June 2002 Monthly Operating Report for Braidwood Units 1 & 2
ML022050063
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 07/12/2002
From: Joyce T
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
BW020065
Download: ML022050063 (4)


Text

Exelon.

Exelon Ceneyation Company, LLC www.exeloncorp.cor Nuclear Braidwood Station 35100 South Rt 53, Suite 84 Braceville, IL 60407-9619 Tel. 815-417-2000 July 12, 2002 BW020065 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Braidwood Station, Units 1 and 2 Facility Operating License Nos. NPF-72 and NPF-77 NRC Docket Nos. STN 50-456 and STN 50-457

Subject:

Monthly Operating Report In accordance with Technical Specification 5.6.4, "Monthly Operating Reports," we are submitting the Monthly Operating Report for Braidwood Station, Units 1 and 2. This report covers the period of June 1, 2002 through June 30, 2002.

If you have any questions regarding this letter, please contact Ms. Amy Ferko, Regulatory Assurance Manager, at (815) 417-2699.

Respec ly, r Tom Joyce Plant Manager Braidwood Station Attachment cc: Regional Administrator - NRC Region III NRC Senior Resident Inspector - Braidwood Station

ATTACHMENT BRAIDWOOD STATION UNITS 1 AND 2 MONTHLY OPERATING REPORT EXELON GENERATION COMPANY, LLC FACILITY OPERATING LICENSE NOS. NPF-72 AND NPF-77 NRC DOCKET NOS. STN 50-456 AND STN 50-457

Docket No: 50-456 Unit: Braidwood 1 Date: 07/11/2002 Completed by: Don Hildebrant Telephone: (815)417-2173 Braidwood Unit 1 REPORTING PERIOD: June 2002 A. OPERATING DATA REPORT Design Electrical Rating (MWe Net) I 1187 Maximum Dependable Capacity (MWe Net) 1165 Month I Year To Date Cumulative Hours Reactor Critical (Hours) 720.0 4,343.0 102,087.5 Hours Generator on Line (Hours) 720.0 4,343.0 101,125.8 Unit Reserve Shutdown Hours (Hours) 0.0 0.0 0.0 Net Electrical Energy (Mwh) 851,216 5,271,346 107,756,526 B. UNIT SHUTDOWNS TYPE REASON METHOD F - Forced A - Equipment Failure (explain) 1 -Manual S - Scheduled B - Maintenance or Test 2 - Manual Trip / Scram C - Refueling 3 - Automatic Trip / Scram D - Regulatory Restriction 4 - Continuation E - Operator Training I Licensee Examination 5 - Other (explain)

F - Administrative G - Operator Error (explain)

H - Other (explain)

No. Date Type Duration Reason Method Cause and Corrective Actions and Hours Comments None

SUMMARY

Unit performed normally at full load for the entire month.

C. SAFETY I RELIEF VALVE OPERATIONS Date Valves Actuated No. &Type Actuation I Plant Condition IDescription of Event None Data From: Production Data Bank and Operator Logs

Docket No: 50-457 Unit: Braidwood 2 Date: 07/11/2002 Completed by: Don Hildebrant Telephone: (815)417-2173 Braidwood Unit 2 REPORTING PERIOD: June 2002 A. OPERATING DATA REPORT Design Electrical Rating (MWe Net) 1155 Maximum Dependable Capacity (MWe Net) 1158 Month Year To Date Cumulative Hours Reactor Critical (Hours) 720.0 3,818.6 105,677.0 Hours Generator on Line (Hours) 720.0 3,809.0 105,156.7 Unit Reserve Shutdown Hours (Hours) 0.0 0.0 0.0 Net Electrical Energy (Mwh) 858,149 4,401,693 112,158,844 B. UNIT SHUTDOWNS TYPE REASON METHOD F - Forced A - Equipment Failure (explain) I - Manual S - Scheduled B - Maintenance or Test 2 - Manual Trip / Scram C - Refueling 3 - Automatic Trip / Scram D - Regulatory Restriction 4 - Continuation E - Operator Training I Licensee Examination 5 - Other (explain)

F - Administrative G - Operator Error (explain)

H - Other (explain)

No. Date Type Duration Reason Method Cause and Corrective Actions and Hours Comments None

SUMMARY

Unit performed normally at full load for the entire month.

C. SAFETY I RELIEF VALVE OPERATIONS Date Valves Actuated No. & Type Actuation Plant Condition I Description of Event None Data From: Production Data Bank and Operator Logs