IR 05000250/1979008

From kanterella
Jump to navigation Jump to search
Forwards IE Insp Repts 50-250/79-08 & 50-251/79-08 on 790227-0301.No Noncompliance Noted
ML17338A705
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 03/23/1979
From: Robert Lewis
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Robert E. Uhrig
FLORIDA POWER & LIGHT CO.
Shared Package
ML17338A706 List:
References
NUDOCS 7905150251
Download: ML17338A705 (11)


Text

~$ IIjggpiWp

~4 O~

~p AnO I

C O~

+a*++

In Reply Refer To:

RII:EHV 50-250

- 51/79-08 UNITEDSTATES NUCLEAR REGULATORY COMMISSION

REGION II

10$ MARIETTASTREET, N.N.

ATLANTA,GEORGIA 30303

)gal g 3 f9tg Florida Power and Iight Company ATTN:

R. E. Uhrig, Vice President P. 0.

Box 529100 Miami, FL 33152 Gentlemen:

This refers to the inspection conducted by E. H. Verdery of this office on February 27 - March 1, 1979, of activities authorized by NRC License Nos.

DPR-31 and DPR-41 for the Turkey Point Units 3 and 4 facility, and to the discussion of our findings held with H. E. Yaeger at the conclusion of the inspection.

Areas examined during the inspection and our findings are discussed in the enclosed ins ection report.

Within these areas, the inspection consisted of selective examinations of procedures and representative records, interviews with personnel, and observations by the inspector.

Within the scope of this inspection, no items of noncompliance were disclosed.

We have examined actions you have taken with regard to previously identified enforcement matters and unresolved items.

The status of these items is discussed in the enclosed report.

In accordance with Section 2.790 of the NRC's "Rules of Practice",

Part 2, Title 10, Code of Federal Regulations, a copy of this letter and the enclosed t 'll be laced in the NRC's Public Document Room. If this report contains any information that you (or your contractor) believe to e

t

cessary that you make a written application within losure.

20 days to this office to withhold such information from public disc osure.

Any suc app ica ion An h

lon must include a full statement of the reasons on the should f

h h it is claimed that. the information is proprietary, and shou be prepared so that proprietary information identified in the app i contained in a separate part of the document.

If we do not hear from you in this regard within the specified period, the report will be placed in the Public Document Roo ;

[

MAR 8 3 1/79 Florida Power and Light Company-2-Should you have any questions concerning this letter, we will be glad to discuss them with you.

Sincerely, c@ -~

Richard C. Lewis, Acting Chief Reactor Operations and Nuclear Support Branch

Enclosure:

Inspection Report Nos. 50-250/79-08 and 50-251/79-08

REGION II==

10$ MARIETTASTREET, N.IlIL ATLANTA,GEORGIA 30303 Report Nos.:

50-250/79-08 and 50-251/79-08 Licensee:

Florida Power and Light Company 9250 West Flagler Street Miami, Florida Facility Name:

Turkey Point Units 3 and 4 Docket Nos.:

50-250 and 50-251 License Nos.:

DPR-31 and DPR-41 Inspection at e

Point Site near Florida City, Florida Inspector:

E

.

erdery Approved by:

F.

.

antrell, Sect Chief, RONS Branch s zzp Date Signed

ate igned SUMMARY Inspection on February 27 - March 1, 1979 This routine, unannounced inspection involved 20 inspector-hours onsite in the areas of refueling maintenance, followup on noncompliance, unresolved and open items, review of reportable occurrences, followup on IE Bulletins and Circulars and a tour of the Auxiliary Building and Unit 3 Containment.

Results Of the six areas inspected, no apparent items of noncompliance or deviations were identified.

.9905150 Z5 g')

II

DETAILS l.

Persons Contacted Licensee Em lo ees

+H. E. Yaeger, Plant Manager J.

K. Hays, Plant Superintendent, Nuclear J.

E. Moore, Operations Superintendent, Nuclear

+V. B. Wager, Operations Supervisor, Nuclear

  • P. J. White, Maintenance Superintendent-D.

W. Jones, Quality Control Supervisor

  • G. D. Whittier, Licensing Engineer, G. 0.
  • W. A. Klein, Senior Plant Engineer
  • R. J.

Spooner, QAO Supervisor

+J.

E. Knox, Maintenance Supervisor

  • J. J. Sullivan, Maintenance Supervisor
  • B. C. Kilpatrick, Assistant Superintendent, Nuc P. Hughes, Health Physics Supervisor lear Maintenance Other licensee employees contacted included 3 technicians, 3 operators and 1 mechanic.

+Attended exit interview.

2.

Exit Interview The inspection scope and findings were summarized on March 1, 1979 with those persons indicated in Paragraph

above.

The inspector discussed the licensee's position on commitment to the equality Assur-ance ANSI Standards and Regulatory Guides listed in the FPL TAHAR.

Licensee management indicated that they did not consider Turkey Point committed to the standards referenced in the TAHAR. The inspector stated that the licensee had been inspected to those standards in the past and would continue to be inspected against them, however, clarifi-I cation was definitely in order.

The inspector stated the licensee s

corrective action for noncompliance on housekeeping procedures was inadequate in that the procedure developed and approved failed to meet ANSI 45.2,3.

The licensee management indicated that they would await clarification on the status of their commitment to the standards, as discussed above, prior to making any changes in the subject procedur.

Licensee Action on Previous Ins ection Findin s (Open)

Infraction (250/78-27-01, 251/78-27-01):

Failure to develop formal controls on housekeepirfg.

This item will remain open pending final resolution of the licensee's commitment to ANSI 45.2.3, Housekeeping During the Construction Phase of Nuclear Power Plants, as endorsed for the Operations Phase by Regulatory Guide 1.39.

The procedure developed by the licensee in response to this item of noncompliance AP 0103.11, Housekeeping, does not include the zoning of the facility into cleanliness control areas as required by Section 2.1 of the referenced standard.

{Open)

Infraction (250/78-27-02, 251/78-27-02):

Failure to conduct QC surveillance of housekeeping practices.

The licensee had not completed QC surveillance activities in conformance with the Quality Procedures, however, the licensee stated that these activities were ongoing and records could be available during subsequent inspections.

b.

Unresolved Items

{Closed)

(250/78-01-02, 251/78-01-02):

Maintenance Quality Assurance Records,

'PMO's not stored in record vault.

The licensee has commenced sending safety-related PRO's to document Control on a timely basis.

This item is resolved.

(Closed)

{250/78-02-03, 251/78-02-03):

Adequacy of Quality Assurance Records storage.

This item has been resolved by transfer of QA records to permanent storage or one hour fire rated cabinets.

5.

Followu on en Items The inspector reviewed the status of several previously identified items which were left open pending licensee action.

This review was facilitated by the issuance of the Corrective Action Status Report dated February 14, 1979.

The following items. were reviewed with the status as indicated:

a ~

Implementation of Continuous Recirculation on Boron Injection Tank.

This item relates to the licensee's continuing problem with implementation of continuous recirc on the BIT. The licensee has completed a preoperational test for PC/M 75-11 as of 2/16/79 on Unit 3 and 2/22/79 on Unit 4.

The mini-recirc pumps have been in continuous operation for several weeks.

This action closes item (250/251/77-01-02).

Rod Bank D Withdrawal Limit Annunicator.

This item was identified during a previous inspection where the annuniciator was illuminated and operators were not taking the corrective action specified in OP 0208.4, Annunciator List, Panel B-Reactor.

The licensee modified this procedure to indicate that no corrective action is required when rod control is in manual.

This closes item (78-02-05).

Environmental (}ualification of Safety-Related Electrical Components.

IE Bulletin 79-01 on this subject details the schedule requirements and requires a licensee response.

This closes item (250/251/78-18-02).

Cleanliness Controls inside Containment and Maintenance of Grade A and B Levels of Cleanliness in Safety-Related Fluid Systems.

The inspector reviewed several related work packages and procedures and interviewed maintenance supervisors to evaluate the mainte-nance of Grade A and B cleanliness levels on safety-related fluid systems.

(}C holdpoints for cleanliness appeared in many of the procedures reviewed, however, the inspector could not determine the level of inspection completed for these holdpoints nor evaluate the discrepancies noted by gC inspectors since no records of detailed cleanliness inspections were available.

The inspector toured the Unit

containment to evaluate the housekeeping status being maintained during the current refueling outage.

It was apparent that significant attention had been given by licensee management to the general cleanliness inside the containment.

Debris, lagging residue, scrap wire and metal fillings were scattered on the deck in several locations, however, these conditions are a

considerable improvement over previous inspections.

This item will be reviewed in conjunction with the corrective action for noncompliances 78-27<<01 and 78-27-02.

Maintenance of Grade A and B levels of cleanliness will remain an open item (250/251/78-18"03).

Routine Audit of Outstanding Clearances.

The licensee agreed to implement a routine audit of outstanding clearances which have been outstanding for more than one month by April 30, 1979.

Item (250/251/78-23-01)

remains open.

Validation of Core Loading Plan.

The inspector verified that the licensee is now. receiving the full size print of the Westinghouse Approved Core Loading Plan prior to conductinp the verification of the actual core loading.

In addition OP 16002.5, Refueling Core Shuffle,has been revised to include this verification as a require-ment.

This action closes (250/251/78-25-02).

Operational Test of Fire Alarm System.

The licensee has completed two tests of the fire alarm system since this item was identified.

The fire alarm horn actuating button has been modified to make it seal in for approximately

seconds.

This modification wi LL preclude having the operator keep it depressed.

The licensee has verified that all annunciators at the facility are operable and audible.

This action closes (250/251/ 78 25-03).

h.

Boric Acid Leakage on Safety-Related Cable Trays.

The inspector toured the 4 ft.

elevation of the Auxiliary Building Waste Hold Up Tank area to examine the status of the leakage of boric acid on cable trays 3FDT10 and 3FCT40.

The leakage has abated, however the licensee has not completed the repairs on the floor drain.

Bechtel has been given a contract to repair the drain and the concrete surrounding it.

In the interim, the licensee has effec-tively diverted the leakage away from the subject cable trays.

This item remains open (250/251/78-27-03).

6.

Followu on IE Bulletins and Circulars IE Circular 78-18 - UL Fire Test The inspector verified that the licensee had received this circular and understood the issues addressed.

As of the date of this inspection the licensee had planned no additional action on sprinkler systems installed at the facility. This item is closed.

7.

Re ortable Events Followu The following event was reviewed to ascertain that:

a

~

reporting requirements were met; b.

corrective action was taken as required by Appendix B to

CFR Part 50; C.

the event was reviewed and evaluated; and d.

the facility was operated within the requirements of 10CFR50.59 and the Technical Specification subsequent to the event.

50-250/78-18,

"Auxiliary Feed Pump A Shaft Seizure."

As discussed in the licensee's report, the cause of this pump failure appears to be a combination of leaking steam supply valves which operate the turbine and pump against a shutoff head.

This occurs during the testing of other Auxiliary Feed Pumps (AFP) in that the operating AFP will not shut the discharge check valve completely and allows operating AFP discharge pressure to block the recircu-

a

lation flow from the other AFP idling because of steam supply valve leakage.

The licensee is grooming the system and repairing the steam supply valves and discharge check valves.

Additionally, long term corrective action may incLude replacing the current turbine casings with high pressure casings which will eliminate the need for steam reducing valves in the system.