IR 05000250/1979028

From kanterella
Jump to navigation Jump to search
IE Insp Repts 50-250/79-28 & 50-251/79-28 on 790902-03.No Noncompliance Noted.Major Areas Inspected:Followup of Licensee Actions Re Hurricane David
ML17339A240
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 09/27/1979
From: Martin R, Vogtlowell R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML17339A239 List:
References
50-250-79-28, 50-251-79-28, NUDOCS 7911090188
Download: ML17339A240 (3)


Text

a'8 Rfgy

"o C

O UNITEDSTATES NUCLEAR REGULATORYCOMMISSION

REGION II

101 MARIETTAST., N.W., SUITE 3100 ATLANTA,GEORGIA 30303 Report Nos. 50-250/79-28 and 50-251/79-28 Licensee:

Florida Power and Light Company 9250 West Flagler Street Miami, Florida 33101 Facility Name: Turkey Point 3 and

Docket Nos.

50-250 and 50-251 I

License Nos.

DPR-31 and DPR-41 Inspection at urk oint Site near. Homestead, Florida Inspected by:

R

.

Vo Lowel te zgn d Approved by:

. D.

Ma in, ction Chief, RONS Branch ate Sign d Inspected on September 2-3, 1979 Areas Inspected This special, announced inspection involved 24 inspector-hours onsite in the area of followup of licensee actions with regard to Hurricane David.

Results Within the area inspected, no apparent items of noncompliance or deviations were identified.

Vgllggg /Pg'

DETAILS 1.

Persons Contacted Licensee Employees

+H. E. Yaeger, Plant Manager J. K. Hays, Plant Superintendent, Nuclear J.

E. Moore, Operations Superintendent, Nuclear Other licensee employees contacted included shift operating personnel.

+Attended exit interview.

2.

Exit Interview The inspection scope and findings were summarized on September 3,

1979 with those persons indicated in Paragraph 1 above.

3.

Licensee Action on Previous Inspection Findings Not inspected.

Unresolved items were not identified during this inspection.

5.

Review of Licensee Actions in Preparation for Hurricane David The inspector conducted a review of licensee plans, procedures and action in regard to the potential effects of Hurricane David.

The following procedures were reviewed by the inspector:

E. P.

20106, "Natural Emergencies" E. P. 20112,

"Communications Network" Several facility tours were conducted by the inspector to verify that preparation activities were progressing on schedule and as prescribed by EP 20106, "Natural Emergencies".

At the conclusion of the inspection, the potential threat from Hurricane David had passed without any observable effect on the plant.

Within the areas inspected, no items of noncompliance or deviations were identified.