UNITED STATES NUCLEAR REGULATORY COMMISSION rch 4, 2015

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR TURKEY POINT NUCLEAR GENERATING UNIT 3 AND UNIT 4 (REPORT 05000250/2014001 AND 05000251/2014001)

Dear Mr. Nazar:

On February 11, 2015, the NRC completed its end-of-cycle performance review of Turkey Point Nuclear Generating Unit 3 and Unit 4. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2014, through December 31, 2014. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined the performance at Turkey Point Nuclear Generating Unit 3 and Unit 4 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green)

safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through June 30, 2016. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence.

Additionally, an NRC audit of licensee efforts towards compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, and Order EA-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," is ongoing for various sites. The audit includes an onsite visit for the NRC staff to evaluate mitigating strategies as described in the licensee submittals, and to receive and review information relative to associated open items. This onsite audit will occur prior to the first unit at the site achieving compliance with the Orders and the audit will aid NRC staff in developing a final Safety Evaluation for the site. The audit at your site has been scheduled for the week of August 17, 2015. A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact Eric Stamm at (404) 997-4575 with any questions you have regarding this letter.

Sincerely,

/RA/

Joel T. Munday, Director Division of Reactor Projects Docket Nos.: 50-250, 50-251 License Nos.: DPR-31, DPR-41 Enclosure: Turkey Point Inspection/Activity Plan (03/01/2015 - 06/30/2016)

cc Distribution via Listserv

_________________________ SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE DRP:RII DRP:RII SIGNATURE EJS2 JTM NAME E. Stamm J. Munday DATE 03/04/2015 03/04/2015 E-MAIL COPY? YES NO YES NO Letter to Mano Nazar from Joel T. Munday dated March 4, 2015.

SUBJECT: ANNUAL ASSESSMENT LETTER FOR TURKEY POINT NUCLEAR GENERATING UNIT 3 AND UNIT 4 (REPORT 05000250/2014001 AND 05000251/2014001)

DISTRIBUTION:

D. Gamberoni, RII L. Gibson, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMTurkeyPoint Resource ROP Assessment ROP Reports Institute of Nuclear Power Operations (INPO)

Page 1 of 2 Turkey Point 03/04/2015 09:43:03 Inspection / Activity Plan Report 22 03/01/2015 - 06/30/2016 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site OL RQ - RQ INSP 2 3, 4 08/31/2015 09/04/2015 IP 7111111B Licensed Operator Requalification Program ISI - UNIT 3 IN-SERVICE INSPECTION 1 3 10/26/2015 10/30/2015 IP 7111108P Inservice Inspection Activities - PWR RP - RP OCCUPATIONAL BASELINE WEEK 1 2 3, 4 11/02/2015 11/06/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 3, 4 11/02/2015 11/06/2015 IP 71124.02 Occupational ALARA Planning and Controls 3, 4 11/02/2015 11/06/2015 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 3, 4 11/02/2015 11/06/2015 IP 71124.04 Occupational Dose Assessment 3, 4 11/02/2015 11/06/2015 IP 71124.05 Radiation Monitoring Instrumentation 3, 4 11/02/2015 11/06/2015 IP 71151 Performance Indicator Verification RP - RP OCCUPATIONAL BASELINE WEEK 2 3 3, 4 11/16/2015 11/20/2015 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 3, 4 11/16/2015 11/20/2015 IP 71124.02 Occupational ALARA Planning and Controls 3, 4 11/16/2015 11/20/2015 IP 71124.03 In-Plant Airborne Radioactivity Control and Mitigation 3, 4 11/16/2015 11/20/2015 IP 71124.04 Occupational Dose Assessment 3, 4 11/16/2015 11/20/2015 IP 71124.05 Radiation Monitoring Instrumentation 3, 4 11/16/2015 11/20/2015 IP 71151 Performance Indicator Verification EP - EP PROGRAM INSPECTION 2 3, 4 01/11/2016 01/15/2016 IP 7111401 Exercise Evaluation 3, 4 01/11/2016 01/15/2016 IP 7111402 Alert and Notification System Testing 3, 4 01/11/2016 01/15/2016 IP 7111403 Emergency Preparedness Organization Staffing and Augmentation System 3, 4 01/11/2016 01/15/2016 IP 7111404 Emergency Action Level and Emergency Plan Changes 3, 4 01/11/2016 01/15/2016 IP 7111405 Correction of Emergency Preparedness Weaknesses and Deficiencies RP - RP PUBLIC RAD SAFETY BASELINE 2 3, 4 02/08/2016 02/12/2016 IP 71124.06 Radioactive Gaseous and Liquid Effluent Treatment 3, 4 02/08/2016 02/12/2016 IP 71124.07 Radiological Environmental Monitoring Program 3, 4 02/08/2016 02/12/2016 IP 71151 Performance Indicator Verification HS - TRIENNIAL HEAT SINK PERFORMANCE 1 3, 4 02/22/2016 02/26/2016 IP 7111107T Heat Sink Performance ISI - UNIT 4 IN-SERVICE INSPECTION 1 4 04/04/2016 04/08/2016 IP 7111108P Inservice Inspection Activities - PWR This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure

Page 2 of 2 Turkey Point 03/04/2015 09:43:03 Inspection / Activity Plan Report 22 03/01/2015 - 06/30/2016 Unit Planned Dates No. of Staff Number Start End Inspection Activity Title on Site RP - RAD HAZARDS ANALYSIS AND TRANSPORTATION 2 3, 4 04/11/2016 04/15/2016 IP 71124.01 Radiological Hazard Assessment and Exposure Controls 3, 4 04/11/2016 04/15/2016 IP 71124.08 Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation SGISI - UNIT 4 SG IN-SERVICE INSPECTION 1 4 04/11/2016 04/15/2016 IP 7111108P Inservice Inspection Activities - PWR This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.