IE Insp Repts 50-348/80-27 & 50-364/80-39 on 800801-29. No Noncompliance Noted.Major Areas Inspected:Plant Operation & Security
ML19339A800
Person / Time
Site: Farley  Southern Nuclear icon.png
Issue date: 09/29/1980
From: Bradford W, Martin R, Mulkey J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML19339A797 List:
References
50-348-80-27, 50-364-80-39, NUDOCS 8011050278
Download: ML19339A800 (8)


Text

,

,-

'e UNITED STATES 8"

N NUCLEAR REGULATORY COMMISSION

$

<$

REGION 11 b[

101 MARIETTA ST., N.W., SUITE 3?00 e

Q

%.

ATLANTA, G EORGIA 30303 o

Report No._50-348/80-27 and 50-364/80-39 Licensee: Alabama Power Company 600 North 18th Street Birminghan:, AL 35202 i

Facility Name: Farley License No. NPF-2 and CPPR-86 Inspection at Farley near Dothan, Alabama Inspectors: [Db 9 hq /cc r.:

A W. H. Bradford Date ' Signed i

7/29/.4 u

srV-J. P. Mulk p Da'te Signed N

Approved by:

. 14)

//,f/4 7M <7

/

t R. D.

artin, Seci. ion Chief, RONS Branch D/te Kgned

~

~

l SUMMARY Inspection on August 1 - August 29, 1980 Areas Inspected This routine, announced inspection involved 284 inspector-hours on site in the areas of Unit 1 plant operation, plant security, Unit 2 plant tour, open items, preoperational test witnessing, Unit No. 2 plant operational status, preopera-tional test status, near term operating licensee requirements, and plant maintenance.

Results Of the nine areas inspected, no items of noncompliance or deviations were identified.

0011 D$U 2 ?

-

... -

- -. _ _. -.

..

.

-

.

--

.

-._

.

.

_

_. _ _ _ _ _

.

_

__.

__

-_ _. _. - -. __.

_... _ _

_

_ _ _ _ _ _ _ _.

p-l

'

,

f

DETAILS

,

W

1.

Persons Contacted Licensee Employees

W. G. Hairston, Plant Manager

J. D. Woodard, Assistant Plant Manager l

D. Morey, Operations Supervisor R. S. Hill, Operations Supervisor

W. D. Shipman, Maintenance Superintendent l

R. W. HCCraken, Technical Superintendent D. E. Mansfield, Unit No. 2, Startup Superintendent R. M. Coleman, Supervisory Engineer Other licensee employees contacted included shif t supervisors, shif t foremen, technicians, plant operators, plant mechanics, security force members, and office personnel.

Other Organizations

!

.

S. M. Hall, Westinghouse Startup Services Manager and certain Westinghouse j

startup engineers.

l NRC Resident Inspector

'

W. H. Bradford

.

l 2.

Exit Interview

i The inspection scope and findings were summarized on August 15 and 29, 1980 with the plant manager and selected members of his staff. The licensee acknowledged the inspection findings.

.

3.

Licensee Action on Previous Inspection Findings

a.

(Olosed) Noncompliance 348/79-37-01.

The inspector reviewed the licensee response' dated January 4, 1980.

The inspector reviewed STP-33.0 " Solid State Protection System Train A (B) Operability Test"

.

and STP.70 " Quadrant Power Tilt Ratio Circulation" to verify that the procedures had been revised.

b.

(Closed) Noncompliance 348/80-02-01. This item concerned the removal from service of 1A -boric acid transt'er pump for maintenance and the improper completion of the Maintenance Request Form. The inspector has reviewed the licensee's corrective action and deems the corrective

,

action to be satisfictory.

.

J

.

-,

-

- ~, _

,

,-.

.,

.,._

-- -

-

..

.-.

-

-

.,

'

-2-4.

Unresolved Items Unresolved items were not identified during this inspection.

5.

Plant Operation The inspector reviewed plant operation to ascertain conformance with regulatory requirements, technical specification and Administrative Procedure No. 16,

" Conduct of Operation - Operation Group". Station logs, such as the shift supervisor, shift foreman, control room operators, shift turnover, the out of service equipment log, night order log book, and the limited condition of operation log, were reviewed. The inspector conducted tours of selected areas of the plant which included portions of the auxiliary building, diesel generator building, and the river water pump house. Observations were made of plant operation, monitoring instrumentation, radiation controls, fluid leaks, piping vibration, pipe hangers, certain valve positions, housekeeping, fire hazards, and equipment tagged out of service for maintenance.

Discussions were held with plant operators throughout the plant concerning certain alarm functions and plant operations.

Within the areas inspected no items of noncompliance or deviations were identified.

6.

Plant Security The inspector verified that physical barriers were intact and that gates into the protected areas were closed and locked if not attended, that doors into vital areas were closed and locked or attended, and that isolation zones were free of visual obstruction.

The inspector verified that access into protected areas was controlled, that persons and packages were identified and authorized prior to entry into protected areas, and that all persons, packages and vehicles were searched prior to entry in accordance with regulatory requirements and security procedures.

Within the areas inspected, no deviations or items of noncompliance were identified.

7.

Plant Tour - Unit No. 2

,

The inspector conducted tours of the Farley Unit No. 2 facility to determine the following:

That welding, burning and cutting in areas turned over to operations a.

had adequate fire protection and that protective measures for equipment in the area had been initiated and were observed.

.

b.

Housekeeping practices had been initiated and were observed.

,

_-

.

--

-

..

.

-3-i c.

A trethod had been initiated for equipment preservation and that an equipment tagging procedure was being carried out on equipment not undergoing testing, d.

That installed instrumentation was protected and had not been abused.

e.

That openings into systems were protected and that cleanliness control was observed.

f.

That deficiencies identified during testing were entered oa a control punch list.

Within the areas inspected no items of noncompliance were observed.

8.

Open Items a.

Closed: Open Item 50-345/80-04-02. This item concerned the licensee revising Administrative Procedure No. 13, " Bypass of Safety Functions and Jumper Control" and administering training on temporary alteration and associated control of alteration to operating personnel, instrument mechanics and craf tsmen.

b.

Closed: Open Item 50-348/80-05-01. This item concerned changes to be made to emergency operating procedures to enhance operator action.

c.

Closed:

Open Item 50-348/80-05-02.

This item concerned additional j

training to be admininstered to operating -personnel in the area of emergency operating procedures.

9.

Witness of Preoperational Testing Portions of the following tests were witnessed by the inspector.

The performance of each test was evaluated against the requirements of ANSI N18.7-1972, Section 6.0, " Test and Inspection Procedures," ANSI N45.2-1971, Section 12, " Test Control," FSAR Chapter 14, " Initial Tests and Operations,"

and Regulatory Guides 1.6,1.9 and 1.41.

'

'

a.

548-6-001 Plant Response to Integrated Safeguards Without Blackout.

The purpose of this test was to verify that.all engineered safeguards components respond to a Loss of Coolant Accident (LOCA) in the as-designed manner without loss of offsite power. This test was attempted three times before the required results were achieved. Minor procedural and-equipment problems were encountered and corrected prior to the-final successful demonstration that all safeguards components responded as required.

>

b.

548-6-002 Plant Response to Integrated Safeguards With Blackout i

The purpose of this test was to demonstrate the diesel generator capa-bility when responding to a LOCA and to verify that all engineered

.

safeguards components respond to a LOCA signal in the as-designed ~

manner.

-.

-

__

-.

- -

-,

-,.

.-

.

-.

_

__ _. _. -

o

'

-4-i The inspector witnessed the majer partions of this test and observed no failure of any major safeguard system components.

The diesel

generators started and assumed their assigned loads as required.

Several minor equipment problems were encountered and corrected prior to the final successful demonstration.

Within the areas inspected there were no discrepancies identified.

!

.

10.

Plant Operational Status The status of Phase I and II testing programs was reviewed and is summarized below:

Testing Completed 59%

Testing in Progress 18%

,

Testing not Started 21%

Test Data Approved by the Lir_ensee 30%

i Followup on the integrated punch list was continued during this inspection.

Revisions to the punch list are issued weekly and periodically licensee'

representatives review the status of each open item on the list. When an

,

item is reported as complete, a systems completion engineer verifies the item status before it is removed from the integrated punch list.

11.

Preoperational Test Status The status of the preoperational test procedures is listed below. These procedures are required to be completed and properly approved prior to initial fuel load.

t Tests which have been completed but test data approval haa.atot_bren-

a.

completed:

303-5-001-Startup Aux Transformer Preop.

004-5-001-4160 VAC Systen Preop.

015-5-0Gi-Regulated AC System Preop.

024-5-001 - Diesel. Load 'equencing Preop. (Train A)

024-5-003-Diesel Generator Lead Sequencing Preop.

(Train b)

040-5-015-CVCS Letdown Preop.

048-5-001-Safeguards Slave-Relay Preop.

052-5-008-'-Safety Injection Hi Head Preop.

059-5-003-Integrated Leak Rate Test 059-5-004-Structural Integrety Test 064-5-013-Reactor Coolant Drain Tank Preop.

067-5-005-Reactor Cavity Filtration 077-5-001-Vital Instrumentation AC Preop.

078-3-001-Nuclear Instrumentation Calibration and Functional Test

.

,

ip-

,y

- - -

,--

- _.

..

_

_

.

._

. _

.

_

_. ___

_

_

.

,

5-

-

+

- 548-6-001-Plant Response to Integrated Safeguards Without Blackout b.

Testing in Progress

.

l 002-5-001-Auxiliary Building 125 VDC Preop.

002-5-002-' D. C. System Cooling and Ventilation 005-5-001-600 VAC. Load Centers Preop.

005-5-002-600 VAC Load Centers Cooling Systems 006-5-001-Motor Control Center Preop.

006-5-002-Motor Control Center Cooling System 013-3-006-CO2 System Calibration and Functional 014-4-001-Lighting Acceptance 040-5-016--CVCS Makeup and Blending 049-5-003-RHR Preop.

062-1-001-Inspection of Reactor Vessel Internals 062-5-001-Reactor Vessel Internals Checkout FLnctional Test Inspection

<

'

079-5-004-Radiation Monitoring Detector Preop.

081-5-003-Fuel Transfer System Preop. with Dummy

,

Assembly a

c.

Tests which have not been started i

010-5-002-Polar Crane Preop.

013-3-005-Dry and Wet Sprinkler System 079-5-005-Radiation Monitoring Actuation Preop.

'

081-5-004-Manipulator Crane Preop.

097-5-001-Security System Preop.

12.

Unit No. 2 Near Term Operation License (NTOL) Requirements The inspector reviewed plant documentation for the following NTOL require-

__

mer:ts which are required to be completed prior to fuel load.

a.

I. A.1.2-Shift Superviosr Administrative Duties.

-This item is addressed in section 3.1.6 of Administrative Procedure No.16 " Conduct fo Operations-Operations Group."

b.

I.C.2-Shift Relief and Turnover Procedures This item'is addressed in section 4.2 and Appendix D of Administrative Procedure No.16 " Conduct of Operation-Operation Group."

,

'

c.

-I.C.3-Shift Supervisor Responsibilities.

This item is addressed-in section 3.1.6 of Administrative Procedure o.

" Conduct of Operation-Operations Group."

.

'1

-.

- _.., _ _ _ _ _

- _

._ ___ _., _ _ _ _....

.

.

,

_

_ _ _

r.

y y

- - -, -

%

-p--y-

_.-5-

+

=v ema s.,

  • -

&-7 g,---

?g p

-

.

.

.. --

.

-

-

-

.... -

.

-.

_ -

-.

i i

'

-6-

,

I d.

'I.C.4-Control Room Access - This item is addressed in Administrative

,

Procedure No.16

" Conduct of Operation-Operation Group."

,

I.C.5-Procedures for Feedback of Operating Experience to the Plant e.

Staff.

.

This item 'is addressed in Administrative Procedure No. 63. " Conduct

of. Operations-Systems / Performance Group."

,

13. - Plant Maintenance Review of administrative controls for corrective plant maintenance following

system turnover from construction revealed the following:

a.

Plant maintenance is required to be perfonned in accordance with defined administrative controls.

b.

Methods have been established for initiating, reviewing, approving and scheduling maintenance.

c.

Methods have been established for controlling replacement materials and parts that are designated for use in safety-related maintenance activities.

d.

Controls have been. established which require that only qualified personnel will perform maintenance activities.

e.

Maintenance administrative controls have been established which include the following:

Criteria for determining when maintenance procedures will be

-

provided.

-

Methods for preparing maintenance procedures.

-

Requirements for reviewing and approving maintenance procedures.

Methods of determining when training of personnel in the use of

-

maintenance procedures is required.

-

A formal method to assure that appropriate approvals will be obtained prior to performing any maintenance activity.

-

Inspection of maintenance work including final inspection of a completed task.

\\

<

i

-

Testing of structures, systems or components following maintenance ll

to reestablish the validity of preoperational tests.

I

l

.. - _ _

_

-.

_...

..

_. _ _ _ _....

/

,

-7-

.

Control of test and measurement equipment utilized in maintenance

-

activities.

f.

Controls have been established which require preparation and retention of maintenance records.

Controls for preventive maintenance were under review at the conclusion of the inspection period.

.