IR 05000263/2024003
ML24318C235 | |
Person / Time | |
---|---|
Site: | Monticello |
Issue date: | 11/13/2024 |
From: | Richard Skokowski NRC/RGN-III/DORS/RPB3 |
To: | Hafen S Northern States Power Company, Minnesota |
References | |
EPID I-2024-003-0062 IR 2024003 | |
Download: ML24318C235 (1) | |
Text
SUBJECT:
MONTICELLO NUCLEAR GENERATING PLANT - INTEGRATED INSPECTION REPORT 05000263/2024003
Dear Shawn Hafen:
On September 30, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Monticello Nuclear Generating Plant. On October 22, 2024, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.
No findings or violations of more than minor significance were identified during this inspection.
This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely, Richard A. Skokowski, Chief Reactor Projects Branch 3 Division of Operating Reactor Safety Docket No. 05000263 License No. DPR-22
Enclosure:
As stated
Inspection Report
Docket Number:
05000263 License Number:
DPR-22 Report Number:
05000263/2024003 Enterprise Identifier:
I2024003-0062 Licensee:
Northern States Power Company, Minnesota Facility:
Monticello Nuclear Generating Plant Location:
Monticello, MN Inspection Dates:
July 01, 2024, to September 30, 2024 Inspectors:
N. Bolling, Resident Inspector J. Kutlesa, Sr. Emergency Preparedness Inspector T. McGowan, Resident Inspector C. Norton, Senior Resident Inspector J. Reed, Health Physicist Approved By:
Richard A. Skokowski, Chief Reactor Projects Branch 3 Division of Operating Reactor Safety
SUMMARY
The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Monticello Nuclear Generating Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.
List of Findings and Violations
No findings or violations of more than minor significance were identified.
Additional Tracking Items
None.
PLANT STATUS
Monticello began the inspection period at rated thermal power. On September 12, 2024, the unit was down powered to 50 percent of rated thermal power for turbine testing and main steam isolation valve testing. The unit was returned to rated thermal power the same day and remained at or near rated thermal for the remainder of the inspection period.
INSPECTION SCOPES
Inspections were conducted using the appropriate portions of the inspection procedures (IPs)in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed onsite portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.
REACTOR SAFETY
71111.01 - Adverse Weather Protection
Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)
- (1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal heavy rains for the following systems:
Intake structure and residual heat removal (RHR) service water system on August 27, 2024
71111.04 - Equipment Alignment
Partial Walkdown Sample (IP Section 03.01) (4 Samples)
The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:
- (1) Fire protection system on July 10, 2024
- (2) Division 1 control room ventilation (CRV) and emergency filtration train (EFT),protected equipment on July 24, 2024
- (3) Division 2 RHR on September 24, 2024
- (4) Division 2 250Vdc electrical system on September 27, 2024
71111.05 - Fire Protection
Fire Area Walkdown and Inspection Sample (IP Section 03.01) (5 Samples)
The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:
- (1) Recirculation pump motor-generator set room on July 8, 2024
- (2) Emergency filtration building 1st floor, division 1 on July 9, 2024
- (3) Fuel pool skimmer tank room on July 10, 2024
- (4) Reactor feed pump and lube oil reservoir room on July 15, 2024
- (5) Lube oil storage tank room on July 16, 2024
Fire Brigade Drill Performance Sample (IP Section 03.02) (1 Sample)
- (1) The inspectors evaluated the onsite fire brigade training and performance during an announced fire drill on July 20, 2024
===71111.07 A - Heat Exchanger/Sink Performance Annual Review (IP Section 03.01) (1 Partial)
The inspectors evaluated readiness and performance of:
(1)
(Partial)
Division 2 emergency diesel generator heat exchanger watched data gathering on July 29, 2024
71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance
Licensed Operator Requalification Training/Examinations (IP Section 03.02)===
- (1) The inspectors observed and evaluated reactor operator as found simulator examination on August 19, 2024.
71111.12 - Maintenance Effectiveness
Maintenance Effectiveness (IP Section 03.01) (3 Samples)
The inspectors evaluated the effectiveness of maintenance to ensure the following structures, systems, and components (SSCs) remain capable of performing their intended function:
- (1) Change out of LC 1057 (14 B high pressure dump valve level controller)on July 31, 2024, and August 6, 2024
- (2) Replacement of components and load test of 250 Vdc safety-related (D80)battery charger for battery 16 on August 20, 2024
- (3) Drainage of waste collector tank T25 involving short limiting condition for operations shutdown action for secondary containment on September 9, 2024
71111.13 - Maintenance Risk Assessments and Emergent Work Control
Risk Assessment and Management Sample (IP Section 03.01) (1 Sample)
The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:
- (1) Verification that set screw on the pinion gear on motor operated valve (MO) 2012, division 2 outboard low pressure coolant injection valve, was in place on August 7, 2024
71111.15 - Operability Determinations and Functionality Assessments
Operability Determination or Functionality Assessment (IP Section 03.01) (5 Samples)
The inspectors evaluated the licensees justifications and actions associated with the following operability determinations and functionality assessments:
(1)
===501000088600, MO2012 pinion may not be secured on the division 2 outboard low pressure coolant injection valve (2)501000088828, core spray header differential pressure switch failed to reset (3)501000089259, APRM2 [average power range monitor] non-critical self-test fault (4)501000087690, EQASCO activation energy issue SV2379 and SV2380
[torus to drywell vacuum breakers]
(5)501000090055, VD9216B [control room fresh air damper] did not open as expected
71111.18 - Plant Modifications
Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)
=
The inspectors evaluated the following temporary or permanent modifications:
- (1) Temporary disconnect of relief valve annunciator for 2R transformer on August 21, 2024
Severe Accident Management Guidelines (SAMG) Update (IP Section 03.03) (1 Sample)
- (1) The inspectors verified the site SAMG were updated in accordance with the BWR generic sever accident technical guidelines and validated in accordance with NEI 14-01, Emergency Response Procedures and Guidelines for Beyond Design Basis Events and Severe Accidents, Revision 1.
71111.24 - Testing and Maintenance of Equipment Important to Risk
The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:
Post-Maintenance Testing (PMT) (IP Section 03.01) (5 Samples)
- (1) Reactor core isolation cooling (RCIC) room air cooling unit on August 16, 2024
- (2) Division 2 250 Vdc battery charger D80 on August 20, 2024
- (3) APRM 2 after replacement of circuit card on August 29, 2024
- (4) RHR division 1 torus spray inboard valve following corrective maintenance on September 9, 2024
- (5) Hydraulic control unit (HCU) 3815 after replacement of accumulator on September 12, 2024
Surveillance Testing (IP Section 03.01) (5 Samples)
- (1) Emergency filtration treatment system, division 1 operability test on July 9, 2024
- (2) Security system emergency generator operability check and alarm on July 10, 2024
- (3) Local power range monitor (LPRM) calibration on July 11, 2024
- (4) RCIC steam line high area temperature test and calibration on August 13, 2024
- (5) Division 2 RHR system quarterly pump and valve testing on September 25, 2024
Diverse and Flexible Coping Strategies (FLEX) Testing (IP Section 03.02) (1 Sample)
- (1) P505 portable diesel fire pump test on August 1, 2024
71114.02 - Alert and Notification System Testing
Inspection Review (IP Section 02.0102.04) (1 Sample)
- (1) The inspectors evaluated the following maintenance and testing of the alert and notification system:
- Annual siren inspection and maintenance records for the period of July 2022 to Jul 2024
- Weekly alert notification system (siren) tests for the period of July 2022 to July 2024
71114.03 - Emergency Response Organization Staffing and Augmentation System
Inspection Review (IP Section 02.0102.02) (1 Sample)
- (1) The inspectors evaluated the readiness of the emergency preparedness organization.
71114.05 - Maintenance of Emergency Preparedness
Inspection Review (IP Section 02.01 - 02.11) (1 Sample)
- (1) The inspectors evaluated the maintenance of the emergency preparedness program.
RADIATION SAFETY
71124.06 - Radioactive Gaseous and Liquid Effluent Treatment
In addition to the normal inspection of this inspection procedure, the NRC inspectors utilized additional resources to review the progress and results of the licensees actions related to the onsite monitoring well that indicated tritium activity above the Offsite Dose Calculation Manual and Nuclear Energy Institute Groundwater Protection Initiative reporting levels, which was previously reviewed (ML23219A155) in 2023. The additional inspection scope of the licensees actions included:
- The revised methodology used by the licensee to quantify the amount of radioactive material leaked to groundwater
- The revised recovery system which was changed from temporary above ground storage tanks to permanent engineered retention ponds
- The methodology and results used to determine the tritium activity in the Mississippi River from background or other sources not attributed to plant operations
- The methodology and results for the calculations of tritium moving to the river and the associated dose to the nearest receptor for this abnormal discharge The results from this additional scope are included as an observation within this report.
Walkdowns and Observations (IP Section 03.01) (4 Samples)
The inspectors evaluated the following radioactive effluent systems during walkdowns:
- (1) Unit 1, reactor building ventilation stack and monitor
- (2) Unit 1, offgas stack and monitor
- (3) Water storage pond, pumphouse, and sample hut
- (4) Unit 1, service water system and monitor
Sampling and Analysis (IP Section 03.02) (4 Samples)
Inspectors evaluated the following effluent samples, sampling processes and compensatory samples:
- (1) Reactor building weekly wide range gas monitor (WRGM) sample
- (2) Plant offgas stack weekly WRGM sample
- (3) Water storage pond sample
- (4) Drywell purge sample
Dose Calculations (IP Section 03.03) (2 Samples)
The inspectors evaluated the following dose calculations:
- (1) Reactor building weekly vent stack dose calculation
- (2) Water storage pond monthly dose calculation
Abnormal Discharges (IP Section 03.04) (1 Sample)
The inspectors evaluated the following abnormal discharges:
- (1) Abnormal liquid discharge from 2022 leak into groundwater
OTHER ACTIVITIES - BASELINE
===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:
MS06: Emergency AC Power Systems (IP Section 02.05)===
- (1) July 1, 2023, through June 30, 2024
MS07: High Pressure Injection Systems (IP Section 02.06) (1 Sample)
- (1) July 1, 2023, through June 30, 2024
MS08: Heat Removal Systems (IP Section 02.07) (1 Sample)
- (1) July 1, 2023, through June 30, 2024 BI01: Reactor Coolant System (RCS) Specific Activity Sample (IP Section 02.10) (1 Sample)
- (1) May 1, 2023, through May 30, 2024
OR01: Occupational Exposure Control Effectiveness Sample (IP Section 02.15) (1 Sample)
- (1) May 1, 2023, through May 30, 2024 PR01: Radiological Effluent Technical Specifications/Offsite Dose Calculation Manual Radiological Effluent Occurrences (RETS/ODCM) Radiological Effluent Occurrences Sample (IP Section 02.16) (1 Sample)
- (1) May 1, 2023, through May 30, 2024
EP01: Drill/Exercise Performance (DEP) Sample (IP Section 02.12) (1 Sample)
- (1) April 1, 2022, through June 30, 2024 EP02: Emergency Response Organization (ERO) Drill Participation (IP Section 02.13) (1 Sample)
- (1) April 1, 2022, through June 30, 2024 EP03: Alert And Notification System (ANS) Reliability Sample (IP Section 02.14) (1 Sample)
- (1) April 1, 2022, through June 30, 2024
71152 A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)
The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:
- (1) Reactor SCRAM that occurred during turbine testing on September 27,
INSPECTION RESULTS
Observation: Subsurface Tritium Activity 71124.06 The inspectors had the following observations from the reviews performed in addition to scope defined by Inspection Procedure 71124.06, Radioactive Gaseous and Liquid Effluent Treatment:
- The revised methodology used by the licensee to quantify the amount of radioactive material leaked to groundwater.
o The original method utilized the observed leak rate from the pipe, and estimated the time the pipe was leaking and the concentration of tritium in the pipe. This method was adequate for the purpose of characterizing the event and estimating the annual dose to a member of the public. The licensee subsequently performed a more detailed mass balance calculation to determine that total activity leaked into the subsurface of plant property.
The licensees revised value is 14 Curies of tritium leaked from the plant into the subsurface on plant property.
- The revised recovery system which was changed from temporary above ground storage tanks to permanent engineered retention ponds.
o The inspectors noted the licensee adequately evaluated and accounted for evaporative losses from the ponds.
- The methodology and results used to determine the tritium activity in the Mississippi River from background or other sources not attributed to plant operations.
o These results indicate no plant impact can be seen on the concentration of Tritium (i.e., above natural background level) in the Mississippi River.
- The methodology and results for the calculations of tritium moving to the river and the associated dose to the nearest receptor for this abnormal discharge.
o The NRC requires licensees to quantify the concentration of radioactive material, tritium in this case, at the point of release to the unrestricted area.
To this end, the licensees contracted hydrogeologist firm used MODFLOW, a U.S. Geological Survey computer code to model/simulate the groundwater flow from the plant site to the Mississippi River. Additionally, licensees are required to demonstrate by measurement or calculation that the total dose equivalent to an individual likely to receive the highest dose does not exceed the annual dose limit. The resulting doses calculated were far below the regulatory requirements and the methodology used to determine the movement of tritium to the Mississippi River was adequate.
These results support and reaffirm the conclusions from the previous inspection (ML23219A155). Specifically, the licensee developed a holistic plan with significant input from contracted vendor with expertise in groundwater management and cleanup. The inspectors noted a high level of support (time and resources) from all levels of the organization to recover and store the contaminated groundwater onsite and mitigate any uncontrolled release from the site. Additionally, these results indicate the abnormal discharge was monitored and evaluated with regard to the environment and public exposure. Finally, the inspections confirm our earlier assessment that the discharge has no impact on public health and safety.
Observation: Corrective Actions for SCRAM That Occurred During Turbine Testing 71152 A On September 27, 2023, an unplanned SCRAM, group I primary containment isolation, and group II primary containment isolation occurred. The SCRAM was attributed to testing the control valves at 75 percent reactor power, a power just below the transition between the large outer piston and the smaller inner piston of the control valve actuators. When one control valve was closed the other control valves did not respond, and reactor pressure increased, resulting in the transient. Corrective actions included revising the turbine control valve test procedure to be performed at 50 percent reactor power, away from the control valve transition between the large outer piston and the smaller inner piston.
On September 12, 2024, the inspectors observed the licensee lower reactor power to 50 percent to perform control valve testing. No issues of concern were identified.
EXIT MEETINGS AND DEBRIEFS
The inspectors verified no proprietary information was retained or documented in this report.
- On October 22, 2024, the inspectors presented the integrated inspection results to S. Hafen, Site Vice President, and other members of the licensee staff.
- On August 2, 2024, the inspectors presented the emergency preparedness inspection results to G. Brown, Plant Manager, and other members of the licensee staff.
- On August 28, 2024, the inspectors presented the radiation protection baseline inspection results to S. Hafen, Site Vice President, and other members of the licensee staff.
DOCUMENTS REVIEWED
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Corrective Action
Documents
501000089312
Roof Section Blown Off During Storm
08/27/2024
NH36048
(M134)
P&ID Fire Protection System Interior Locations
NH36246
(M120)
P&ID Residual Heat Removal System
NH36516
(M810)
P&ID Fire Protection System Yard Areas
Drawings
NH36666
(M812)
P&ID Intake Structure Screen Wash
Fire & Water Treatment System
100
269
Fire Protection Valve Check
201
Plant Prestart Checklist CRV-EFT System
B.03.0405
Residual Heat Removal System
B.08.0505
Fire Protection - System Operation
B.08.1305
Control Room Heating and Ventilation (H&V) and
Emergency Filtration Train (EFT)
B.09.0905
250 VDC System
Procedures
EWI11.01.06
Battery Monitoring and Maintenance Program
Strategy A.303-A
Fire Zone 3A, Recirc MG Set Room
Strategy A.305-C
Fire Zone 5C, Fuel Pool Skimmer Tank Room
Strategy A.313-A
Fire Zone 13A, Lube Oil Storage Tank Room
Strategy A.313-B
Fire Zone 13B, Rx Feedpump and
Lube Oil Reservoir Room
Fire Plans
Strategy A.331-A
Fire Zone 31A, EFT Building 1st Floor (DIV I)
Miscellaneous
Drill Guide 24.01
Fire Brigade Drill Guide (Fire Zone 24)
07/20/2024
Procedures
140101
Emergency Diesel Generator Emergency Service Water
Heat Exchanger Performance Test
Miscellaneous
RQSS173
RPV Flood
C.51100
Reactor Pressure Vessel Control
C.51200
Primary Containment Control
Procedures
C.52006
Reactor Pressure Vessel Flood
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Corrective Action
Documents
501000089045
D80 Circuit Card Replacement Part
08/19/2024
28OCD
Waste Collector Filter T25 Cleaning
Procedures
25PM
No. 23 & 16 Battery Charger Preventive Maintenance
2000032398
Type 2Operational Decision Making Issue Evaluation,
LC1057 (HIP HTR 14B Level Dump Controller)
07/22/2024
Work Orders
700118940020
28 Waste Collector Filter T25 Cleaning
09/09/2024
Work Orders
70001417310010
MO 2012 Secure Motor Pinion
08/07/2024
501000087690
EQASCO Activation Energy Issue
07/12/2024
501000088600
MO2012 Motor Pinion May Not be Secured
08/05/2024
501000088828
Switch Not Reset
08/14/2024
501000089259
APRM2 Non-Critical Self-Test Fault
08/26/2024
Corrective Action
Documents
501000090055,
VD9216B [Control Room Fresh Air Damper]
Did Not Open as Expected
09/20/2024
Engineering
Evaluations
EE
608000001175
Evaluation of ASCO Solenoid Valve Activation Energy Issue
N/A
A4993AN003
Continuous Energization of ASCO Catalog NP1 Valves
During a Loss-ofCoolant Accident
2/11/1979
Miscellaneous
N03651ASCO
Environmental Qualification Temperature Test of ASCO 206
and NP Series Solenoid Valves
June 2000
Drawings
ECR5149NX-
23674450-1
2R Auxiliary Transformer Wiring Diagram
08/21/2024
Engineering
Changes
601000005149
Temporary Disconnect 2R Relief Valve Annunciator
08/21/2024
A.7SAMG01
RPV and Primary Containment Injection (Modes 14)
A.7SAMG02
RPV, Containment, and Radioactive Release Control
(Modes 14)
A.7SAMG03
Refueling (Mode 5)
C.5GM-02.01
Plant Specific Technical Guidelines
C.5GM-02.02
Plant Specific Technical Guidelines
C.6008-B01
No. 2R XFMR Trouble
Procedures
Ops Man
C.5.11004
SAMG Technical Bases (Modes 1, 2, 3, 4)
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Ops Man
C.5.11005
SAMG Technical Bases (Mode 5)
Work Orders
7001414770020
Install TMOD (601000005149)
08/21/2024
501000088823
Error Likely Situation with Procedure 0062
08/13/2024
501000089259
APRM2 Non Critical Self Test Fault
08/26/2024
501000089397
APRM DNSCL/TRBL
08/29/2024
501000089804
HCU 3815
09/16/2024
Corrective Action
Documents
501000089861
RHR86 Spins Freely
09/15/2024
0062
RCIC Steam Line High Area Temperature Test and
Calibration Procedure
0074
Control Rod Dive Exercise
0081
Control Rod Drive SCRAM Insertion Time Test
25504-IA12
RHR Loop B Quarterly Pump and Valve Tests
105
29802
Security System Emergency Generator Operability Check &
Alarm
046501
Emergency Filtration Treatment System (A Train, Control
Room Emergency Filtration)
7100
CRD-HCU Instrument Maintenance Procedure
ISP-NIP058901
APRM Channel Functional Test - Run Mode
NUC02.02
OD1/LPRM Calibration
OSP-FIR0582
P505, Portable Diesel Fire Pump Testing
OSP-NIP0546
LPRM Calibration
OSP-RHR0012
MO2023 Open Supplemental Position Indication Test
Procedures
OSP-RHR0556
RHR Water Fill Verification
70001306360020
PMT: Charger, D6A (16) Battery
08/20/2024
7001079900040
PMT: RCIC Room Air Cooling Unit
08/16/2024
7001224460020
PMT: RHR DIV I Torus Spray Inboard Valve
09/04/2024
700135027
046501 DIV 1 EFT Quarterly Operation
07/09/2024
700136224
04651 DIV 1 CRV Monthly Operation
07/09/2024
700136227
OSP-NIP0546 LPRM CAL (1000 MWD/T)
07/11/2024
7001388010010
25504-21 RHR Loop B Quarterly Pump and Valve Test
09/25/2024
7001407490020
PMT: Hydraulic Control Unit for CRD3815
09/12/2024
Work Orders
700142944
PMT: Perform APRM Channel 2 Functional Test
08/29/2024
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
Part B of Procedure ISP-NIP058901
EPLAN10
Monticello Alert and Notification System (ANS)
Design Report
Miscellaneous
N/A
ANS Testing Raw Data
07/06/2022
through
07/10/2024
Procedures
FPEP-WI01
Public Alert Notification System (Pans) Maintenance and
Testing
Corrective Action
Documents
501000080918
(MT)
NOS Finding: EP OnShift Staff Analysis
01/17/2024
LXE22006 10 CFR 50.90
Response to a Request for Additional Information RE: Xcel
Energy Amendment Request to Create a Common
Emergency Plan and Emergency Operations Facility for
Monticello and Prairie Island (EPID: L2021LLA0210)
06/10/2022
Miscellaneous
N/A
EP Training Records
Various
EPLAN08
OnShift Staffing Analysis
Procedures
Plan Revision: 0
Standard Emergency Plan
Corrective Action
Documents
Resulting from
Inspection
501000088419
EVES Building Condition Observation
08/01/2024
N/A
NELCOM Service Report
07/01/2022
through
05/01/2024
Miscellaneous
N/A
LOA & MOU: GE Labs; US Dept. of Energy; MN Homeland
Security and Emergency Management; North Memorial
Med. Center: Sherbune County; Wright County;
CNTNRACARE Monticello & St. Cloud: Regions Hospital;
City of Monticello
Various
Procedures
255360F
Model DCFCTB Installation, Operation & Service Manual
Rev 7/06
MTGC2024055
Gaseous Effluent Release Report via Pond
06/04/2024
Calculations
MTGC2024073
Gaseous Effluent Release Report via Reactor Building
Ventilation
07/17/2024
Corrective Action
501000068729
Elevated Monitoring Well 9 Tritium Result
11/21/2022
Inspection
Procedure
Type
Designation
Description or Title
Revision or
Date
501000069072
MW9 Iodine Results
2/07/2022
501000073844
Groundwater Data in 2022 ARERR
05/22/2023
501000077554
ODCM-APP-A Error Found
10/09/2023
501000081265
Missed ODCM Surveillance Requirements
01/25/2024
Documents
501000087801
Lake Tanks 3&4 Outside Gaseous Boundary
07/16/2024
Miscellaneous
NBGAS
Stack-Vent
Compensatory Sampling Gamma Isotopic for Noble Gas
05/13/2022
0066B
Reactor Building Vent Release Rate Determination
29
Off-Gas/Storage Tank Gross Activity Limit
0362
Monitoring for Containment Purging
0505
Radioactive Effluent Release Report Preparation and
Review
I.02.06
Airborne Continuous Release Report
Monticello
Updated Safety
Analysis Report
Monticello USAR
Procedures
ODCM01
Offsite Dose Calculation Manual
Miscellaneous
QF2116
EP Quarterly Performance Indicator
April 1, 2022,
through
June 30,
24
22
Reactor Coolant I131 Dose Equivalent Activity
71151
Procedures
QF0444 (FPR-
PI01)
NRC and MOR Data Collection and Submittal Forms
501000077129
50.72 Non-Emergency Report to NRC
09/27/2023
501000077170
Reactor SCRAM Number 141
09/27/2023
Corrective Action
Documents
501000077171
Potential Equipment Malfunction CV4
09/27/2023
104001
Turbine - Generator
09/09/2024
71152 A
Procedures
2300
Reactivity Adjustment
27