mr. D. Jernigan and

other members of your staff, who acknowledged the findings. The team confirmed that

proprietary information is included in this report.

40A7 Licensee-Identified Violations

The following findings of very low safety significance (Green) were identified by the

licensee and are violations of NRC requirements which meet the criteria of Section VI of

the NRC Enforcement Policy, NUREG-1600, for being dispositioned as NCVs.

Requirements, Subpart G, Fire protection of safe shutdown capability, requires

that for cables, that could prevent operation or cause maloperation due to hot

shorts, open circuits or shorts to ground, of redundant trains of systems

necessary to achieve and maintain hot shutdown conditions and located inside

noninerted containments, one of the following fire protection means shall be

provided:

1. Separation of cables of redundant trains by a horizontal distance of more

than 20-feet with no intervening combustibles or fire hazards; or

2. Separation of cables of redundant trains by a non-combustible radiant

energy shield.

Contrary to this, since the requirement became effective, the required fire

protection was not provided for the following redundant cables:

1. Shutdown cooling valves V3652 and V3481 on Unit 2.

2. Pressurizer pressure instrumentation PT-1 107 and PT-I 108 on Unit 2

3. Pressurizer level instrumentation LT-I11OX and LT-110Yon Unit.-I-& 2-_-

4.--- Cabl6s contained in cable trays L2223 (Train A) and L2224 (Train B)

These findings have been entered into the CAP (CR 99-1963, Rev. 2, and CR

00-0386), corrected by plant modifications, and are of very low safety

significance for reasons given in Sections 4AO3.1 and .2.

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee Personnel

D. Albritton, Assistant Nuclear Plant Supervisor

19

P. Barnes, Fire Protection Engineering Supervisor

R. De La Esprella, Site Quality Manager

B. Dunn, Site Engineering Manager

K. Frehafer, Licensing Engineer

J. Hoffman, Design Engineering Manager

D. Jernigan, Site Vice President

G. Madden, Licensing Manager

R. Maier, Protection Services Manager

R. McDaniel, Fire Protection Supervisor

T. Patterson, Operations Manager

R. Rose, Plant General Manager

V. Rubano, Engineering Special Projects Manager

S. Short, Electrical Engineering Supervisor

NRC Personnel

C. Ogle, Branch Chief

R. Rodriguez, Nuclear Safety Intern (Trainee)

T. Ross, Senior Resident Inspector

S. Sanchez, Resident Inspector

. I-