IR 05000255/2009008

From kanterella
Jump to navigation Jump to search
IR 05000255-09-008, on 10/01/2009 - 11/09/2009, Palisades Nuclear Plant; Problem Identification and Resolution
ML093431098
Person / Time
Site: Palisades  Entergy icon.png
Issue date: 12/09/2009
From: Stephanie West
Division Reactor Projects III
To: Schwarz C
Entergy Nuclear Operations
References
EA-09-269 IR-09-008
Download: ML093431098 (23)


Text

UNITED STATES ber 9, 2009

SUBJECT:

PALISADES NUCLEAR PLANT NRC INSPECTION REPORT 05000255/2009008; PRELIMINARY WHITE FINDING

Dear Mr. Schwarz:

On November 9, 2009, the U.S. Nuclear Regulatory Commission (NRC) completed an inspection at your Palisades Nuclear Plant. The enclosed report documents the inspection findings, which were discussed on November 9, 2009, with you and other members of your staff.

The inspection examined activities conducted under your license as they relate to safety and compliance with the Commissions rules and regulations and with the conditions of your license.

The inspectors reviewed selected procedures and records, observed activities, and interviewed personnel.

This report documents one NRC-identified finding that appears to have low to moderate safety significance (White). This finding was determined to involve a violation of NRC requirements.

As documented in Section 4OA2 of this report, the Spent Fuel Pool (SFP) neutron absorber degraded to the extent that the SFP no longer met the requirements of the Design Feature for fuel storage in Technical Specification 4.3.

This finding was assessed based on the best available information, using the Significance Determination Process (SDP). Preliminarily, we consider this a NRC-identified finding having low to moderate safety significance based on a qualitative review using Inspection Manual Chapter (IMC) 0609 Appendix M. The degradation of the fixed neutron absorber resulted in a significant loss of one of the two barriers preventing criticality in the SFP. Although the condition did not lead to a criticality, the condition did present an immediate safety concern, and your staff implemented compensatory measures to ensure that the SFP remained subcritical.

The NRC acknowledged the compensatory measures in Confirmatory Action Letter (CAL)

RIII-08-003 in September of 2008. In February 2009, the NRC approved, and you implemented, a licensee amendment that resulted in restoration of the SFP to compliance with the Design Feature in Technical Specification 4.3. The NRC closed the CAL on February 20, 2009. This finding is also an apparent violation of NRC requirements and is being considered for escalated enforcement action in accordance with the NRC Enforcement Policy. The current Enforcement Policy can be found on the NRCs Web site at http://www.nrc.gov/reading-rm/doc-collections/enforcement.

In accordance with IMC 0609, we intend to complete our evaluation using the best available information and issue our final determination of safety significance within 90 days of this letter.

The SDP encourages an open dialogue between the staff and the licensee; however, the dialogue should not impact the timeliness of the staffs final determination. Before the NRC makes its enforcement decision, we are providing you an opportunity to either: (1) present to the NRC your perspectives on the facts and assumptions used by the NRC to arrive at the finding and its significance at a Regulatory Conference, or (2) submit your position on the finding to the NRC in writing. If you request a Regulatory Conference, it should be held within 30 days of the receipt of this letter and we encourage you to submit supporting documentation at least 1 week prior to the conference in an effort to make the conference more efficient and effective. If a conference is held, it will be open for public observation. The NRC will also issue a press release to announce the conference. If you decide to submit only a written response, such a submittal should be sent to the NRC within 30 days of the receipt of this letter. If you decline to request a Regulatory Conference or to submit a written response, you relinquish your right to appeal the final SDP determination; in that, by not doing either you fail to meet the appeal requirements stated in the Prerequisite and Limitation Sections of Attachment 2 of IMC 0609.

Please contact John Giessner at (630) 829-9619 within 10 days of the date of this letter to notify the NRC of your intended response. If we have not heard from you within 10 days, we will continue with our significance determination and enforcement decision. You will be advised by a separate correspondence of the results of our deliberations on this matter.

Since the NRC has not made a final determination in this matter, no Notice of Violation is being issued for this inspection finding at this time. Please be advised that the number and characterization of the apparent violation described in the enclosed inspection report may change as a result of further NRC review.

If you decide to provide a written response in lieu of the Regulatory Conference, the submission should be sent to the U.S. Nuclear Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, with copies to the Regional Administrator, U.S. Nuclear Regulatory Commission - Region III, 2443 Warrenville Road, Suite 210, Lisle, IL 60532-4352; the Director, Office of Enforcement, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; and the Resident Inspector Office at the Palisades Nuclear Power Plant. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Steven West, Director Division of Reactor Projects Docket Nos. 50-255;72-007 License Nos. DPR-20

Enclosure:

Inspection Report 05000255/2009008; w/Attachment: Supplemental Information

REGION III==

Docket Nos: 50-255 License Nos: DPR-20 Report No: 05000255/2009008 Licensee: Entergy Nuclear Operations, Inc.

Facility: Palisades Nuclear Plant Location: Covert, MI Dates: October 1, 2009, through November 9, 2009 Inspectors: J. Ellegood, Senior Resident Inspector T. Taylor, Resident Inspector L. Kozak, Senior Reactor Analyst Approved by: J. Giessner, Chief Branch 4 Division of Reactor Projects Enclosure

TABLE OF CONTENTS 4. OTHER ACTIVITIES................................................................................................................2 4OA2 Identification and Resolution of Problems ...................................................2 4OA6 Management Meetings ................................................................................7 SUPPLEMENTAL INFORMATION ...............................................................................................1 Key Points of Contact ................................................................................................................1 List of Items Opened, Closed and Discussed............................................................................1 List of Documents Reviewed .....................................................................................................2 List of Acronyms Used ..............................................................................................................3 Enclosure

SUMMARY OF FINDINGS

IR 05000255/2009008; 10/01/2009 - 11/09/2009; Palisades Nuclear Plant; Problem

Identification and Resolution This report covers an inspection by the resident inspectors of degradation of the fixed neutron absorber in the Spent Fuel Pool (SFP). The inspectors identified one apparent violation (AV) with a preliminary significance of

White.

The significance of most findings is indicated by their color (Green, White, Yellow, Red) using Inspection Manual Chapter (IMC) 0609, Significance Determination Process (SDP). Cross-cutting aspects were determined using IMC 0305, "Operating Reactor Assessment Program." Findings for which the SDP does not apply may be Green or be assigned a severity level after NRC management review. The NRCs program for overseeing the safe operation of commercial nuclear power reactors is described in NUREG-1649, Reactor Oversight Process, Revision 4, dated December 2006.

NRC-Identified

and Self-Revealed Findings

Cornerstone: Initiating Events

Preliminary

White.

The inspectors identified a finding and associated violation of the Design Feature for fuel storage in Technical Specification 4.3.1 due to loss of neutron absorption capability in the spent fuel pool (SFP) racks. Over the life of the facility, the neutron absorber in the SFP had degraded such that the Region I of the SFP could no longer maintain an effective neutron multiplication factor (Keff) of less than .95 without credit for soluble boron. Specifically, the licensee did not evaluate the effects of spent fuel pool rack swelling or available operating experience to validate the neutron absorber in the SFP continued to meet the assumptions in the criticality analysis. After testing revealed that the SFP no longer met assumptions in the criticality analysis, the licensee implemented compensatory actions to ensure the SFP remained subcritical.

The inspectors concluded the finding was more than minor because, if left uncorrected, it would become a more significant safety concern; in addition, the finding impacted the initiating event cornerstone objective of limiting events that challenge safety functions; for example, preventing criticality in an area not designed for criticality. Because probabilistic risk assessment tools were not suited for this finding, the inspectors evaluated the finding using IMC 0609, Appendix M, Significance Determination Process Using Qualitative Criteria. Based on the degradation that resulted in a significant loss of margin to criticality, NRC management concluded the finding was preliminarily of low to moderate safety significance (White). The inspectors determined that the performance deficiency did not reflect current licensee performance due to its age; therefore, the finding does not include a cross-cutting aspect. (4OA2)

Licensee-Identified Violations

No violations of significance were identified.

REPORT DETAILS

OTHER ACTIVITIES

4OA2 Identification and Resolution of Problems

.1 Selected Issues for Follow-Up: Degradation of Fixed Neutron Absorber in the Spent Fuel

Pool (SFP)

a. Inspection Scope

The inspectors reviewed data related to the degradation of the SFP fixed neutron absorber. Since the issue has been the subject of prior NRC inspection activities, this inspection focused on reviewing the analysis by the licensee to determine SFP Keff and determine any performance deficiencies related to the degradation of the SFP. Based on the inspection, the inspectors concluded that the licensee had opportunities to identify the degradation through both evaluations of Operating Experience and analysis of swelling of the rack in the SFP.

b. Findings

Introduction:

The inspectors identified a finding and associated violation of the Design Feature for fuel storage in Technical Specification 4.3.1 due to loss of neutron absorption capability in the SFP racks. Over the life of the facility, the neutron absorber in the SFP had degraded such that Region I of the SFP could no longer maintain a Keff of less than

.95 without credit for soluble boron.

Description:

In September, 2007, while making fuel moves in the SFP in preparation for a refueling outage, the licensee initiated a condition report documenting that a bundle in the spent fuel pool could not be removed from its current storage location. This was the second bundle the licensee had identified as stuck during the preparations for the outage. The Palisades resident inspectors read the condition report during a routine review of condition reports and questioned the licensee on conditions in the SFP. The licensee informed the inspectors that the fuel became stuck due to swelling of the fuel rack. The licensee also informed the inspectors that there were multiple bundles stuck in their current storage location and the licensee did not consider the condition to adversely affect safety. The licensee assigned the condition report a significance level of C, which would not receive a cause determination. In October of 2007, after the inspectors engaged licensee management regarding the potential safety implications, the licensee upgraded the condition report to a B level. The licensee decided that the condition would be the subject of a lower tier apparent cause evaluation - the lowest level of cause evaluation in the licensees corrective action process. The inspectors performed a Problem Identification and Resolution inspection sample on the condition in the fourth quarter of 2007, but insufficient data existed to determine if there was any performance deficiency associated with the SFP racks.

Palisades has one spent fuel pool with two different rack designs forming two regions with different criticality controls for each region. Each region has different rack designs and requirements for soluble boron. Region I racks were manufactured by the Nuclear Utility Services (NUS) Corporation and include boron carbide (B4C) plates manufactured by the Carborundum Corporation. The B4C acts as a neutron absorber and the licensee assumed no change in the neutron absorption characteristics over the life of the SFP.

For this region, the Palisades design feature Technical Specifications (TS) required Keff to be less than 0.95 if fully flooded with unborated water. At the time of discovery, there were no limiting conditions for operations associated with Region I. In Region II, the design feature TS credit 850 ppm soluble boron to maintain Keff less than 0.95. In addition, Keff must remain below 1.00 if Region II is flooded with unborated water.

Limiting Conditions for Operations for Region II address boron concentration and the types of spent fuel that can be stored in the region. The controls for both of the regions meet the requirements of 10 CFR 50.68, Criticality Accident Requirements. Although the Region II racks contain Boraflex as a neutron absorber, the criticality analysis does not credit the Boraflex.

In 1988, the licensee first identified that some rack locations were swelling when they were unable to load a fuel bundle into a storage location. The licensee first identified a stuck bundle in 1991 and there are now 11 fuel bundles that are stuck in their current location and 3 more locations that have swollen walls. However, in 1994, the licensee and NUS evaluated the condition and concluded gas generated from irradiation caused the swelling. This conclusion has not been confirmed; therefore, there may be another cause of the rack swelling. The licensee could not show that the effects of the swelling on neutron absorber degradation had ever been evaluated nor that the effects of gas pockets on the criticality analysis had been considered. Until July of 2008, the licensee had not performed testing on the SFP neutron absorption capability. In response to the inspectors concerns, the licensee accelerated testing committed for license extension to determine the neutron absorption capability of the SFP racks. In July of 2008, the testing revealed that the neutron absorber in the SFP racks had deteriorated and the SFP no longer met the TS requirements for Keff in Region I of the SFP. The licensee performed a criticality assessment of the pool and concluded that with 50 percent depletion of the neutron absorber, the pool remained with a Keff of less than 1.00 and with a Keff of less than 0.95 with 150 ppm boron. The licensee committed to additional controls to ensure the SFP remained sub-critical. On September 19, 2008, the NRC issued confirmatory action letter (CAL) RIII-08-003 to Palisades to confirm these commitments. On February 6, 2009, the NRC approved a license amendment for the SFP and the licensee established compliance with the TS. The CAL was closed on February 20, 2009.

On September 15, 2008, the licensee issued Licensee Event Report (LER)08-004 which informed the NRC that the licensee did not comply with their TS requirements for Region I of the SFP. The inspectors reviewed the LER in inspection report 2008-004, but did not close the LER because the licensee did not have enough information for the NRC to determine the cause and safety significance of the condition. The NRC discussed the need for additional information with the licensee and the licensee informed the inspectors of their plans for additional testing of the SFP, as well as plans to evaluate the criticality conditions in the pool prior to adoption of additional controls.

As part of licensee actions to better understand the degradation of the neutron absorber in the SFP, the licensee conducted additional testing of the SFP neutron absorber in December 2008. This testing confirmed the degradation and provided enough information for the licensee to quantify the degradation for the sample of neutron absorber panels that were tested. Approximately 2 percent of all the panels were tested.

Testing could not be completed on panels where irradiated fuel was stuck. The testing showed significant degradation of up to 70 percent loss of boron (by mass) of the absorber in some of the panels.

In the spring of 2009, the licensee performed a criticality assessment of the historical pool conditions that incorporated the results from the testing and provided the evaluation to the inspectors in June of 2009. The calculation performed by the licensee evaluated the infinite neutron multiplication factor ( Kinf). Kinf assumes an infinite array of fissile material and yields a conservative value. Since the licensee did not test all the panels, the assessment used statistical methods to determine the worst case boron depletion.

The licensee concluded that the SFP did not meet the requirements of the design features, but the pool would remain slightly subcritical for the most reactive fuel stored in the SFP without credit for soluble boron. Criticality experts from the office of Nuclear Reactor Regulation performed an independent evaluation of the licensee conclusions on the extent of the Carborundum neutron absorber degradation and identified the following concerns with the licensees analysis:

1) The licensee assumed a Carborundum boron 10 isotope (B-10) areal density reduction of 85 percent, a value 0.0135 gm/cm2. This was approximately 50 percent below the areal density measured during the licensees limited testing.

a) Although testing of a limited number of panels did not identify any Carborundum with a B-10 areal density less than 0.0135 gm/cm2, the NRC could not conclude that other panels in the pool did not have a lower areal density, especially since no testing could be completed where irradiated fuel was stuck. Since the degradation mechanism is not known, the NRC did not believe that the licensee could bound areal B-10 density at 0.0135 gm/cm2.

b) The NRC did not agree that representing the decrease in B-10 areal density from the original 0.09166 gm/cm2 as material thinning was supported.

c) The licensee replaced the lost Carborundum with SFP water. The potential for the lost Carborundum to be filled with inert material was not addressed.

2) Localized boron dilution events were not considered or discussed.

3) The effect of the swelling on the criticality analysis was not addressed. The submittal in November 2008 indicated the maximum swelling was worth approximately 0.05 delta () Keff. If even 10 percent of this maximum is present, the licensees conclusion was potentially invalid.

4) The licensee mixed analysis codes CASMO 3 and MONK results. The licensee determined the reactivity worth of the degraded Carborundum with CASMO 3 and added that value to a total reactivity calculated from MONK. The NRC could not conclude that CASMO 3 and MONK would come up with the same Kinf, which might invalidate the licensees conclusion.

5) The licensee made an implicit assumption that all of the biases, uncertainties, and limiting conditions have not changed even though there was a significant reduction in the B-10 areal density and swelling in the cell walls.

In the licensees evaluation, with no credit for soluble Boron and 85 percent degradation of the Carborundum, the calculated Kinf was 0.995016. Because of these questions regarding the licensees criticality analysis, the NRC concluded that the analysis did not provide a reasonable bound on Keff for the SFP and, therefore, did not demonstrate that Keff would be less than 1.0 without credit for soluble Boron.

Analysis:

In accordance with NRC IMC 0612, Appendix B, Issue Screening, the inspectors determined that the licensees failure to maintain Keff less than 0.95 in Region I without credit for soluble Boron was a performance deficiency warranting a significance determination. The inspectors determined the finding was within the licensees ability to foresee and correct since the licensee had access to operating experience indicating degradation of Carborundum racks at other facilities. In addition, the licensee took ineffective action for fuel binding in the spent fuel pool. The inspectors determined that the finding did not have an actual safety consequence, did not impact the NRCs ability to perform a regulatory function and did not include any willful aspects.

Therefore, the inspectors concluded that the finding did not require use of traditional enforcement. The inspectors concluded the finding was more than minor for the following reasons:

1) If left uncorrected, the racks would continue to degrade. The degradation would further reduce the neutron absorption capability and become a more significant safety concern.

2) The finding is associated with the increase in the likelihood of an initiating event; that is, a criticality SDP Phase 1 does not address SFP criticality issues. Although the barrier cornerstone has questions related to SFP cooling and handling, it does not address criticality. Since probabilistic risk assessment tools and existing SDP guidance did not address SFP criticality issues, the inspectors reviewed the issue using Appendix M of IMC 0609. The completed Appendix M is attached.

While evaluating the significance of the condition, the inspectors concluded an inadvertent criticality would result in a Red or Severity Level I finding. The inspectors based this conclusion on multiple supplements in the Enforcement Policy identifying an inadvertent criticality as a Severity Level I finding and the inclusion of preventing a criticality as a strategic objective. The inspectors qualitatively considered the amount of remaining margin to an inadvertent criticality while preparing Appendix M. In this case, of the two required criticality controls (soluble boron and rack geometry/design), one criticality control (namely, the rack design with neutron absorber capability), was significantly degraded. It could not be determined if other, untested racks locations, could be more degraded.

Although one of the factors contributing to the finding was related to use of operating experience, the inspectors concluded that the opportunities were not recent enough to be reflective of current performance. Therefore, the finding does not include a cross-cutting aspect.

Old Design Issue Review During review of the safety significance, the inspectors evaluated the finding for treatment as an old design issue. The performance deficiency did not meet the criteria for an old design issue. NRC IMC 0305, Operating Reactor Assessment Program, Section 04.11 defines an old design issue as an inspection finding involving a past design-related problem in the engineering calculations or analyses, the associated operating procedure, or installation of plant equipment that does not reflect a performance deficiency associated with existing licensee programs, policy, or procedures. As discussed in Section 12.01 of IMC 0305, some old design issues may not be considered in the assessment program. Section 12.01(a) provides guidance for the treatment of old design issues, and states that the NRC may refrain from considering safety significant inspection findings in the assessment program for a design-related finding in the engineering calculations or analysis, associated operating procedure, or installation of plant equipment if all of the following criteria are true:

1. It was licensee-identified as a result of a voluntary initiative such as a design

basis reconstitution. For the purposes of IMC 0305, self-revealing issues are not considered to be licensee-identified. Self-revealing issues are those deficiencies which reveal themselves to either the NRC or licensee through a change in process, capability or functionality of equipment, or operations or programs.

False. The issue was identified by the NRC resident inspectors during review of condition reports that documented a stuck fuel bundle during fuel movement in the SFP. The fuel movement occurred as part of outage preparations and not as part of an effort to identify issues with the SFP. Although the licensee was aware of fuel bundles sticking, they had not assessed the condition or determined if the Carborundum was losing absorption capability.

2. It was or will be corrected, including immediate corrective action and long term

comprehensive corrective action to prevent recurrence, within a reasonable time following identification (this action should involve expanding the initiative, as necessary, to identify other failures caused by similar root causes). For the purpose of this criterion, identification is defined as the time from when the significance of the finding is first discussed between the NRC and the licensee.

Accordingly, issues being cited by the NRC for inadequate or untimely corrective action are not eligible for treatment as an old design issue.

True. The issue was corrected through submittal and implementation of a license amendment. It should be noted; however, this took considerable NRC involvement and issuance of a CAL. The license revision did not occur until 18 months after the inspectors initially raised concerns with the SFP racks.

3. It was not likely to be previously identified by recent ongoing licensee efforts such

as normal surveillance, quality assurance activities, or evaluation of industry information.

False. There were multiple opportunities for the licensee to identify the issue as more fuel bundles became stuck due to swelling of the racks.

4. The issue does not reflect a current performance deficiency associated with

existing licensee programs, policy, or procedure.

False. The issue reflected current performance as of the time the inspectors identified the issue because the inspectors became aware of the issue due to additional fuel bundles becoming stuck. The licensee did not adequately evaluate the condition until the inspectors raised concerns with licensee management.

The inspectors concluded the issue met only one of the criteria for treatment as an old design issue.

Enforcement:

Technical Specification 4.3.1, Amendment 189, required, in part that Region I fuel storage racks be designed and maintained with a Keff 0.95, if fully flooded with unborated water, which includes allowances for uncertainties as described in Section 9.11 of the Updated Final Safety Analysis Report (UFSAR).

Contrary to the above, from October 2007 until February 20, 2009, the licensee failed to maintain the Region I fuel storage racks with a Keff 0.95 when fully flooded with unborated water. Specifically, the Region I fuel storage racks contained fixed poison in the form of B4C manufactured by the Carborundum Corporation that was significantly less than required by TS to ensure the design feature was met. The Carborundum neutron absorption capability degraded to the point that Keff in Region I was greater than 0.95 under the bounding conditions described in Section 9.11 of the UFSAR if fully flooded with unborated water. Pending determination of final safety significance, this finding with the associated apparent violation will be tracked as AV 05000255/2009008-01, Loss of Spent Fuel Pool Neutron Absorption Capability. The licensee has moved fuel and obtained a license amendment to control fuel movement such that TS 4.3.1 is now satisfied.

4OA6 Management Meetings

.1 Exit Meeting Summary

On November 9, 2009, the inspectors presented the inspection results to C. Schwarz and other members of the licensee staff. The licensee acknowledged the issues presented. The inspectors confirmed that none of the potential report input discussed was considered proprietary.

s: 1.

Supplemental Information

Appendix M

SUPPLEMENTAL INFORMATION

KEY POINTS OF CONTACT

Licensee

C. Schwarz, Site Vice President
A. Blind, Engineering Director
T. Kirwin, Plant General Manager
M. Sicard, Operations Manager
R. Schmidt, Reactor Engineering Supervisor

NRC

M. Chawla, Palisades Project Manager

M. Yoder

K. Woods

LIST OF ITEMS

OPENED, CLOSED AND DISCUSSED

Opened

05000255/2009008-01 AV Loss of Spent Fuel Pool Neutron Absorption Capability

Closed

NONE

Discussed

05000255/2009008-004 LER Noncompliance with TS 4.3.1.b Attachment

LIST OF DOCUMENTS REVIEWED