f
=
.
parary
- o, UNITED STATES
NUCLEAR REGULATORY COMMISSION
,
o
$
- [E REGION il
- -
o 101 MARIETTA ST., N.W., SUITE 3100 ATLANTA, GEORGIA 30303
-
s
.
Report No. 50-364/80-08
.
Licensee: Alabama Power Company 600 North 18'; Street Birmingham, A 35202 f
Facility: Farley Nuclear Plant Docket No. 50-364 License No. CPPR-86 Inspection at Farley Nuclear Plant near Dothan, Alabama Inspector: h i
4 - 2 3 -50 W. P.
Date Signed Approved by:
[ /[
N ~SO ' 0 A. R. Herdt, Section Chief, RCES Branch Date Signed SUMMARY Inspection on April 9-11, 1980 Areas Inspection
-
This routine, announced inspection involved 20 inspector-hours on site in the areas of pipe support baseplate designs using concrete expansion bolts (IEB 79-02); seismic analysis for as-built safety related piping systems.
Results Of the areas inspected, no items of noncompliance or deviations were identified.
-
,
$
,,,
.
e esm
8006030 d.73
__
.
- - - - -
..
-
.
.
= :. a
.
.
....
,
.
.
t
-
s DETAILS
1.
Perscns Contacted
-
Licensee Employees
- J. A. Mooney, Project Manager-Construction
.
- R.'E. Hollands, Quality Assurance Supervisor
- J. G. Hegi, Project Quality Control Engineer
- R. M. Colemant, Production Engineering Supervisor
- J. C. Bozeman, Construction Supervisor
.
Other licensee employees contacted included 4 construction craftsmen and 4
technicians.
Other Organizations i
- L. F. Warrik, Project Manager-Daniel Construction Company
- D. L. Garrison, QA Manager-Daniel Construction Company
- L. C. Easterwood, QC Manager-Daniel Construction Company
!
- Attended exit interview 2.
Exit Interview The inspection scope and findings were summarized on April 11, 1980, with those persons indicated in paragraph I above.
,
3.
Licensee Action on Previous Inspection Findings Not inspected.
.
4.
Unresolved Items Unresolved items were not identified during this inspection.
5.
Pipe Support Baseplate Designs Using Concrete Expansion Bolts (IEB 79-02)
t On January 7, 1980, the licensee provided a response to IE Bulletin 79-02.
An inspection was performed to verify licensee compliance with IE Bulletin 79-02 requirements and licensee commitments.
.
Daniel Field Quality Control Procedure 5.4.2.1A, Rev.
1, Verification of Acceptab1'e Concrete Expansion Anchors for Selected Piping Systems, was
'
reviewed. Component Cooling Water System Support No. 2-CCW-R359 and Auxil-iary Feedwater System Supports 2AFW-R119 and 1AFW-R120 were randomly selected and inspected for compliance with IEB 79-02 requirements and licensee commit-ments.
.
,.
<
r y
,
- - -
-
e
,
y
---
,
.. _ _ __
____ _ _.
_ _ _ __
_ _
_ _ _ _ _ _ _
e
..
.
(
-2-
~
The licensee's IEB 79-02 site work was approximately 60 percent complete.
Pending completion of IEB 79-02 requirements, the bulletin shall remain open.
No items of noncompliance or deviations were identified..
6.
Seismic Analysis for As-Built Safety Related Piping Systems (IEB 79-14)
On' November 2, 1979, the licensee provided a response to IE Bulletin 79-14.
An inspection was performed to verify licensee compliance with IE Bulletin 79-14 requirements and licensee commitments.
The' following procedures that provided the licensee IEB 79-14 inspection requirements were reviewed:
Daniel Field Quality Control Procedure 5.4.2.1, Rev.12-Quality Control Procedure for Installation of Piping.
Alabama Power Company (APCO) FNP-QCP4.01-APC0 Construction Department Inspection of Seismic Category 1 Piping Systems.
Portions of the component cooling water system piping shown on Daniel drawing SK-P17-CV364 and Auxiliary Feedwater System piping shown on Daniel drawing SK-N21-CV041 were inspected. Some minor discrepancies were noted in the measurement of clearances for support 2CCW-R359, 2AFW-R119 and 2AFW-R120. The licensee is performing a reinspection of the clearances of the supports and will evaluate the results of the reinspection.
Pending licensee completion of IEB 79-14 requirements, the bulletin shall remain open.
<
No items of noncompliance or deviations were noted.
.