Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000263/2025002
ML25010A072
Person / Time
Site: Monticello Xcel Energy icon.png
Issue date: 01/10/2025
From: Rosario E
NRC/RGN-III/DORS/EB1
To: Hafen S
Northern States Power Company, Minnesota
References
IR 2025002
Download: ML25010A072 (1)


See also: IR 05000263/2025002

Text

Shawn Hafen

Site Vice President

Monticello Nuclear Generating Plant

Northern States Power Company, Minnesota

2807 West County Road 75

Monticello, MN 55362-9637

SUBJECT:

MONTICELLO NUCLEAR GENERATING PLANT - NOTIFICATION OF NRC

BASELINE INSPECTION AND REQUEST FOR INFORMATION: INSPECTION

REPORT 05000263/2025002

Dear Shawn Hafen:

On April 21, 2025, the U.S. Nuclear Regulatory Commission (NRC) will begin the Baseline

Inservice Inspection Procedure 71111.08. This onsite inspection is scheduled to be performed

April 21, 2025, through May 2, 2025.

Experience has shown that this inspection is resource intensive both for the NRC inspector and

your staff. To minimize the impact to your onsite resources and to ensure a productive

inspection for both sides, we have enclosed a request for documents needed for this inspection.

These documents have been divided into two groups.

The first group identifies information necessary to ensure that the inspector is adequately

prepared. The second group identifies the information the inspector will need upon arrival at the

site. It is important that all these documents are up-to-date, and complete, to minimize the

number of additional documents requested during the preparation and/or the onsite portions of

the inspection.

We have discussed the schedule for inspection activities with your staff and understand that our

regulatory contact for this inspection will be Carol Seipp of your organization. If there are any

questions about this inspection or the material requested, please contact the lead inspector

Eucherius Rosario at (630) 829-9577, or via email at Eucherius.Rosario@nrc.gov.

This letter does not contain new or amended information collection requirements subject to the

Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection

requirements were approved by the Office of Management and Budget, Control

Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to

respond to, a request for information or an information collection requirement unless the

requesting document displays a currently valid Office of Management and Budget Control

Number.

January 10, 2025

S. Hafen

2

This letter and its enclosure will be made available for public inspection and copying at

http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in

accordance with Title 10 of the Code of Federal Regulations, Part 2.390, Public Inspections,

Exemptions, Requests for Withholding.

Sincerely,

Eucherius Rosario, Reactor Inspector

Engineering Branch 1

Division of Operating Reactor Safety

Docket No. 05000263

License No. DPR-22

Enclosure:

Document Request for Inservice Inspection

cc: Distribution via LISTSERV

Signed by Rosario, Eucherius

on 01/10/25

S. Hafen

3

Letter to Shawn Hafen from Eucherius Rosario dated January 10, 2025.

SUBJECT:

MONTICELLO NUCLEAR GENERATING PLANT - NOTIFICATION OF NRC

BASELINE INSPECTION AND REQUEST FOR INFORMATION: INSPECTION

REPORT 05000263/2025002

DISTRIBUTION:

Alejandro Alen Arias

RidsNrrDorlLpl3

RidsNrrPMMonticello

RidsNrrDroIrib Resource

Jack Giessner

Mohammed Shuaibi

Diana Betancourt-Roldan

Harral Logaras

David Curtis

Jared Heck

R3-DORS

ADAMS Accession Number: ML25010A072

Publicly Available

Non-Publicly Available

Sensitive

Non-Sensitive

OFFICE

RIII

NAME

ERosario

DATE

01/10/2025

OFFICIAL RECORD COPY

DOCUMENT REQUEST FOR INSERVICE INSPECTION

Enclosure

Inspection Report: 05000263/2025002

Inspection Dates:

April 21, 2025 - May 2, 2025

Inspection Procedures:

Inspection Procedure 71111-08, Inservice Inspection

Lead Inspector:

Eucherius Rosario, DORS/EB1

(630) 829-9577

Eucherius.Rosario@nrc.gov

A.

Information for the In-Office Preparation Week

The following information (electronic copy) is requested by April 7, 2025, to facilitate the

selection of specific items that will be reviewed during the onsite inspection week. The

inspector will select specific items from the information requested below and request a

list of additional documents needed onsite to your staff. We request that the specific

items selected from the lists be available and ready for review on the first day of

inspection. The following information is applicable to the outage Unit unless otherwise

indicated. If you have any questions regarding this information, please call the inspector

as soon as possible.

For the upcoming outage, a detailed schedule (including dates, if possible) and

description of:

a.

List of all Non-Destructive Examinations (NDEs) planned to be performed as part

of your American Society of Mechanical Engineers (ASME) Code Inservice

Inspection (ISI) Program (include edition and addenda of Code committed to),

and NDEs planned for other systems performed as part of a Risk-Informed ISI

Program, or other augmented inspection programs (e.g., ASME Code Case

N-770 examination of dissimilar metal welds and examinations to meet an

industry initiative). Description shall include component ASME Code Class,

component IDs, categorization (Section XI, Risk-Informed, or Augmented, etc.),

and dates/times the NDEs are scheduled to be performed.

b.

List of Welding on Code Class 1, 2, or 3 components to be performed during the

outage.

c.

List identifying NDE reports (Volumetric, Surface, and Visual), which have

identified relevant indications on ASME Code Class 1 and 2 Systems since the

beginning of the last refueling outage. For indications that were accepted as-is for

continued service, provide schedule of successive exams required by Code.

d.

List of repair/replacement welds in ASME Code Class 1, 2 and 3 Systems, which

have been fabricated since the beginning of the last refueling outage.

DOCUMENT REQUEST FOR INSERVICE INSPECTION

2

e.

List of Title 10 CFR Part 21 reports applicable to your structures, systems, or

components within the scope of ASME Code Section XI that have been identified

since the beginning of the last refueling outage.

f.

Copy of latest revision to the Inservice Inspection Program Plan.

g.

List of corrective action documents related to ISI such as piping degradation or

damage, or errors identified during piping examinations since the beginning of

the last refueling outage

h.

Point of contact information (names and site numbers) for ISI/NDE/Welding.

B.

Onsite Information to be provided to the inspector on the first onsite date.

The following information is requested for only specific items that are

selected by the inspector from list A above:

a) A copy of ASME Section XI, Code Relief Requests applicable to the selected

items.

b) Copies of applicable NDE procedures, weld procedure specifications (WPS),

NDE procedure qualification records, WPS qualification records, NDE personnel

performance qualification records, welder performance qualification records, and

associated screenings/evaluations, ISI-related corrective action documents.

c)

Copy of the ASME Section XI, Code of record for the selected items.

d) Copy of the applicable Code of Construction for repair/replacement activities on

selected items.