IR 05000456/2023004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000456/2023004 and 05000457/2023004
ML24032A475
Person / Time
Site: Braidwood  Constellation icon.png
Issue date: 02/02/2024
From: Hironori Peterson
NRC/RGN-III/DORS/RPB3
To: Rhoades D
Constellation Energy Generation
References
IR 2023004
Download: ML24032A475 (1)


Text

SUBJECT:

BRAIDWOOD STATION - INTEGRATED INSPECTION REPORT 05000456/2023004 AND 05000457/2023004

Dear David Rhoades:

On December 31, 2023, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Braidwood Station. On January 17, 2024, the NRC inspectors discussed the results of this inspection with G. Gugle, Site Vice President, and other members of your staff.

The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Hironori Peterson, Chief Reactor Projects Branch 3 Division of Operating Reactor Safety Docket Nos. 05000456 and 05000457 License Nos. NPF-72 and NPF-77

Enclosure:

As stated

Inspection Report

Docket Numbers:

05000456 and 05000457

License Numbers:

NPF-72 and NPF-77

Report Numbers:

05000456/2023004 and 05000457/2023004

Enterprise Identifier:

I-2023-004-0044

Licensee:

Constellation Energy Generation, LLC

Facility:

Braidwood Station

Location:

Braceville, IL

Inspection Dates:

October 01, 2023 to December 31, 2023

Inspectors:

K. Barclay, Senior Reactor Inspector

R. Bowen, Illinois Emergency Management Agency

J. Cassidy, Senior Health Physicist

D. Kimble, Senior Resident Inspector

J. Robbins, Senior Resident Inspector

P. Smagacz, Resident Inspector

P. Zurawski, Senior Resident Inspector

Approved By:

Hironori Peterson, Chief

Reactor Projects Branch 3

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Braidwood Station, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

Unit 1 began the inspection period operating at full power. With the exception of minor reductions in power to support scheduled testing activities and load changes requested by the transmission system dispatcher, the unit remained operating at or near full power for the entire inspection period.

Unit 2 began the inspection period operating at full power. With the exception of minor reductions in power to support scheduled testing activities and load changes requested by the transmission system dispatcher, the unit remained operating at or near full power for the entire inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk-significant activities, and completed on-site portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal cold temperatures during the weeks ending December 2 through December 16, 2023.

Impending Severe Weather Sample (IP Section 03.02) (1 Sample)

(1) The inspectors evaluated the adequacy of the overall preparations to protect risk-significant systems from impending severe weather when thunderstorms were predicted during elevated risk conditions due to 2B Auxiliary Feedwater (AF) Pump maintenance during the week ending October 14, 2023.

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1)1B Safety Injection (SI) Train while protected for 1A SI Train maintenance during the week ending October 7, 2023 (2)2A AF Train while protected for 2B AF Train maintenance during the week ending October 14, 2023

(3) Unit 1 AF after restoration from maintenance of the 1B AF Train during the week ending November 11, 2023

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (1 Sample)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) Fire Zone 11.3A-1, Auxiliary Building 364' Elevation, SI Pump 1A Room during the week ending December 2, 2023

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

The inspectors observed and evaluated the following licensed operator activities in the main control room:

(1) Various activities involving on-watch operations crews. These activities included, but were not limited to:
  • Observation of selected portions of the operation and loading of the 1B Emergency Diesel Generator (EDG) during the week ending November 11, 2023
  • Observation of selected 4160 Vac electrical bus switching operations during the week ending November 11, 2023

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

The inspectors observed and evaluated the following licensed operator training activity:

(1) A complex casualty evaluated scenario involving a crew of licensed operators was observed in facilitys simulator on November 7, 2023

71111.12 - Maintenance Effectiveness

Maintenance Effectiveness (IP Section 03.01) (2 Samples)

The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:

(1) Maintenance effectiveness review associated with continued monitoring and assessment of the 15X55AA piping leakage during the weeks ending November 11 through November 18, 2023
(2) Maintenance effectiveness review associated with the main Control Room ventilation system during the week ending December 6, 2023

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following SSC remains capable of performing its intended function:

(1) Maintenance effectiveness, performance history, and quality reviews for the 2B AF Pump, with specific emphasis on the diesel engine following identification of unacceptable fuel oil contamination in the engine lubricating oil, as documented in Issue Report (IR) 4703982 during the weeks ending October 7 through October 21, 2023

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Review and evaluation of the risk associated with an emergent Technical Specification (TS) RICT [Risk-Informed Completion Time] for the 2WO056A primary containment isolation valve, as documented in IR 4706461 during the week ending October 7, 2023
(2) Review and evaluation of the risk associated with an emergent TS 3.7.5 RICT for the 2B AF Pump, as documented in Work Order (WO) 5402459 during the week ending October 14, 2023

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (3 Samples)

The inspectors evaluated the licensees justifications and actions associated with the following operability determinations and functionality assessments:

(1) Evaluation of the operability of the Unit 1 Power Distribution Monitoring System (PDMS) following identification of anomalous core exit thermocouple readings, as documented in IR 4709877 during the week ending October 28, 2023
(2) Evaluation of the operability of the excore power range instruments, as documented in IR 4713882 during the weeks ending October 4 through 11, 2023
(3) Evaluation of the operability of the 2C Steam Generator (SG) Power-Operated Relief Valve (PORV) following identification of a nontypical setup on the installed amplifier module signal conditioner, as documented in IR 4717796 during the week ending November 18, 2023

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (2 Samples)

(1) Functional and operational testing of the 2B AF Pump diesel engine following a significant maintenance work window, as documented in WOs 541827 and 5402459 during the weeks ending October 14 through November 4, 2023
(2) Functional and operational testing of the 1A Containment Spray Pump after cubicle cooler maintenance, as documented in WO 5401820 during the week ending December 16, 2023

Surveillance Testing (IP Section 03.01) (2 Samples)

(1) Semiannual fast start surveillance testing of the 2B EDG, as documented in WO 5383878 during the weeks ending October 21 through October 29, 2023
(2) Unit 1 Train A Auxiliary Feedwater Quarterly Surveillance, as documented in WO 5408735 during the week ending December 2, 2023

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.01-02.03) (1 Sample)

(1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes.
  • EP-AA-1001 Addendum 3, Revision 7; 10 CFR 50.54(q)(3) Evaluation No. 21-72: Emergency Action Levels for Braidwood Station of January 20, 2022
  • EP-AA-1001: Radiological Emergency Plan Annex for Braidwood Station, Revision 35
  • EP-AA-1001: Addendum 1 Braidwood Station On-Shift Staffing Technical Basis, Revision 2
  • EP-AA-1001: Addendum 3 Emergency Action Levels for Braidwood Station, Revision 7 This evaluation does not constitute NRC approval.

71114.06 - Drill Evaluation

Drill/Training Evolution Observation (IP Section 03.02) (1 Sample)

The inspectors evaluated sites emergency plan by observing the following emergency response organization (ERO) activities:

(1) The 2023 Braidwood off-year full-scale ERO exercise during the week ending October 7,

OTHER ACTIVITIES - BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10)===

(1) Unit 1 (October 1, 2022 through September 30, 2023)
(2) Unit 2 (October 1, 2022 through September 30, 2023)

BI02: RCS Leak Rate Sample (IP Section 02.11) (2 Samples)

(1) Unit 1 (October 1, 2022 through September 30, 2023)
(2) Unit 2 (October 1, 2022 through September 30, 2023)

OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)

(1) October 1, 2022 through September 30, 2023 PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
(1) October 1, 2022 through September 30, 2023

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Review and assessment of the stations corrective actions for recurring 2C SG PORV operability issues, as documented in IRs 4702773, 4704254, 4697594, 4706721, and

===4708650, during the weeks ending October 21 through November 4, 2023

(2) Review and assessment of the stations corrective actions associated with a pinhole leak on the 10-inch safety-related essential service water (SX) return line 1SX27DA, as documented in IR 4550413-22 during the week ending November 25, 2023 71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)===
(1) The inspectors reviewed the licensees corrective action program for potential adverse trends in the EDG Starting Air System that might be indicative of a more significant safety issue during the weeks ending November 4 through December 2, 2023.

71153 - Follow-up of Events and Notices of Enforcement Discretion Event Follow-up (IP Section 03.01) (1 Partial)

(1)

(Partial)

Review and assessment of the identification of fuel oil in the 2B AF Pump diesel engine oil system, as documented in IR 4703982 during the weeks ending October 7 through December 16,

INSPECTION RESULTS

Observation: 2MS018C: 2C Steam Generator (SG) Power-Operated Relief Valve (PORV) Operability Issues 71152A The inspectors performed a detailed review of several issue reports (IRs) related to the subject performance problem. These included, but were not limited to:

- IR 4697594, 2MS018C Abnormal Indications; 08/21/2023

- IR 4702773, 2MS018JC Abnormal Indications; 09/15/2023

- IR 4704254, 2MS018C Abnormal Indications; 09/22/2023

- IR 4706721, 2MS018C Abnormal Indications; 10/03/2023

- IR 4716007, 2MS018JC Abnormal Indications (Repeat Issue); 10/07/2023

- IR 4708650, 2MS018C Abnormal; 10/11/2023

- IR 4710584, 2MS018JC Fan Filter Replacement; 10/18/2023

- IR 4717796, 2MS018JC Amplifier Replacement; 11/15/2023

- IR 4719624, 2MS018JC Abnormal Indications (Repeat Issue); 11/26/2023 In late August 2023, the station began experiencing recurring trips of the 2C SG PORV controller, each of which rendered the 2C SG PORV inoperable and necessitated the entry into a 30-day action, leading to a unit shutdown per Technical Specification (TS) 3.7.4. Upon investigation, plant operators noted essentially the same fault indications on the controller with each instance. While the indications pointed to an overtemperature condition within the controller electronics, the condition was able to be reset by operators and rapidly cleared in each case. As the licensee worked through troubleshooting efforts, however, what began as a recurring problem once every 2 to 3 weeks eventually became a recurring issue once every few days.

In mid-October 2023, the licensee identified that the controller electronics cabinet fan filter was nearly completely blocked. Temperatures and airflow within the controller electronics cabinet following replacement of the fan filter immediately improved, and the licensee assumed that the problem had been identified and corrected after several days without another trip of the 2C SG PORV controller.

In late November 2023, the 2C SG PORV controller again tripped, with plant operators noting essentially the same fault indications on the controller as before. At this point, the licensee elected to replace the controller chassis with a new module, which appeared to finally correct the issue.

With the final return of the 2C SG PORV to service, the inspectors examined the licensees corrective actions from the previous several weeks to assess whether outstanding issues and performance problems had been addressed. Several observations by the inspectors were discussed with station management, which included but were not limited to:

  • Each instance of the tripping of the 2C SG PORV controller required the station to enter a 30-day action leading to a unit shutdown per TS 3.7.4. While each controller electronics trip was, in actuality, fairly easily and readily cleared by operators via the performance of a manual reset of the controller logic per established plant procedures, each recurrence of the trip carried with it the risk that the controller might actually have failed to be able to be easily reset. Such an eventuality would have placed the station into a more emergent mode of response that potentially could have resulted in a forced unit shutdown, per plant TS. Additionally, each recurrence of the issue required plant operators to stroke test the 2C SG PORV following the resetting of its controller logic in order to positively demonstrate operability prior to exiting the TS 3.7.4 30-day required action. Considering the recurring nature of the 2C SG PORV controller trips, the inspectors questioned whether or not a more aggressive overall troubleshooting effort by the licensee should have been employed.
  • The inspectors noted that the licensees identification of the nearly fully plugged controller electronics cabinet fan filter came approximately 2 months after the initial 2C SG PORV controller trip. Given the electronics trip indications pointed to, at least in part, a possible overtemperature condition within the electronics, the inspectors noted that a review of the timeliness of this identification on the part of the licensee might be warranted.
  • Following the identification of the nearly completely plugged controller electronics cabinet fan filter and its replacement, the inspectors noted that the licensee quickly concluded that the issue had been corrected. While the inspectors noted that the preponderance of the evidence would seem to have validated this conclusion by the licensee, a review of this decision, with an emphasis on the length of time dedicated to obtaining overall confidence that the issue had been resolved, might also be warranted.

In the course of the inspectors review, no findings or violations of NRC requirements were identified.

Observation: 1SX27DA-10 Pinhole Leak Corrective Actions 71152A On January 25, 2023, a pinhole leak in a 90-degree elbow on the 10-inch essential service water (SX) system return line to the Braidwood cooling lake from the 1A Emergency Diesel Generator (EDG) was discovered by plant operators during a 1A EDG surveillance run. The licensee performed a formal operability evaluation and planned replacement of the affected section of the 10-inch SX line for the next scheduled 1A EDG maintenance work window.

In late September 2023, the 1DX27DA-10 affected elbow was replaced with a new 10-inch carbon steel elbow during a scheduled 1A EDG maintenance period. The removed 10-inch SX elbow was sent by the licensee to their Constellation PowerLabs facility for a detailed failure analysis, which was documented within the licensees Corrective Action Program (CAP) as IR 4550413, Action No. 22, Failure Analysis of 1SX27DA Leak Location, on November 10, 2023. The inspectors chose to perform a detailed review of this licensee analysis, as well as the licensees planned corrective actions for the underlying cause, due to the overall risk significance associated with the SX system and the additional safety significance imposed by the leak locations potential impact on the availability and reliability of the 1A EDG.

The licensees failure analysis concluded that the pinhole through the pipe elbow wall was the result of under-deposit corrosion, with tuberculation pitting. The licensees analysis further concluded that stagnate water conditions favorable for under-deposit pit formation present when the 1A EDG is in a standby condition allowed for an anaerobic (low oxygen)environment to form under the deposit layers at the metal surface and accelerate metal corrosion. No evidence of microbially induced corrosion (MIC) was detected by the licensees PowerLabs facility.

In response to this information, the licensee revisited their original corrective action that replaced the 1DX27DA-10 elbow with a new, like-for-like 10-inch carbon steel elbow, and determined the replacement of the carbon steel elbow with a stainless steel pipe elbow would be more effective at reducing the likelihood of under-deposit corrosion and through-wall penetration. Consequently, future replacements of these similar elbow sections with stainless steel components are planned and appear to be appropriate.

In the course of the inspectors review, no findings or violations of NRC requirements were identified.

Observation: Emergency Diesel Generator Non-Safety Starting Air System 71152S The inspectors performed a review of plant issues, particularly those entered into the licensees corrective action program (CAP) over the past several months. During their review, the inspectors noted that the licensee continues to experience performance issues involving the stations non-safety-related diesel generator starting air systems. Specific CAP entries reviewed by the inspectors included, but were not limited to:

- IR 4714650; 2DG01SB-B Not Working Properly

- IR 4710909; 2B DG Fast Start Time >7.5 sec

- IR 4699075; 1DG01SA-B Cycling Excessively

- IR 4696456; 2-22-C8, 2DG01SB-B O/L Tripped, 2B DG Support System

- IR 4691998; 2DG01SA-B Running Continuously

- IR 4690736; 2B DG Starting Air Compressor #1 Continuously Running

- IR 4689060; Abnormal Starting Air Indication During 2A DG Run

- IR 4683897; 2B DG #2 Air Compressor 2DG01SB-B Tripped Overloads

- IR 4681228; 2B D/G #2 Air Compressor Tripped Thermals

- IR 4538267; 1DG01SA-A, 1A DG #1 Air Compressor Running Continuously The starting air system for each diesel generator consists of two independent and redundant non-safety-related air systems for each emergency diesel generator (EDG). Although not safety-related, they are essential support equipment for the stations EDGs, which are highly risk significant. Each subsystem consists of one compressor, the associated drier assemblies, and all the associated control equipment and interconnecting piping. During normal operation, the air compressors maintain starting air header pressure in the air receiver tanks to start the EDGs and will automatically start if pressure drops too low.

The inspectors reviewed numerous IRs documenting issues with the compressors over the course of the year and the potential effects on operability of the EDGs. Each issue documented required an operability review of the EDGs and corrective maintenance to restore the compressors to a functional status. Although the issues never presented an operability concern at the time they arose, the inspectors noted that the repeat issues stressed operations and maintenance resources and had the capability if left uncorrected to affect the operability of the EDGs.

The inspectors did not identify any findings or violations of NRC requirements in the course of this review.

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 17, 2024, the inspectors presented the integrated inspection results to G. Gugle, Site Vice President, and other members of the licensee staff.
  • On December 20, 2023, the inspectors presented the emergency action level and emergency plan changes inspection results to D. Edwards, Emergency Preparedness Coordinator, and other members of the licensee staff.

THIRD PARTY REVIEWS As discussed in IMC 0611, Section 13.01, the inspectors completed a review of the report issued by the World Association of Nuclear Operators (WANO) for the most recent periodic plant evaluation completed at the Braidwood Station in August 2023.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

4719872

Division 11 MEER Temperature Low

11/27/2023

Corrective Action

Documents

22602

2A SAC Receiver Pressure Low SER 1849 During Cold

Weather

2/10/2023

Miscellaneous

Letter from Greg Gugle, Braidwood Generating Station Site

Vice President, to Marri Marchionda-Palmer, Senior Vice

President of Nuclear Operations Constellation Nuclear,

Certification of 2023-2924 Winter Readiness

11/15/2023

0BwOA ENV-1

Adverse Weather Conditions Unit 0

26

0BwOS XFT-A1

Unit Common Freezing Temperature Equipment Protection

Surveillance

0BwOS XFT-A2a

Unit Common Station Heat Area Heaters Freezing

Temperature Equipment Protection Surveillance

0BwOS XFT-A2b

Unit Common Station Heat Area Heaters Freezing

Temperature Equipment Protection Surveillance

0BwOS XFT-A3

Unit Common Cold Weather Surveillance

0BwOS XFT-A4

Unit Common Freezing Temperature Equipment Protection

Inside Surveillance

BwOP SI-10

RWST Heating Pump and Heater Operations

OP-AA-102-102

General Area Checks and Operator Field Rounds

OP-AA-108-111-

1001

Severe Weather and Natural Disaster Guidelines

OP-BR-102-102-

1001

Augmented Operator Field Rounds

71111.01

Procedures

WC-AA-107

Seasonal Readiness

BwOP AF-E1

Electrical Lineup - Unit One Operating

BwOP AF-E2

Electrical Lineup - Unit 2 Operating

BwOP AF-M1

Operating Mechanical Lineup Unit 1, Auxiliary Feedwater

BwOP AF-M2

Operating Mechanical Lineup Unit 2

BwOP SI-E1

Electrical Lineup - Unit 1 Operating

71111.04

Procedures

BwOP SI-M1

Operating Mechanical Lineup Unit 1

71111.05

Fire Plans

Pre-Fire Plan No.

118

Fire Zone 11.3A-1; Auxiliary Building 364' Elevation, Safety

Injection Pump 1A Room

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Pre-Fire Plan No.

135

Fire Zone 11.4A-0; Auxiliary Building 383' Elevation Control

Room, Refrigeration Equipment Room

BwAP 1110-1

Fire Protection System Requirements

OP-AA-201-008

Pre-Fire Plan Manual

Procedures

OP-AA-201-009

Control of Transient Combustible Material

OP-AA-101-111-

1001

Operations Standards and Expectations

OP-AA-101-113

Operator Fundamentals

OP-AA-101-113-

1006

4.0 Crew Critique Guidelines

OP-AA-103-102

Watch-Standing Practices

OP-AA-103-102-

1001

Strategies for Successful Transient Mitigation

OP-AA-103-103

Operation of Plant Equipment

OP-AA-104-101

Communications

OP-AA-111-101

Operating Narrative Logs and Records

OP-AA-300

Reactivity Management

TQ-AA-10

Systematic Approach to Training Process Description

TQ-AA-150

Operator Training Programs

TQ-AA-155

Conduct of Simulator Training and Evaluation

TQ-AA-201

Examination Security and Administration

TQ-AA-306

Simulator Management

71111.11Q

Procedures

TQ-BR-201-0113

Braidwood Training Department Simulator Examination

Security Actions

4348354

0VA01CC Vibration Analysis Results

06/05/2020

4388101

A Train VC Heaters Not Functioning Properly

2/04/2020

29807

0TIC-VC086 Not Maintaining MCR Temperature

10/16/2022

4548411

0VC05FB Charcoal Test Canister Depleted

01/13/2023

Corrective Action

Documents

22049

WO #05423567-06; 0F-VC236

2/07/2023

ER-AA-310-1002

Maintenance Rule FunctionsSafety Significant Classification

ER-AA-320-1001

Maintenance Rule 18-10Scoping

ER-AA-320-1003

Maintenance Rule 18.10Failure Definitions

71111.12

Procedures

ER-AA-320-1004

Maintenance Rule 18-10Performance Monitoring and

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Dispositioning Between (a)(1) and (a)(2)

ER-AA0320

Maintenance Rule Implementation per NEI-18-10

Corrective Action

Documents

4706461

2WO56A Open Light Indication Lost

10/02/2023

Miscellaneous

Final RICT Record for 2B Auxiliary Feedwater Pump Diesel

Engine Bearing Inspections/Replacements Maintenance

Window

10/16/2023

ER-AA-600

Risk Management

ER-AA-600-1023

PARAGON Model Capability

ER-AA-600-1042

On-Line Risk Management

ER-AA-600-1052

Risk Management Support of RICT

ER-AA-600-1053

Calculation of RMAT and RICT for Risk Informed Completion

Time Program

ER-BW-600-2001

Braidwood RICT System Guidelines

OP-AA-107

Integrated Risk Management

OP-AA-108-117

Protected Equipment Program

OP-AA-108-118

Risk Informed Completion Time

Procedures

WC-AA-101-1006

On-Line Risk Management and Assessment

71111.13

Work Orders

5404748

2WO056A Open LIght Indication Lost

10/17/2023

4709877

Unexpected Annunciators 1-10-D7 and 1-10-E7

10/16/2023

Corrective Action

Documents

4713882

Unexpected Alarm, 2-10-B4 Power Range Lower Detector

Flux Deviation High

10/31/2023

1BwOS PDMS-1a

AAR Power Distribution Monitoring System (ODMS)

1BwOS TRM

3.3.h.1

Unit One Power Distribution Monitoring System (PDMS)

Operability Weekly Surveillance

71111.15

Procedures

BwOP RC-12

Placing RVLIS/HJTC/CETC in Service

4704174

Abnormalities Stroking 1AF004A (1BwOSR 5.5.8.AF-3A)

09/21/2023

4710909

2B EDG Fast Start Time >7.5 sec

10/19/2023

4719810

1AF022A Close Limit Switch Needs Replacement

11/27/2023

Corrective Action

Documents

4719814

1AF024 Indication Limit Switch Needs Adjustment

11/27/2023

1BwOSR

5.5.8.AF-3A

Group A IST Requirements for Unit One Motor Driven Auxiliary

Feedwater Pump

71111.24

Procedures

1BwOSR

Comprehensive Full Flow Test for 1A Containment Spray

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

5.5.8CS-3A

Pump (1CS01PA) and Check Valves 1CS003A, 1CS011A)

2BwOSR 3.8.1.2-

Unit Two 2B Diesel Generator Operability Surveillance

2BwOSR

5.5.8.AF-3B

Group A IST Requirements for Unit Two Diesel Driven

Auxiliary Feedwater Pump

5383878

2B EDG Operability Monthly

10/19/2023

5401820

OP ASME Surveillance on Unit 1 Train A Containment Spray

(1CS01PA)

2/06/2023

5401827

Unit 2 Diesel Driven Auxiliary Feedwater Pump Monthly Run

10/14/2023

5402459

Post-Maintenance Testing 2AF01PB: Perform ASME and

Verify No Leaks

10/13/2023

5404667

2B Diesel Generator Operability Semi-Annual Surveillance

10/19/2023

Work Orders

5408735

Unit 1 Motor Driven Auxiliary Feedwater Pump ASME

Quarterly Surveillance

11/27/2023

Calculations

EP-AA-1001

Addendum 3

Revision: 7

Evaluation No.:

21-72

§50.54(q) Program Evaluation/Assessment Review:

Emergency Action Levels for Braidwood Station

01/20/2022

EP-AA-1000

Standardized Radiological Emergency Plan

EP-AA-1001

Radiological Emergency Plan Annex for Braidwood Station

EP-AA-1001

Addendum 1

Braidwood Station On-Shift Staffing Technical Basis

71114.04

Procedures

EP-AA-1001

Addendum 3

Emergency Action Levels for Braidwood Station

Miscellaneous

23 Braidwood Off Year Exercise Scenario

10/03/2023

EP-AA-1000

Standardized Radiological Emergency Plan

EP-AA-1001

Radiological Emergency Plan Annex for Braidwood Station

71114.06

Procedures

EP-AA-1001

Addendum 3

Constellation EP-AA-1001 Addendum 3

NRC Performance Indicator Data; Barrier Integrity - RCS

Identified Leakage

10/01/2022-

09/30/2023

71151

Miscellaneous

LS-AA-2090

Monthly Data Elements for NRC ROP Indicator - Reactor

Coolant System (RCS) Specific Activity

various

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

LS-AA-2140

Monthly Data Elements for NRC ROP Indicator - Occupational

Exposure Control Effectiveness

various

LS-AA-2150

Monthly Data Elements for NRC ROP Indicator - RETS/ODCM

Radiological Effluent Occurrences

various

LS-AA-2001

Collecting and Reporting of NRC Performance Indicator Data

Procedures

LS-AA-2100

Monthly Data Elements for NRC Reactor Coolant System

(RCS) Leakage

4550393

Leak on Underside of Piping Just Downstream of 1SX057A

01/25/2023

4550412

Trend in SX System Leaks

01/25/2023

4551315

Scope Expansion Inspections on 1SX27DB-10'

01/30/2023

4551316

Scope Expansion Inspections on 2SX27DA-10'

01/30/2023

4551318

Scope Expansion Inspections on 1SX26AB-10"

01/30/2023

4551319

Scop Expansion Inspections on 1SX26AA-10'

01/30/2023

4555829

Review of UT [Ultrasonic Testing] Data from 2SX27DA-10'

2/20/2023

4697594

2MS018JC Abnormal Indications

08/21/2023

4702773

2MS018JC Abnormal Indications

09/15/2023

4704254

2MS018JC Abnormal Indications

09/22/2023

4706721

2MS018JC Abnormal Indications

10/03/2023

4708516

Review of 10/5/23 UT [Ultrasonic Testing] Follow Up Data

from 2SX27DA-10'

10/10/2023

4708650

2MS018JC Abnormal

2/11/2023

4710584

2MS018JC Fan Filter Replacement

10/18/2023

4716007

2MS018JC Abnormal Indications (Repeat Issue)

10/07/2023

4717796

2MS018JC Amplifier Replacement

11/15/2023

Corrective Action

Documents

4719624

2MS018JC Abnormal Indications (Repeat Issue)

11/26/2023

BwOP MS-14

Resetting of the Steam Generator Power Operated Relief

Valve

NO-AA-10

Quality Assurance Topical Report (QATR)

PI-AA-120

Issue Identification and Screening Process

PI-AA-125

Corrective Action Program (CAP) Procedure

PI-AA-125-1001

Root Cause Analysis Manual

PI-AA-125-1003

Corrective Action Program Evaluation Manual

71152A

Procedures

PI-AA-125-1004

Effectiveness Review Manual 2NO-AA-10

Q

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

5310334-04

Replace 2C PORV Controller PWM Chassis with New

11/30/2023

Work Orders

IR 4550413,

Action No. 22

Failure Analysis of 1SX27DA Leak Location

11/10/2023

4538267

1DG01SA-A, 1A DG #1 Air Compressor Running Continuously

11/22/2022

4681228

2B D/G #2 Air Compressor Tripped Thermals

05/29/2023

4683897

2B DG #2 Air Compressor 2DG01SB Tripped Overloads

06/10/2023

4689060

Abnormal Starting Air Indication During 2A DG Run

07/06/2023

4690736

2B DG Starting Air Compressor #1 Continuously Running

07/15/2023

4691998

2DG01SA-B Running Continuously

07/22/2023

4696456

2-22-C8 2DG01SB O/L Tripped, 2B DG Support System

08/15/2023

4699075

1DG01SA-B Cycling Excessively

08/29/2023

4710909

2B DG Afast Start Time >7.5 sec

10/19/2023

71152S

Corrective Action

Documents

4714650

2DG01SB Not Working Properly

11/02/2023

238259

1AF01PB Crankcase Oil Analysis Degrading Trend

04/10/2019

4703982

Degraded Oil in 2B Diesel-Driven Auxiliary Feedwater

(2AF01PB) Engine Crank Case

09/21/2023

4704473

2AF01PB - 5L Return Line Leaking

09/23/2023

4704480

2AF01PB - 2R Ruel Return Line Leaking

09/23/2023

4706623

Review of 2B AF Pump Oil Results

10/02/2023

4708247

Review of 2B AF Pump Oil Results

10/09/2023

4708461

2B AF Main Bearing Degraded

10/10/2023

4708525

2B AF Pump 3L Fuel Injector Leaking

10/10/2023

4708613

Inspect/Repair Fuel Leak Visually Identified Abnormality

10/10/2023

4708713

2B Auxiliary Feedwater Removed Fuel Injector on No. 3 Left

10/11/2023

4709470

1B AF Pump Extent-of-Condition Fuel Dilution Review Results

10/13/2023

Corrective Action

Documents

4709534

2AF01PB Rocker Cover Leaks

10/14/2023

Corrective Action

Documents

Resulting from

Inspection

4706606

Information in 2B AF Vendor Manual and Oil Sample

10/02/2023

71153

Miscellaneous

Various Bureau Veritas (VEndor) Lube Oil Analysis

Management System (LOAMS) Reports for the 2B AF Diesel

Engine (2AF01PB)

03/10/2023-

2/14/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Detroit Diesel

Series 149

Engine Service

Manual

08/1997

2BwOS TRM

2.7.a.1

Unit Two Auxiliary Feedwater Diesel Prime Mover

Performance Surveillance

2BwOSR 3.7.5.4-

Unit Two Diesel Driven Auxiliary Feedwater Pump

Surveillance

BwMP 3200-014

Auxiliary Feedwater Pump Diesel Drive Unit Inspection and

Maintenance

BwOP AF-300

Sampling Auxiliary Feedwater Diesel Lube Oil (AF01PB)

BwOP AF-7

Auxiliary Feedwater Pump B (Diesel) Startup on Recirc

MA-AA-716-230

Predictive Maintenance Program

MA-AA-716-230-

1001

Oil Analysis Interpretation Guideline

Procedures

MA-AA-716-230-

1004

Lubricant Sampling Guideline

1865780

2AF01PB-K 12-Year Preventative Maintenance (PM) for

Auxiliary Feedwater Diesels

05/01/2023

230646

2AF01PB - Perform 18-Month Inspection

04/28/2023

5350643

Unit 2 Diesel-Driven Auxiliary Feedwater Pump ASME

Quarterly Surveillance

05/19/2023

5371917

Unit 2 Diesel-Driven Auxiliary Feedwater Pump Monthly Run

06/08/2023

5378877

Unit 2 Diesel-Driven Auxiliary Feedwater Pump Monthly Run

07/14/2023

5379233

Unit 2 Diesel-Driven Auxiliary Feedwater Pump ASME

Quarterly Surveillance

09/01/2023

5385077

Unit 2 Diesel-Driven Auxiliary Feedwater Pump Monthly Run

08/10/2023

5402459-01

Mechanical Maintenance: Change Oil in 2AF01PB Crank Case

09/22/2023

5402459-03

Mechanical Maintenance: 2AF01PB - Repair Suspected Fuel

Leak

09/22/2023

5402459-09

Mechanical Maintenance: 2AF01PB - Inspect Main Crank

Shaft Bearings

10/09/2023

Work Orders

5402959-13

Mechanical Maintenance: 2AF01PB - Inspect/Repair Fuel

Leak

10/09/2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

5402959-18

Operations: Perform 2AF01PB Engine Break-In Following

Maintenance

10/13/2023