Closure of NRCs Review of Firstenergy Nuclear Operating Companys Response to GL 2006-03 for Beaver Valley, Units 1 and 2; Davis-Besse, Unit and Perry Unit 1
ML070680131
Person / Time
Site: Beaver Valley, Davis Besse, Perry, Trojan
Issue date: 03/17/2007
From: Gratton C
NRC/NRR/ADRO/DORL/LPLIII-2
To: Leidich G
FirstEnergy Nuclear Operating Co
Gratton C, NRR, DORL, 415-1055
References
TAC MD1548, TAC MD1549, TAC MD1572, TAC MD1615
Download: ML070680131 (6)


Text

March 17, 2007 Mr. Gary R. Leidich President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company 76 South Main Street Akron, OH 44308

SUBJECT:

CLOSURE OF NRC=S REVIEW OF FIRSTENERGY NUCLEAR OPERATING COMPANY=S RESPONSE TO GENERIC LETTER 2006-03, APOTENTIALLY NONCONFORMING HEMYC AND MT FIRE BARRIER CONFIGURATIONS@

(TAC NOS. MD1548, MD1549, MD1572, and MD1615)

Dear Mr. Leidich:

The Nuclear Regulatory Commission (NRC) acknowledges the receipt of FirstEnergy Nuclear Operating Company=s (FENOC=s) responses to Generic Letter 2006-03, APotentially Nonconforming Hemyc and MT Fire Barrier Configurations,@ for Beaver Valley Power Station, Units 1 and 2; Davis-Besse Nuclear Power Station, Unit No. 1; and Perry Nuclear Power Plant, Unit No. 1, in letters dated June 8, 2006, and February 1, 2007. Under oath or affirmation, Mr. Danny L. Pace stated that the FENOC nuclear power plant fleet does not rely on either the Hemyc or MT fire barrier system. You have submitted documentation under oath or affirmation that other 1 or 3-hour fire barriers that separate redundant safe shutdown trains located within the same fire areas at each FENOC unit have been designed and installed in accordance with current NRC guidance.

Based on your June 8, 2006, and February 1, 2007, responses, the bases for stating that these other fire barriers have been designed and installed in accordance with NRC guidance should be maintained on site for each unit, and will be subject to inspection during the normal NRC inspection process. Accordingly, the NRC staff=s review of FENOC=s response is complete and it will close TACs MD1548, MD1549, MD1572, and MD1615.

If you have any questions regarding this response, please contact me at (301) 415-1055.

Sincerely,

/RA/

Christopher Gratton, Sr. Project Manager Plant Licensing Branch III-2 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-334, 50-412, 50-346 and 50-440 cc: see next page

ML070680131 NRR-106 OFFICE LPL3-2/PM LPL3-2/LA AFPB/BC LPL3-2/BC NAME CGratton:mw EWhitt SWeerakkody RGibbs DATE 3/15/07 3/15/07 3/5/07 3/17/07

Davis-Besse Nuclear Power Station, Unit 1 cc:

Manager, Site Regulatory Compliance FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3065 5501 North State Route 2 Oak Harbor, OH 43449-9760 Director, Ohio Department of Commerce Division of Industrial Compliance Bureau of Operations & Maintenance 6606 Tussing Road P.O. Box 4009 Reynoldsburg, OH 43068-9009 Regional Administrator, Region III U.S. Nuclear Regulatory Commission Suite 210 2443 Warrenville Road Lisle, IL 60532-4352 Resident Inspector U.S. Nuclear Regulatory Commission 5503 North State Route 2 Oak Harbor, OH 43449-9760 Stephen Helmer Supervisor, Technical Support Section Bureau of Radiation Protection Ohio Department of Health 35 East Chestnut Street, 7th Floor Columbus, OH 43215 Carol O=Claire, Chief, Radiological Branch Ohio Emergency Management Agency 2855 West Dublin Granville Road Columbus, OH 43235-2206 Zack A. Clayton DERR Ohio Environmental Protection Agency P.O. Box 1049 Columbus, OH 43266-0149 State of Ohio Public Utilities Commission 180 East Broad Street Columbus, OH 43266-0573 Attorney General Office of Attorney General 30 East Broad Street Columbus, OH 43216 President, Board of County Commissioners of Ottawa County Port Clinton, OH 43252 President, Board of County Commissioners of Lucas County One Government Center, Suite 800 Toledo, OH 43604-6506 The Honorable Dennis J. Kucinich United States House of Representatives Washington, D.C. 20515 The Honorable Dennis J. Kucinich United States House of Representatives 14400 Detroit Avenue Lakewood, OH 44107 Gary R. Leidich President and Chief Nuclear Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-19 76 South Main Street Akron, OH 44308 Joseph J. Hagan Senior Vice President of Operations and Chief Operating Officer FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 David W. Jenkins, Attorney FirstEnergy Corporation Mail Stop A-GO-18 76 South Main Street Akron, OH 44308

Davis-Besse Nuclear Power Station, Unit 1 cc:

Danny L. Pace Senior Vice President, Fleet Engineering FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Manager, Fleet Licensing FirstEnergy Nuclear Operating Company Mail Stop A-GHE-115 395 Ghent Road Akron, OH 44333 Director, Fleet Regulatory Affairs FirstEnergy Nuclear Operating Company Mail Stop A-GHE-315 395 Ghent Road Akron, OH 44333 Jeannie M. Rinckel Vice President, Fleet Oversight FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Richard Anderson Vice President, Nuclear Support FirstEnergy Nuclear Operating Company Mail Stop A-GO-14 76 South Main Street Akron, OH 44308 Mark B. Bezilla Site Vice President FirstEnergy Nuclear Operating Company Davis-Besse Nuclear Power Station Mail Stop A-DB-3080 5501 North State, Route 2 Oak Harbor, OH 43449-9760

Perry Nuclear Power Plant, Unit 1 cc:

Resident Inspector's Office U.S. Nuclear Regulatory Commission P.O. Box 331 Perry, OH 44081-0331 Regional Administrator, Region III U.S. Nuclear Regulatory Commission 2443 Warrenville Road Lisle, IL 60532-4531 Sue Hiatt OCRE Interim Representative 8275 Munson Mentor, OH 44060 Manager, Site Regulatory Compliance FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant Mail Stop A-PY-A210 P.O. Box 97, 10 Center Road Perry, OH 44081-0097 Mayor, Village of North Perry North Perry Village Hall 4449 Lockwood Road North Perry Village, OH 44081 Donna Owens, Director Ohio Department of Commerce Division of Industrial Compliance Bureau of Operations & Maintenance 6606 Tussing Road P.O. Box 4009 Reynoldsburg, OH 43068-9009 Mayor, Village of Perry P.O. Box 100 Perry, OH 44081-0100 Chairman Perry Township Board of Trustees 3750 Center Road, Box 65 Perry, OH 44081 Daniel Z. Fisher Transportation Department Public Utilities Commission 180 East Broad Street Columbus, OH 43215-3793 L. W. Pearce Site Vice President FirstEnergy Nuclear Operating Company Perry Nuclear Power Plant Mail Stop A-PY-A290 P.O. Box 97 10 Center Road Perry, OH 44081-0097

Beaver Valley Power Station, Unit Nos. 1 and 2 cc:

Manager, Site Regulatory Compliance FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-A P.O. Box 4, Route 168 Shippingport, PA 15077 Commissioner James R. Lewis West Virginia Division of Labor 749-B, Building No. 6 Capitol Complex Charleston, WV 25305 Director, Utilities Department Public Utilities Commission 180 East Broad Street Columbus, OH 43266-0573 Director, Pennsylvania Emergency Management Agency 2605 Interstate Dr.

Harrisburg, PA 17110-9364 Dr. Judith Johnsrud Environmental Coalition on Nuclear Power Sierra Club 433 Orlando Avenue State College, PA 16803 Director Bureau of Radiation Protection Pennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469 Mayor of the Borough of Shippingport P.O. Box 3 Shippingport, PA 15077 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406 Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 298 Shippingport, PA 15077 James H. Lash Site Vice President FirstEnergy Nuclear Operating Company Beaver Valley Power Station Mail Stop A-BV-SEB1 P.O. Box 4, Route 168 Shippingport, PA 15077