ML023450244

From kanterella
Jump to navigation Jump to search
Ltr. to Stephen M. Quennoz from Ken E. Brockman NRC Unresolved Item 50-344/0202-01 & Confirmatory Survey of Containment
ML023450244
Person / Time
Site: Trojan File:Portland General Electric icon.png
Issue date: 12/11/2002
From: Brockman K
Division of Nuclear Materials Safety IV
To: Quennoz S
Portland General Electric Co
References
+sispmjr200507, -RFPFR IR-02-002, IR-02-003
Download: ML023450244 (13)


See also: IR 05000344/2002002

Text

December 11, 2002

Stephen M. Quennoz, Vice President

Power Supply/Generation

Portland General Electric Company

Trojan Nuclear Plant

71760 Columbia River Highway

Rainier, Oregon 97048

SUBJECTS: (1) NRC UNRESOLVED ITEM NO. 50-344/0202-01

(2) CONFIRMATORY SURVEY OF CONTAINMENT

Dear Mr. Quennoz:

This refers to the subject Unresolved Item that was identified during the May 13-16, 2002,

inspection (NRC Inspection Report 50-344/2002-02) and the confirmatory survey that was

conducted during the August 5-15, 2002, inspection (NRC Inspection Report 50-344/2002-03).

During the May 2002 inspection, the NRC reviewed your staffs downward reclassification of

certain final survey units from the classification specified for these units in your approved

License Termination Plan (LTP). Although your license prohibits you from reducing scan

coverages for a given survey unit class, the License Termination Plan does not specifically

address downward reclassification of survey units; a condition which directly impacts scan

coverage for the reclassified survey unit. This issue was identified as an Unresolved Item. An

Unresolved Item is a matter about which more information is required to determine whether the

issue in question is an acceptable item, a deviation, a nonconformance, or a violation of NRC

requirements.

In reviewing the Unresolved Item, the NRC conducted a detailed review of your LTP, associated

implementing procedures, final survey results, NRCs confirmatory survey results as well as

interviews with personnel. In addition, the NRC met with Portland General Electric Company

(PGE) on July 10, 2002 to discuss the Unresolved Item and the issue of criteria for requiring

prior NRC approval for future final radiological survey activities. In response to the NRCs

concerns, your staff agreed to take several actions including providing NRC with advance

written notification of a proposed downward reclassification of a survey unit. Details of this

proposal were provided in PGEs letter to the NRC dated October 17, 2002. Consequently,

based on our further review of this matter, and consistent with your October 17, 2002 letter, we

consider Unresolved Item 50-344/0202-01 to be closed. A summary of our review of this item is

included in Enclosure 1 to this letter.

During the August 2002 inspection, the NRC conducted a confirmatory survey of the interior of

the containment structure. This survey was conducted by Oak Ridge Institute for Science and

Education, Environmental Survey and Site Assessment Program (ORISE/ESSAP), on behalf of

the NRC. As documented in the final ESSAP report, the confirmatory survey verified the

Portland General Electric Company -2-

radiological conditions of containment as reported by PGE and indicated that survey units were

classified appropriately as defined in NUREG-1575, Multi-Agency Radiation Survey and Site

Investigation Manual (MARSSIM), with one exception. NRC analysis of selected portions of the

confirmatory survey are provided in Enclosure 2 to this letter, and the final ESSAP report is

provided as Enclosure 3.

In the near future, PGE is expected to submit a final status survey report for the containment

structure interior to the NRC for review. The information provided in that report, as well as

information provided in the final ESSAP report and NRC inspections, will be used in the NRCs

determination of whether to approve the release of the containment structure for unrestricted

use. This decision will be provided to you under separate correspondence at a later date.

In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter, its

enclosure, and your response (if any) will be made available electronically for public inspection

in the NRC Public Document Room or from the Publicly Available Records (PARS) component

of NRCs document system (ADAMS). ADAMS is accessible from the NRC Web site at

http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

If you have any questions concerning this inspection, please contact D. Blair Spitzberg, Ph.D.,

Chief, Fuel Cycle & Decommissioning Branch, at (817) 860-8191, or Mr. Robert J. Evans,

Senior Health Physicist, at (817) 860-8234.

Sincerely,

/RA MRShaffer Acting for/

Ken E. Brockman, Director

Division of Nuclear Materials Safety

Docket No.: 50-344

License No.: NPF-1

Enclosures:

1. Unresolved Item 50-344/0202-01

2. Confirmatory Survey of Containment

3. Confirmatory Survey of the Containment Building,

ORISE/ESSAP Report

cc w/Enclosures 1 & 2:

Lansing G. Dusek

Manager, Plant Support

Portland General Electric Company

Trojan Nuclear Plant

71760 Columbia River Highway

Rainier, Oregon 97048

Portland General Electric Company -3-

Chairman

Board of County Commissioners

Columbia County

St. Helens, Oregon 97501

David Stewart-Smith

Oregon Office of Energy

625 Marion Street NE

Salem, Oregon 97301

Lloyd K. Marbet

19142 S.E. Bakers Ferry Road

Boring, Oregon 97009

Jerry Wilson

Do It Yourself Committee

570 N.E. 53rd

Hillsboro, Oregon 97124

Eugene Roselie

Northwest Environment Advocates

133 S.W. 2nd Avenue

Portland, Oregon 97204

Douglas Nichols, Esq.

Vice President, General Counsel

and Secretary

Portland General Electric Company

121 SW Salmon Street

Portland, Oregon 97204

Michael B. Lackey

General Manager, Trojan

Portland General Electric Company

Trojan Nuclear Plant

71760 Columbia River Highway

Rainier, Oregon 97048

Portland General Electric Company -4-

bcc w/enclosure (via ADAMS distrib):

EWMerschoff

KEBrockman

DBSpitzberg

JLMinns, NRR/DLPM/PDIV-1

SWBrown, NMSS/DWM/DCB

SXSchneider, NMSS/DWM/DCB

JCDehmel, NMSS/DWM/DCB

CMCraig, NMSS/DWM/DCB

DTDiec, NRR/DSSA/SPLB

RJEvans

EMGarcia

FCDB File

MIS System

DOCUMENT NAME: S:DNMS\Fcdb\RJE\tn0202-URI.wpd Final: R:\_tn\2002\tn0202-URI.wpd

RIV:DNMS:FCDB NMSS:DWM:DCB NMSS:DWM C:FCDB D:DNMS

RJEvans JCDehmel CMCraig DBSpitzberg KEBrockman

/RA/ /RJEvans for via e /RJEvans for via e /RA/ /MRShaffer for/

12/03/02 12/09/02 12/09/02 12/10/02 12/10/02

OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax

ENCLOSURE 1

UNRESOLVED ITEM 50-344/0202-01

During the May 13-16, 2002, inspection (documented in Inspection Report 50-344/2002-02), the

NRC identified a number of concerns associated with the implementation of the final

radiological survey program in the decontaminated portions of the Reactor Containment

Building (Containment). The NRC determined that Portland General Electric (PGE) had

reclassified 18 survey units from MARSSIM1 Class 1 to Class 2, and designated the

reclassification of these survey units as initial, even though the Trojan Decommissioning Plan

and License Termination Plan (Trojan LTP) had already assigned an initial classification to

these areas at the time of its approval by the NRC. An Unresolved Item was identified in order

to determine whether the issues and approach used by PGE were acceptable practices, a

deviation, nonconformance, or violation. In addition, the NRC initiated a series of confirmatory

surveys in selected areas of the Containment and conducted an evaluation of the procedures

implementing the related elements of the final status survey program.

The NRC confirmatory surveys were conducted by Oak Ridge Institute for Science and

Education, Environmental Survey and Site Assessment Program (ORISE/ESSAP), under

contract with the NRC, during the August 5-15, 2002, inspection (NRC Inspection

Report 50-344/2002-03). The results of the confirmatory surveys indicated that the approved

Derived Concentration Guideline Level (DCGL) was exceeded in one area of the Containment

in which: (1) the survey unit classification had been down-classified because it was not

expected to contain areas exceeding the DCGL; and (2) the final surveys had failed to identify

the areas with elevated levels of residual radioactivity. The NRC was concerned because

PGEs final surveys had failed to identify areas exceeding the DCGL and that the survey units

did not meet the criteria for a change in classification. Details of the confirmatory survey are

included in the ORISE report2 which was issued in October 2002. A copy of the ORISE report

is attached as Enclosure 3.

During the October 7-10, 2002, inspection (NRC Inspection Report 50-344/2002-04), PGE

submitted to NRC inspectors additional information reflecting changes in final status survey

procedures that were prompted by the results of the earlier inspections of May 13-16 and

August 5-15, 2002. A review of the ORISE report along with information submitted by PGE,

indicated that the staff had enough information to address the Unresolved Item.

The NRC has reconsidered PGEs justification for reclassifying several survey units located in

Containment from a MARSSIM Class 1 to a Class 2 status in light of NRC confirmatory survey

results indicating that some portions of the areas located in the Containment were still above

the DCGL. The specific areas of concern to the NRC, as identified in prior inspection reports,

are addressed separately below.

1

Multi-Agency Radiation Survey and Site Investigation Manual (MARSSIM), NUREG-1575,

Revision 1, August 2000.

2

Confirmatory Survey of the Containment Building, Trojan Nuclear Plant, Rainier, Oregon,

ORISE/ESSAP, October 2002, performed under NRC contract.

-2-

Regarding classification of survey units, PGE has maintained that the classification may be

assigned after remediation and prior to conducting final status surveys. The Trojan LTP allows

changes in survey unit classification using approved plant procedures prior to the start of final

status survey (LTP Section 4.2.4.4). The initial classification, listed in Table 4-4 of the LTP,

reflects the plants operational history and results obtained during characterization and

remediation. One procedure (RP 451, Final Survey Unit Design) addresses reclassification,

but the focus is on initial and upward reclassifications using professional judgment, along with

other information that may indicate that another classification might be more appropriate. The

process addressing upward reclassification was found to be acceptable and consistent with

MARSSIM. Regarding downward reclassification (i.e., from Class 1 to 2, Class 1 to 3, Class 2

to 3, or impacted to non-impacted), the LTP does not identify any data quality objectives to be

considered in the evaluation process.

The NRC maintains that any subsequent reclassification of plant areas should be identified as

revised since the LTP (Section 4.2.4.3 and Tables 4-2 and 4-4) indicates that the

classifications were the initial classifications. The classification of survey units is a critical

decision because it determines how much of any survey unit will be scanned, and this

determination carries more implications than sampling locations and number of samples taken

for analysis. It can be seen that if a Class 1 survey unit were reclassified as Class 2 with

insufficient radiological information and the scan coverage were reduced to less than

100 percent, there is the possibility that elevated levels of radioactivity could have gone

undetected and, consequently, a survey unit could be released with radioactivity still above the

cleanup criteria. In practice, radiological scanning provides the means to readily identify

locations where residual contamination levels exceed the DCGL. Accordingly, surface scan

coverage is one of the fundamental MARSSIM tenets and it should not be compromised.

MARSSIM specifically identifies criteria for assigning classifications. Sections 2.2, 2.5.2,

and 4.4 of MARSSIM indicate that areas characterized by contamination levels that are above

the DCGL prior to remediation; areas that were subjected to remediation or spills or leaks; or

areas where contamination levels are unknown must be classified as Class 1. The NMSS

Standard Review Plan (NUREG-1727, Appendix E, Section 1) reinforces this concept and

further states that areas that are on the borderline between classes should receive the more

restrictive classification. For these areas, PGE should have assigned the more restrictive

Class 1 designation, rather than Class 2, to the areas of the Containment either contaminated

at levels above the DCGL prior to remediation, or that were subjected to remediation or spills or

leaks.

In response to recent inspections and discussions with NRC staff, PGE has proposed3 an

alternative to provide the NRC with written notification prior to engaging in final surveys in

survey units that have been reclassified from Class 1 to Class 2, Class 1 to Class 3, or Class 2

to Class 3, as compared to Table 4-4 of the approved Trojan LTP. In its notification, PGE will

inform the NRC in no fewer than 14 calendar days prior to conducting any final status surveys

in affected survey units. The notification will include background information as to the

3

Letter from Mr. Stephen M. Quennoz, Vice President, Power Supply/Generation, to the U.S.

Nuclear Regulatory Commission, NRC Inspection Report No. 50-344/2002-02, Unresolved Item 50-344-

0202-01, Final Survey Unit Reclassification, dated Oct. 17, 2002, VPN-056-2002.

-3-

operational history and radiological information for the survey unit as the basis supporting the

change in classification. In support of that decision, PGE will take into account the fundamental

MARSSIM tenets on downward reclassification (Sections 2.2 and 5.5.3). The tenets include:

(1) a confirmation that no individual measurement would exceed the DCGL by using

measurements that provide a high degree of confidence; (2) a verification that contamination

profiles are absent of small areas of elevated activity; and (3) assigning a level of surface scan

coverage that is proportional to the potential of finding areas of elevated activity. PGE has

committed to revise the associated procedure (RP 451) in addressing the implementation of the

alternative approach. Under these conditions, the Staff finds the alternative approach

acceptable. In addition, the implementation of the revised procedure will be the subject of

future NRC inspections.

Recognizing that PGE is assembling similar information for areas of the Containment that were

not part of the confirmatory survey of August 5-15, 2002, the NRC staff will evaluate the related

results once it receives the final status survey reports from PGE. Any questions identified

during that review about sample results and removable surface activity levels will be handled as

requests for additional information (RAIs). Accordingly, Unresolved Item No. 50-344/0202-01 is

considered closed.

ENCLOSURE 2

CONFIRMATORY SURVEY OF CONTAINMENT

The NRC confirmatory surveys, conducted during August 5-15, 2002, focused on 25 out of 75

survey units located in the Containment. The 25 survey units were selected by the NRC based

on information provided by PGE, discussions held with PGEs staff, and walk-down of the

containment building. The NRC survey results indicated that, although most areas of the

Containment were below the applicable Derived Concentration Guideline Level (DCGL), some

measurements were found to be above the criterion. The survey results revealed that the

DCGL was exceeded in 5 areas, with 11 direct measurements above the limit. Table 1 provides

a list of survey units that were identified with small, discrete areas that exceeded the applicable

DCGL:

Table 1

Results of NRC Confirmatory Surveys Conducted in the Reactor Containment Building (a)

Survey Unit Section/Item Size (m2) Class Coverage (%)(b) Range of Results (c)

S01044E Sect. 17 & 18 591 2 50/60 0.2 - 2.3

S01044H Sect. 11 82 1 100 0.8 - 1.4

S01044J Sect. 13 & 14 81 1 22 1.2

S01044L Sect. 12 & Floor 110 1 100/90 0.5 - 1.30

S01195C Sect. 17 & 18 12 1 100/100 1.04

(a) The survey information is based on the final ORISE Report (Enclosure 3) and field data.

(b) Approximate percentage of area coverage by surface scan measurements.

(c) Rounded off results, expressed in multiples of the DCGL (22,000 disintegrations per minute per 100 square

centimeters, dpm/100 cm2). The results have not been corrected for the presence of naturally occurring radioactivity

in the materials and surfaces that were surveyed.

One Class 2 survey unit (S01044E) had a discrete area that exceeded the DCGL by a factor of

about 2.3. By definition, a Class 2 survey unit is not expected to have contamination exceeding

the DCGL. During the August 2002 inspection, the licensee confirmed the NRCs findings. The

initial actions taken by PGE included separating the survey unit into two units. The area with

the radioactivity above the DCGL was reclassified as a Class 1 survey unit, while the remainder

of the survey unit remained a Class 2 survey unit. This approach was determined to be

acceptable to the staff as a short term solution, pending the results of PGEs full investigation.

During the inspection of October 7-10, 2002, PGE submitted to NRC inspectors the results of

its evaluation4 and corrective actions. PGE confirmed via additional measurements that these

areas were indeed above the DCGL, a new Class 1 survey unit (S01044S) was carved out of

the Class 2 survey unit with the offending results, survey unit specifications for the prior survey

unit (S01044E) were revised to show this change, and a new survey was conducted in the new

4

PGE Memorandum from Mr. Larry Rocha to Ms. Gina Huey, NRC Inspection Follow-up Item

(IFI) 50-344/0203-01, FS-017-02, October 8, 2002.

-2-

survey unit. The PGE survey results confirmed those of the NRC and reported yet other

elevated levels in the same vicinity. The results reported by PGE were found to be similar to

that of ORISE, ranging from 23,040 to 54,040 dpm/100 cm2. The sizes of the areas with

elevated radioactivity levels were reported to be very small, ranging from 0.01 to 0.8 square

meters (m2) and corresponding to about 0.01 to 0.80 percent of the total area of each survey

unit. In addition, smear samples taken in these area did not reveal removable surface

contamination levels that were above the limit of 2,200 beta dpm/100 cm2. The areas were

evaluated against the elevated measurements comparison test and found to pass the

associated criteria, using the Trojan LTP process and by applying As Low As Reasonably

Achievable (ALARA) concepts.

Among its findings, PGE stated that a more thorough evaluation of its operational and final

survey data might have concluded that an increase in scan coverage in the Class 2 survey unit

that failed the DCGL would have been warranted. Also, PGE noted that more detailed

instructions should have been given to the technicians who performed the final status surveys.

As a lessons-learned, PGE committed to revise its procedure (RP 453, Final Survey Data

Processing) to reduce the risk of missing areas with elevated activity levels. Collectively, the

NRC finds these corrective actions to be acceptable. The implementation of the revised

procedure will be the subject of future NRC inspections.

During the confirmatory survey, ORISE obtained five concrete samples that PGE had collected

and analyzed during the conduct of its own final surveys. Three steel samples (rebars) and one

steel sample taken from the steel liner, were obtained for analysis by high resolution gamma

spectrometry. In addition, 84 smears samples were taken on exposed surfaces. The results of

the concrete, steel, and smear samples were evaluated by the NRC:

  • Concrete samples - The results for the five concrete samples were found to be under or

just above analytical detection limits. Radionuclide concentrations ranged from 0.27

to 0.84 picocuries per gram (pCi/g) for cobalt-57 (Co-57); from 0.24 to 0.80 pCi/g for

Co-60; from 0.02 to 0.20 pCi/g for cesium-137 (Cs-137); and from 0.61 to 1.86 pCi/g for

europium-152 (Eu-152). The results reported by PGE were noted to range from 0.188

to 0.772 pCi/g for Co-60, and from 0.69 to 1.88 pCi/g for Eu-152. PGE did not report

Co-57 and Cs-137 results for these samples since Co-60 and Eu-152 were deemed to

be the limiting radionuclides as defined in the derivation of the building-specific DCGL.

A comparison of the results indicates that PGE radionuclide concentrations are in

agreement with those of the NRC and below their respective DCGLs of 3.8 pCi/g for

Co-60, 11 pCi/g for Cs-137, and 8.7 pCi/g for Eu-152, as adjusted for surrogates, hard-

to-detect radionuclides, and the 10 percent rule in eliminating radionuclides (e.g., Co-57)

with minimal impacts on dose. Accordingly, the NRC finds PGEs concrete sample

results acceptable.

  • Steel samples - The steel samples were analyzed by semi-quantitative screening using

high resolution gamma spectrometry. The analysis focused on the detection of Co-57,

Co-60, Cs-137, and Eu-152 using metal shavings collected from the bulk samples. All

results were found to be under their respective analytical detection limits, ranging from

0.37 to 1.3 pCi/g. The results reported by PGE range from -0.23 to 0.19 pCi/g for

Co-57, from -0.12 to 0.36 pCi/g for Co-60, from -0.15 to 0.04 pCi/g for Cs-137, and from

-0.13 to 0.03 pCi/g for Eu-152. A comparison of the results indicates that PGEs

-3-

concentrations are in agreement with those of the NRC and below their respective

DCGLs of 3.8 pCi/g for Co-60, 11 pCi/g for Cs-137, and 8.7 pCi/g for Eu-152, as

adjusted for surrogates, hard-to-detect radionuclides, and the 10 percent rule in

eliminating radionuclides (e.g., Co-57) with minimal impacts on dose. Accordingly, the

NRC finds PGEs steel sample results acceptable.

  • Removable surface contamination - A review of the smear/wipe data, indicates that the

results, taken at 84 locations, were either non-detectable or under the removable

surface contamination limit, i.e., #2,200 beta dpm/100 cm2 or #10 percent of the DCGL

adopted in the Trojan LTP. The results ranged from -4 to 120 dpm/100 cm2 for gross

beta radioactivity, determined using an automated gas-flow proportional counter.

Accordingly, the NRC finds that the approach used by PGE in demonstrating

compliance with removable surface contamination levels produces results that are in

agreement with its own results.