|
---|
Category:INSPECTION REPORT
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes IR 05000336/19982021998-06-11011 June 1998 Insp Rept 50-336/98-202 on 980302-0409.Violations Noted. Major Areas Inspected:Cooling Water Sys ML20248E6131998-05-26026 May 1998 Insp Repts 50-245/98-206,50-336/98-206 & 50-423/98-206 on 980101-0228.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000423/19980811998-05-22022 May 1998 Insp Rept 50-423/98-81 on 980302-31 & 0412.Violations Noted. Major Areas Inspected:Plant Support IR 05000423/19982051998-05-0808 May 1998 Insp Rept 50-423/98-205 on 980223-0306.Violations Noted. Major Areas Inspected:Corrective Action Implemention Insp IR 05000423/19980011998-05-0606 May 1998 Insp Rept 50-423/98-01 on 980223-26.Violation Noted.Major Areas Inspected:Emergency Preparedness Program,Plant Support IR 05000245/19982101998-04-21021 April 1998 Evaluation Repts 50-245/98-210,50-336/98-210 & 50-423/98-210 on 971208-12 & 980105-09.No Violations Noted.Major Areas Inspected:Status & Effectivness of Independent third-party, Oversight Program,Established to Oversee ECP Implementation IR 05000245/19970121998-04-20020 April 1998 Evaluation Repts 50-245/97-12,50-336/97-12 & 50-423/97-12 on 971208-12 & 980105-09.No Violations Noted.Major Areas Evaluated:Implementation of ECP & Employee Concerns Oversight Program at Millstone IR 05000423/19972101998-04-0303 April 1998 Insp Rept 50-423/97-210 on 980105-0206.Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Program,Effectiveness of Sargent & Lundy Review of Sys Objectives & Quench & Recirculation Spray Sys IR 05000245/19980801998-04-0101 April 1998 Insp Repts 50-245/98-80,50-336/98-80 & 50-423/98-80 on 980223-26.No Violation Noted.Major Areas Inspected:Status of EP Facilities,Equipment & Resources,Ep Procedures & Documentation & Staff Knowledge & Performance IR 05000423/19972091998-04-0101 April 1998 Insp Rept 50-423/97-209 on 971027-980128.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Licensing Bases Deficiencies IR 05000423/19980821998-03-27027 March 1998 Insp Rept 50-423/98-82 on 980209-27.Violations Noted.Major Areas Inspected:Millstone Unit 3 MOV Program,Including Various C/A Taken IR 05000245/19972081998-02-25025 February 1998 Insp Repts 50-245/97-208,50-336/97-208 & 50-423/97-208 on 971201-31.Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000336/19970841998-02-0909 February 1998 Insp Repts 50-336/97-84 & 50-423/97-84 on 970915-19.No Violations Noted.Major Areas Inspected:Review of post-fire Safe Shutdown Program for Unit 2 & Control of Configuration of post-fire Safe Shutdown Equipment for Unit 3 IR 05000336/19972111998-02-0909 February 1998 Insp Rept 50-336/97-211 on 970825-29,0902-05 & 1201-05.No Violations Noted.Major Areas Inspected:Evaluation of Parson Implementation of Independent CA Verification Program Audit Plan IR 05000245/19970851998-02-0606 February 1998 Insp Repts 50-245/97-85,50-336/97-85 & 50-423/97-85 on 971001-17,1120-21 & 1204-12.No Violations Noted.Major Areas Inspected:Simulator Portion of Annual Operating Tests of Licensed Operator Requalification Training Programs IR 05000245/19972071998-01-0909 January 1998 Insp Repts 50-245/97-207,50-336/97-207 & 50-423/97-207 on 971002-1130.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20202J8191997-12-0505 December 1997 Insp Rept 50-423/97-206 on 970818-29 & 0908-19.Violations Noted.Major Areas Inspected:Licensees Configuration Mgt Plan & Emergency Core Cooling & Seal Injection Functions of Charging Sys ML20202A7071997-11-24024 November 1997 Insp Repts 50-245/97-81,50-336/97-81 & 50-423/97-81 on 970820-22.No Violations Noted.Major Areas Inspected: Licensee Emergency Response Organization During Biennial, full-participation Exercise IR 05000245/19972031997-11-21021 November 1997 Insp Repts 50-245/97-203,50-336/97-203 & 50-423/97-203 on 970722-1001.Violations Noted.Major Areas Inspected:Maint, Engineering,Plant Support & Conduct of Operations ML20210S8861997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970520-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support Re Performance in Emergency Preparedness & Control of FP Activities IR 05000245/19972021997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970529-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support,Including Emergency Preparedness Issues & Fire Protection Activities ML20141E3411997-06-24024 June 1997 Insp Repts 50-245/97-02,50-336/97-02 & 50-423/97-02 on 970311-0519.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20140C5641997-04-11011 April 1997 Insp Repts 50-245/97-01,50-336/97-01 & 50-423/97-01 on 970101-0310.Violations Noted.Major Areas Inspected:Maint, Engineering & Plant Support ML20140C0421997-03-26026 March 1997 Insp Repts 50-245/97-03,50-336/97-03 & 50-423/97-03 on 970203-07.No Violations Noted.Major Ares Inspected: Audits,Security Training,Equipment Testing & Management Support 1999-09-14
[Table view] Category:NRC-GENERATED
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes IR 05000336/19982021998-06-11011 June 1998 Insp Rept 50-336/98-202 on 980302-0409.Violations Noted. Major Areas Inspected:Cooling Water Sys ML20248E6131998-05-26026 May 1998 Insp Repts 50-245/98-206,50-336/98-206 & 50-423/98-206 on 980101-0228.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000423/19980811998-05-22022 May 1998 Insp Rept 50-423/98-81 on 980302-31 & 0412.Violations Noted. Major Areas Inspected:Plant Support IR 05000423/19982051998-05-0808 May 1998 Insp Rept 50-423/98-205 on 980223-0306.Violations Noted. Major Areas Inspected:Corrective Action Implemention Insp IR 05000423/19980011998-05-0606 May 1998 Insp Rept 50-423/98-01 on 980223-26.Violation Noted.Major Areas Inspected:Emergency Preparedness Program,Plant Support IR 05000245/19982101998-04-21021 April 1998 Evaluation Repts 50-245/98-210,50-336/98-210 & 50-423/98-210 on 971208-12 & 980105-09.No Violations Noted.Major Areas Inspected:Status & Effectivness of Independent third-party, Oversight Program,Established to Oversee ECP Implementation IR 05000245/19970121998-04-20020 April 1998 Evaluation Repts 50-245/97-12,50-336/97-12 & 50-423/97-12 on 971208-12 & 980105-09.No Violations Noted.Major Areas Evaluated:Implementation of ECP & Employee Concerns Oversight Program at Millstone IR 05000423/19972101998-04-0303 April 1998 Insp Rept 50-423/97-210 on 980105-0206.Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Program,Effectiveness of Sargent & Lundy Review of Sys Objectives & Quench & Recirculation Spray Sys IR 05000245/19980801998-04-0101 April 1998 Insp Repts 50-245/98-80,50-336/98-80 & 50-423/98-80 on 980223-26.No Violation Noted.Major Areas Inspected:Status of EP Facilities,Equipment & Resources,Ep Procedures & Documentation & Staff Knowledge & Performance IR 05000423/19972091998-04-0101 April 1998 Insp Rept 50-423/97-209 on 971027-980128.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Licensing Bases Deficiencies IR 05000423/19980821998-03-27027 March 1998 Insp Rept 50-423/98-82 on 980209-27.Violations Noted.Major Areas Inspected:Millstone Unit 3 MOV Program,Including Various C/A Taken IR 05000245/19972081998-02-25025 February 1998 Insp Repts 50-245/97-208,50-336/97-208 & 50-423/97-208 on 971201-31.Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000336/19970841998-02-0909 February 1998 Insp Repts 50-336/97-84 & 50-423/97-84 on 970915-19.No Violations Noted.Major Areas Inspected:Review of post-fire Safe Shutdown Program for Unit 2 & Control of Configuration of post-fire Safe Shutdown Equipment for Unit 3 IR 05000336/19972111998-02-0909 February 1998 Insp Rept 50-336/97-211 on 970825-29,0902-05 & 1201-05.No Violations Noted.Major Areas Inspected:Evaluation of Parson Implementation of Independent CA Verification Program Audit Plan IR 05000245/19970851998-02-0606 February 1998 Insp Repts 50-245/97-85,50-336/97-85 & 50-423/97-85 on 971001-17,1120-21 & 1204-12.No Violations Noted.Major Areas Inspected:Simulator Portion of Annual Operating Tests of Licensed Operator Requalification Training Programs IR 05000245/19972071998-01-0909 January 1998 Insp Repts 50-245/97-207,50-336/97-207 & 50-423/97-207 on 971002-1130.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20202J8191997-12-0505 December 1997 Insp Rept 50-423/97-206 on 970818-29 & 0908-19.Violations Noted.Major Areas Inspected:Licensees Configuration Mgt Plan & Emergency Core Cooling & Seal Injection Functions of Charging Sys ML20202A7071997-11-24024 November 1997 Insp Repts 50-245/97-81,50-336/97-81 & 50-423/97-81 on 970820-22.No Violations Noted.Major Areas Inspected: Licensee Emergency Response Organization During Biennial, full-participation Exercise IR 05000245/19972031997-11-21021 November 1997 Insp Repts 50-245/97-203,50-336/97-203 & 50-423/97-203 on 970722-1001.Violations Noted.Major Areas Inspected:Maint, Engineering,Plant Support & Conduct of Operations ML20210S8861997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970520-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support Re Performance in Emergency Preparedness & Control of FP Activities IR 05000245/19972021997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970529-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support,Including Emergency Preparedness Issues & Fire Protection Activities ML20141E3411997-06-24024 June 1997 Insp Repts 50-245/97-02,50-336/97-02 & 50-423/97-02 on 970311-0519.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20140C5641997-04-11011 April 1997 Insp Repts 50-245/97-01,50-336/97-01 & 50-423/97-01 on 970101-0310.Violations Noted.Major Areas Inspected:Maint, Engineering & Plant Support ML20140C0421997-03-26026 March 1997 Insp Repts 50-245/97-03,50-336/97-03 & 50-423/97-03 on 970203-07.No Violations Noted.Major Ares Inspected: Audits,Security Training,Equipment Testing & Management Support 1999-09-14
[Table view] Category:INSPECTION REPORT
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes IR 05000336/19982021998-06-11011 June 1998 Insp Rept 50-336/98-202 on 980302-0409.Violations Noted. Major Areas Inspected:Cooling Water Sys ML20248E6131998-05-26026 May 1998 Insp Repts 50-245/98-206,50-336/98-206 & 50-423/98-206 on 980101-0228.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000423/19980811998-05-22022 May 1998 Insp Rept 50-423/98-81 on 980302-31 & 0412.Violations Noted. Major Areas Inspected:Plant Support IR 05000423/19982051998-05-0808 May 1998 Insp Rept 50-423/98-205 on 980223-0306.Violations Noted. Major Areas Inspected:Corrective Action Implemention Insp IR 05000423/19980011998-05-0606 May 1998 Insp Rept 50-423/98-01 on 980223-26.Violation Noted.Major Areas Inspected:Emergency Preparedness Program,Plant Support IR 05000245/19982101998-04-21021 April 1998 Evaluation Repts 50-245/98-210,50-336/98-210 & 50-423/98-210 on 971208-12 & 980105-09.No Violations Noted.Major Areas Inspected:Status & Effectivness of Independent third-party, Oversight Program,Established to Oversee ECP Implementation IR 05000245/19970121998-04-20020 April 1998 Evaluation Repts 50-245/97-12,50-336/97-12 & 50-423/97-12 on 971208-12 & 980105-09.No Violations Noted.Major Areas Evaluated:Implementation of ECP & Employee Concerns Oversight Program at Millstone IR 05000423/19972101998-04-0303 April 1998 Insp Rept 50-423/97-210 on 980105-0206.Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Program,Effectiveness of Sargent & Lundy Review of Sys Objectives & Quench & Recirculation Spray Sys IR 05000245/19980801998-04-0101 April 1998 Insp Repts 50-245/98-80,50-336/98-80 & 50-423/98-80 on 980223-26.No Violation Noted.Major Areas Inspected:Status of EP Facilities,Equipment & Resources,Ep Procedures & Documentation & Staff Knowledge & Performance IR 05000423/19972091998-04-0101 April 1998 Insp Rept 50-423/97-209 on 971027-980128.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Licensing Bases Deficiencies IR 05000423/19980821998-03-27027 March 1998 Insp Rept 50-423/98-82 on 980209-27.Violations Noted.Major Areas Inspected:Millstone Unit 3 MOV Program,Including Various C/A Taken IR 05000245/19972081998-02-25025 February 1998 Insp Repts 50-245/97-208,50-336/97-208 & 50-423/97-208 on 971201-31.Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support IR 05000336/19970841998-02-0909 February 1998 Insp Repts 50-336/97-84 & 50-423/97-84 on 970915-19.No Violations Noted.Major Areas Inspected:Review of post-fire Safe Shutdown Program for Unit 2 & Control of Configuration of post-fire Safe Shutdown Equipment for Unit 3 IR 05000336/19972111998-02-0909 February 1998 Insp Rept 50-336/97-211 on 970825-29,0902-05 & 1201-05.No Violations Noted.Major Areas Inspected:Evaluation of Parson Implementation of Independent CA Verification Program Audit Plan IR 05000245/19970851998-02-0606 February 1998 Insp Repts 50-245/97-85,50-336/97-85 & 50-423/97-85 on 971001-17,1120-21 & 1204-12.No Violations Noted.Major Areas Inspected:Simulator Portion of Annual Operating Tests of Licensed Operator Requalification Training Programs IR 05000245/19972071998-01-0909 January 1998 Insp Repts 50-245/97-207,50-336/97-207 & 50-423/97-207 on 971002-1130.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20202J8191997-12-0505 December 1997 Insp Rept 50-423/97-206 on 970818-29 & 0908-19.Violations Noted.Major Areas Inspected:Licensees Configuration Mgt Plan & Emergency Core Cooling & Seal Injection Functions of Charging Sys ML20202A7071997-11-24024 November 1997 Insp Repts 50-245/97-81,50-336/97-81 & 50-423/97-81 on 970820-22.No Violations Noted.Major Areas Inspected: Licensee Emergency Response Organization During Biennial, full-participation Exercise IR 05000245/19972031997-11-21021 November 1997 Insp Repts 50-245/97-203,50-336/97-203 & 50-423/97-203 on 970722-1001.Violations Noted.Major Areas Inspected:Maint, Engineering,Plant Support & Conduct of Operations ML20210S8861997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970520-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support Re Performance in Emergency Preparedness & Control of FP Activities IR 05000245/19972021997-08-29029 August 1997 Insp Repts 50-245/97-202,50-336/97-202 & 50-423/97-202 on 970529-0721.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support,Including Emergency Preparedness Issues & Fire Protection Activities ML20141E3411997-06-24024 June 1997 Insp Repts 50-245/97-02,50-336/97-02 & 50-423/97-02 on 970311-0519.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support ML20140C5641997-04-11011 April 1997 Insp Repts 50-245/97-01,50-336/97-01 & 50-423/97-01 on 970101-0310.Violations Noted.Major Areas Inspected:Maint, Engineering & Plant Support ML20140C0421997-03-26026 March 1997 Insp Repts 50-245/97-03,50-336/97-03 & 50-423/97-03 on 970203-07.No Violations Noted.Major Ares Inspected: Audits,Security Training,Equipment Testing & Management Support 1999-09-14
[Table view] Category:UTILITY
MONTHYEARIR 05000245/19900231990-11-15015 November 1990 Insp Repts 50-245/90-23,50-336/90-25 & 50-423/90-23 on 901001-05.No Violations Noted.Major Areas Inspected: Radiological Controls Program IR 05000423/19900191990-11-14014 November 1990 Insp Rept 50-423/90-19 on 900905-1015.Violations Noted. Major Areas Inspected:Operations,Radiological & Chemistry Controls & Security & Maint & Surveillance IR 05000213/19900831990-11-0505 November 1990 Insp Repts 50-213/90-83,50-245/90-82,50-336/90-82 & 50-423/90-83 on 900924-28.No Violations Noted.Major Areas Inspected:Licensee Timeliness for Reporting/Operability Determinations IR 05000336/19900181990-11-0505 November 1990 Insp Rept 50-336/90-18 on 900822-1001.One Cited Violation, One Noncited Violation & One Deviation Noted.Major Areas Inspected:Plant Operations,Surveillance,Maint,Previously Identified Items,Engineering/Technical Support IR 05000245/19900191990-10-26026 October 1990 Safety Insp Repts 50-245/90-19,50-336/90-21 & 50-423/90-17 on 900904-07.No Violations or Deviations Identified.Major Areas Inspected:Qa Program Implementation IR 05000213/19900821990-10-23023 October 1990 Insp Repts 50-213/90-82,50-245/90-81,50-336/90-81 & 50-423/90-82,on 901001-12.No Violations Noted.Major Areas Inspected:Licensee Occupational Radiation Protection Program Activities During Unit 1 Refueling Outage IR 05000336/19900191990-10-15015 October 1990 Insp Rept 50-336/90-19 on 900910-14.No Violations Noted. Major Areas Inspected:Open Items & Allegations from Insp Rept 50-336/89-13 IR 05000245/19900161990-10-0303 October 1990 Partially Withheld Insp Repts 50-245/90-16,50-336/90-17 & 50-423/90-16 on 900827-31.Violations Noted IR 05000423/19900101990-08-17017 August 1990 Insp Rept 50-423/90-10 on 900612-0723.Violations Noted.Major Areas Inspected:Normal & Backshift Work Periods of Plant Operations,Maint & Surveillance,Security,Engineering & Technical Support,Radiological Controls & Safety Assessment IR 05000245/19900141990-08-16016 August 1990 Insp Repts 50-245/90-14,50-336/90-15 & 50-423/90-13 on 900723-27.One Noncited Violation Noted.Major Areas Inspected:Radiological Controls IR 05000423/19900061990-08-14014 August 1990 Insp Rept 50-423/90-06 on 900604-08.No Violations or Deviations Noted.Major Areas Inspected:Training Program, Including Licensed Operator Training Program for Initial Licensing & Requalification Program for Licensed Operators IR 05000245/19900111990-08-0909 August 1990 Insp Repts 50-245/90-11,50-336/90-12 & 50-423/90-09 on 900611-15 & 25-29.No Violations Noted.Major Areas Inspected: Review of Licensee Emergency Diesel Generator Fuel Oil Program IR 05000423/19900801990-08-0202 August 1990 Insp Rept 50-423/90-80 on 900416-25.No Violations Noted. Major Areas Inspected:Development of Sufficient Procedures in Appropriate Areas to Cover Broad Spectrum of Accidents & Equipment Failures IR 05000336/19900111990-07-31031 July 1990 Insp Rept 50-336/90-11 on 900530-0711.Noncited Violations Noted.Major Areas Inspected:Plant Operations,Radiological Controls/Emergency Preparedness,Maint/Surveillance, Engineering/Technical Support & Security IR 05000245/19900131990-07-24024 July 1990 Insp Repts 50-245/90-13,50-336/90-13 & 50-423/90-11 on 900609-13.No Violations or Deviations Noted.Major Areas Inspected:Radiological Environ Monitoring Program,Including Mgt Controls,Audits & Surveillance Procedures IR 05000245/19900091990-07-20020 July 1990 Insp Rept 50-245/90-09 on 900515-0625.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint/Surveillance,Security,Engineering/Technical Support & Safety Assessment/Quality Verification IR 05000245/19900071990-07-0606 July 1990 Insp Rept 50-245/90-07 on 900403-0514.No Violations Noted. Major Areas Inspected:Plant Operations,Radiological Controls,Maint/Surveillance,Security,Engineering/Technical Support & Safety Assessment/Quality Verification IR 05000423/19900081990-07-0303 July 1990 Partially Withheld Insp Rept 50-423/90-08 on 900503-0611 (Ref 10CFR73.21).Violations Noted.Major Areas Inspected: Maint & Surveillance,Security,Engineering & Technical Support & Safety Assessment & Quality Verification IR 05000336/19900081990-07-0202 July 1990 Insp Rept 50-336/90-08 on 900425-27.No Violations Noted. Major Areas Inspected:Results of Eddy Current Exam of Steam Generators Performed During Oct 1989,w/emphasis on Acceptable Period of Operation for Steam Generators ML20055E7991990-06-29029 June 1990 Insp Rept 50-336/90-09 on 900417-0529.Violations Noted. Major Areas Inspected:Plant Operations,Surveillance,Maint, Previously Identified Items,Engineering/Technical Support, Committee Activities,Periodic Repts,Lers & Allegations ML20055D1431990-06-20020 June 1990 Enforcement Conference Rept 50-245/90-08 on 900615.Major Areas Discussed:Findings in Insp Rept 50-245/90-08 Re Shipment of Irradiated Hardware as Radwaste to Low Level Waste Disposal Facility in Barnwell,Sc on 900507 ML20055C3161990-02-21021 February 1990 Insp Rept 50-245/89-19 on 891023-27.Unresolved Items Noted. Major Areas Inspected:Review of Selected Deviations from Rev 4 to to GE Topical Rept NEDO-31331, Emergency Procedure Guidelines & Response to NRC Bulletin 88-007,Suppl 1 IR 05000423/19890191989-09-22022 September 1989 Insp Rept 50-423/89-19 on 890828-0901.No Violations Noted. Major Areas Inspected:Radiological & non-radiological Chemistry Program Including Confirmatory Measurements, Chemistry & Lab Qa/Qc IR 05000245/19890181989-09-13013 September 1989 Insp Repts 50-245/89-18,50-336/89-18 & 50-423/89-15 on 890807-11.No Violations Noted.Major Areas Inspected:Util Compliance W/Atws Rule (10CFR50.62) & QA Annual Review, Including Procurement Program & Matl Receipt & Storage IR 05000245/19890801989-08-31031 August 1989 Insp Repts 50-245/89-80,50-336/89-80 & 50-423/89-80 on 890530-0616 & 0710-14.No Violations Noted.Major Areas Inspected:Units 1,2 & 3 Maint Program & Implementation, Review of Maint Documents & Observation of Work in Progress IR 05000336/19890161989-08-21021 August 1989 Insp Rept 50-336/89-16 on 890616-0726.Violation Noted.Major Areas Inspected:Plant Operations,Surveillance,Maint, Previously Identified Items,Committee Activities,Emergency Diesel Generator Operation & Fuel Oil Sys IR 05000423/19890131989-08-21021 August 1989 Insp Rept 50-423/89-13 on 890724-28.No Violations Noted. Major Areas Inspected:Fire Protection Prevention Program IR 05000245/19890161989-08-0202 August 1989 Insp Repts 50-245/89-16 & 50-336/89-15 on 890711-14.No Violations Noted.Major Areas Inspected:Implementation of Radiation Protection Program IR 05000423/19890111989-08-0202 August 1989 Insp Rept 50-423/89-11 on 890613-0717.No Violations Noted. Major Areas Inspected:Facility Tours of MP-3 Site,Esf Sys Walkdowns of Recirculation Spray Sys,Si Pump Cooling Sys, Turbine Driven Auxiliary Feed Pump Sys & Review of LERs IR 05000245/19890141989-07-28028 July 1989 Insp Rept 50-245/89-14 on 890616-0717.No Unsafe Conditions Noted.Major Areas Inspected:Plant Operations,Physical Security,Control Room Exercise Equipment & NRC Temporary Instruction 2513/93 IR 05000423/19890121989-07-21021 July 1989 Insp Rept 50-423/89-12 on 890626-30.No Violations or Deviations Noted.Major Areas Inspected:Inservice Insp Program,Steam Generator Eddy Current Insps & Water Chemistry Results IR 05000336/19890111989-07-21021 July 1989 Insp Rept 50-336/89-11 on 890505-0615.No Unsafe Conditions Noted.Major Areas Inspected:Plant Operations,Surveillance, Maint,Previously Identified Items,Allegations,Committee Activities,Licensee self-assessment & LERs IR 05000245/19890121989-07-19019 July 1989 Insp Rept 50-245/89-12 on 890509-0615.Major Areas Inspected: Previously Identified Items,Outage Activities,Plant Operations,Physical Security,Recirculation Pump Seal Failure Event,Reactor Scram on Low Main Condenser Vacuum & LERs IR 05000423/19890081989-07-11011 July 1989 Insp Rept 50-423/89-08 on 890515-0612.No Violations Noted. Major Areas Inspected:Plant Operations,Unresolved Item 50-423/87-12-01,previous Insp Findings,Plant Incident Repts, in-core Thimble Degradation & 10CFR50.59 Safety Evalautions IR 05000245/19890151989-07-0505 July 1989 Insp Repts 50-245/89-15,50-336/89-14 & 50-423/89-10 on 890619-23.No Violations or Deviations Noted.Major Areas Inspected:Effluent,Transportation & Solid Radwaste Programs, Including Mgt Controls,Audits,Qa & Program Implementation IR 05000245/19890131989-06-29029 June 1989 Enforcement Conference Rept 50-245/89-13 on 890621.Major Areas Discussed:Shipment of High Pressure Pump & Trailer W/ Removable External Radioactive Contamination from Licensee Reactor Site to Vendor Site in Moorestown,Nj IR 05000423/19890041989-06-28028 June 1989 Insp Rept 50-423/89-04 on 890405-0515.No Violations Noted. Major Areas Inspected:Plant Incident Repts,Reactor Scrams, Shutdown to Repair High Unidentified Leakage & Repair to Svc Water Piping & Physical Security IR 05000336/19890081989-06-20020 June 1989 Insp Rept 50-336/89-08 on 890324-0504.No Violations Noted. Major Areas Inspected:Plant Operations,Outage Activities, Surveillance,Maint,Plant Incident Repts & Allegations IR 05000245/19890081989-06-15015 June 1989 Insp Rept 50-245/89-08 on 880328-0508.No Unsafe Plant Conditions Noted.Major Areas Inspected:Plant Operations, Physical Security,Licensee Receipt Insp of New Fuel, Refueling,Plant Mods & LERs ML20245A8371989-06-0909 June 1989 Insp Rept 50-245/89-13 on 890517-18.Violations Noted Re Shipment of Package W/Removable External Radioactive Contamination in Excess of Limits & Failure to Supply Shipping Papers.Major Areas Inspected:Shipment of Pump IR 05000245/19890101989-06-0707 June 1989 Insp Repts 50-245/89-10 & 50-336/89-12 on 890515-19.No Violations Noted.Major Areas Inspected:Fire Protection & Prevention Program,Including Program Administration & Organization & Administrative Control of Combustibles ML20245A6781989-06-0707 June 1989 Insp Rept 50-245/89-11 on 890501-05.No Violations Noted. Major Areas Inspected:Observations,Review of Data,Licensee Response to Generic Ltr 88-01,NDE Procedures,Engineering Support & QA Involvement IR 05000245/19890091989-05-18018 May 1989 Insp Repts 50-245/89-09 & 50-336/89-10 on 890417-21.No Violations Noted.Major Areas Inspected:Review of Radiation Protection Activites at Unit 2 & Begining of Refueling Outage at Unit 1 IR 05000245/19890051989-05-17017 May 1989 Insp Repts 50-245/89-05 & 50-336/89-07 on 890417-21.No Violations Noted.Major Areas Inspected:Engineering Organization & Staffing,Qa,Plant Mods & Technical Training IR 05000423/19890031989-05-0303 May 1989 Insp Rept 50-423/89-03 on 890228-0404.No Violations Noted. Major Areas Inspected:Plant Operations,Status of Previous Insp Findings,Fuel Receipt & Insp,Generic Concerns About Steam Generator Tube Plugs,Esf Walkdown & LERs IR 05000245/19890041989-05-0303 May 1989 Insp Rept 50-245/89-04 on 8902214-0327.Major Areas Inspected:Previously Identified Items,Plant Operations, Physical Security,Ultrasonic Testing of Condensate Storage Tank,Maint Program Implementation & Committee Activities ML20246K0931989-04-26026 April 1989 Insp Rept 50-336/89-05 on 890211-0323.No Violations Noted. Major Areas Inspected:Outage Activities,Surveillance,Maint, Previously Identified Items,Plant Incident Repts & Allegations IR 05000245/19890061989-04-0707 April 1989 Insp Repts 50-245/89-06,50-336/89-09 & 50-423/89-06 on 890306-10.No Violations Noted.Major Areas Inspected:Review of Implementation of Radiation Protection Program at Unit 2 During Refueling Outage & Preparation of Outages for Units IR 05000245/19890071989-03-23023 March 1989 Insp Repts 50-245/89-07,50-336/89-06 & 50-423/89-07 on 890221-0303.No Violations or Deviations Noted.Major Areas Inspected:Site Observations & in-ofc Review of Data in Areas of Inservice Insp & Secondary Water Chemistry IR 05000245/19890031989-03-15015 March 1989 Insp Repts 50-245/89-03 & 50-336/89-04 on 890213-17.No Violations Noted.Major Areas Inspected:Unit 2 Refueling Outage Activities,Unit 1 Refueling Outage Preparation Activities & Station ALARA Practices 1990-08-09
[Table view] Category:TEXT-INSPECTION & AUDIT & I&E CIRCULARS
MONTHYEARIR 05000245/19990081999-09-14014 September 1999 Insp Repts 50-245/99-08,50-336/99-08 & 50-423/99-08 on 990615-0809.Four Violations Noted & Being Treated as Ncvs. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000423/19990071999-08-27027 August 1999 Insp Rept 50-423/99-07 on 990614-0715.Violations Noted & Being Treated as Ncvs.Major Areas Inspected:Review of C/A Program Using IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems IR 05000336/19990061999-07-19019 July 1999 Insp Repts 50-336/99-06 & 50-423/99-06 on 990420-0614.Ten Violations Occurred & Being Treated as non-cited Violations. Major Areas Inspected:Operations,Maint,Engineering & Plant Support IR 05000336/19982191999-06-10010 June 1999 Insp Rept 50-336/98-219 on 981214-18,990126-29,0208-19 & 0301-05.Noncited Violations Identified.Major Areas Inspected:Exam of Licensee Corrective Action Implementation IR 05000245/19990051999-06-0404 June 1999 Errata to Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05,consisting of Figure 1 ML20207G1211999-06-0303 June 1999 Insp Repts 50-245/99-05,50-336/99-05 & 50-423/99-05 on 990302-0419.No Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20207F1521999-05-25025 May 1999 Notice of Violation from Investigation Rept 1-94-021 on 940506-960329.Violation Noted:Between 740831-910407,licensee Made Changes to Facility Described in Safety Analysis Rept for Refueling Core Offloads Without Performing Evaluation ML20196K2621999-05-24024 May 1999 EN-99-020:on 980525,notice of Violation & Exercise of Enforcement Discretion Will Be Issued to Licensee.Action Based on Severity Level III Problem Consisting of Four Individual Violations Involving Refueling Outage PNO-I-99-022, on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions1999-05-11011 May 1999 PNO-I-99-022:on 990509,Millstone Unit 2 Established Reactor Criticality.Nrc Staff Providing Augmented Insp Coverage of Restart Activities,Including round-the-clock Observations of Licensee Activities During Key Operational Evolutions IR 05000336/19990031999-05-10010 May 1999 Insp Rept 50-336/99-03 on 990322-26.No Violations Noted. Major Areas Inspected:Review of Actions Taken by Util to Resolve Significant Issues List Item 21,fire Protection ML20206F4601999-04-30030 April 1999 Insp Rept 50-336/99-04 on 990315-31.Violation Noted.Major Areas Inspected:Monitored Licensee Activities During Plant Transition Between Operational Modes,Both During Normal & off-normal Working Hours PNO-I-99-016, on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair Valve1999-04-0707 April 1999 PNO-I-99-016:on 990406,operators Initiated Plant Cooldown from Normal Operating Pressure & Temp in Mode 3,hot Standby. Cooldown Was Necessary to Minimize Further Degradation of Bonnet Pressure Seal for Valve 2-SI-652 & to Repair Valve ML20205M7201999-04-0606 April 1999 Notice of Violation from NRC OI Case 1-96-002 & Conclusions of Millstone Independent Review Team.Violation Noted. E Debarba,Deliberately Discriminated Against Supervisor in Performance Engineering Group at Millstone Station ML20205M7351999-04-0606 April 1999 Notice of Violation from Investigation in Case Numbers 1-96-002 & 1-97-007.Violation Noted:Licensee Discriminated Against Supervisor in Performance Engineering Group at Plant Due to Involvement in Protected Activities IR 05000245/19990021999-04-0202 April 1999 Insp Repts 50-245/99-02,50-336/99-02 & 50-423/99-02 on 990112-0301.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support IR 05000336/19990011999-03-29029 March 1999 Insp Rept 50-336/99-01 on 990117-0217.Violations Noted.Major Areas Inspected:Licensee C/A Program Implementation Using Guidance of NRC IP 40500, Effectiveness of Licensee Controls in Identifying,Resolving & Preventing Problems ML20205J0941999-03-12012 March 1999 Rept of Review of Millstone Units 1,2 & 3:Allegations of Discrimination in NRC Ofc of Investigations Cases 1-96-002, 1-96-007,1-97-007 & Associated Lessons Learned ML20207M1131999-03-0909 March 1999 Notice of Violation & Proposed Imposition of Civil Penalty in Amount of $88,000.Violation Noted:Employment of Two Contractor Employees Terminated in Aug 1997,in Part Because Individuals Raised Concerns Re MOV Program Manual ML20205G6161999-03-0909 March 1999 EN-99-010:on 990309,notice of Proposed Imposition of Civil Penalty in Amount of $88,000 Issued to Licensee.Action Based Upon Severity Level II Problem Involving Discrimination Against Two Contractor Employees at Millstone MOV Dept IR 05000245/19980061999-03-0101 March 1999 Insp Repts 50-245/98-06,50-336/98-06 & 50-423/98-06 on 981123-990111.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support PNO-I-99-006, on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys1999-01-29029 January 1999 PNO-I-99-006:on 990128,operators Inadvertently Reduced Spent Fuel Pool Water Level by Two Inches When Purification of Spent Fuel Pool Water Initiated.Operators Held Shift Briefing to Discuss Realigning Purification Sys IR 05000245/19982171999-01-22022 January 1999 Evaluation Repts 50-245/98-217,50-336/98-217 & 50-423/98-217 Conducted on 981026-30.Areas Evaluated:Whether NNECO Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ PNO-I-99-004, on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review1999-01-20020 January 1999 PNO-I-99-004:on 990115,carbon Dioxide Was Inadvertently Discharged Into Unit 3 Cable Spreading Room,Containing Electrical Wiring.Ambulance Reported to Site as Precautionary Measure.Licensee Assembled Event Review IR 05000336/19980051999-01-0707 January 1999 Insp Repts 50-336/98-05 & 50-423/98-05 on 981006-1123. Violations Noted.Major Areas Inspected:Operations, Maintenance,Engineering & Plant Support ML20199C6381999-01-0707 January 1999 Notice of Violation from Insp on 981006-1123.Violation Noted:On or Before 981120,conduit 9-15,in Fire Area A-24,not Sealed & Tested in Accordance with Astme E-119,fire Endurance Test PNO-I-99-001, on 981231,Millstone Unit 2 Began Reloading Fuel Into Reactor After Extended Shutdown.Millstone Unit 3 Went Critical on 981230,after Forced Outage Due to Inadvertent MSIV Closure During Surveillance Testing at Power1999-01-0404 January 1999 PNO-I-99-001:on 981231,Millstone Unit 2 Began Reloading Fuel Into Reactor After Extended Shutdown.Millstone Unit 3 Went Critical on 981230,after Forced Outage Due to Inadvertent MSIV Closure During Surveillance Testing at Power PNO-I-98-062, on 981211,Millstone Unit 3 Tripped from 100% Reactor Power During MSIV Partial Stroke Testing.Solenoid Valve Integral to MSIV Failed to Reopen When Licensed Operator Released Test Switch1998-12-15015 December 1998 PNO-I-98-062:on 981211,Millstone Unit 3 Tripped from 100% Reactor Power During MSIV Partial Stroke Testing.Solenoid Valve Integral to MSIV Failed to Reopen When Licensed Operator Released Test Switch ML20195H6901998-11-18018 November 1998 Notice of Violation from Insp on 980818-1005.Violation Noted:Engineering Evaluations Not Performed When RCS Heatup Rate Limit Exceeded on 951217 & When RCS Cooldown Rate Limit Exceeded on Three occasions,940424,0728 & 951215 IR 05000245/19982161998-11-18018 November 1998 Insp Repts 50-245/98-216,50-336/98-216 & 50-423/98-216 on 980818-1005.Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000336/19982031998-11-0505 November 1998 Insp Rept 50-336/98-203 on 980824-0904.No Violations Noted. Major Areas Inspected:Effectiveness of Configuration Mgt Plan ML20155B1521998-10-23023 October 1998 Notice of Violation from Insp on 980810-0903.Violation Noted:Design Basis,As Described in FSAR Chapter 14,Accident Analyses Had Not Been Correctly Translated Into Plant Procedures & Acceptance Criteria IR 05000336/19982131998-10-23023 October 1998 Insp Rept 50-336/98-213 on 980810-0903.Violations Noted. Major Areas Inspected:Certain Aspects of Accident Mitigation Sys IR 05000245/19982151998-10-14014 October 1998 Evaluation Repts 50-245/98-215,50-336/98-215 & 50-423/98-215 on 980824-28.Major Areas Evaluated:Whether Licensee Has Improved Sufficiently & Has Demonstrated Sustained Performance in Maintaining safety-conscious Work Environ IR 05000336/19980041998-10-0101 October 1998 Insp Rept 50-336/98-04 on 980914-18.No Violations Noted. Major Areas Inspected:Mov Program Associated with GL 89-10 IR 05000245/19982121998-09-25025 September 1998 Insp Repts 50-245/98-212,50-336/98-212 & 50-423/98-212 on 980630-0817.No Violations Noted.Major Areas Inspected: Operations,Maintenance,Engineering & Plant Support IR 05000423/19982111998-09-11011 September 1998 Insp Rept 50-423/98-211 on 980413-24,0511-15,27-29,0609-11 & 23-25.Violation Noted.Major Areas Inspected:Evaluation of Licensee C/As & Other ICAVP Process Activities ML20154D1151998-09-11011 September 1998 Notice of Violation from Insp on 980413-24-0511-15,27-29, 0609-11 & 23-25.Violation Noted:Program Implemented TS 6.8.4.a,failed to Include Provisions to Reduce Leakage from RSS Heat Exchangers to SW Sys IR 05000424/19980061998-09-10010 September 1998 Insp Repts 50-424/98-06 & 50-425/98-06 on 980628-0815.No Violations Noted.Major Areas Inspected:Aspects of Licensee Operations,Engineering,Maint & Plant Support PNO-I-98-039, 980812,Millstone Unit 3 Was Shutdown to Repair Small Leak on Afws Discharge Noted.Current Leakage Does Not Exceed Regulatory Requirements & Shutdown Not Required by Tech Specs.Licensee Issued Press Release on 9808111998-08-12012 August 1998 PNO-I-98-039:980812,Millstone Unit 3 Was Shutdown to Repair Small Leak on Afws Discharge Noted.Current Leakage Does Not Exceed Regulatory Requirements & Shutdown Not Required by Tech Specs.Licensee Issued Press Release on 980811 ML20237D3041998-08-12012 August 1998 Notice of Violation from Insp on 980413-0508.Violations Noted:Two Examples Identified Where Licensee Not Performing Leakage Testing of safety-related Valves in Sys That Could Contain Highly Radioactive Fluids During Accident IR 05000245/19982081998-08-12012 August 1998 Insp Repts 50-245/98-208,50-336/98-208 & 50-423/98-208 on 980428-0629.Violations Noted.Major Areas Inspected: Operations,Maint,Engineering & Plant Support ML20237B0741998-08-12012 August 1998 Notice of Violation from Insp on 980428-0629.Violation Noted:Licensee Failed to Direct Test Personnel to Close & Lock RHR Outboard Drain Valve IR 05000336/19982011998-08-12012 August 1998 Insp Rept 50-336/98-201 on 980413-0508.Violations Noted. Major Areas Inspected:Licensee Ability to Identify & Resolve Deficiencies Focusing,But Not Limited To,Period of CMP Implementation & ICAVP at Parsons Power Group,Inc PNO-I-98-026, on 980701,Millstone Unit 3 Criticality Update Made.Nrc Staff Continues to Provide Augmented Insp of Unit 3 Restart Activities,Including round-the-clock Coverage of Key Operational.Licensee Plans No Press Release1998-07-0101 July 1998 PNO-I-98-026:on 980701,Millstone Unit 3 Criticality Update Made.Nrc Staff Continues to Provide Augmented Insp of Unit 3 Restart Activities,Including round-the-clock Coverage of Key Operational.Licensee Plans No Press Release PNO-I-98-025, on 980630,unit 3 Established Reactor Criticality,However Reactor Was Shut Down When Control Room Operator Noticed Spiking Intermediate Range Monitor.Licensee Troubleshooting1998-06-30030 June 1998 PNO-I-98-025:on 980630,unit 3 Established Reactor Criticality,However Reactor Was Shut Down When Control Room Operator Noticed Spiking Intermediate Range Monitor.Licensee Troubleshooting IR 05000245/19982071998-06-19019 June 1998 Insp Repts 50-245/98-207,50-336/98-207 & 50-423/98-207 on 980301-0427.Violations Noted.Major Areas Inspected:Maint, Operations,Engineering & Plant Support ML20249C6931998-06-19019 June 1998 Notice of Violations from Combined Insp on 980301-0427. Violations Noted:Prior to 980424,instrument Min Accuracy of Wind Speed Channels Were Not Measured as Required by Table 3.3-8 of Unit 2 TS 3/4.3.3.4 IR 05000423/19970831998-06-12012 June 1998 Insp Rept 50-423/97-83 on 980413-24.Violations Noted. Major Areas Inspected:Readiness of Plant Hardware,Staff & Mgt Programs to Support Safe Restart & Continued Operation of Plant Unit 3 ML20249B0421998-06-12012 June 1998 Notice of Violations from Insp on 980413-24.Violations Noted:Only 1 RCS Loop Operable W/Plant in Mode 4 on 980407 IR 05000423/19970821998-06-11011 June 1998 Insp Rept 50-423/97-82 on 980209-20.Violations Noted.Major Areas Inspected:Corrective Actions Processes 1999-09-14
[Table view] |
Text
.
...
.
.
U.S. NUCLEAR REGULATORY COMMISSION
REGION I
I Report N /85-65 Docket N License N CPPR-113 Category C licensee: Northeast Nuclear Energy Company P. O. Box 270 Hartford, Connecticut 06101 Facility Name: Millstone Nuclear Power Station, Unit 3 Inspection At:' Waterford, Connecticut Inspection Conducted: October 21-25 and November-12-15, 1985 Inspectors: 'f -
R. K. Struckmeyer, Radia gon Specialist
/A/d/F5 date'
[/ A. A: Weadock, Radiation Specialist
/2 ' 85-
' ate d
Approved by: b ,. . Ir3 r~c - /2.!/7h[
'
M. M. $3anbaky, Chief, PWR Radiation Safety Section
/ K dater Inspection Summary:
Inspection on October 21-25 and November 12-15, 1985 (Report No. 50-423/85-65)
Areas Inspected: Routine, announced, pre-operational inspection of the chemistry and radioactive effluent control programs. Areas' reviewed included: organization and staffing, training and qualification program, facilities and equipment, radiological confirmatory measurements, and plans and procedures. The inspection involved 100 inspector hours on-site by two NRC reglor based inspector Results: No violations were identifie fok D G
.
.
DETAILS Individuals Contacted (1) J. Crockett, Unit 3 Superintendent M. Brown, I&C Supervisor, Unit 3 M. Ciccone, Startup Engineer, NNEC0 F. Chamberland, Startup Engineer, NNECO J. Chunis, Startup Engineer, NNECO (1) R. Cikatz, QC Engineer, NNECO (1) G. Closius, QA/QC Supervisor, NNECO (2) R. Enoch, Assistant I&C Supervisor R. Grebasch, Startup Engineer, NNECO T. Lane, Startup Engineer, S&W (1) R. Langer, Assistant Chemistry Supervisor, Unit 3 (1) J. LaWare, CQA Engineering Technologist, NUSCO C. Mallory, Chemistry Trainer, NUSCO M. Manolakis, Unit 3 I&C Trainer, NNECO (1) D. Miller,'Startup Manager, NNECO C. Myers, Nuclear Containment Systems, In (1) (2) L. Nadeau, Assistant Project Engineer, NUSCO J. Niemeyer, Air Balance Test Engineer, S&W R. Olsen, I&C Engineer, NUSCO (1) V. Papadopoli, CQA Supervisor, NUSCO F. Perry, Assistant Radiation Protection Supervisor, NNECO D. Powers, Startup Engineer, S&W L. Rayburn, Associate Scientist, RAB, NUSCO D. Robinson, I&C Engineer (1) R. Sachatello, Radiation Protection Supervisor D. Scace, Startup Engineer, NNECO (2) A. Stengel, Startup Engineer, NNEC0 W. Thomas, Thomas Young Associates H. Thompson, Startup Engineer, NNEC0 J. Townsend, Instrument Specialist (1) J. Waters, Chemistry Supervisor (1) Indicates those present at final exit meeting on November 15, 1985.
(2) Indicates those present at exit meeting on October 25, 1985.
2. Status of Previously Identified Items (0 pen) Inspector Followup Item (50-423/85-19-01): Status of Radiation Monitoring System (RMS). All monitors have been turned over, and all but two have been field tested (exceptions are 3RMS*RE04 and 3RMS*RE05, Containment High-Range Monitors). Phase II testing is in progress, involving communications capability between monitors and RMS compute This capability is not needed for fuel load. Monitor status is given in Attachment I to this report; those required for fuel load (as identified by the licensee) are identified by the letter "F" in the second column of the table, i
.
'
(0 pen) Inspector Followup Item (50-423/85-19-02): Status of RMS Surveil-lance Procedure and Generic Procedure development. All surveillance procedures pertaining to calibration and operability testing of RMS monitors have been written and PORC approved. The status of these pro-cedures is indicated in Attachment II. Procedure numbers 3449 001, 3449 D11, 3449 F01, 3449 Fil, 3450 001, and 3450 011 have been deleted from this list since last update. The monitors covered by these procedures are not covered by Technical Specifications, therefore, surveillance procedures are not required. The calibration and operability of these monitors will be covered by I&C procedures as noted in the tabl The status of RMS generic procedures (I&C procedures) is given in Attach-ment III. A licensee representative stated that these procedures would be finalized and approved prior to commercial operation (0 pen) Inspector Followup Item (50-423/85-42-01): Training of NNECO chemistry technicians, and training and qualifications of contractor technicians. The inspector reviewed the training program for NNECO chemistry technicians, including lesson plans, course materials, training conducted through mid-October, and plans for continuing training. The licensee has not yet finalized plans concerning train-ing for contractor technicians. These areas will remain open pending further NRC ceview. See Section 3 of this repor .
(Closed) Inspector Followup Item (50-423/85-42-02): Training and Quali-fications of NNECO and Contractor I&C Technician The inspector reviewed training plans and selected personnel records. These records indicate that the licensee has adequate controls to ensure that its I&C technicians have the appropriate qualifications, and that training will be provided to technicians. See Section 3 of this repor (0 pen) Inspector Followup Item (50-423/85-42-03): Status of liquid and gaseous radwaste systems. The inspector completed walkdowns on the Liquid Waste System (LWS), the Boron Recovery System (BRS), the Condensate Demin-eralizer Clean-up System (CND), and the Gaseous Waste System (GWS), as well as those ventilation systems for which HEPA and charcoal filtration is required, and verified that major components of these systems (except HEPA and charcoal filters) have been installed as described on the Piping and Instrument Diagrams in the FSA Installation and testing of filtra-tion components (HEPA, charcoal, and pre-filters) will be conducted on an as-needed basis (i.e., for initial criticality, power ascension, etc.).
The Control Room Emergency Ventilation system filters have been installed and tested, as required for fuel load. Testing (Phase III) has been con-ducted on the Primary System Sampling Station, as required for fuel-loa A design deficiency (DDR 759) identified during testing, regarding an ina-bility to obtain steam generator samples when at low pressure due to pres-sure drop caused by restricting orifices in sample lines, was resolved subsequent to the conclusion of this inspectio The status of systems will continue to be followed in future inspections of this are F'
.
.
(Closed) Unresolved Item (50-423/85-42-04): Adequacy of Radiation Monitoring System (RMS) calibration procedures. The inspector reviewed additional information provided by the licensee (details, Section 4). The proper calculation and application of a Radiological Engineered Calibration Factor (RECF), which is updated for each monitor at each calibration, provides the necessary link to the original factory calibratio In addi-tion, the correct operation of each detector is verified by checking its high voltage threshold, and by the use of radioactive sources to check the linearity of respons (0 pen) Inspector Followup item (50-423/85-42-05): Status of chemistry analytical and surveillance procedures. The inspector determined that chemistry surveillance procedures required for fuel load have been written and PORC approve Two surveillance procedures (Nos. 3866 and 3822) were identified by the licensee as required for initial criticality rather than for fuel load. These pertain to noble gas release rate control and moni-toring, and to offsite dose calculation per the REM 0DCM, respectivel The responsibility for procedures pertaining to Radiological Environmental Monitoring was transferred to the corporate office (NUSCO). The licensee reviewed its chemistry analytical procedures to determine which are needed for fuel load and which are needed in later phases of startup. Within the former group, the licensec stated that all procedures have been p0RC ap-proved. The status of procedures not needed for fuel load, and not yet approved, will be reviewed in a future inspectio (0 pen) Inspector Followup Item (50-423/85-4; -06): Status of Phase II startup procedures for liquid and gaseous cacy- te systems and ventilation systems. The Liquid Waste System (LWS), Boron covery System (BRS), and Gaseous Waste System (GWS) are not required to be fully tested and opera-tional until the power-ascension phase of startup; therefore, testing of these systems was not reviewed. Draft copies of the Phase II test procedures were reviewed and found to be adequate. The licensee stated that these procedures have received PORC approval. The status of these procedures, including test results, will continue to be followed in a future inspectio (0 pen) Inspector Followup Item (50-423/85-42-07): Status of filtration system (HEPA and charcoal) surveillance test procedures. Testing of the Control Room Emergency Ventilation (CREV) System filtration components is required for fuel load. The test procedure was reviewed and a portion of the test was witnessed by the inspector; all of the necassary tests have been completed and are undergoing internal review. Test procedures for other filtration systems are similar to the procedure for the CREV. These procedures and the test results will be reviewed in a future inspectio . Organization and Staffing The inspector reviewed, in P.eport No. 50-423/85-42, the licensee's organi-zation with respect to staffing and management structure in the areas of chemistry and radioactive effluent control. That review included qualifi-cation and training of technicians in the licensee's Chemistry Department and in its Instrumentation and Controls (I&C) Departmen f-
.
'
The inspectors reviewed the training program for NNECO chemistry techni-cians, includf ag lesson plans, course materials, training conducted through mid-October, and plans for continuing training. Preliminary testing indicated that refresher training was necessary for some techni-cians in nuclear physics, math, and/or chemistry. After this training, the attendees were retested. Three did not pass; of these, two had been unable to attend the refresher training. These three individuals will be provided additional refresher training and testing. The licensee had not decided what action would be taken if any technicians continued to fall
.the tests. This area will be reviewed in a future inspectio The-licensee stated, in a telephone conversation with the inspector, that its contractor technicians meet the qualification requirements of ANSI N 18.1; however, the inspector has not reviewed the documentatio In addition, the licensee has not yet finalized plans concerning training of-contractor technicians. These areas will remain open pending further NRC .
review (50-423/85-42-01).
The inspector reviewed training plans and selected I&C personnel record Periodic training will be provided to NNECO I&C technicians; however, details of the training program have not been settled upon. It will include.both technical and plant related (e.g. systems and procedures)
materials. During a previous inspection (see Report No. 50-423/85-42)
I&C management indicated that the following criteria would be used to
'
screen contractor technicians:
a) technicians would require a minimum of two years technical experience not necessarily nuclear-related, with a preference for those over five years experience, and b) technicians would be required to pass a written examination covering technical areas related to the work of the departmen The inspector reviewed personnel files of selected I&C contractor techni-cians and verified that all technicians met the experience criteria and had received the licensee's written examination. The inspector noted that besides being used as a hire /no-hire criterion, the exam was used to iden-tify weak areas in the technician's experience and knowledge. Assignment of contractor technicians to one of the I&C department's working groups (Analog, Digital, or Analog and Digital) was made partly on the basis of exam performanc . Facilities and Equipment The inspectors reviewed the status of the liquid and gaseous radwaste systems and the primary and secondary system sampling stations with respect to the FSAR design criteria for these systems. This review included walkdowns of the major components of these systems. With regard to the Radioactive Liquid Waste System, a virtually complete
- - _ _ _ _ _ - _ _ _ - _ _ _ _ _ - - _ _ _ _ _ . . _ _ _ _ _ - _ _ - - _ _ _ _ _ _ _- .___ - _ ______ __ _ _ __-_ _ ___ __ _
o
..
'
I walkdown was performed, including all tanks, valves, pumps, filters, i radiation monitor, and piping connections between components. All major opponents of the Boron Recovery System, the Condensate Demin- .
eralizer Liquid Waste System and the Gaseous Waste System were examined, as wel!.
!
'
The inspector noted that most Phase I tests and the majority of Phase II tests concerning liquid and gaseous effluent systems have been complete There is just one Phase II test procedure covering all filtration system component (HEPA and charcoal) testing; at the conclusion of this inspection, only the Control Room Emergency Ventilation filtration components (HEPA and charcoal) had been tested. Installation and testing of filtration components for the remaining systems required by Technical Specifications will be conducted on an as-needed basis (i.e., initial criticality, power ascension,etc.). The status of tests will continue to be followed in
' future inspections of this area (50-423/85-42-03). ,
4.1 Radiation Monitoring System The Radiation Monitoring System (RMS) was reviewed in NRC Inspection Report 85-19, which included a brief system description and reported the status in terms of operability and testing of equipment, and development of procedures. The licensee's Instrumentation and Control (I&C) group has responsibility fo** the testing, calibration,
,
and maintenance of the RMS, and for development of surveillance procedure The purpose of this review of the RMS was to update the status of the licensee's progress in making the system operational, and to review monitor calibration procedures and dat O g .oility Selected process and effluent radiation monitors were examined with i regard to their locations, operability, and appropriate connections to the systems to be monitore As of November 20, 1985, the operational status of the RMS was as depicted in Attachment 1. Most process, effluent, and area radiation monitors have been installed and tested individually. The integrated system test (Phase II) is in progress. The inspectors stated that the status of the RMS would again be examined during a subsequent inspection (50-423/85-19-01).
Calibration The licensee is currently using a secondary transfer source calibra-tion technique to calibrate the RMS. This technique is recommended
.
'
by the RMS vendor (KAMAN) and was previously reviewed and described in NRC Inspection Report 85-42. Inspector concerns with the cali-bration technique identified during that inspection included:
1) use of a single radionuclide source during field calibrations to link back to a generic, multi-isotope energy response curve, and 2) lack of acceptance criteria to evaluate detector response to the transfer sourc Inspector effort during this inspection was directed towards the further investigation and resolution of the above concerns. Review in this area included:
1) review of vendor-supplied isotopic energy-response curves, 2) discussion with engineering personne1'concerning the calculation of calibration factors linking detector response to the generic energy and efficiency calibration to ensure energy response stability of the system, and 3) discussion with I&C supervisory and vendor personnel concerning detector respons The inspector determined the licensee's current technique is adequate for performing detector calibrations for the RMS. The proper calcu-lation and application of a Radiological Engineered Calibration Factor (RECF), updated for each monitor at each calibration, relates current monitor response to the response at the original primary calibratio This provides an adequate link back to the original energy response curve. Performance of a linearity check and the establishment of high voltage thresholds for the detectors provides an adequate check of detector respons . Plans and Procedures The inspectors reviewed the licensee's procedures for pre-operational testing of liquid and gaseous radwaste systems, ventilation systems, and radiation monitoring system. The inspectors noted that virtually all procedures for individual component (Phase I) testing had been written and approved. Procedures for integrated system (Phase II) testing have been written and approved for the following systems: primary system sampling station, gaseous redwaste processing system and ventilation systems (for those which may contain radioactivity during normal operations), liquid radwaste system, charcoal and HEPA filter tests, and radiation monitoring syste Approxi,rately 85 percent of chemistry procedures, including all of those required for fuel load have been written and approved. Chemistry is also responsible for developing and implementing 27 Surveillance Procedures; at the conclusion of this inspection, all but two (which are not required for fuel load) had been written and PORC approved.
-
-
e-
.
.
The inspectors reviewed the current status of Radiation Monitoring System (RMS) surveillance procedures, for operation, testing, and calibration of RMS units that are expected to be addressed by Technical Specification Attachments 2 and 3 depict the status of these procedures as of November 15, 198 The status of the licensee's procedures will continue to be followed in subsequent inspections of this area; including:
Chemistry analytical and surveillance procedures (50-423/85-42-05).
RMS generic (I&C) procedures (50-423/85-19-02).
- Phase II startup procedures for liquid and gaseous radwaste systems and ventilation systems (50-423/85-42-06).
Filtration system (HEPA and charcoal) surveillance testing (50-423/85-42-07).
6. Capability Test Rasults The licensee maintains the capability for analysis by gamma spectroscopy in both its chemistry and its health physics laboratorie There are three such systems available in chemistry, and two in health physic The inspector submitted test samples to these laboratories in order to evaluate the licensee's capability to measure radioactivity in effluent and in plant sample The test samples consisted of a simulated particu-late filter and a spiked charcoal cartridge, both of which are representa-tive of samples the licensee would encounter during operation. The test samples were analyzed by the licensee using the licensee's normal methods and equipmen The results of the test sample measurements comparison indicated that all of the measurements were in agreement under the criteria used for inter-comparing results, listed in Attachment I The intercomparison results data are listed in Attachment Additional intercomparison data will be obtained for evaluation of the licensee's capability to measure radioactivity in liquid samples. These samples will be prepared by the NRC reference laboratory (the DOE Radio-logical and Environmental Sciences Laboratory) and sent to the license One sample, containing radioactivity detectable by gamma spectroscopy, will be analyzed by the licensee's chemistry and health physics laboratories. A second sample, containing tritium, strontium, and mixed alpha emitters, will be forwarded to the licensee's vendor laboratory for analysis. The results of these analyses will be sent to the NRC Region I office as they are obtained by the licensee, and will be documented in a future inspection of this area (50-423/85-65-01).
- , v
.. p ,-
A, ,
t E
7~ .n ,
- .
, Laboratory quality Control Program
-
U y a: ' Chemistry F' '
l 6-The chemistry laboratory QC program is detailed in Procedures CP 3800,
" Chemistry Quality Assurance Program," and CP 3800 B, "QA Control Chart Preparation." Procedure CP 3800 addresses equipment calibration, intra-
,
laboratory analyses of dukiicate and spiked samples, interlaboratory analyses of. split water & mples, and preparation of reagent,and standard sMutio',is for QA analyse Procedure CP 3800..B discusses the method of preparing quality control charts for various types of chemical p measurement <
The inspector noted that the licensee's quality assurance procedure con-tained no reference to a quality control program for its< vendor laboratory, in which QC samples (spikeh splits, duplicates, etc.) are prepared by the licensee and sent to therverdor laboratory for analysis. The licensee stated that such a program is maintained by the Units 1 and 2 chemistry laboratory, and that the Unit 3 laboratory uses the same vendor. The
, inspector stated that the Unit 3' quality assurance procedure should referenc'a this vendor QC prograni.. The licensee agreed to reference this program pnd stated tnat any prib>.as with the vendor laboratory would be communic eed to the Unit 3 laboratory tia the Millstone site Chemistry
. Shperviso/. This will be reviewed in a future inspection (50-423/85-65-02).
e, o Health Physin V
-
L The knspector rtviewed the Itcensee m rocedure number HP 908/2908/3908 C,
" Health Physics Spectrometer Instrumentation," and ndted that it contains instructions for daily performance checks, and-instructions for energy and efficiency calibration. The procedure does not provide for the preparation of QC kharts. The inspector stated that such charts should be utilized c,
'
because of the additio,a1 benefits \the.p hfford with regard to displaying
$
detector trends; e.g.l; bias (most W 2.11 results above or below the known val'2) and drift (results tend to %ove steadily, up or down over a period of time). Control charts enable tne operator to recognize potential problems before the instrument 6t1 outhf control, and, therefore, take steps to correct the problem. The licensee stated that the next revision of its proced_upe will specify that control charts be established and main-tained for it's gamma spectroscopy systena (50-423/85-65-03). Exit Interview
l w The inspector eet with the licensee representattves (denoted in j Paragraph 1) at the tonclusion of the inspections on October 25 and l November 15, 1985.Vand summarized the purpose and sc' ope of the inspec-
!
tions and the inspection findings. The licensee agreed to perform the i
'
analyses listed in Faragraph 6 and report the results to the NR ,; . ,
j At no time during these inspections was w'itten material prnvided to the l licensee by the inspecto . L.
,
I.,
i \
L
r
.
.
ATTACHMENT I Radiation Monitoring System Status Instrument Number Mile- Field Communications (Mark No.) stone Tested Loop Established Comments Ventilation / Gas Monitors 3HVRRE10A/B* F (* Testing complete, eval-( uation of results in ( progres HVRRE19A/B* F (* Check source response ( malfunction under ( investigatio HVRRE11A/B C X X Flow adjustment required 3HVRRE12A/B C X X Flow adjustment required 3HVRRE13A/B C X X Flow adjustment required 3HVRRE14A/B C X X Flow adjustment required 3HVRRE15A/B C X X Flow adjustment required 3HVRRE16A/B C X X Flow adjustment required 3HVRRE17A/B C X X Flow adjustment required 3HVRRE18A/B C X X Flow adjustment required 1HVCRE91A/B C X X 3CMSRE22A/B* P X X 3HVZRE09A/B C X X Monitor reads too high 3HVQRE49A/B* F X X 3HVCRE16A/B* F X X
-
,
t
'-
,
g
'
s ATTACHMENT I'(Continued)
Radiation Monitoring System Status Instrument
' Number Mile- Field Communications (Mark No.) stone Tested Loop Established Comments Liquid Process Monitors 3CHSRE69 C X X
'3CCPRE31' C X t X s
i 3CNARE47 C X X 3DASRE50 F X X Q,d 3LWSRE70 F X X ..
J-
'3LWCRE65 F A X 3CNDRE07 F X X 3SSRRE08- F X
,
35WPRE60A/B 'C X X 3GWSRE48 C X X lb -3ARCRE21- C X X 3MSSRE75- C X X 3MSSRE76 C X~ X 3MSSRE77 C X X 3MSSRE78 C X X 3MSSRE79 C X v 5-1 b,-
.
.- _
.
-,
ATTACHMENT I (Continued)
Radiation Monitoring System Status Instrument Number Mile- Field Communications
~(Mark No.) stone Tested Loop Established Comments Area Monitors 3RMSRE01- C X X 3RMSRE02 C X X 3RMSRE03 C X X 3RMSRE06 C X X 3RMSRE07 C X X 3RMSRE08 C X X 3RMSRE09 C X X 3RMSRE10 C X X 3RMSRE11' C X- X 3RMSRE12 C X X
~3RMSRE1 C X X
!3RMSRE14 C X X
-
3RMSRE15 C- X X 3RMSRE38 C X X 3RMSRE52* C X X 3RMSRE16 C X X
. 13RMSRE17 C- X X
<
-* Category IE Monitors .
.
'
1 ATTACHMENT I (Continued)
Radiation Monitoring System Status Instrument Number Mile- Field Communications (Mark No.) stone Tested Loop Established Comments Area Monitors 3RMSRE18 C X X 3RMSRE19 C X X 3RMSRE20 C X X 3RMSRE21- C X X 3RMSRE22 'C X X 3RMSRE24 X X 3RMSRE25 C X X 3RMSRE28 C X X 3RMSRE29 C X X
~3RMSRE31 C X X 3RMSRE32 C X 'X 3RMSRE33 C X -X 3RMSRE34 C X X 3RMSRE35 C X RMSRE3 C X X 3RMSRE37 C X X L
n
.
..
ATTACHMENT I (Continued)
Radiation Monitoring System Status Instrument
. Number- Mile- Field Communications (Mark No.) stone Tested Loop Established Comments Area Monitors
'3RMSRE04* P ( Installed and calibrated; (
3RMSRE05* P ( Cable check and surveil-( lance incomplete 3RMSRE41* F ( Testing complete (11/19);
( evaluation of results in
- 3RMSRE42* F ( progress Milestone:
F = Fuel ~ 1oad P = Post-core hot functional ~
C = Commercial operation t
,
<
s
p
.,
L.
f-
'
ATTACHMENT II RMS Surveillance Procedure Summary Procedure PORC Number Monitor Identification Approval Comments
,
3449A01 3HVR-RE10A/B Vent Part/ Gas 10/25/85 66'6" Aux. Bldg. Cal. Pro A11 3HVR-RE10A/B Vent Part/ Gas 10/19/85 66'6" Aux. Bldg. Oper. Test 3449801 3HVR-RE19A/B SLCRS Part/ Gas 11/01/85 Cal. Pro .3449B11 3HVR-RE19A/B SLCRS'Part/ Gas 10/29/85 Oper. Test 3449C01 3 CMS-RE22A/B CTMT Atmo /29/85 Part/ Gas Cal. Proc.-
3449C11 3 CMS-RE22A/B CTMT Atmo /29/85 Part/ Gas Oper. Test 3449D01 '3SWP-RE60A/B CTMT Recir Deleted Changed to I&C Cooler'Syc. Water Outlet Proc. No. 3490 B12 Cal. Pro D11 35WP-RE60A/B CTMT Recir Deleted t
Cooler Svc. Water Outlet Oper. Test
'3449E01 3RMS-RE41/42 Fuel Drop Monitor 10/29/85 51'4" Cal. Pro E11 3RMS-RE41/42' Fuel Drop Monitor 10/29/85 51'4" Oper. Test 3449E21 Fuel Pool Storage Criticality 09/03/85
~ Monitor Cal. Pro '
3449E31 Fuel Pool Storage Criticality 09/06/85 Monitor Oper. Test 3449F01 3HVZ-RE09A/B Recom. Cub. A/B Deleted Changed to I&C
~Exh. 7'6" Cal. Pro Proc. No. 3490 B05 3449F11 3HVZ-RE09A/B Recom. Cub A/B Deleted Exh. 7'6" Oper. Test
E
.
.
ATTACHMENT II (Continued)
RMS Surveillance Procedure Summary Procedure PORC Number- Monitor Identification Approval Comments 3449G01 3HVC-RE16A/B Control Bld /11/85 Inlet Cal. Pro G11 3HVC-RE16A/B Control Bld /03/85 Inlet Oper. Test 3449H01 3RMS-RE04/05 Cont. HR Inte /25/85 51'4" CTMT Cal. Pro H11 3RMS-RE04/05 Cont. HR Inter 09/20/85 51'4" CTMT Oper. Test 3449J01 3HVQ-RE49 ESF Part & Gas Ra /05/85'
Monitor Cal. Pro J11 3HVQ-RE49-ESF Part & Gas Ra /29/85 Monitor Oper. Test 3450D01 3 MSS-RE75, 76, 77, 78 Main St Deleted ' Changed to I&C
' Rel . Line A-D Cal . Pro Proc. No. 3490 B08 3450011 3 MSS-RE75,-76,.77, 78 Main St Deleted Rel. Line A-D Oper. Test 3450E01. '3 MMS-RE79 Turb. Drv. Aux. Fd Deleted Changed to I&C Pump Dsch.-Cal. Pro Proc. No. 3490 808 3450E11 3 MMS-RE79 Turb. Drv. Aux. Fd Deleted
. Pump Dsch. Oper. Test 3450F01 3CND-RE07. Waste Neut. Sump Ra /23/85 Monitor Cal. Pro F11 3CND-RE07 Waste Neut. Sump Ra /13/85 Monitor Oper. Test
.
3450G01 3DAS-RE50 Turb. Bldg. Floor 09/10/85 Drains Rad. Monitor Ca Pro G11 3DAS-RE50 Turb. Bldg. Floor 09/13/85 Drains Rad. Monitor Ope Test
. - -. ..
. . . -. - _ _ - . . ._ - .- . - -
.
L
,
,
ATTACHMENT II (Continued)
' RMS Surveillance Procedure Summary
'
Procedure . PORC Number Monitor Identification Approval Comments 3450H01 3LWS-RE70 Liquid Waste Ra /23/85
Monitor Cal. Proc.
'
3450H11 3LWS-RE70 Liquid Waste Rad - 09/17/85 Monitor Oper. Test 3450J01 -3LWC-RE65 Regen. Evap. Ra /23/85
' Monitor Cal. Pro J1 ~' 3LWC-RE65 Regen. Evap. Ra /13/85
. Monitor Oper.-Test 3450K01' 3SSR-RE08 S/G Blowdown Ra /23/85 Monitor Ca K11 3SSR-RE08 S/G Blowdown Ra /05/85 Monitor Oper. Test
)
3450L41 - T/B Floor Drains, Regen. Eva . 11/19/85
.and S/G Blowdown Source Check
,
l x
a -
'
,
e
, _ _
l
- g wc,-- r4 f .. p , s- w-- - - = , -,.-y-- _ ~ _ - - - - .- -- ,e-, ,.re-,.-
__
.
-.
ATTACHMENT III RMS Generic Procedure Summary l
Generic I&C N Procedure Monitor (GPIC) N Identification Status / Comment 20.01 3490B01 Kaman_ Science (KMG-HRN) Radiation Approved * Rev. O Monitor 20.02 3490B02 Kaman Science (KMG-HRH) Radiation Rev. O in Typing Monitor 20.03 3490B03 Kaman Science (KMPG) Radiation Approved * Rev. O Monitor 20.04 3490B04 Kaman Science (KML) Radiation Approved * Rev. O Monitor Draft-Rev. 1~
20.05 3490B05 Kaman Science (KMG) Radiation Draft Rev. O Monitor to Author for Corrections 20.06 3490B06 Kaman Science Hydrogen Vent Draft Rev. O Monitor -in Review 20.07 3490B07 Deleted 20.08 3490B08 Kaman Science (KMA-HR) Radiation In Review Monitor
.20.09 3490B09 Deleted 20.10 3490816 Kaman Science (KMA) Radiation Approved * Rev. O Monitor 20.11 3490B11 Kaman Science Fuel Failure Monitor In Typing 20.12 -3490812 Kaman Science Service Water In Review Effluent Monitor 20.13 ECl-4 Eberline Radiation Monitor In Development
- Approval of these procedures is by the I&C Department Supervisor and the Startup Manage _
.
.
ATTACHMENT IV Criteria for Comparing Analytical Measurements This attachment provides criteria for comparing results of capability tests and verification measurements. The criteria are based on an empirical relationship which combines prior experience and the accuracy needs of this progra In these criteria, the judgement limits are variable in relation to the com-parison of the NRC Reference Laboratory's value to its associated uncertaint As that ratio, referred to in this program as " Resolution," increases, the acceptability of a licensee's measurement should be more selective. Conversely, poorer agreement must be considered acceptable as the resolution decrease Resolution Agreement
<3 0.4 - .5 - .6 - 1.66 16 - 50 0.75 - 1.33 51 - 200 0.80 - 1.25
>200 0.85 - 1.18 t
+. .
o
. ATTACHMENT V-s Cacaollity Test Re4ults - Chemi st ry Licensee Results *
lsotope NRC Value * Resolution Chem. Det. 1 Ratio ** Chem. Det. 2 Ratio ** Chem. Det. 3 Ratio **
- Particulate Filter Ce-144' (3.4610.02)E-02 173 (3.4310.10)E-02 0.99 (3.6110.08)E-02 1.04 (3.6010.10)E-02 1.04 Cs-137 (1.5010.02)E-02 75- (1.4910.02)E-02 0.99 (1.5610.02)E-02 1.04 (1.6110.02)E-02 1.07 Mn-54 (1.4710.02)E-02 74 (1.5210.04)E-02- 1.03 (1.5510.04)E-02 1.05 (1.5310.04)E-02 1.04 Co-60' (2.6810.02)E-02 134 (2.6510.03)E-02- 0.99 (2.9210.03)E-02 1.09 (2.8310.03)E-02- 1.0 Cha rcoa l Ca rtridge Cd-109 (3.4210.05)E-02 68 Not Detected + (3.910.2)E-02 1.14 v+ Not Detected +
Co-57 (9.8010.12)E-04 82 (8.211.2)E-04 0.84 (1.110.2)E-03 1.12 (1.0710.17)E-03 1.09 Ce-139 (5.1810.10)E-04 52 Not Detected + Not Detected + Not Detected +
Cs-137 (9.7410.05)E-03 195 (8.8410.12)E-03 0.91 (1.0210.01)E-02 1.05 (1.0010.01)E-02 1.03 Co-60 (9.8410.05)E-03 197 (9.3310.17)E-03 0.95 (1.1110.02)E-02 1.13 (1.0210.02)E-02 1.04 Notes:
- Value given in total microcuries or isotope 'in sample
- Ratio of licensee value to NRC value
+ Nuclide not contained in licensee's isotopic library for charcoal cartridge sample
++ Alternate isotope library used for this analysis
,
~
'
. . . .
.
., - > ;_ '
l : ATTACHMENT V (Continued)
Capability Test Results - Health Physics Licensee Results *
Isotone NRC Value * Resolution H. P. Det. 1 Ratio ** H. P. Det. 2 Ratio **
s Pa rticulate Filter .
' Ce-144 (3.4610.02)E-02 173 (3.8710.11)E-02 1.12 (3.8210.13)E-02 1.10 Cs-137 (1.5010.02)E-02 75 (1.5610.02)E-02 1.04 (1.5410.02)E-02 1.03 Mn-54 (1.4710.02)E-02 74 (1.6610.05)E-02 1.13 (1.6010.05)E-02 1.09 Co-60 (2.6810.02)E-02 13 (3.0210.03)E-02 1.13 (3.1610.03)E-02 1.18 l Cha rcoa l Ca rt ridge Cd-109 (3.4210.05)E-02 68 (2.810.1)E-02 0.82 (4.210.2)E-02 1.23
. Co-57 (9.8010.12)E-04 82 (8.711.0)E-04 0.89 (9.912. )E-04 1.01 Ce-139 (5.1810.10)E-04 52 <2.7 E-03 <4.2 E-03 Cs-137 ,(9.7410.05)E-03 195 (8.210.1)E-03 0.84 (1.0310.01)E-02 1.06 Co-60 -(9.84to.05)E-03 197 (8.910.2)E-03 0.90 (1.110.02)E-02 1.12 Notes:
- Value given in total microcuries of isotope in sample
- Ratio of licensee value to NRC value
.
L