Category:Inspection Report Correspondence
MONTHYEARML24108A0632024-04-18018 April 2024 – Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML23216A1412023-06-30030 June 2023 August 2023 RP Inspection Document Request ML22251A3682022-09-0909 September 2022 Notification of an NRC Fire Protection Team Inspection (FPTI) (NRC Inspection Report 05000335 2022011, 05000389 2022011) and Request for Information (RFI) ML22077A3732022-03-22022 March 2022 Review of the Spring 2021 Steam Generator Tube Inspection Report IR 05000335/20170112017-04-18018 April 2017 Final Significance Determination of a White Finding; NRC Inspection Report 05000335/2017011 IR 05000335/20080072008-04-18018 April 2008 IR 05000335-08-007, IR 05000389-08-007, and IR 07200061-08-001, on 02/25/2008 - 03/14/2008, for St. Lucie, Units 1 and 2, and ISFSI, Inspector Notes IR 05000335/20074022007-07-26026 July 2007 Transmittal Letter for St. Lucie Nuclear Plant - NRC Security Inspection Report 05000335/2007402 and 05000389/2007402 - SGI Removed ML0708501102007-03-22022 March 2007 NRC Inspection Report No. 05000335,389/2007401 IR 05000335/20070012007-03-0101 March 2007 Annual Assessment Letter - St. Lucie Nuclear Plant (NRC Inspection Report 05000335, 389/2007001) IR 05000335/20064012007-01-18018 January 2007 NRC Inspection Report 05000335-06-401 and 05000389-06-401 IR 05000335/20060072006-11-24024 November 2006 IR 05000335-06-007, 05000389-06-007, Safeguards Information Removed IR 05000033/20060032006-07-27027 July 2006 IR 0500033-06-003, 05000389-06-003, on 04/01/2006 - 06/30/2006, St. Lucie, Units 1 & 2 ML0401608942003-12-22022 December 2003 Undated Input for St. Lucie Fire Protection Baseline Inspection on 03/10-14 and 24-28/2003 ML0401201012003-12-22022 December 2003 Undated Input for St. Lucie Fire Protection Baseline Inspection on 03/10-14 and 24-28/2003 ML0401200992003-12-22022 December 2003 Undated Input for St. Lucie Fire Protection Baseline Inspection on 03/10-14 and 24-28/2003 ML0400902832003-12-22022 December 2003 Undated Inspection Post-Inspection Debrief to Region II DRS Managers Regarding St. Lucie Triennial Fire Protection Inspection ML0401201042003-04-0404 April 2003 Input for St Lucie Inspection Report 03-02 IR 05000335/20020052002-05-21021 May 2002 IR 05000335/2002-005 & 05000389/2002-005, St. Lucie Nuclear Plant, Inspection on 04/15/2002-04/25/2002 Related to Identification & Resolution of Problems. No Findings of Significance Identified ML0209508842002-04-0505 April 2002 IR 05000335/2002-006, St. Lucie Nuclear Power Plant, Inspection on 03/14/2002-04/03/2002 Related to Fire Protection Unresolved Item 50-335, 389/98-201-09 IR 05000335/20010072002-03-0707 March 2002 IR 05000335/2001-007 & IR 05000389/2001-007 for Inspection on 02/01/2002 Related to Safety System Design & Performance Capability. No Violations Noted IR 05000335/20010052002-01-28028 January 2002 IR 05000335/2001-005 & IR 05000389/2001-005, St. Lucie, Units 1 & 2, Inspection on 09/30 - 12/29/2001 Related to Administrative & Engineering Controls. Non-cited Violation Noted 2024-04-18
[Table view] Category:Letter
MONTHYEARIR 05000335/20250102024-10-21021 October 2024 Notification of St. Lucie Plant Units 1 & 2 Comprehensive Engineering Team Inspection - U.S. Nuclear Regulatory Commission Inspection Report 05000335/2025010 and 05000389/2025010 ML24227A9702024-10-18018 October 2024 Letter to Kenneth Mack Dir, License and Reg Compliance, NextEra Energy, Inc Response to Request Re Engagement Re Sub License Renewal Environmental Review - St Lucie Nuclear Plant 1 and 2 L-2024-085, Refueling Outage SL1-32 Low Pressure Turbine Rotor Inspection Results2024-10-15015 October 2024 Refueling Outage SL1-32 Low Pressure Turbine Rotor Inspection Results L-2024-165, Report of 10 CFR 50.59 Plant Changes, Tests and Experiments Made2024-10-14014 October 2024 Report of 10 CFR 50.59 Plant Changes, Tests and Experiments Made L-2024-118, Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1)2024-10-0808 October 2024 Fleet License Amendment Request to Relocate Staff Qualifications from Technical Specifications to the Quality Assurance Topical Report (FPL-1) ML24255A3092024-09-30030 September 2024 SLRA - Revised SE Letter L-2024-155, Subsequent License Renewal Application, Third Annual Update2024-09-27027 September 2024 Subsequent License Renewal Application, Third Annual Update L-2024-158, Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-25025 September 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes 05000335/LER-2024-001, Unplanned Reactor Scram2024-09-25025 September 2024 Unplanned Reactor Scram IR 05000335/20240112024-09-18018 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000335/2024011 and 05000389/2024011 L-2024-136, Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-09-16016 September 2024 Supplement to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-138, License Amendment Request L-2024-138, Fuel Methodology Changes in Support of St. Lucie, Unit 2 Transition to 24-Month Fuel Cycles2024-09-11011 September 2024 License Amendment Request L-2024-138, Fuel Methodology Changes in Support of St. Lucie, Unit 2 Transition to 24-Month Fuel Cycles L-2024-148, Submittal of Offsite Dose Calculation Manual (Odcm), Revision 552024-09-0909 September 2024 Submittal of Offsite Dose Calculation Manual (Odcm), Revision 55 IR 05000335/20240052024-08-22022 August 2024 Updated Inspection Plan for St. Lucie, Units 1 & 2 - Report 05000335/2024005 and 05000389/2024005 L-2024-140, Cycle 28 Core Operating Limits Report2024-08-14014 August 2024 Cycle 28 Core Operating Limits Report L-2024-133, Snubber Program Plan Submittal2024-08-14014 August 2024 Snubber Program Plan Submittal L-2024-132, 2024 Population Update Analysis2024-08-13013 August 2024 2024 Population Update Analysis IR 05000335/20240022024-08-13013 August 2024 Integrated Inspection Report 05000335-2024002 and 05000389-2024002 L-2024-129, Relief Request (RR) 14. Limited Coverage Exams Due to Impractical Inservice Inspection Requirements - Fourth Ten-Year Inservice Inspection Program Interval2024-08-0707 August 2024 Relief Request (RR) 14. Limited Coverage Exams Due to Impractical Inservice Inspection Requirements - Fourth Ten-Year Inservice Inspection Program Interval 05000389/LER-2024-003, Unplanned Reactor Scram2024-08-0505 August 2024 Unplanned Reactor Scram ML24163A0012024-08-0505 August 2024 LTR-24-0119-1-1 Response to Nh Letter Regarding Review of NextEras Emergency Preparedness Amendment Review L-2024-121, Subsequent License Renewal Commitment 30 Revision2024-07-30030 July 2024 Subsequent License Renewal Commitment 30 Revision L-2024-123, Submittal of In-Service Inspection Program Owners Activity Report (OAR-1)2024-07-29029 July 2024 Submittal of In-Service Inspection Program Owners Activity Report (OAR-1) L-2024-125, Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes2024-07-24024 July 2024 Notice of Intent to Provide Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes ML24184B2822024-07-16016 July 2024 – Request to Use a Later Code Edition and Addenda of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI ML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan 05000389/LER-2024-002-01, Safety Injection Tank Vent Through Wall Leakage2024-07-11011 July 2024 Safety Injection Tank Vent Through Wall Leakage L-2024-110, Environmental Protection Plan Report, Unusual or Important Environmental Event - Manatee in Intake2024-07-10010 July 2024 Environmental Protection Plan Report, Unusual or Important Environmental Event - Manatee in Intake L-2024-114, Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal2024-07-10010 July 2024 Quality Assurance Topical Report (FPL-1 Revision 31 Annual Submittal L-2024-109, Schedule for Subsequent License Renewal Environmental Review2024-07-0303 July 2024 Schedule for Subsequent License Renewal Environmental Review ML24172A1562024-06-27027 June 2024 Relief Request - PSL2-I5-RR-01 Proposed Alternative to Amse Code XI Code Examination Requirements - System Leakage Test of Reactor Pressure Vessel Bottom Head and Class 1 and 2 Piping in Covered Trenches L-2024-104, Response to Request for Additional Information, St. Luce Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1 Extension of Inspection Interval for Reactor Pressure Vessel Welds from 102024-06-26026 June 2024 Response to Request for Additional Information, St. Luce Relief Request (RR) 7, Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1 Extension of Inspection Interval for Reactor Pressure Vessel Welds from 10 L-2024-097, Technical Specification Special Report2024-06-20020 June 2024 Technical Specification Special Report L-2024-102, Official Service List Update2024-06-19019 June 2024 Official Service List Update ML24149A2862024-06-12012 June 2024 NextEra Fleet - Proposed Alternative Frr 23-01 to Use ASME Code Case N-752-1, Risk-Informed Categorization and Treatment for Repair/Replacement Activities in Class 2 and 3 Systems Section X1, Division 1 (EPID L-2023-LLR-0009) - Letter L-2024-090, Revised Steam Generator Tube Inspection Reports2024-06-0404 June 2024 Revised Steam Generator Tube Inspection Reports IR 05000335/20244012024-06-0303 June 2024 Security Baseline Inspection Report 05000335/2024401 and 05000389/2024401 ML24135A0642024-05-17017 May 2024 Correction Letter - Amendment Nos. 253 and 208 Regarding Conversion to Improved Standard Technical Specifications L-2024-075, Notification of Improved Standard Technical Specifications (ITS) Implementation2024-05-13013 May 2024 Notification of Improved Standard Technical Specifications (ITS) Implementation IR 05000335/20240012024-05-10010 May 2024 Integrated Inspection Report 05000335/2024001 and 05000389/2024001 ML24127A0632024-05-0606 May 2024 Supplemental Information to License Amendment Request to Adopt Common Emergency Plan with Site-Specific Annexes L-2024-053, License Amendment Request L-2024-053, Updated Spent Fuel Pool Criticality Analysis2024-04-30030 April 2024 License Amendment Request L-2024-053, Updated Spent Fuel Pool Criticality Analysis L-2024-070, Cycle 32 Core Operating Limits Report2024-04-29029 April 2024 Cycle 32 Core Operating Limits Report L-2024-071, Cycle 27 Core Operating Limits Report2024-04-29029 April 2024 Cycle 27 Core Operating Limits Report ML24108A0632024-04-18018 April 2024 – Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection L-2024-056, Annual Radiological Environmental Operating Report for Calendar Year 20232024-04-17017 April 2024 Annual Radiological Environmental Operating Report for Calendar Year 2023 L-2024-064, Florida Power & Light Company - 10 CFR 50.46 - Emergency Core Cooling System SBLOCA 30-Day Report2024-04-17017 April 2024 Florida Power & Light Company - 10 CFR 50.46 - Emergency Core Cooling System SBLOCA 30-Day Report L-2024-054, 2023 Annual Environmental Operating Report2024-04-0909 April 2024 2023 Annual Environmental Operating Report ML24093A2612024-04-0202 April 2024 – Investigation Summary, Office of Investigations Case Number 2-2023-005 L-2024-047, Proposed Use of a Subsequent ASME Code Edition and Addenda2024-03-28028 March 2024 Proposed Use of a Subsequent ASME Code Edition and Addenda 2024-09-09
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24193A2432024-07-12012 July 2024 – Interim Audit Summary Report in Support of Review of License Amendment Requests Regarding Fleet Emergency Plan ML24192A2302024-07-10010 July 2024 003 Radiation Safety Baseline Inspection Information Request ML24108A0632024-04-18018 April 2024 – Notification of Inspection and Request for Information for NRC Problem Identification and Resolution Inspection ML24177A2512024-02-12012 February 2024 Acceptance Review for RR 7-Proposed Alternative - Extension of Inspection Interval for St. Lucie Unit 1 Reactor Pressure Vessel Welds from 10 to 20 Years ML24177A2532024-02-12012 February 2024 Request for Additional Information Relief Request RR 7, Alternative Examination of Reactor Vessel Welds for Florida Power & Light Company, St. Lucie Nuclear Plant, Unit 1 ML23243A9862023-08-31031 August 2023 NRR E-mail Capture - Draft RAIs for EP Staff Augmentation Times LAR (L-2022-LLA-0166) ML23226A0762023-08-14014 August 2023 NRR E-mail Capture - Request for Additional Information - St. Lucie Plant, Units 1 and 2 - Adopt 10 CFR 50.69 (L-2022-LLA-0182) ML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23254A4022023-01-24024 January 2023 RP Inspection_2023-001_Document Request ML22311A5582022-11-22022 November 2022 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request for Cep ML22325A0692022-11-18018 November 2022 RAI Set 4 ML22270A1482022-09-26026 September 2022 SLRA Second Round RAI Letter 2 - Class 1 Fatigue (Final) ML22217A0032022-08-0404 August 2022 SLRA Second Round RAI Letter 1) ML22217A0022022-08-0404 August 2022 Email from Brian Harris (NRC) to Robert Coffey (FPL) - St. Lucie SLRA Second Round RAI Letter 1) ML22193A0872022-07-11011 July 2022 Letter RAI Set 3 (Final) ML22133A0032022-05-12012 May 2022 SLRA Rai'S Set 1 ML22101A2322022-05-0202 May 2022 Summary of the Environmental Remote Audit Related to the Review of the Subsequent License Renewal Application Enclosure RCIs and RAIs ML22094A1672022-04-0101 April 2022 2022 St. Lucie POV Inspection Information Request ML22075A1212022-03-16016 March 2022 Stl Problem Identification and Resolution (Pi&R) Information Request Final Report ML21350A4262021-12-21021 December 2021 Supplemental Information Needed for Acceptance of Licensing Amendment Request Concerning Technical Specification Conversion to NUREG-1432, Revision 5 ML21119A3142021-04-28028 April 2021 Requests for Additional Information Regarding License Amendment Requests to Apply Risk Informed Completion Times (RICT) for the 120-Volt AC (EPID L-2020-LLA-0283) (Email) ML21063A3192021-03-0404 March 2021 Request for Additional Information Regarding Relief Request RR 15 - Extension of RPV Welds from 10 to 20 Years ML20092G3442020-04-0101 April 2020 RAIs for LAR to Revise Technical Specifications 6.8.4.o, Reactor Coolant Pump Flywheel Inspection Program ML20094G2022020-03-30030 March 2020 Request for Additional Information Regarding License Amendment Request to Adopt EAL Schemes Pursuant to NEI 99-01 (L-2019-LLA-0210) ML19225D3152019-08-13013 August 2019 NRR E-mail Capture - St. Lucie Plant, Unit No. 2, Request for Additional Information Regarding License Amendment Request to Relocate the MOV Thermal Overload Bypass Devices (L-2019-LLA-0106) ML19218A2742019-08-0606 August 2019 Notification of Inspection and Request for Information ML19193A1982019-07-12012 July 2019 Emailed St. Lucie Heat Sink RFI ML19192A1372019-07-11011 July 2019 NRR E-mail Capture - Request for Additional Information - St. Lucie Plant, Unit No. 2, Fall 2018 Refueling Outage Steam Generator Tube Inspection Report ML19192A1352019-06-25025 June 2019 NRR E-mail Capture - Draft Request for Additional Information - St. Lucie Plant, Unit No. 2, Fall 2018 Refueling Outage Steam Generator Tube Inspection Report ML19151A8312019-05-31031 May 2019 NRR E-mail Capture - St. Lucie Plant, Unit Nos. 1 and 2, Request for Additional Information Regarding Emergency Diesel Generator Surveillance Requirement Amendment Request ML19151A5092019-05-21021 May 2019 NRR E-mail Capture - Draft Request for Additional Information - St. Lucie Plant, Unit Nos. 1 and 2 Emergency Diesel Generator Surveillance Requirement Amendment Request ML19109A1392019-04-18018 April 2019 NRR E-mail Capture - St. Lucie Plant, Unit No. 2, Request for Additional Information Regarding the License Amendment Request Pertaining to the Iodine Removal System ML19053A2242019-02-0101 February 2019 NRR E-mail Capture - St. Lucie Plant Unit No. 1 - Draft Request for Additional Information Related to Relief Request 6 Regarding the Refueling Water Tank Bottom Liner ML18296A2052018-10-22022 October 2018 NRR E-mail Capture - St. Lucie Plant, Unit No. 2, Request for Additional Information Regarding License Amendment Request to Reduce the Number of Control Element Assemblies (EPID L-2018-0181) L-2018-018, St. Lucie Plant, Unit No. 2, Request for Additional Information Regarding License Amendment Request to Reduce the Number of Control Element Assemblies (EPID L-2018-0181)2018-10-22022 October 2018 St. Lucie Plant, Unit No. 2, Request for Additional Information Regarding License Amendment Request to Reduce the Number of Control Element Assemblies (EPID L-2018-0181) ML18197A4112018-08-0101 August 2018 Supplemental Information Needed for Acceptance of Requested Licensing Action License Amendment Request to Reduce the Number of Control Element Assemblies ML18019A0712018-01-18018 January 2018 NRR E-mail Capture - Request for Additional Information - St. Lucie Inop AFW Steam Supply LAR (L-2017-LLA-0296) ML17331B1532017-11-27027 November 2017 NRR E-mail Capture - Request for Additional Information - St. Lucie IST Relief Request #5 - PR-01 (L-2017-LLR-0113) ML17277A3692017-10-0404 October 2017 NRR E-mail Capture - Request for Additional Information - St. Lucie Rict LAR - MF5372/MF5373 ML17152A1842017-06-0101 June 2017 Request for Additional Information - RPS Rate of Change and LCO Change LAR (CACs MF9119 9120) ML16356A1432016-12-20020 December 2016 Notification of Inspection and Request for Information ML16326A0092016-11-18018 November 2016 NRR E-mail Capture - Request for Additional Information Re. Nextera/Fpl LAR to Adopt TSTF-545 - CACs MF8203, MF8204, MF8208, and MF8209 ML16308A3232016-11-0303 November 2016 NRR E-mail Capture - Request for Additional Information - St. Lucie EDG Day Tank LAR - MF8006 ML16292A8212016-10-14014 October 2016 Emergency Preparedness Inspection and Request for Information ML17003A0452016-10-11011 October 2016 NRR E-mail Capture - (External_Sender) FW: St. Lucie Response to RAI on SL2-22 SG Tube Inspection Report (MF7604) ML16244A2602016-08-26026 August 2016 Notification of Inspection and Request for Information ML16155A3502016-06-0303 June 2016 Notification of Inspection and Request for Information ML16089A0052016-03-28028 March 2016 NRR E-mail Capture - Request for Additional Information - St. Lucie Srxb Mtc Surv - MF7269 & MF7270 ML16077A1062016-03-17017 March 2016 NRR E-mail Capture - Request for Additional Information - St Lucie Vacuum Gothic LAR - MF6980/MF6981 ML16068A2612016-03-0808 March 2016 NRR E-mail Capture - Request for Additional Information - St Lucie TSTF-422 - MF6683/MF6684 2024-07-12
[Table view] |
Text
Bob Coffey Executive Vice President Nuclear Division and Chief Nuclear Officer Florida Power & Light Company 700 Universe Blvd Mail Stop: EX/JB Juno Beach, FL 33408
SUBJECT:
SAINT LUCIE UNITS 1 AND 2 - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION FOR NRC PROBLEM IDENTIFICATION AND RESOLUTION INSPECTION
Dear Bob Coffey:
The purpose of this letter is to notify you that the U.S. Nuclear Regulatory Commission (NRC)
Region II staff will conduct a problem identification and resolution (PI&R) inspection at Saint Lucie Units 1 and 2 during the weeks of June 10-14, 2024, and June 24-28, 2024. The inspection team will be led by Ms. Natasha Childs, a Senior Project Engineer from the NRCs Region II office. This inspection will be conducted in accordance with baseline inspection procedure (IP) 71152, Problem Identification and Resolution, issued October 31, 2023.
The biennial PI&R inspection and assessment of Saint Lucies corrective action program (CAP) complements and expands upon the resident baseline inspections of routine daily screening of all corrective action program issues, quarterly focused issue reviews, and semiannual trend PI&R reviews.
On April 10, 2024, Ms. Childs confirmed the initial arrangements for the two-week inspection with Mr. Tim Falkiewicz of Florida Power and Light (FPL).
The enclosure lists documents that will be needed prior to the inspection. Unless otherwise noted, please have the referenced information available no later than May 24, 2024. Contact Ms. Childs with any questions concerning the requested information. The inspectors will try to minimize your administrative burden by specifically identifying only those documents required for inspection preparation. If additional documents are needed, they will be requested when identified.
Prior to the on-site inspection, Ms. Childs will discuss with your staff, the following inspection support administrative details: availability of knowledgeable plant engineering and licensing personnel to serve as points of contact during the inspection; method of tracking inspector requests during the inspection; access to licensee computers; working space; arrangements for site access; and other applicable information.
April 17, 2024 B. Coffey 2 In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Thank you for your cooperation in this matter. If you have any questions regarding the information requested or the inspection, please contact Ms. Childs at (404) 997-4559 or the resident inspectors.
Sincerely, Ryan C. Taylor, Acting Chief Reactor Projects Branch 3 Division of Reactor Projects Docket No.: 05000335 and 05000389 License No.: DPR-67 and NPF-16
Enclosure:
Information Request for Saint Lucie PI&R Inspection cc: Distribution via ListServ PAPERWORK REDUCTION ACT STATEMENT This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, control number 3150-0011.
PUBLIC PROTECTION NOTIFICATION The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Office of Management and Budget control number.
Signed by Taylor, Ryan on 04/17/24
B. Coffey 3
SUBJECT:
SAINT LUCIE UNITS 1 AND 2 - NOTIFICATION OF INSPECTION AND REQUEST FOR INFORMATION FOR NRC PROBLEM IDENTIFICATION AND RESOLUTION INSPECTION - DATED APRIL 17, 2024
DISTRIBUTION:
S. Bruneau, RI R. Reyes, RII M. Riley, RII R2EICS RIDSNRRPMStLucie Resource RIDSNRRDRO Resource
ADAMS ACCESSION NUMBER: ML24108A63 SUNSI Review Non-Sensitive Publicly Available Sensitive Non-Publicly Available OFFICE RII: DRP RII: DRP NAME N. Childs R. Taylor DATE 4/17/24 4/17/24
OFFICIAL RECORD INFORMATION REQUEST FOR THE SAINT LUCIE PROBLEM IDENTIFICATION & RESOLUTION (PI&R) INSPECTION (JUNE 10-14, 2024 AND JUNE 24-28, 2024)
Note: Unless otherwise noted, the information requested below corresponds to documents generated since April 1, 2022. Please provide the requested documents in electronic format. If the information is not available in electronic format, please contact the inspection team leader to coordinate other available methods to provide the information.
- 1. Copies of the corporate and site level procedures and sub-tier procedures associated with the corrective action program (CAP). This should include procedures related to:
a) Corrective action process b) Cause evaluation c) Operating experience program d) Employee concerns program e) Self-assessment program f) Maintenance rule program and implementing procedures g) Operability determination process h) Degraded/non-conforming condition process (e.g., RIS 2005-20) i) System health process or equivalent equipment reliability improvement programs j) Preventive maintenance deferral process k) Work management (i.e., work orders and requests)
If any of the procedures requested above were revised after April 1, 2022, please provide (or have available) copies of all revisions during the on-site inspection.
- 2. Please provide by May 10, 2024, a list of top ten risk-significant systems, top ten risk-significant components for each one of the top ten risk-significant systems, and top ten risk-significant operator manual actions.
- 3. List of all Action Requests (ARs) initiated, including the following information for each AR:
a) AR number and initiation date b) Brief, but complete problem description c) Priority or level d) Affected system e) Affected component f) Responsible plant department g) AR status
Provide this list in a format compatible with spreadsheet software (i.e., Excel example shown below) and ensure the list is searchable and can be filtered by system.
AR # Initiation Problem Priority System Component Org Status Date AR001 1/1/2022 A RHR Pump 2 RHR 2-RHR-PMP-ENG Open failed flow A
Enclosure
- 4. List of outstanding corrective actions including the following information for each action:
a) Corrective action number b) Corrective action type (e.g., corrective action to prevent recurrence, enhancement, maintenance rule evaluation, etc.)
c) Brief, but complete corrective action description d) Associated AR number e) Affected system f) Corrective action initiation date g) Number of extensions h) Corrective action due date i) Corrective action status
Provide this list in a format compatible with spreadsheet software (i.e., Excel example shown below) and ensure the list is searchable and can be filtered/sorted.
Corrective Type Description AR System Initiation Extensions Due Status Action # Date Date 001 CAPR Revise AR0058 RHR 01/05/22 2 06/15/24 Awaiting Procedure review NGK-003-4585
- 5. List of control room deficiencies with a brief, but complete description with corresponding AR and/or work order (WO) number and affected system, ensure the list is searchable and can be filtered/sorted.
- 6. List of operator workarounds and operator burdens with a brief, but complete description with corresponding AR number and affected system, ensure the list is searchable and can be filtered/sorted.
- 7. List of all currently extended or overdue ARs, ensure the list is searchable and can be filtered/sorted and includes the following information:
a) AR number b) AR initiation date c) Priority or Significance d) Affected system e) AR title and short description
- 8. List of all ARs that have been voided, canceled, or deleted. Ensure the list is searchable and can be filtered/sorted. Provide the following information for each AR:
a) AR number b) Affected system c) Brief, but complete problem description d) Reason voided, canceled, or deleted
2
- 9. List of all structures, systems, and components (SSCs) which were classified as (a)(1) in accordance with the maintenance rule since April 1, 2022. Include the following information for each system in (a)(1):
a) Date of classification in (a)(1) b) Reason for being placed in (a)(1) c) Copy of the (a)(1) evaluation d) Planned actions and their status
10.List of Maintenance Preventable Functional Failures (MPFFs) of risk-significant systems, including actions completed and current status.
11.List of corrective and deficient maintenance WOs that is searchable and can be filtered/sorted. Include the following information for each WO:
a) WO number b) Brief, but complete work description c) Affected system and components d) Date of initiation e) Date of completion (if completed) f) Associated AR (if applicable)
Provide this list in a format compatible with spreadsheet software (i.e., Excel example shown below) and ensure the list is searchable and can be filtered/sorted.
Work Description System Component Initiation Completion Status Order # Date Date WO01345 Replace breaker SI 2A-SI-PMP, 01/05/21 03/15/22 Closed 2A-BKR-08-BB4 for BKR-08-BB4 2A SI Pump.
- 12. Corrective action closeout packages, including ARs with description of corrective actions, for all NRC findings and licensee-identified violations (LIVs). Include a cross-reference linking NRC finding numbers and LIVs to appropriate AR numbers.
- 13. Corrective action closeout packages, including ARs with description of corrective actions, for all licensee event reports (LERs) submitted. Include a cross-reference linking LER number to appropriate AR number.
- 14. List of all NRC generic communications (e.g., Information Notices, Generic Letters, etc.) and industry operating experience (OpE) documents (e.g., Part 21 reports, vendor information letters, information from other sites, etc.) evaluated by the site for applicability to the station, regardless of the determination of applicability. Include the reference number (e.g., AR number) for the documents that evaluated the aforementioned OpE information.
- 15. Copies of all quality assurance audits and/or assessments issued, including the last two audits/assessments of the CAP.
- 16. Copies of all department self-assessments.
3
- 17. Copy of the most recent integrated plant trend report, departmental trend reports, and corrective action trend reports, including any human performance and equipment reliability trends.
18.Copy of the latest CAP statistics (if exists) such as the number of ARs initiated by department, human performance errors by department, and others as may be available.
19.List of routine meetings involving the CAP (including, but not limited to CAP screening, maintenance rule, operating experience, etc.) to be held during the on-site inspection weeks.
- 20. List of ARs related to equipment aging issues in the top ten risk-significant systems initiated since April 1, 2019 (e.g., system erosion and/or corrosion problems; electronic component aging or obsolescence of circuit boards, power supplies, relays, etc.; environmental qualification). Provide the following information for each AR, in a format compatible with spreadsheet software and ensure the list is sortable and searchable:
a) AR number b) AR initiation date c) Priority d) AR problem description
- 21. If performed, provide all recent self-assessments of the sites safety culture.
- 22. Copies of CAP documents related to cross-cutting issues (human performance, problem identification and resolution, and safety conscious work environment) identified via trending, self-assessments, safety review committee or other oversight methods.
- 23. List of all root cause, apparent cause, common cause and related or similar equipment cause evaluations with a brief description.
- 24. Copy of probabilistic risk assessment importance measures report, if available.
- 25. Please provide by May 29, 2024, and following notification of system selections, system health reports, system design basis documents, maintenance rule functions and status, and system description information.