Hurricane David

From kanterella
Jump to navigation Jump to search

14 September 1979

See also: Hurricane

Scrams (0)

General

 Start dateSiteTitle
ML21081A03822 March 2021Probabilistic Risk Assessment (PRA) Lessons from Storms and Floods
ML21208A41830 September 2020Surry2 to Updated Final Safety Analysis Report, Chapter 2, Site Characteristics - (EPID L-2020-LRO-0076) - Redacted
ML20049G02024 February 2020ASP Program Summary Description (Revision 1)
ML18135A10920 June 2018Qualitative PRA Insights from Operational Events
ML16194A14412 July 2016Saint LucieUpdated Final Safety Analysis Report, Volume 17A
ML14233A51430 June 2014Surry
07200002
Redacted - Surry Power Station Units 1 & 2, Independent Spent Fuel Storage Installation (ISFSI) - Safety Analysis Report - Revision 20
ML20245J48227 June 1989SeabrookTranscript of 890627 Evidentiary Hearing in Boston,Ma Re Offsite Emergency Planning.Pp 27,427-27,778.Supporting Info Encl.Witnesses:Sj Ellis,Am Callendrello,Cm Frank,Tf Grew & Tm Carter
ML20214M1045 September 1986PerryTranscript of 860905 Meeting in Washington,Dc Re Full Power OL for Plant.Pp 1-112
ML20137L96826 November 1985HarrisIdentifies Various Exhibits Which Applicant,Nrc & FEMA Have Agreed May Be Admitted to Record & Exhibits Not Agreed to
ML20209G1989 September 1985Transcript of 850909 Public Meeting in Washington,Dc Re Earthquakes & Emergency Planning.Pp 1-97
ML20112C40110 September 1984HarrisIntervenor Exhibit I-JOINT-24,consisting of Attachment I-16 Listing of Offline Outages at Brunswick & Robinson Nuclear Units for 1978-83
ML20092E2313 May 1984CatawbaApplicant Exhibit A-EP-13,consisting of 840416 Testimony of Je Neves,Jt Pugh,J Gregory,Pr Lunsford,Wm Mcswain, Be Phillips,Lw Broome,D Johnson & P Needham Re Emergency Planning Contention 3
ML20084F9161 May 1984HarrisAnswers to Joint Intervenors Interrogatories & Request for Production of Documents to Applicants on Joint Contention I (First Set).Certificate of Svc Encl.Related Correspondence
ML17214A36828 April 1983Saint LucieReactor Containment Bldg Integrated Leakage Rate Test, Final Rept
ML17341B01331 December 1981Turkey PointAnnual Nonradiological Environ Monitoring Rept,1981.
ML19115A33131 October 1981Saint LucieNUREG-0843, Safety Evaluation Report Related to the Operation of St. Lucie Plant, Unit 2.
ML17266A50121 September 1981Saint LucieForwards Response to NRC Request for Addl Info Re Fsar.Matl Will Be Incorporated in Future FSAR Amend
ML17266A25326 August 1980Saint LucieSubmits Info Requested in NRC 800711 Ltr Re up-to-date Const Completion Schedules.Facility Will Be Ready for Fuel Loading in Nov 1982.Three Oversize Photographs & Supporting Documentation Encl
ML17266A16128 March 1980Saint LucieForwards Annual Nonradiological Monitoring Rept,1979, Vols 1,2 & 3.Vol 1 Summarizes Abiotic Monitoring for 1979 & Vols 2 & 3 Discuss Biotic Monitoring
ML17266A17124 March 1980Saint LucieForwards General Info Section of Application for OL
ML19309B61629 February 1980Saint LucieAnnual Nonradiological Environ Monitoring Rept,1979. Vol 2,biotic Monitoring
ML18082A34325 February 1980SalemAnnual Financial Rept 1979
ML17266A14511 February 1980Saint LucieUpdated LER 79-028/01X-1:on 790903,in Cold Shutdown During Hurricane,Cable Fell Into Startup Transformer B.Ac Electrical Sys B de-energized & Diesel Generator Failed to Start.Caused by Delay in B Diesel Binding
ML17208A4458 February 1980Saint Lucie
Turkey Point
Annual Financial Rept 1979
ML17208A3151 February 1980Saint LucieFinal Const Deficiency Rept:On 790903,Chicago Bridge & Iron Guyed Derrick Collapsed During Hurricane David,Damaging Reactor Auxiliary & Concrete Shield Bldgs.Caused by Inadequate Securing.New Derrick Will Be Erected 800107
ML17208A3131 February 1980Saint LucieForwards Final Const Deficiency Rept Re Hurricane David Damage
ML19257A04427 December 1979Crystal RiverDraft Emergency Procedure EM-100.
ML17207A7237 December 1979Saint LucieSupplements 791004 Interim Deficiency Re Derrick Collapse During Hurricane.Manufacturer Design Review Recommends Actions to Secure Replacement Derrick,Including Raising Boom & Removing Spreader Beam
ML17207A6757 December 1979Saint LucieResponse to Intervenor Interrogatories.Lists sys-wide & Offsite Power Disturbances Occurring within Past 10 Yrs. States Reasoning for Not Interconnecting W/Ga Power Co. Certificate of Svc Encl
ML17207A7217 December 1979Saint LucieAdvises That Mh Hodder & Tj Anderson,Counsel & co-counsel for Intervenors,Will Take Part in 791211 Visit to Util Sys Control Ctr
ML17207A67827 November 1979Saint LucieFirst Set of Interrogatories.Requests Info Re sys-wide Power Failures,Offsite Power Failures,Failure to Provide Intertie W/Ga Power Corp,Test Results & Performance Records. Certificate of Svc Encl
ML17208A5956 October 1979Saint Lucie
Turkey Point
Monthly Operating Repts for Sept 1979
ML17207A4964 October 1979Saint LucieForwards Interim Deficiency Rept Re Damage of Reactor Auxiliary & Shield Bldgs Resulting from 790903 Derrick Collapse During Hurricane David
ML17207A4984 October 1979Saint LucieInterim Deficiency Rept Re Damage to Reactor Auxiliary & Shield Bldgs from 790903 Derrick Collapse During Hurricane David.Forwards Six Drawings Detailing Storm Damage.Available in Central Files
ML20196K48014 September 1979Transcript of 790914 Meeting in Silver Spring,Md in Matter of Advisory Committee on Nuclear Power Plant Const During Adjudication.Pp 1-90