IR 05000051/2014001

From kanterella
(Redirected from IR 05000250/2014001)
Jump to navigation Jump to search
Annual Assessment Letter for Turkey Point Nuclear Generating Unit 3 and Unit 4, (Report 05000250/2014001 and 0500051/2014001)
ML15063A371
Person / Time
Site: Turkey Point, 05000051  NextEra Energy icon.png
Issue date: 03/04/2015
From: Joel Munday
Division Reactor Projects II
To: Nazar M
Nextera Energy
References
IR 2014001
Download: ML15063A371 (6)


Text

March 4, 2015

SUBJECT:

ANNUAL ASSESSMENT LETTER FOR TURKEY POINT NUCLEAR GENERATING UNIT 3 AND UNIT 4 (REPORT 05000250/2014001 AND 05000251/2014001)

Dear Mr. Nazar:

On February 11, 2015, the NRC completed its end-of-cycle performance review of Turkey Point Nuclear Generating Unit 3 and Unit 4. The NRC reviewed the most recent quarterly performance indicators (PIs) in addition to inspection results and enforcement actions from January 1, 2014, through December 31, 2014. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.

The NRC determined the performance at Turkey Point Nuclear Generating Unit 3 and Unit 4 during the most recent quarter was within the Licensee Response Column of the NRCs Reactor Oversight Process (ROP) Action Matrix because all inspection findings had very low (i.e., green)

safety significance, and all PIs indicated that your performance was within the nominal, expected range (i.e., green). Therefore, the NRC plans to conduct ROP baseline inspections at your facility.

The enclosed inspection plan lists the inspections scheduled through June 30, 2016. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last nine months of the inspection plan are tentative and may be revised at the mid-cycle performance review. The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes. This inspection plan does not include security-related inspections, which will be sent via separate, non-publicly available correspondence.

Additionally, an NRC audit of licensee efforts towards compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events, and Order EA-12-051, "Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation," is ongoing for various sites. The audit includes an onsite visit for the NRC staff to evaluate mitigating strategies as described in the licensee submittals, and to receive and review information relative to associated open items. This onsite audit will occur prior to the first unit at the site achieving compliance with the Orders and the audit will aid NRC staff in developing a final Safety Evaluation for the site. The audit at your site has been scheduled for the week of August 17, 2015. A site-specific audit plan for the visit will be provided in advance to allow sufficient time for preparations.

In accordance with 10 CFR 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Please contact Eric Stamm at (404) 997-4575 with any questions you have regarding this letter.

Sincerely,

/RA/

Joel T. Munday, Director Division of Reactor Projects

Docket Nos.: 50-250, 50-251 License Nos.: DPR-31, DPR-41

Enclosure: Turkey Point Inspection/Activity Plan (03/01/2015 - 06/30/2016)

cc Distribution via Listserv

_________________________

SUNSI REVIEW COMPLETE FORM 665 ATTACHED OFFICE DRP:RII DRP:RII

SIGNATURE EJS2 JTM

NAME E. Stamm J. Munday

DATE 03/04/2015 03/04/2015

E-MAIL COPY?

YES NO YES NO Letter to Mano Nazar from Joel T. Munday dated March 4, 2015.

SUBJECT: ANNUAL ASSESSMENT LETTER FOR TURKEY POINT NUCLEAR GENERATING UNIT 3 AND UNIT 4 (REPORT 05000250/2014001 AND 05000251/2014001)

DISTRIBUTION:

D. Gamberoni, RII L. Gibson, RII OE Mail RIDSNRRDIRS PUBLIC RidsNrrPMTurkeyPoint Resource ROP Assessment ROP Reports Institute of Nuclear Power Operations (INPO)

Page 1 of 2 03/04/2015 09:43:03 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Turkey Point Inspection / Activity Plan 03/01/2015 - 06/30/2016 OL RQ

- RQ INSP

3,4 IP Licensed Operator Requalification Program 7111111B 08/31/2015 09/04/2015 ISI

- UNIT 3 IN-SERVICE INSPECTION

3 IP Inservice Inspection Activities - PWR 7111108P 10/26/2015 10/30/2015 RP

- RP OCCUPATIONAL BASELINE WEEK 1

3,4 IP Radiological Hazard Assessment and Exposure Controls 71124.01 11/02/2015 11/06/2015 3,4 IP Occupational ALARA Planning and Controls 71124.02 11/02/2015 11/06/2015 3,4 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 11/02/2015 11/06/2015 3,4 IP Occupational Dose Assessment 71124.04 11/02/2015 11/06/2015 3,4 IP Radiation Monitoring Instrumentation 71124.05 11/02/2015 11/06/2015 3,4 IP Performance Indicator Verification 71151 11/02/2015 11/06/2015 RP

- RP OCCUPATIONAL BASELINE WEEK 2

3,4 IP Radiological Hazard Assessment and Exposure Controls 71124.01 11/16/2015 11/20/2015 3,4 IP Occupational ALARA Planning and Controls 71124.02 11/16/2015 11/20/2015 3,4 IP In-Plant Airborne Radioactivity Control and Mitigation 71124.03 11/16/2015 11/20/2015 3,4 IP Occupational Dose Assessment 71124.04 11/16/2015 11/20/2015 3,4 IP Radiation Monitoring Instrumentation 71124.05 11/16/2015 11/20/2015 3,4 IP Performance Indicator Verification 71151 11/16/2015 11/20/2015 EP

- EP PROGRAM INSPECTION

3,4 IP Exercise Evaluation 7111401 01/11/2016 01/15/2016 3,4 IP Alert and Notification System Testing 7111402 01/11/2016 01/15/2016 3,4 IP Emergency Preparedness Organization Staffing and Augmentation System 7111403 01/11/2016 01/15/2016 3,4 IP Emergency Action Level and Emergency Plan Changes 7111404 01/11/2016 01/15/2016 3,4 IP Correction of Emergency Preparedness Weaknesses and Deficiencies 7111405 01/11/2016 01/15/2016 RP

- RP PUBLIC RAD SAFETY BASELINE

3,4 IP Radioactive Gaseous and Liquid Effluent Treatment 71124.06 02/08/2016 02/12/2016 3,4 IP Radiological Environmental Monitoring Program 71124.07 02/08/2016 02/12/2016 3,4 IP Performance Indicator Verification 71151 02/08/2016 02/12/2016 HS

- TRIENNIAL HEAT SINK PERFORMANCE

3,4 IP Heat Sink Performance 7111107T 02/22/2016 02/26/2016 ISI

- UNIT 4 IN-SERVICE INSPECTION

4 IP Inservice Inspection Activities - PWR 7111108P 04/04/2016 04/08/2016 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.

Enclosure

Page 2 of 2 03/04/2015 09:43:03 Report 22 Unit Number Planned Dates Start End Inspection Activity Title No. of Staff on Site Turkey Point Inspection / Activity Plan 03/01/2015 - 06/30/2016 RP

- RAD HAZARDS ANALYSIS AND TRANSPORTATION

3,4 IP Radiological Hazard Assessment and Exposure Controls 71124.01 04/11/2016 04/15/2016 3,4 IP Radioactive Solid Waste Processing and Radioactive Material Handling, Storage, and Transportation 71124.08 04/11/2016 04/15/2016 SGISI

- UNIT 4 SG IN-SERVICE INSPECTION

4 IP Inservice Inspection Activities - PWR 7111108P 04/11/2016 04/15/2016 This report does not include INPO and OUTAGE activities.

This report shows only on-site and announced inspection procedures.