Category:Inspection Report
MONTHYEARML24010A1532024-01-10010 January 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection IR 05000528/20230112023-12-18018 December 2023 License Renewal Inspection Report 05000528/2023011 IR 05000528/20234032023-11-13013 November 2023 NRC Security Inspection Report 05000528 2023403, 05000529 2023403, 05000530 2023403 (Full Report) IR 05000528/20230032023-10-17017 October 2023 Integrated Inspection Report 05000528 2023003 and 05000529 2023003 and 05000530 2023003 ML23270B9232023-09-28028 September 2023 Notification of Age-Related Degradation Inspection (05000528/2024012, 05000529/2024012, and 05000530/2024012) and Request for Information IR 05000528/20243012023-09-0606 September 2023 Notification of NRC Initial Operator Licensing Examination 05000528/2024301; 05000529/2024301; 05000530/2024301 IR 05000528/20230102023-08-22022 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000528/2023010, 05000529/2023010 and 05000530/2023010 IR 05000528/20230052023-08-21021 August 2023 Updated Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2023005 and 05000529/2023005 and 05000530/2023005) IR 05000528/20230022023-08-0808 August 2023 Integrated Inspection Report 05000528/2023002 and 05000529/2023002 and 05000530/2023002 IR 05000528/20233012023-06-0505 June 2023 NRC Examination Report 05000528/2023301, 05000529/2023301 and 05000530/2023301 IR 05000528/20230012023-05-0808 May 2023 and Independent Spent Fuel Storage Installation - Integrated Inspection Report 05000528/2023001 and 05000529/2023001 and 05000530/2023001 and 07200044/2023001 ML23115A4012023-04-26026 April 2023 Review of the 2022 Steam Generator Tube Inspections During Refueling Outage 23 IR 05000528/20230122023-04-19019 April 2023 Notification of Commercial Grade Dedication Inspection (05000528/2023012, 05000529/2023012, and 05000530/2023012) and RFI IR 05000528/20224012023-04-13013 April 2023 Cyber Security Inspection Report 05000528/2022401 and 05000529/2022401 and 05000530/2022401 IR 05000528/20234022023-03-29029 March 2023 and 3 - NRC Security Inspection Report 05000528-2023402, 05000529-2023402, and 05000530-2023402, (Cover Letter Only) IR 05000528/20220062023-03-0101 March 2023 Annual Assessment Letter for Palo Verde Nuclear Generating Station Units 1, 2 and 3 (Report 05000528/2022006, 05000529/2022006, and 05000530/2022006) IR 05000528/20234012023-02-27027 February 2023 NRC Security Inspection Report 05000528/2023401, 05000529/2023401, 05000530/2023401, and 07200044/2023401 (Full Report) IR 05000528/20220042023-01-30030 January 2023 Integrated Inspection Report 05000528/2022004 and 05000529/2022004 and 05000530/2022004 IR 05000528/20220102023-01-17017 January 2023 Design Basis Assurance Inspection (Teams) Inspection Report 05000528/2022010 and 05000529/2022010 and 05000530/2022010 IR 05000528/20220032022-10-24024 October 2022 Units, 1, 2 and 3 Integrated Inspection Report 05000528/2022003, 05000529/2022003, and 05000530/2022003 IR 05000528/20224032022-10-14014 October 2022 Security Baseline Inspection Report 05000528/2022403 and 05000529/2022403 and 05000530/2022403 IR 05000528/20220052022-08-23023 August 2022 Updated Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2022005 and 05000529/2022005 and 05000530/2022005) ML22235A6662022-08-23023 August 2022 Notification of NRC Design Bases Assurance Inspection (Team) (05000528/2022010, 05000529/2022010, and 05000530/2022010) and Request for Information IR 05000528/20224022022-08-0808 August 2022 Cover Letter Only - Palo Verde Nuclear Generating Station, Units 1, 2, and 3 NRC Security Inspection Report 05000528 2022402, 05000529 2022402, 05000530 2022402, and 07200044 2022402 IR 05000520/20220022022-08-0505 August 2022 Integrated Inspection Report 05000528/2022002 and 05000529/2022002 and 05000520/2022002 IR 05000528/20223012022-06-21021 June 2022 NRC Examination Report 05000528/2022301, 05000529/2022301, and 05000530/2022301 IR 05000528/20220012022-05-0909 May 2022 Integrated Inspection Report 05000528/2022001, 05000529/2022001 and 05000530/2022001 ML22105A0512022-04-19019 April 2022 Review of the 2021 Steam Generator Tube Inspections During Refueling Outage 22 IR 05000528/20224202022-03-0808 March 2022 Security Baseline Inspection Report 05000528/2022420, 05000529/2022420 and 05000530/2022420, Cover Letter IR 05000528/20210062022-03-0202 March 2022 Annual Assessment Letter for Palo Verde Nuclear Generating Station - Units 1, 2 and 3 (Report 05000528/2021006, 05000529/2021006, and 05000530/2021006) IR 05000528/20210042022-02-0707 February 2022 Integrated Inspection Report 05000528/2021004, 05000529/2021004, and 05000530/2021004 IR 05000528/20210032021-11-12012 November 2021 Integrated Inspection Report 05000528/2021003, 05000529/2021003 and 05000530/2021003 IR 05000528/20210152021-10-27027 October 2021 Temporary Instruction 2515/194 Report 05000528/2021015 and 05000529/2021015 and 05000530/2021015 ML21273A3172021-10-0404 October 2021 Station. NON-SENSITIVE IR 05000528/20214042021-09-23023 September 2021 NRC Security Inspection Report 05000528/2021404, 05000529/2021404, 05000530/2021404 and 07200044/2021401 IR 05000528/20214012021-09-14014 September 2021 Security Baseline Inspection Report 05000528/2021401 and 05000529/2021401 and 05000530/2021401 IR 05000528/20210052021-09-0101 September 2021 Mid-Cycle Inspection Plan Transmittal Letter for Palo Verde Nuclear Generating Station - Units 1, 2 and 3 (Report 05000528/2021005, 05000529/2021005, and 05000530/2021005) IR 05000528/20210022021-08-0909 August 2021 Integrated Inspection Report 05000528/2021002, 05000529/2021002, and 05000530/2021002 and Exercise of Enforcement Discretion IR 07200044/20214012021-07-21021 July 2021 ISFSI, Information Request, Security Inspection Report 07200044/2021401 IR 05000528/20210142021-07-14014 July 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000528/2021014, 05000529/2021014 and 05000530/2021014 IR 05000528/20213012021-06-21021 June 2021 NRC Initial Examination Report 05000528/2021301, 05000529/2021301, and 05000530/2021301 IR 05000528/20214032021-05-28028 May 2021 Security Baseline Inspection Report 05000528/2021403; 05000529/2021403 and 05000530/2021403 (Public) IR 05000528/20210012021-05-12012 May 2021 PV 2021001, Palo Verde Nuclear Generating Station - Integrated Inspection Report 05000528/2021001 and 05000529/2021001 and 05000530/2021001 IR 05000528/20210122021-05-0404 May 2021 Triennial Fire Protection Inspection Report 05000528/2021012, 05000529/2021012 and 05000530/2021012 IR 05000528/20210102021-04-28028 April 2021 Biennial Problem Identification and Resolution Inspection Report 05000528/2021010 and 05000529/2021010 and 05000530/2021010 ML21105A1012021-04-19019 April 2021 Review of the 2020 Steam Generator Tube Inspections During Refueling Outage 22 IR 05000528/20210902021-03-0404 March 2021 Notice of Violation; NRC Inspection Report 05000528/2021090, 05000529/2021090, and 05000530/2021090 IR 05000528/20200062021-03-0303 March 2021 Annual Assessment Letter for Palo Verde, Units 1, 2 and 3, (Report 05000528/2020006, 05000529/2020006, and 05000530/2020006) ML21028A4402021-01-28028 January 2021 PV 2020 004 Integrated Inspection Report CAP IR 05000528/20203012021-01-27027 January 2021 NRC Initial Examination Report 05000528/2020301, 05000529/2020301, and 05000530/2020301 2024-01-10
[Table view] Category:Letter
MONTHYEARML24019A2012024-01-19019 January 2024 Fourth 10-Year Interval, Second Period Owners Activity Report Number 1R24 ML24019A1362024-01-18018 January 2024 Inservice Inspection Request for Information ML24012A2452024-01-12012 January 2024 Response to Request for Additional Information to Proposed Method to Manage Environmentally Assisted Fatigue for the Pressurizer Surge Line ML24010A1532024-01-10010 January 2024 Information Request for the Cybersecurity Baseline Inspection, Notification to Perform Inspection ML23341A0062023-12-21021 December 2023 Project Manager Assignment IR 05000528/20230112023-12-18018 December 2023 License Renewal Inspection Report 05000528/2023011 ML23335A0782023-11-30030 November 2023 Independent Spent Fuel Storage Installation - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23325A1602023-11-17017 November 2023 Supplemental Submittal - Relief Request 70 Proposed Alternatives for Pressurizer Lower Shell Temperature Nozzle IR 05000528/20234032023-11-13013 November 2023 NRC Security Inspection Report 05000528 2023403, 05000529 2023403, 05000530 2023403 (Full Report) ML23311A2082023-11-0909 November 2023 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML23299A3052023-10-26026 October 2023 Response to Request for Additional Information Relief Request 70 Proposed Alternatives for Pressurizer Lower Shell Temperature Nozzle IR 05000528/20230032023-10-17017 October 2023 Integrated Inspection Report 05000528 2023003 and 05000529 2023003 and 05000530 2023003 ML23270B9232023-09-28028 September 2023 Notification of Age-Related Degradation Inspection (05000528/2024012, 05000529/2024012, and 05000530/2024012) and Request for Information ML23251A2332023-09-13013 September 2023 Notification of Post Approval Site Inspection for License Renewal and Request for Information Inspection (05000528/2023011) ML23241B0182023-09-13013 September 2023 Use of Honeywell Mururoa V4F1 and MTH2 Supplied Air Suits within Respiratory Protection Program IR 05000528/20243012023-09-0606 September 2023 Notification of NRC Initial Operator Licensing Examination 05000528/2024301; 05000529/2024301; 05000530/2024301 IR 05000528/20230102023-08-22022 August 2023 Biennial Problem Identification and Resolution Inspection Report 05000528/2023010, 05000529/2023010 and 05000530/2023010 IR 05000528/20230052023-08-21021 August 2023 Updated Inspection Plan for Palo Verde Nuclear Generating Station, Units 1, 2, and 3 (Report 05000528/2023005 and 05000529/2023005 and 05000530/2023005) ML23222A2762023-08-10010 August 2023 Independent Spent Fuel Storage Installation, Registration of Dry Spent Fuel Transportable Storage Canister Identification Numbers AMZDFX175 and AMZDFX176 and Vertical Concrete Cask Identification Numbers AMZDNE175, and AMZDNE176 ML23199A2942023-08-0909 August 2023 Issuance of Amendment Nos. 221, 221, and 221, to Revise Technical Specifications to Adopt TSTF-107, Separate Control Rods That Are Untrippable Versus Inoperable IR 05000528/20230022023-08-0808 August 2023 Integrated Inspection Report 05000528/2023002 and 05000529/2023002 and 05000530/2023002 ML23207A2482023-07-26026 July 2023 License Renewal Pressurizer Surge Line Inspection ML23188A1872023-07-0707 July 2023 Fourth 10-Year Interval, Second Period Owners Activity Report Number 2R24 ML23166B0832023-07-0505 July 2023 Independence Spent Fuel Storage Installation - Issuance of Exemption ML23181A1602023-06-30030 June 2023 2 to Updated Final Safety Analysis Report, and Revision 3 to Operations Quality Assurance Program Description ML23180A2222023-06-29029 June 2023 Application to Revise Technical Specifications (TS) 3.5.1, Safety Injection Tanks (Sits) - Operating, TS 3.5.2, Safety Injection Tanks (Sits) - Shutdown, and TS 3.6.5, Containment Air Temperature ML23181A0772023-06-29029 June 2023 Program Review - Simulator Testing Methodology ML23157A1292023-06-0101 June 2023 Annual Report of Guarantee of Payment of Deferred Premium ML23144A3722023-05-24024 May 2023 Response to Regulatory Issue Summary (RIS) 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23143A3912023-05-23023 May 2023 Independent Spent Fuel Storage Installation - Request for Exemption from NAC-MAGNASTOR Certificate of Compliance 72-1031 - Cask Lid Batch 3 Design Requirements ML23145A2772023-05-17017 May 2023 10-PV-2023-05 Post-Exam Comments ML23132A3392023-05-12012 May 2023 Application to Revise Technical Specifications 3.3.11 to Adopt TSTF-266-A, Revision 3, Eliminate the Remote Shutdown System Table of Instrumentation and Controls IR 05000528/20230012023-05-0808 May 2023 and Independent Spent Fuel Storage Installation - Integrated Inspection Report 05000528/2023001 and 05000529/2023001 and 05000530/2023001 and 07200044/2023001 ML23128A0692023-05-0808 May 2023 Notification of Biennial Problem Dentification and Resolution Inspection and Request for Information ML23122A1822023-04-29029 April 2023 Transmittal of Technical Specification Bases Revision 76 ML23122A1912023-04-29029 April 2023 Unit 1 Core Operating Limits Report Revision 32, Unit 2 Core Operating Limits Report Revision 25, Unit 3 Core Operating Limits Report Revision 31 ML23116A2772023-04-26026 April 2023 Independent Spent Fuel Storage Installation, Annual Radioactive Effluent Release Report 2022 ML23115A4012023-04-26026 April 2023 Review of the 2022 Steam Generator Tube Inspections During Refueling Outage 23 ML23115A4982023-04-25025 April 2023 2022 Annual Environmental Operating Report IR 05000528/20230122023-04-19019 April 2023 Notification of Commercial Grade Dedication Inspection (05000528/2023012, 05000529/2023012, and 05000530/2023012) and RFI ML23108A0342023-04-18018 April 2023 NRC Initial Operator Licensing Examination Approval 05000528/2023301; 05000529/2023301; 05000530/2023301 ML23103A4642023-04-13013 April 2023 Annual Radiological Environmental Operating Report 2022 ML23103A4312023-04-13013 April 2023 Emergency Core Cooling System Performance Evaluation Models, 10 CFR 50.46(a)(3)(ii) Annual Report for 2022 IR 05000528/20224012023-04-13013 April 2023 Cyber Security Inspection Report 05000528/2022401 and 05000529/2022401 and 05000530/2022401 ML23102A3292023-04-12012 April 2023 Application for Authorized Use of Mururoa Single-Use, Supplied Air Suits, Models V4F1 and MTH2 ML23102A3242023-04-12012 April 2023 Supplement to Application to Revise Technical Specifications to Adopt TSTF-107-A, Separate Control Rods That Are Untrippable Versus Inoperable ML23089A4002023-03-30030 March 2023 Consolidated Decommissioning Funding Status Report - 2022 ML23088A4012023-03-30030 March 2023 Project Manager Assignment IR 05000528/20234022023-03-29029 March 2023 and 3 - NRC Security Inspection Report 05000528-2023402, 05000529-2023402, and 05000530-2023402, (Cover Letter Only) ML23080A3002023-03-21021 March 2023 Present Levels of Financial Protection 2024-01-19
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24011A1002024-01-10010 January 2024 March 2024 Emergency Preparedness Program Inspection - Request for Information ML23334A1612023-11-30030 November 2023 NRR E-mail Capture - Palo Verde 1, 2, and 3 - RAIs Associated with License Renewal Commitment for Pressurizer Surge Line Welds Inspection Program to Manage Environmentally Assisted Fatigue ML23334A0072023-11-29029 November 2023 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAIs for LAR That Revises TSs 3.5.1, SITs - Operating; 3.5.2, SIT Shutdown; 3.6.5, Containment Air Temperature; and SRs for TS 3.5.1, SITs Operating ML23298A1232023-10-25025 October 2023 NRR E-mail Capture - Palo Verde, Unit 1 - RAIs for Relief Request 70, Proposed Alternatives for Pressurizer Lower Shell Temperature Nozzle ML23031A3392023-01-31031 January 2023 In-service Inspection Request for Information ML23013A0632023-01-13013 January 2023 NRR E-mail Capture - Palo Verde Unit 1 -Request for Additional Information - U1R23 Inspection Summary Report for Steam Generator Tubing ML22348A1672022-12-14014 December 2022 March 2023 Emergency Preparedness Exercise Inspection - Request for Information ML22339A2372022-12-0505 December 2022 NRR E-mail Capture - Palo Verde Unit 1 Request for Additional Information - U1R23 Inspection Summary Report for Steam Generator Tubing ML22272A3252022-09-29029 September 2022 Licensed Operator Positive Fitness-For-Duty Test Request for Additional Information ML22209A1752022-07-28028 July 2022 Inservice Inspection Request for Information ML22187A2632022-07-0606 July 2022 Notification of Inspection (NRC IR 05000528/2022004, 05000529/2022004 and 05000530/2022004) and Request for Information ML22067A2292022-03-0202 March 2022 Inservice Inspection Inspection PWR Request for Information ML22055A5842022-02-24024 February 2022 NRR E-mail Capture - Palo Verde, Unit 3 - Final RAIs for 22nd Refueling Outage (Spring 2021) Steam Generator Tube Inservice Inspection Report ML22035A3302022-02-10010 February 2022 Requests for Confirmation of Information for Exemption to Delete Diverse Auxiliary Feedwater Actuation System Based on Risk-Informed Process for Evaluations ML22025A4012022-01-0303 January 2022 March 2022 Emergency Preparedness Program Inspection - Request for Information ML21245A2222021-09-0101 September 2021 Request for Information ML21200A2392021-07-20020 July 2021 Docs Request AC - AA August 2021 ML21154A0082021-05-26026 May 2021 NRR E-mail Capture - Palo Verde 1, 2 and 3 - Official RAIs for LAR Associated with Permanent Extension of Containment ILRT Frequency to 15 Years (Type a) and CIV Leak Rate Test Frequency to 75 Months (Type C) ML21064A2372021-03-0303 March 2021 ISI Request for Information Rls ML21042B9692021-02-18018 February 2021 Notification of NRC Design Bases Assurance Inspection and Initial Request for Information ML21043A1462021-02-11011 February 2021 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAI for an Order Associated with Indirect License Transfer from Public Service Company of New Mexico to Avangrid, Inc ML21023A0212021-01-13013 January 2021 PVNGS PI&R Request for Information RA ML21011A1972021-01-12012 January 2021 Unit 2, and Unit 3 - Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000528/2021012, 05000529/2021012 and 05000530/2021012) and Request for Information ML20227A0992020-08-14014 August 2020 Licensed Operator Positive Fitness-For-Duty Test Request for Additional Information ML20118D1362020-04-28028 April 2020 Licensed Operator Positive Fitness-For-Duty Test Request for Additional Information ML20049A0992020-02-14014 February 2020 Notification of Cyber Security Inspection (NRC Inspection Report 05000528/2020401; 05000529/2020401; and 05000530/2020401) and Request for Information ML20049A0252020-02-12012 February 2020 NRR E-mail Capture - Palo Verde Nuclear Generating Station, Unit 1 - Official RAIs for License Amendment Request Associated with Changes to Emergency Plan Staffing Requirements ML20021A3172020-01-21021 January 2020 NRR E-mail Capture - Palo Verde Nuclear Generating Station, Unit 1 - Official RAIs for Relief Request 64, Impractical Examinations for the Third 10-Year ISI Interval ML19317D0782019-11-13013 November 2019 NRR E-mail Capture - Palo Verde 1 - Requests for Additional Information on Unit 1 21st Refueling Outage Steam Generator Tube Inspection Report ML19234A3202019-08-29029 August 2019 Redacted - Request for Additional Information for Amendment and Exemption Request to Support the Implementation of Framatome High Thermal Performance Fuel (EPID L-2018-LLA-0194; EPID L-2018-LLE-0010) ML19155A1842019-05-30030 May 2019 NRR E-mail Capture - Palo Verde Nuclear Generating Station, Unit 3 - Mvib Official RAIs for RR-63, Impractical Examinations for the Third 10-Year ISI Interval ML19095A6552019-04-0404 April 2019 NRR E-mail Capture - Palo Verde Nuclear Generating Station, Unit 3 - Mphb Official RAIs for RR-63, Impractical Examinations for the Third 10-Year ISI Interval ML19044A7342019-02-13013 February 2019 NRR E-mail Capture - Palo Verde1, 2, and 3 - Official Requests for Additional Information for RR 62, Third and Fourth 10-Year ISI Intervals, Proposed Alternative - Pressurizer Heat Sleeve Repairs ML19008A3612019-01-0808 January 2019 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAIs for LAR Associated with Response Time Testing of Pressure Transmitters ML18341A0252018-12-0303 December 2018 Notification of NRC Design Bases Assurance Inspection (Teams)(05000528/2019011, 05000529/2019011, and 05000530/2019011) and Initial Request for Information ML18271A0392018-10-0202 October 2018 Non Proprietary - Supplemental Information Needed for Acceptance of Requested License Amendments and Exemptions Implementation of Framatome High Thermal Performance Fuel (Epids L-2018-LLA-0194 and L-2018-LLE-0010) ML18221A5102018-08-23023 August 2018 Request for Additional Information License Amendment Request to Adopt Risk-Informed Completion Times (CAC Nos. MF6576, MF6577, and MF6578; EPID: L-2015-LLA-0001) ML18229A3132018-08-17017 August 2018 NRR E-mail Capture - Request for Additional Information Relief Request 58: Impractical Examinations for the Third 10-Year Inservice Inspection Interval Arizona Public Service Company Palo Verde Nuclear Generation Station, Unit 2 - Second Se ML18227A8672018-08-15015 August 2018 NRR E-mail Capture - Request for Additional Information Relief Request 58: Impractical Examinations for the Third 10-Year Inservice Inspection Interval Arizona Public Service Company Palo Verde Nuclear Generation Station, Unit 2 ML18124A0112018-05-0303 May 2018 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official Eeob RAIs for TSTF-505 (4b) LAR (CAC Nos. MF6576, MF6577, and MF6578; EPID L-2015-LLA-0001) ML18099A0072018-04-0606 April 2018 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAIs for 10 CFR 50.69 LAR (CAC Nos. MF9971, MF9972, and MF9973; EPID L-2017-LLA-0276) ML18094B1122018-04-0404 April 2018 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Final RAIs for TSTF-505 (Initiative 4b) LAR (CAC Nos. MF6576, MF6577, and MF6578: EPID L-2015-LLA-0001) ML18066A7032018-03-0707 March 2018 Notification of Nrc Design Bases Assurance Inspection (Programs) 05000528/2018011, 05000529/2018011, and 05000530/2018011 Initial Request for Information ML17248A0162017-08-31031 August 2017 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Final RAI for RRs PRR-03, PRR-04 and PRR-05, Pump Testing ML17107A0052017-04-14014 April 2017 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Ngf LAR and Exemption RAIs (CAC Nos. MF8076 to MF8081) ML17082A4462017-03-28028 March 2017 PVNGS Units 1, 2, and 3 Transition to CE 16x16 Ngf - Draft RAIs Rev 3 ML17003A0182017-01-0202 January 2017 NRR E-mail Capture - Palo Verde, Unit 3 - Draft RAIs for the Second Emergency LAR Associated with EDG 3B Failure ML16258A0312016-09-14014 September 2016 PVNGS Units 1-3 - Notif of NRC Insp of the Implementation of Mitigation Strategies and Spent Fuel Pool Instr. Orders and Emer. Prep. Comm./Staffing/Multi-Unit Dose Assessment Plns(05000528/ 2016009;05000529/2016009;and 05000530/2016009) and ML16111B3312016-04-20020 April 2016 Notification of NRC Component Design Bases Inspection (05000528/2016007; 05000529/2016007; 05000530/2016007) and Initial Request for Information ML16083A2502016-03-23023 March 2016 NRR E-mail Capture - Palo Verde Nuclear Generating Station, Units 1, 2, and 3 - Official RAIs for EAL LAR 2024-01-10
[Table view] |
See also: IR 05000528/2019011
Text
December 3, 2018
Mr. Robert S. Bement
Executive Vice President Nuclear/
Chief Nuclear Officer
Arizona Public Service Company
P.O. Box 52034, MS 7602
Phoenix, AZ 85072-2034
SUBJECT: PALO VERDE NUCLEAR GENERATING STATION - NOTIFICATION OF NRC
DESIGN BASES ASSURANCE INSPECTION (TEAMS) (05000528/2019011,
05000529/2019011, AND 05000530/2019011) AND INITIAL REQUEST FOR
INFORMATION
Dear Mr. Bement:
On January 24, 2019, the NRC will begin a triennial baseline design bases assurance
inspection at the Palo Verde Nuclear Generating Station. A six person team will perform this
inspection using NRC Inspection Procedure (IP) 71111, Attachment 21M, Design Bases
Assurance Inspection (Teams).
The inspection focuses on the maintenance of the design bases and modifications made to
structures, systems, and components. The samples reviewed during this inspection will be
identified during an information gathering visit. In addition, a number of operating experience
issues will also be selected for review during the in-office preparation week.
The inspection will include an information gathering site visit by the team leader and 2 weeks of
onsite inspection by the team. The inspection will consist of three NRC inspectors and two NRC
contractors, who will focus on engineering, and one NRC inspector that will focus on operations.
The current inspection schedule is as follows:
Onsite Information Gathering Visit: January 24, 2019
Preparation Week: February 4-8, 2019
Onsite Weeks: February 11-15, 2019, and February 25, 2019 - March 1, 2019
The purpose of the information gathering visit is to meet with members of your staff to identify
potential risk-significant components and operator actions. The lead inspector will also request
a tour of the plant with members of your operations staff and probabilistic safety assessment
staff. During the onsite weeks, several days and administration will be needed on the plant-
referenced simulator in order to facilitate the development of operator action-based scenarios.
R. Bement 2
Additional information and documentation needed to support the inspection will be identified
during the inspection, including interviews with engineering managers, engineers, and
probabilistic safety assessment staff.
Our experience with these inspections has shown that they are extremely resource intensive,
both for the NRC inspectors and the licensee staff. In order to minimize the inspection impact
on the site and to ensure a productive inspection, we have enclosed a request for information
needed for the inspection. The request has been divided into two groups. The first group lists
information necessary for the information gathering visit and for general preparation. This
information should be available to the regional office no later than January 21, 2019, unless
otherwise stated. If possible, this information should be provided electronically to the lead
inspector. Since the inspection will be concentrated on high risk/low margin components and
modifications, calculations associated with your list of high risk components and modifications
should be available to review during the information gathering visit to assist in our selection of
components based on available design margin.
The second group of documents requested lists information necessary to aid the inspection
team in tracking issues identified as a result of the inspection. It is requested that this
information be provided to the lead inspector as the information is generated during the
inspection. An additional request will be made by the team during the preparation week once
the specific components and modifications have been selected. Additional requests by
inspectors will also be made throughout the onsite weeks for specific documents needed to
complete the review. It is important that all of these documents are up-to-date and complete in
order to minimize the number of additional documents requested during the preparation and/or
onsite portions of the inspection. In order to facilitate the inspection, we request that a contact
individual be assigned to each inspector to ensure information requests, questions, and
concerns are addressed in a timely manner.
The lead inspector for this inspection is Gerond A. George, Senior Reactor Inspector. We
understand that our licensing engineer contact for this inspection is Ms. L. Weaver. If there are
any questions about the inspection or the requested materials, please contact the lead inspector
by telephone at 817-200-1562 or by e-mail at Gerond.George@nrc.gov.
This letter does not contain new or amended information collection requirements subject
to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information
collection requirements were approved by the Office of Management and Budget, control
number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to
respond to, a request for information or an information collection requirement unless the
requesting document displays a currently valid Office of Management and Budget control
number.
In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter will be
made available electronically for public inspection in the NRC Public Document Room or from
R. Bement 3
the Publicly Available Records (PARS) component of NRCs document system (ADAMS).
ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the
Public Electronic Reading Room).
Sincerely,
/RA/
Thomas R. Farnholtz, Chief
Engineering Branch 1
Division of Reactor Safety
Dockets: 50-528; 50-529; and 50-530
Licenses: NPF-41; NPF-51; and NPF-74
Enclosure: Design Bases Assurance
Inspection (Teams) Request for
Information
Initial Request for Information
Design Bases Assurance Inspection (Teams)
Palo Verde Nuclear Generating Station
Inspection Reports: 05000528/2019011, 05000529/2019011, AND
05000530/2019011
EPID ID: I-2019-011-0009
Information Gathering Dates: January 24, 2019
Inspection Dates: February 11, 2019, to March 1, 2019
Inspection Procedure: IP 71111, Attachment 21M, Design Bases Assurance
Inspection (Teams)
Lead Inspector: Gerond A. George, Senior Reactor Inspector
I. Information Requested Prior to Information Gathering Visit (due January 21, 2019)
The following information (Section I of this enclosure) should be sent to the Region IV
office in hard copy or electronic format to the attention of Gerond A. George by
January 21, 2019, to facilitate the reduction in the items to be selected for a final list.
The inspection team will finalize the selected list during the preparation week. The
specific items selected from the lists shall be available and ready for review on the day
indicated in this request. *Please provide requested documentation electronically in
pdf files, Excel, or other searchable formats, if possible. The information should
contain descriptive names and be indexed and/or hyperlinked to facilitate ease of use.
Information in lists should contain enough information to be easily understood by
someone who has knowledge of pressurized water reactor technology. If requested
documents are large and only hard copy formats are available, please inform the
inspector and provide subject documentation during the first day of the onsite inspection.
1. An Excel spreadsheet of equipment basic events (with definitions), including
importance measures sorted by risk achievement worth and Fussell-Vesely from
your internal events probabilistic risk assessment. Include basic events with risk
achievement worth value of 1.3 or greater.
2. A list of the top 50 cut-sets from your PRA.
3. Copies of probabilistic risk assessment system notebooks and the latest
probabilistic risk assessment summary document.
4. An Excel spreadsheet of probabilistic risk assessment human action basic events or
risk ranking of operator actions from your site-specific PSA sorted by risk
achievement worth and Fussell-Vesely. Provide copies of your human reliability
worksheets for these items.
5. If you have an external events or fire PSA model, provide the information requested
in items 1-4 for external events and fire.
Enclosure
6. A list of high large early release frequency impact events and associated
components.
7. Structures, systems, and components in the Maintenance Rule (a)(1) category.
8. A list of high risk maintenance rule systems/components and functions; based on
engineering or expert panel judgment.
9. Site top 10 issues list, if available.
10. Any pre-existing list of components and associated calculations with low design
margins.
11. A list of operating experience evaluations for the last 3 years.
12. A list of all time-critical operator actions in procedures.
13. A list of current operator work arounds/burdens.
14. Procedures, including emergency and abnormal, used to accomplish operator
actions associated with the basic events credited in your PRA.
15. Lists of permanent and temporary modifications performed in the past 5 years to
structures, systems, and components sorted by component identified in Item 1.
16. List of root cause evaluations associated with component failures or design issues
initiated/completed in the last 5 years.
17. A list of any common-cause failures of components in the last 3 years.
18. A copy of any internal/external self-assessments and associated corrective action
documents generated in preparation for this inspection.
19. A copy of engineering/operations-related audits completed in the last 2 years.
20. Electronic copies of the Technical Specifications, Technical Specifications Bases,
and the Final Safety Analysis Report, as updated.
21. A copy of the Individual Plant Examination of External Events, if available
electronically.
22. One-line drawings of emergency core cooling system, ultimate heat sink, emergency
feedwater, safety-related electrical systems.
23. A copy of condition reports associated with inspection findings from the previous
NRC Inspection Procedure 71111.21 (or 71111.21 Attachment M inspection).
24. A list of licensee contacts for the inspection team with phone numbers.
25. A copy of the current management and engineering organizational charts.
2
II. Information Requested to be provided throughout the inspection.
1. Electronic copies of the design bases documents for selected components and
modifications.
2. Electronic copies of the system health notebooks for selected components and
modifications.
3. A list of the design calculations that provide the design margin information for
selected components.
4. Calculations and drawings associated with selected components.
5. Modification documentation associated with modifications selected from Item I.15,
this includes:
a. Post-modification testing, including performance characteristics affected,
assumptions, and acceptance criteria associated with modifications selected.
b. Updated maintenance and surveillance procedures associated with
modifications.
c. Updated operation procedures and training plans associated with the
modifications.
6. Copies of any corrective action documents generated as a result of the teams
questions or queries during this inspection.
7. Copies of the list of questions submitted by the team members and the
status/resolution of the information requested (provide daily during the inspection to
each team member).
Inspector Contact Information:
Gerond A. George
Senior Reactor Inspector
817-200-1562
Gerond.George@nrc.gov
Mailing Address:
U.S. NRC, Region IV
Attn: Gerond A. George
1600 East Lamar Blvd.
Arlington, TX 76011-4511
3
ML18341A025
SUNSI Review: ADAMS: Non-Publicly Available Non-Sensitive Keyword:
By: GAG Yes No Publicly Available Sensitive NRC-002
OFFICE SRI:EB1 C:EB1
NAME GGeorge TFarnholtz
SIGNATURE /RA/ /RA/
DATE 11/27/2018 12/03/2018