VPN-008-202, Portland General Electric Company Revision 31 to PGE-8010, Trojan ISFSI Quality Assurance Program

From kanterella
(Redirected from ML23272A032)
Jump to navigation Jump to search
Portland General Electric Company Revision 31 to PGE-8010, Trojan ISFSI Quality Assurance Program
ML23272A032
Person / Time
Site: 07100327, Trojan
Issue date: 09/14/2023
From: Felton B
Portland General Electric Co
To:
Document Control Desk, Division of Fuel Management
References
VPN-008-2023
Download: ML23272A032 (1)


Text

Portland General Electric Company Trojan ISFSI 71760 Columbia River Hwy Rainier, Oregon 97048 September 14, 2023 VPN-008-2023 Trojan ISFSI Docket Nos.72-017 and 71-0327 License No. SNM-2509 ATTN: Document Control Desk Director, Division of Fuel Management Office of Nuclear Material Safety and Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Revision 31 to PGE-8010. Trojan ISFSI Quality Assurance Program Pursuant to 10 CFR 72.140(6) and (c), 10 CFR 71.101 (b) and (c), and 10 CFR 71.106(a),

this letter submits for Nuclear Regulatory Commission (NRC) approval proposed Revision 31 to PGE-8010, "Portland General Electric (PGE) Nuclear Quality Assurance Program for Trojan Independent Spent Fuel Storage Installation (10 CFR 72) Operations and Radioactive Material Packaging and Transportation (10 CFR 71) Activities" (Trojan ISFSI OAP).

In addition, this letter also requests the NRC to issue a revision to Form 311, OAP Approval for Radioactive Material Packages No. 0327, to reflect NRC approval of the proposed Revision 31 to the Trojan ISFSI OAP. The current OAP Approval for Radioactive Material Packages No. 0327 is Revision 17.

As required by 10 CFR 170.31 Section 1 0.B.2, the $4,200.00 Application Fee, for QA Program Users associated with this 10 CFR 71 QA Program change, accompanies this letter in the form of an "Authorization for Payment by Credit Card" form.

The Trojan ISFSI is the only licensed nuclear facility on the site of the decommissioned Trojan Nuclear Plant. All spent nuclear fuel has been transferred to the ISFSI, the Trojan Nuclear Plant has been dismantled, and the 10 CFR 50 operating license was terminated in 2005. The ISFSI is in a "static" state with no additional dry storage systems (DSSs) to be added. The only activities at the site governed by the Trojan ISFSI OAP involve operations and maintenance of the 34 in-service DSSs (including aging management program implementation), support activities such as procurement, and C')

NMss1-~

&ov'-t NN\\_s,S

Document Control Desk September 14, 2023 VPN-008-2023 Page 2 future preparation of the spent fuel canisters for shipment off-site. Security for the ISFSI is conducted under the applicable provisions of 10 CFR 73.

The changes proposed for Revision 31 to the Trojan ISFSI OAP are the outcome of a recent PGE self-assessment of the design and implementation of the Trojan ISFSI OAP for an ISFSl-only site that has completed transfer of all spent fuel to dry storage. That self-assessment revealed opportunities to more clearly focus the OAP on important-to-safety (ITS) activities conducted at the site under 10 CFR 72 and 10 CFR 71, while removing OAP applicability to non-ITS activities. Non-ITS regulatory programs will still be required by the OAP to be implemented via written procedures. Otherwise, the proposed OAP changes are primarily focused on the Organization and Program elements of the OAP.

The proposed revised Trojan ISFSI OAP was developed to comply with all applicable 10 CFR 72 and 10 CFR 71 regulatory requirements using current industry standards and guidance. However, because the industry standards and guidance pertain to either operating nuclear plants or "active" ISFSls, certain adaptations of the standards and guidance were necessary for an ISFSl-only site where no additional DSSs are being loaded and deployed. These adaptations were informed by other NRC-approved decommissioning site OAPs, including Lacrosse Boiling Water Reactor (LACBWR),

Rancho Seco, Crystal River, Fort Calhoun, and the Three Yankees. The following documents were used to develop a customized OAP for the Trojan ISFSI:

10 CFR 72, Subpart G, 10 CFR 71, Subpart H, 10 CFR 21 NRC Regulatory Guide 7.10, "Establishing Quality Assurance Programs for Packaging Used in Transport Of Radioactive Material," Revision 3 (licensee-applicable portions)

NEI 11-04A, "Nuclear Generation Quality Assurance Program Description" NEl-14-0SA, "Guidelines for the Use of Accreditation in lieu of Commercial Grade Surveys for Procurement of Laboratory Calibration and Test Services" NEI Efficiency Directive 16-23, "Streamlined Use of Offsite Review Committee" The key changes included in the attached revised Trojan ISFSI OAP are:

Replacement of the terms "Quality-Related" and "Augmented Quality" with "Important-to-Safety" and removal from the scope of the OAP activities that are not ITS.

A revised and simplified organization chart to better reflect ISFSI operations and functional reporting chains. The organization chart has also been relocated to Appendix A.

Document Control Desk September 14, 2023 VPN-008-2023 Page 3 Replacement of a standing offsite ISFSI Safety Review Committee (ISRC) with an Independent Management Assessment (IMA) function reporting to the Corporate Executive Responsible for Trojan. The current independent oversight of the Trojan ISFSI is provided by the ISRC. The Trojan ISFSI will transition this function to an IMA process within two years of the approval of this Quality Assurance Program revision. The Corporate Executive Responsible for Trojan will make the determination as to when ISRC activities are concluded. PGE will ensure an effective transition from an ISRC to an IMA.

Consistent with 10 CFR 72.140(d) "Previously Approved Programs,"

incorporation of the 10 CFR 71.106(6) OAP change controls dir~ctly into the OAP. This proposed change clarifies that changes made to the OAP that do not involve a reduction in commitment may: 1) be implemented without NRC approval and 2) apply to both 10 CFR 72 and 10 CFR 71 ITS activities. This change puts the Trojan ISFSI, operated under a Part 72 specific license, on an equal footing in this regard with ISFSls operated by Part 72 general licensees and Part 72 specific licensees who still have an active Part 50 license. Both of these types of ISFSI licensees apply their 10 CFR 50, Appendix B OAPs to Part 72 activities on site, and control changes to their ISFSI OAPs under 10 CFR 50.54(a},

allowing changes to those OAPs without prior NRC approval if no reduction in commitment is involved.

Limiting the applicability of 10 CFR 21 to ITS-A items and services. This change is based on a determination that only ITS-A items and services meet the definition of "basic component" in 10 CFR 21.3, as applicable to a Part 72-licensed facility.

Removal of the glossary from the OAP to a future site procedure.

Addition of two new appendices. New Appendix B lists regulatory requirements, commitments, and guidance applicable to the OAP. New Appendix C lists regulatory-required site programs that, while not governed by the OAP, will be implemented by written procedures.

Because this is a substantial re-write of the Trojan ISFSI OAP, individual changes are not identified with revision bars. As mentioned above, the most significant changes are in the "Organization" and "Program" sections, with other sections revised to make conforming changes (e.g., replacing "quality-related" with "ITS"). In some sections, rather than repeat extensive requirements, other documents are incorporated by reference into the OAP. For example, NEI 14-05A is incorporated by reference in Section 12 for acceptance of calibration services for portable M& TE by commercial-grade suppliers.

Document Control Desk September 14, 2023 VPN-008-2023 Page 4 These proposed changes to the Trojan Nuclear OAP continue to satisfy the requirements of 10 CFR 72 Subpart G and 10 CFR 71 Subpart H for Quality Assurance Programs.

Upon receipt of the NRC approvals requested in this letter, PGE will need to implement the revised OAP with new or revised implementing procedures. Therefore, PGE requests a 180-day implementation period for OAP Revision 31.

lfthere are any questions regarding this letter, please contact Mr. Tom Romay of my staff at (503) 556-7001.

Benjamin F. Felton Executive Vice President and Chief Operating Officer Enclosures c:

Director, NRC Region IV, DNMS Todd Cornett, Assistant Director, Energy Siting, ODOE