IR 05000263/2024004

From kanterella
Jump to navigation Jump to search
Integrated Inspection Report 05000263/2024004
ML25029A173
Person / Time
Site: Monticello 
Issue date: 01/30/2025
From: Dariusz Szwarc
NRC/RGN-III/DORS/RPB3
To: Hafen S
Northern States Power Company, Minnesota
References
IR 2024004
Download: ML25029A173 (1)


Text

SUBJECT:

MONTICELLO NUCLEAR GENERATING PLANT - INTEGRATED INSPECTION REPORT 05000263/2024004

Dear Shawn Hafen:

On December 31, 2024, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at Monticello Nuclear Generating Plant. On January 23, 2025, the NRC inspectors discussed the results of this inspection with you and other members of your staff. The results of this inspection are documented in the enclosed report.

No findings or violations of more than minor significance were identified during this inspection.

This letter, its enclosure, and your response (if any) will be made available for public inspection and copying at http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in accordance with Title 10 of the Code of Federal Regulations 2.390, Public Inspections, Exemptions, Requests for Withholding.

Sincerely, Dariusz Szwarc, Chief Reactor Projects Branch 3 Division of Operating Reactor Safety Docket No. 05000263 License No. DPR-22

Enclosure:

As stated

Inspection Report

Docket Number:

05000263

License Number:

DPR-22

Report Number:

05000263/2024004

Enterprise Identifier:

I2024004-0061

Licensee:

Northern States Power Company, Minnesota

Facility:

Monticello Nuclear Generating Plant

Location:

Monticello, MN

Inspection Dates:

October 01, 2024, to December 31, 2024

Inspectors:

J. Kutlesa Sr. Emergency Preparedness Inspector

T. McGowan, Emergency Preparedness Inspector

C. Norton, Senior Resident Inspector

K. Pusateri, Resident Inspector

Approved By:

Dariusz Szwarc, Chief

Reactor Projects Branch 3

Division of Operating Reactor Safety

SUMMARY

The U.S. Nuclear Regulatory Commission (NRC) continued monitoring the licensees performance by conducting an integrated inspection at Monticello Nuclear Generating Plant, in accordance with the Reactor Oversight Process. The Reactor Oversight Process is the NRCs program for overseeing the safe operation of commercial nuclear power reactors. Refer to https://www.nrc.gov/reactors/operating/oversight.html for more information.

List of Findings and Violations

No findings or violations of more than minor significance were identified.

Additional Tracking Items

None.

PLANT STATUS

The unit began the inspection period at rated thermal power. On October 21, 2024, the licensee reduced power to 95 percent to perform control rod maintenance and returned to 100 percent.

On December 10, 2024, the licensee reduced power to 33 percent for condenser water box cleaning and returned the unit to 100 percent on December 12, 2024. The unit remained at or near rated thermal power for the remainder of the inspection period.

INSPECTION SCOPES

Inspections were conducted using the appropriate portions of the inspection procedures (IPs) in effect at the beginning of the inspection unless otherwise noted. Currently approved IPs with their attached revision histories are located on the public website at http://www.nrc.gov/reading-rm/doc-collections/insp-manual/inspection-procedure/index.html. Samples were declared complete when the IP requirements most appropriate to the inspection activity were met consistent with Inspection Manual Chapter (IMC) 2515, Light-Water Reactor Inspection Program - Operations Phase. The inspectors performed activities described in IMC 2515, Appendix D, Plant Status, observed risk significant activities, and completed onsite portions of IPs. The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel to assess licensee performance and compliance with Commission rules and regulations, license conditions, site procedures, and standards.

REACTOR SAFETY

71111.01 - Adverse Weather Protection

Seasonal Extreme Weather Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated readiness for seasonal extreme weather conditions prior to the onset of seasonal cold temperatures for the following systems:

Reactor building chiller water system and EPA pumps operational for anticipated low river temperatures on November 29, 2024

71111.04 - Equipment Alignment

Partial Walkdown Sample (IP Section 03.01) (3 Samples)

The inspectors evaluated system configurations during partial walkdowns of the following systems/trains:

(1) Reactor recirculation system on October 8, 2024
(2) Off-gas system, recombiner and holdup subsystems on October 18, 2024
(3) Reactor core isolation cooling protected train on October 24, 2024

71111.05 - Fire Protection

Fire Area Walkdown and Inspection Sample (IP Section 03.01) (4 Samples)

The inspectors evaluated the implementation of the fire protection program by conducting a walkdown and performing a review to verify program compliance, equipment functionality, material condition, and operational readiness of the following fire areas:

(1) West shutdown cooling area on October 9,2024 (2)125V division 1 battery room on October 10, 2024 (3)250V division 1 battery room on October 10, 2024
(4) East shutdown cooling area on October 11, 2024

71111.06 - Flood Protection Measures

Flooding Sample (IP Section 03.01) (1 Sample)

(1) The inspectors evaluated external flooding mitigation protections for beyond-design-basis flooding

71111.07A - Heat Exchanger/Sink Performance

Annual Review (IP Section 03.01) (1 Sample)

The inspectors evaluated readiness and performance of:

(1) Division 2 emergency diesel generator (EDG) emergency service water (ESW)heat exchanger

71111.11A - Licensed Operator Requalification Program and Licensed Operator Performance

Requalification Examination Results (IP Section 03.03) (1 Sample)

(1) The inspectors reviewed and evaluated the licensed operator examination failure rates for the requalification annual operating exam administered from October 21, 2024, to December 09, 2024.

71111.11Q - Licensed Operator Requalification Program and Licensed Operator Performance

Licensed Operator Performance in the Actual Plant/Main Control Room (IP Section 03.01) (1 Sample)

(1) The inspectors observed and evaluated licensed operator performance in the control room during the main steam high flow group 1 instrument test surveillance procedure on November 20, 2024

Licensed Operator Requalification Training/Examinations (IP Section 03.02) (1 Sample)

(1) The inspectors observed and evaluated simulator exercise guide (SEG) RRSS185 for crew 5 on October 31, 2024

71111.12 - Maintenance Effectiveness

Quality Control (IP Section 03.02) (1 Sample)

The inspectors evaluated the effectiveness of maintenance and quality control activities to ensure the following structures, systems, and components (SSCs) remains capable of performing its intended function:

(1) Added drain line to the residual heat removal service water (RHRSW) system in accordance with work order 700145119 on November 19, 2024

Aging Management (IP Section 03.03) (1 Sample)

The inspectors evaluated the effectiveness of the aging management program for the following SSCs that did not meet their inspection or test acceptance criteria:

(1) Completed aging management walkdown for reactor recirculation system (outside of drywell) in the presence of the strategic engineer on December 16, 2024

71111.13 - Maintenance Risk Assessments and Emergent Work Control

Risk Assessment and Management Sample (IP Section 03.01) (2 Samples)

The inspectors evaluated the accuracy and completeness of risk assessments for the following planned and emergent work activities to ensure configuration changes and appropriate work controls were addressed:

(1) Emergent replacement of EDG ESW 11 on October 16, 2024
(2) Backseat MO2034, HPCI steam line isolation inboard valve on October 24, 2024

71111.15 - Operability Determinations and Functionality Assessments

Operability Determination or Functionality Assessment (IP Section 03.01) (4 Samples)

The inspectors evaluated the licensees justifications and actions associated with the following operability determinations and functionality assessments:

(1)

===501000090899 CV1478 (instrument air isolation to the drywell) opening trend time longer than expected (2)501000092314 Safe shutdown cable route (Appendix R) question (3)501000092267 reactor core isolation cooling system condensate pump discharge to rad waste open indication delayed during Inservice testing (IST)

(4)50100092992 Intakes issues & entry into A.6 (acts of nature procedure, on low river level)

71111.18 - Plant Modifications

Temporary Modifications and/or Permanent Modifications (IP Section 03.01 and/or 03.02)

=

The inspectors evaluated the following temporary or permanent modifications:

(1) Installation and removal of a jumper while performing 0523, RWCU [reactor water cleanup] high flow and high room temperature trip unit instrument test and calibration

71111.24 - Testing and Maintenance of Equipment Important to Risk

The inspectors evaluated the following testing and maintenance activities to verify system operability and/or functionality:

Post-Maintenance Testing (PMT) (IP Section 03.01) (5 Samples)

(1) Anticipated without SCRAM (ATWS) system B train after replacement of inverter and ground troubleshooting on October 3, 2024
(2) Replacement of ESW 11 pump (P111A) due to low flow degradation on October 17, 2024
(3) Traversing incore probe (TIP) system 2 after gearbox replacement on October 30, 2024
(4) Division 2 core spray system after pump discharge relief valve replacement on November 20, 2024
(5) Rerouting of wiring for the EDG 12 fast start relay for divisional separation on November 27, 2024

Inservice Testing (IST) (IP Section 03.01) (1 Sample)

(1) Reactor core isolation cooling (RCIC) condensate pump discharge valve to contaminated rad waste (CV2848) red open light slow to illuminate on November 12, 2024

Containment Isolation Valve (CIV) Testing (IP Section 03.01) (1 Sample)

(1) Core spray 12 test return to torus (MO1750) valve manipulation on November 18, 2024

71114.04 - Emergency Action Level and Emergency Plan Changes

Inspection Review (IP Section 02.0102.03) (1 Sample)

(1) The inspectors evaluated the following submitted Emergency Action Level and Emergency Plan changes.
  • QF0724, 10CFR 50.54(q) Review Screening Form, 2024786
  • QF0724, 10CFR 50.54(q) Review Screening Form, FT2023 780
  • QF0724, 10CFR 50.54(q) Review Screening Form, MT2023 778
  • QF0724, 10CFR 50.54(q) Review Screening Form, MT2023 779
  • QF0724, 10CFR 50.54(q) Review Screening Form, MT2023 781
  • QF0724, 10CFR 50.54(q) Review Screening Form, MT2024 782
  • QF0724, 10CFR 50.54(q) Review Screening Form, MT2024 783
  • MONTICELLO NUCLEAR GENERATING PLANT AND PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 - ISSUANCE OF AMENDMENTS RE: STANDARD EMERGENCY PLAN AND CONSOLIDATED EMERGENCY OPERATIONS FACILITY (EPID L2021LLA0210), March 31, 2023 This evaluation does not constitute NRC approval.

71114.06 - Drill Evaluation

Additional Drill and/or Training Evolution (1 Sample)

The inspectors evaluated:

(1) Licensed operator requalification including emergency classification on October 31,

OTHER ACTIVITIES

BASELINE

===71151 - Performance Indicator Verification The inspectors verified licensee performance indicators submittals listed below:

MS09: Residual Heat Removal Systems (IP Section 02.08)===

(1) October 1, 2023, through September 30, 2024

MS10: Cooling Water Support Systems (IP Section 02.09) (1 Sample)

(1) October 1, 2023, through September 30, 2024

71152A - Annual Follow-up Problem Identification and Resolution Annual Follow-up of Selected Issues (Section 03.03)

The inspectors reviewed the licensees implementation of its corrective action program related to the following issues:

(1) Environmental qualification issues associated with the required activation energy of Automatic Switch Co. (ASCO) solenoid valves

71152S - Semiannual Trend Problem Identification and Resolution Semiannual Trend Review (Section 03.02)

(1) The inspectors reviewed the licensees corrective action program to identify potential trends in motor operated valves (MOVs) failure to operate in manual that might be indicative of degradation in the MOVs ability to perform safety-related functions.

INSPECTION RESULTS

Observation: Licensee Corrective Actions Associated with Environmental QualificationASCO Activation Energy Issue 71152A On July 12, 2024, the licensee identified that a 2004 communication revised the activation energy of ASCO solenoid valves from 1.37eV to 1.0eV. This had no environmental qualification (EQ) effect on a majority of EQ solenoid valves because other, more limiting characteristics, were used in determining solenoid valve replacement frequency. However, two solenoid valves associated with the reactor building to suppression chamber vacuum breakers were determined to be overdue for replacement because of the change. The licensee performed prompt and past operability determinations and found the affected solenoid valves were and had been operable. They replaced and lowered the replacement intervals for the affected solenoid valves and updated the appropriate EQ files. Corrective actions were completed by August 26,

EXIT MEETINGS AND DEBRIEFS

The inspectors verified no proprietary information was retained or documented in this report.

  • On January 23, 2025, the inspectors presented the integrated inspection results to S. Hafen, Site Vice President, and other members of the licensee staff.
  • On December 20, 2024, the inspectors presented the emergency action level and emergency plan changes inspection results to G. Medina, Emergency Preparedness Manager, and other members of the licensee staff.

DOCUMENTS REVIEWED

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

Corrective Action

Documents

501000091798

L5313 Outlets in SHC House Do Not Work

10/31/2024

1151

Winter Checklist

104

71111.01

Procedures

FPWMSR01

Seasonal Readiness Program

NH352431

(M117)

P&ID Recirc Loops Pumps and Motors Nuclear Boiler

System

NH362421

(M1161)

P&ID Jet Pump Instrumentation Nuclear Boiler System

NH36243

(M117)

P&ID Recirculation Loops Nuclear Boiler System

NH36251

(M125)

P&ID RCIC (Steam Side)

NH36252

(M126)

P&ID RCIC (Water Side)

NH548174

P&ID Off-Gas Modification Train A Engineering Flow

Diagram Recombiner Building

NH548181

P&ID Off-Gas Modification Train B Engineering Flow

Diagram Recombiner Building

Drawings

NH548222

P&ID Off-Gas Modification Engineering Flow Diagram

Off-Gas Storage Area

B.01.0405

Reactor Recirculation System

B.02.0305

Reactor Core Isolation Cooling

B.07.02.0105

Recombiner System

71111.04

Procedures

B.07.02.0205

Off-Gas Holdup System

Strategy A.302-G

Fire Zone 2G East Shutdown Cooling Area

Strategy A.302-H

Fire Zone 2H West Shutdown Cooling Area

Strategy A.307-A

Fire Zone 7A 125V Division I Battery Room

71111.05

Fire Plans

Strategy A.307-B

Fire Zone 7B 250V Division I Battery Room

501000086301

Annual Exterior Flood Surveillance Discrepancies

06/04/2024

Corrective Action

Documents

501000088635

Flood Protection Feature Found Unsealed

08/07/2024

71111.06

Procedures

1478

External Flood Monthly and Annual Surveillance

06/04/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

1478

External Flood Monthly and Annual Surveillance

10/01/2024

147801

External Flood Five-Year Surveillance

09/17/2024

71111.07A

Procedures

140401

EDG ESW Heat Exchanger Performance Test

Miscellaneous

SEG RRSS185

Simulator Exercise Guide (Crew 5)

71111.11Q

Procedures

0051

Main Steam Line High Flow Group 1 Instrument Test

501000052447

Recirc Pump Speed Indicator is Reading Lower

Than Historical Values

05/22/2021

501000052595

Recirc MG Set Tachometer Coupling is Shifting Axially

by About 1/2 Inch

05/26/2021

501000052651

Trend - Recirc MG Set Equip Issues

05/28/2021

501000088944

ECR to correct RHRSW13 Not Progressing

08/16/2024

501000093375

REC MG Set Oil Leaks

2/16/2024

Corrective Action

Documents

501000093391

VF4 Gaps Between Filter and Support

2/16/2024

Drawings

NH36664

(M112)

PI&D RHR Service Water and Emergency Service Water

Systems

29

CRVEFT Low Flow Test

Procedures

FPE-SE05

Strategic Engineering Walkdowns

7001318550010

Rx Recirculation System (Perform Aging Management

Walkdown)

2/16/2024

700140005010

Replace FIC9116A Manual/Auto Controller

10/08/2024

71111.12

Work Orders

7001451190010

RHRSW13, Install Drain Line

11/19/2024

501000091102

P111A 11 ESW Degraded Flow

10/13/2024

501000091457

Spike in Unidentified Drywell Leakage

10/22/2024

501000091512

Change in DW Leak Rate at ACMP Limit

10/22/2024

Corrective Action

Documents

501000091551

MO2023 Packing Lessons Deep-Dive

10/24/2024

7001401230010

HPCI Steam Line Isolation Inboard Valve (MO2034,

Backseat)

10/24/2024

71111.13

Work Orders

700145330020

P111A, Replace Pump

10/16/2024

501000090899

CV1478 Trend Time Longer Than Expected

10/09/2024

501000092267

CV - 2848 Red Light Indication Delayed

11/13/2024

501000092314

Safe Shutdown Cable Route Question

11/13/2024

Corrective Action

Documents

501000092922

Intakes Issues & Entry into A.6

2/02/2024

71111.15

Drawings

NE364033A

Standby Diesel Generator Start Circuits

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

NF46111

Connection Diagram 4160V Switchgear A7, A8, A511, A610

& C565

NH 3604912

P&ID Instrument Air Reactor Building & Drywell

NX92165

Physical Schematic & Field Connections Model 999 EDG 12

25508-IA1

RCIC Quarterly Pump and Valve Tests

Procedures

25517-IA1

Instrument Air Valve Exercise

Corrective Action

Documents

501000091630

RWCU [Reactor Water Cleanup] Trip During

23 Procedure

10/25/2024

71111.18

Procedures

23

RWCU High Flow and Room Temperature Trip

Unit Instrument Test and Calibration

501000060614

Housing gasket leak TIP 1 Drive Gear Box

2/17/2022

501000091749

TIP 2 Slow Drive Speed is too Fast

10/30/2024

501000092267

CV2848 Red Light Indication Delayed

11/13/2024

Corrective Action

Documents

501000092314

Safe Shutdown Cable Route Question

11/13/2024

3789

Relief Valve Test Data Sheet

Miscellaneous

ISTBasis

Pump and Valve InService Testing Program

Basis -CV2848

25508-IA1

RCIC Quarterly Pump and Valve Tests

278B

ATWSRecirc Trip for Reactor Pressure and Level Trip

4777

ATWS Panel Shutdown

B.03.0105

Core Spray Cooling System

Procedures

B.05.0305

Automated Traversing InCore Probe

7000667940020

Core Spray Test Line Return to Torus

11/18/2024

700091442

Core Spray Pump Discharge Relief Valve

11/19/2024

7001035470070

TIP 2 Detector/Drive Cable (PMT/RTS)

10/30/2024

7001433730025

ATWS RCP Trip Reactor Level

10/03/2024

700145331040

ESW Pump PMT/RTS

10/17/2024

71111.24

Work Orders

7001471440010

G3B, Reroute Cable ECR 601X5374 (12 EDG)

QF0724

10CFR 50.54(q) Review Screening Form

MT2023

779

QF0724

10CFR 50.54(q) Review Screening Form

MT2023

2

71114.04

Calculations

QF0724

10CFR 50.54(q) Review Screening Form

MT2023

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

783

QF0724

10CFR 50.54(q) Review Screening Form

24786

QF0724

10CFR 50.54(q) Review Screening Form

FT2023 780

QF0724

10CFR 50.54(q) Review Screening Form1

MT2023

778

QF0724

10CFR 50.54(q) Review Screening Form

MT2023

781

Miscellaneous

ML22357A100

MONTICELLO NUCLEAR GENERATING PLANT AND

PRAIRIE ISLAND NUCLEAR GENERATING PLANT,

UNITS 1 AND 2 - ISSUANCE OF AMENDMENTS RE:

STANDARD EMERGENCY PLAN AND CONSOLIDATED

EMERGENCY OPERATIONS FACILITY (EPID

L2021LLA0210)

03/31/2023

Procedures

EPLAN02

Monticello Emergency Plan Annex

Rev 0

71114.06

Miscellaneous

SEG# RQSS184

Simulator Exercise Guide (Crew 5) - EAL Classification

Miscellaneous

QF0445

NRC and MOR Data Collection and Submittal Forms

71151

Procedures

FPRPI01

Preparation of NRC Performance Indicators

501000087690

EQASCO Activation Energy Issue

07/12/2024

Corrective Action

Documents

501000087690

EQASCO Activation Energy Issue-Closure

09/16/2024

501000087690

Past operability Review

08/22/2024

71152A

Engineering

Evaluations

501000087690

Prompt Operability Determination

07/17/2024

501000087225

MO2012 Failed to Cycle as Expected

06/28/2024

501000087255

MO2012 Failed to Cycle as Expected Root Cause

10/11/2024

501000087269

LPCI Vulnerability

06/29/2024

501000087273

Broken Spring Found in Actuator

06/29/2024

501000087285

MO2012 AsLeft Diagnostic Anomalies

06/29/2024

501000087286

Post Job Critique MO2012 Event Response

06/29/2024

501000087791

LPCI Valve Extent of Condition

07/16/2024

501000088600

MO2012 Motor Pinion May Not be Secured

08/05/2024

501000088639

MO2012 LST Discrepancy

08/07/2024

501000088681

MO2012 Set Screw

08/08/2024

501000088690

WO 700141731 MO2012 Issue

08/07/2024

71152S

Corrective Action

Documents

501000089575

Unclear LST Requirement for MO2012

09/04/2024

Inspection

Procedure

Type

Designation

Description or Title

Revision or

Date

501000090123

RCE Revision Not Tracked in CAP

09/22/2024

7000899300080

PMT RHR MO2012

06/29/2024

Corrective Action

Documents

Resulting from

Inspection

501000076674

FLEX Applicability Question on MO2012

07/01/2024

Miscellaneous

LER2024002-00

Low Pressure Coolant Injection Inoperable Due to Motor

Valve Failure

06/28/2024