Functional Engineering Inspection Commercial Grade Dedication Report 05000456/2023010 and 05000457/2023010
ML23286A014
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 10/18/2023
From: Karla Stoedter
NRC/RGN-III/DORS/RPB3
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
References
IR 2023010
Download: ML23286A014 (1)


Text

SUBJECT:

BRAIDWOOD STATION - FUNCTIONAL ENGINEERING INSPECTION - COMMERCIAL GRADE DEDICATION REPORT 05000456/2023010 AND 05000457/2023010

Dear David Rhoades:

On September 29, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Braidwood Station and discussed the results of this inspection with James Petty, Plant Manager, and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Karla K. Stoedter, Chief Engineering Branch 1 Division of Operating Reactor Safety Docket Nos. 05000456 and 05000457 License Nos. NPF-72 and NPF-77

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000456 and 05000457

License Numbers:

NPF-72 and NPF-77

Report Numbers:

05000456/2023010 and 05000457/2023010

Enterprise Identifier:

I-2023-010-0046

Licensee:

Constellation Energy Generation, LLC

Facility:

Braidwood Station

Location:

Braceville, IL

Inspection Dates:

August 14, 2023 to September 29, 2023

Inspectors:

Benny Jose, Senior Reactor Inspector (Team Member)

Joon Park, Reactor Inspector (Team Lead)

Thomas Hartman, Senior Project Engineer (Observer)

Eucherius Rosario, Reactor Inspector (Team Member)

Approved By:

Karla K. Stoedter, Chief

Engineering Branch 1

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting a Functional Engineering Inspection - Commercial Grade Dedication at Braidwood Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.21N.03 - Commercial Grade Dedication Commercial Grade Dedication (section 03.01)

The inspectors reviewed the implementation of the licensees processes for dedicating commercial-grade items/services as basic components and/or for procuring safety-related structures, systems, and components for the following samples:

(1)5631-2, Diode, Rectifier, Rated Current 150 AMPS, Repetitive Peak Reverse Voltage 800 V (Commercial Grade Item (CGI) Dedication)

(2)9329-2, Differential Pressure Switch, 5 AMPS, 125 VAC, 0 - 6.0 in. Water Column, 1/4" NPT (CGI Dedication)

(3)18910-2, Instrument Valve, 1/2", Carbon Steel, 2500 PSI, Socketweld Ends, A-105 (CGI Dedication)

(4)19304-1, Reactor Vessel Closure Stud, 7", Material SA-540, Gr. B23, Class 3, Mark No. 89-1 (Safety Related (SR) Procurement)

(5)19819-2, Secondary Filter Element for Fuel Filter Assembly (CGI Dedication)

(6)26440-2, Grayloc Seal Ring, Size 25, AISI 630, 0.2% Max. Cobalt, Neolube #1 (CGI Dedication)

(7)28165-1, Time Delay Relay, 125 VDC, 0.5 AMP, DPDT, 20 to 200 Seconds, with Off-Delay Operation (SR Procurement)

(8)34379-1, Molded Case Circuit Breaker, 150 AMP, 600 VAC, Three Pole (SR Procurement)

(9)35718-2, Valve Positioner, Type H/FR, Two-Stage, 150 PSIG, BUNA-N Diaphragm (CGI Dedication)

(10)42896-2, Valve Rebuilt/Repair Kit, Includes Two Seats, Two Seat Rings, Two Stem Seals and One Cover Gasket (CGI Dedication)

(11)770091-2, Strainer Element, Spare Parts for 36" VDWS-118 R.P. Adams Strainer (CGI Dedication)

(12)1236238-2, Pressure Transmitter, 1-100 PSI Input, 1-5 VDC Signal Output, 10-35 VDC Power Requirement (CGI Dedication)

(13)1400115-1, Hydranut Assembly, 1 3/8" x 8" TPI UN, SA-453, Gr. 660, Class A or B (SR Procurement)

INSPECTION RESULTS

No findings were identified.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On September 29, 2023, the inspectors presented the Functional Engineering Inspection - Commercial Grade Dedication results to James Petty, Plant Manager, and other members of the licensee staff.
  • On September 1, 2023, the inspectors presented the initial Functional Engineering Inspection - Commercial Grade Dedication inspection results to Greg Gugle, Site Vice President, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Calculations

E.M. 7121

Analysis of Hydranuts for Braidwood Pressurizer Safety

Valve Inlet and Outlet Flanges

Corrective Action

Documents

105700

Replacement Secondary Fuel Oil Filter Not "Like-for-Like"

04/28/2002

4699141

NRC ID: Piping Support 2SX71016X Near 2SX178 is

Misaligned

08/29/2023

4699480

NRC ID: Dedication of Ball Valve Rebuilt Kit

08/30/2023

4699959

NRC ID: CGD Audit PD

09/01/2023

Corrective Action

Documents

Resulting from

Inspection

4705579

NRC ID: CGD Audit PD Update

09/28/2023

337149

Temporary Configuration Change Package to Add

Parameter Monitoring Devices to 1B Auxiliary Feed Water

(AFW) Pump

351459

Design Report Review for Alternate Non-Standard Nuts on

the Inlet and Outlet Flanges of the Pressurizer Safety

Valves

Engineering

Changes

2609

Add a Number of Parameter Monitoring Devices to the

Unit 1 B Diesel Driven AFW Pump to Monitor Diesel

Performance

15127

Parts Evaluation for 42896-2, Valve Repair Kit

2/14/2002

18022

CGD Evaluation for 1236238-2, Pressure Transmitter

07/12/2002

203432

Parts Evaluation for 18910-2, Instrument Valve

06/27/2017

213407

Parts Evaluation for 19819-2, Secondary Filter Element

04/11/2018

20829

Parts Evaluation for 35718-2, Valve Positioner

08/22/2018

2564

Parts Evaluation for 26440-2, Seal Ring

03/19/2003

27339

Parts Evaluation for 26440-2, Seal Ring

11/07/2003

280873

Parts Evaluation for 18910-2, Instrument Valve

04/27/2023

283121

Parts Evaluation for 770091-2, Strainer Element

06/29/2023

39940

Part Evaluation for 5631-2, Diode Rectifier

05/05/2005

64650

Parts Evaluation for 1400115-1, Hydranut Assembly

2/16/2009

64653

Parts Evaluation for 1400115-1, Hydranut Assembly

2/16/2009

64891

Parts Evaluation for 19819-2, Secondary Filter Element

03/09/2009

71111.21N.03

Engineering

Evaluations

88442

Parts Evaluation for 18910-2, Instrument Valve

04/30/2015

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

2774

Parts Evaluation for 19304-1, Reactor Vessel Closure

Stud

03/02/2016

A-91-003-0207-

Parts Evaluation for 19304-1, Reactor Vessel Closure

Stud

10/30/1991

M-1993-0121-

001

Parts Evaluation for 42896-2, Valve Repair Kit

09/19/1997

1081000

Purchase Order for 19819-2, Secondary Filter Element

11188

Purchase Order for 1236238-2, Pressure Transmitter

08/19/2002

27051

Receipt Inspection Package for 1400115-1, Hydranut

Assembly

04/04/2017

230857

Receipt Inspection Package for 42896-2, Valve Repair Kit

09/02/2017

235674

Receipt Inspection Package for 5631-2, Diode Rectifier

03/10/2018

238381

Receipt Inspection Package for 19819-2, Secondary Filter

Element

05/29/2018

238919

Receipt Inspection for 9329-2, Differential Pressure Switch

06/13/2018

240927

Receipt Inspection Package for 35718-2, Valve Positioner

09/22/2018

243859

Receipt Inspection Package for 28165-1, Time Delay

Relay

01/09/2019

245400

Receipt Inspection Package for 18910-2, Instrument Valve

03/28/2019

254356

Receipt Inspection Package for 26440-2, Seal Ring

2/21/2020

255805

Receipt Inspection Package for 19304-1, Reactor Vessel

Closure Stud

03/19/2020

258129

Receipt Inspection Package for 34379-1, Molded Case

Circuit Breaker (MCCB)

05/28/2020

268420

Receipt Inspection for 770091-2, Element Strainer

10/20/2021

588401

Purchase Order for 5631-2, Diode Rectifier

604856

Purchase Order for 1400115-1, Hydranut Assembly

618004

Purchase Order for 42896-2, Valve Repair Kit

653875

Purchase Order for Differential Pressure Switch 9329-2

06/15/2018

664573

Purchase Order for 35718-2, Valve Positioner

67494

Receipt Inspection Package for 1236238-2, Pressure

Transmitter

08/26/2002

Miscellaneous

67949

Exelon Power Labs Test Report for 1236238-2, Pressure

09/11/2002

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Transmitter

680798

Purchase Order for 18910-2, Instrument Valve

688729

Purchase Order for 19304-1, Reactor Vessel Closure Stud

710152

Purchase Order for 26440-2, Seal Ring

790121

Purchase Order for 34379-1, MCCB

05/22/2020

25106

Purchase Order for 770091-2, Element Strainer

BRW-47277

Exelon Power Labs Test Report on 34379-1, MCCB

06/03/2020

BRW-08229

Commercial Grade Dedication (CGD) Requirements for

29-2, Differential Pressure Switch

06/28/2018

BRW-5501

Exelon Power Labs Test Report on 28165-1, Agastat Time

Delay Relay

2/14/2019

Project Number

BRW- 08229

Exelon Power Labs CGD Test Report for 9329-2,

Differential Pressure Switch

06/26/2018

BwMP 3300-075

Reactor Vessel Level Indicating System Flange Assembly

and Disassembly

NO-AA-500

Approved Supplier Qualification Activities

NO-AA-501

Commercial Grade Surveys

PI-AA-115

Operating Experience Program

PI-AA-115-1003

Processing of Level 3 OPEX Evaluations

SM-AA-102

Warehouse Operations

SM-AA-300

Procurement Engineering Support Activities

Procedures

SM-AA-300-1001

Procurement Engineering Process and Responsibilities

04605041-02

Perform a Functional Run of 1VD03CA, Verify Proper

Operation

2/14/2018

04861604

Reactor Vessel Disassembly/Reassembly

04/13/2020

05198651-01

Replace Transmitter 2PTAF109

10/26/2021

Work Orders

4612416-01

MM - Valve 2SX2077A Rebuild Valve

2/04/2020