 Issue dateTitleTopic
ML24011A10010 January 2024March 2024 Emergency Preparedness Program Inspection - Request for Information
ML23334A16130 November 2023NRR E-mail Capture - Palo Verde 1, 2, and 3 - RAIs Associated with License Renewal Commitment for Pressurizer Surge Line Welds Inspection Program to Manage Environmentally Assisted FatigueAging Management
License Renewal
ML23334A00729 November 2023NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAIs for LAR That Revises TSs 3.5.1, SITs - Operating; 3.5.2, SIT Shutdown; 3.6.5, Containment Air Temperature; and SRs for TS 3.5.1, SITs Operating
ML23298A12325 October 2023NRR E-mail Capture - Palo Verde, Unit 1 - RAIs for Relief Request 70, Proposed Alternatives for Pressurizer Lower Shell Temperature Nozzle
ML23031A33931 January 2023In-service Inspection Request for InformationBoric Acid
Nondestructive Examination
Foreign Material Exclusion
Dissimilar Metal Weld
Scaffolding
ML23013A06313 January 2023NRR E-mail Capture - Palo Verde Unit 1 -Request for Additional Information - U1R23 Inspection Summary Report for Steam Generator Tubing
ML22348A16714 December 2022March 2023 Emergency Preparedness Exercise Inspection - Request for Information
ML22339A2375 December 2022NRR E-mail Capture - Palo Verde Unit 1 Request for Additional Information - U1R23 Inspection Summary Report for Steam Generator Tubing
ML22272A32529 September 2022Licensed Operator Positive Fitness-For-Duty Test Request for Additional Information
ML22209A17528 July 2022Inservice Inspection Request for InformationBoric Acid
Nondestructive Examination
Scaffolding
ML22187A2636 July 2022Notification of Inspection (NRC IR 05000528/2022004, 05000529/2022004 and 05000530/2022004) and Request for Information
ML22067A2292 March 2022Inservice Inspection Inspection PWR Request for InformationBoric Acid
Nondestructive Examination
Scaffolding
ML22055A58424 February 2022NRR E-mail Capture - Palo Verde, Unit 3 - Final RAIs for 22nd Refueling Outage (Spring 2021) Steam Generator Tube Inservice Inspection Report
ML22035A33010 February 2022Requests for Confirmation of Information for Exemption to Delete Diverse Auxiliary Feedwater Actuation System Based on Risk-Informed Process for EvaluationsExemption Request
ML22025A4013 January 2022March 2022 Emergency Preparedness Program Inspection - Request for Information
ML21245A2221 September 2021Request for InformationBoric Acid
Nondestructive Examination
Scaffolding
ML21200A23920 July 2021Docs Request AC - AA August 2021
ML21154A00826 May 2021NRR E-mail Capture - Palo Verde 1, 2 and 3 - Official RAIs for LAR Associated with Permanent Extension of Containment ILRT Frequency to 15 Years (Type a) and CIV Leak Rate Test Frequency to 75 Months (Type C)Incorporated by reference
ML21064A2373 March 2021ISI Request for Information RlsBoric Acid
Nondestructive Examination
Pandemic
Scaffolding
ML21042B96918 February 2021Notification of NRC Design Bases Assurance Inspection and Initial Request for InformationStroke time
Power-Operated Valves
ML21043A14611 February 2021NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAI for an Order Associated with Indirect License Transfer from Public Service Company of New Mexico to Avangrid, Inc
ML21023A02113 January 2021PVNGS PI&R Request for Information RATemporary Modification
Pandemic
ML21011A19712 January 2021Unit 2, and Unit 3 - Notification of an NRC Fire Protection Baseline Inspection (NRC Inspection Report 05000528/2021012, 05000529/2021012 and 05000530/2021012) and Request for InformationSafe Shutdown
Commercial Grade Dedication
Hydrostatic
Probabilistic Risk Assessment
Temporary Modification
Aging Management
Job Performance Measure
Pandemic
Fire Protection Program
ML20227A09914 August 2020Licensed Operator Positive Fitness-For-Duty Test Request for Additional Information
ML20118D13628 April 2020Licensed Operator Positive Fitness-For-Duty Test Request for Additional Information
ML20049A09914 February 2020Notification of Cyber Security Inspection (NRC Inspection Report 05000528/2020401; 05000529/2020401; and 05000530/2020401) and Request for InformationCyber Security
ML20049A02512 February 2020NRR E-mail Capture - Palo Verde Nuclear Generating Station, Unit 1 - Official RAIs for License Amendment Request Associated with Changes to Emergency Plan Staffing RequirementsMinimum staff
ML20021A31721 January 2020NRR E-mail Capture - Palo Verde Nuclear Generating Station, Unit 1 - Official RAIs for Relief Request 64, Impractical Examinations for the Third 10-Year ISI Interval
ML19317D07813 November 2019NRR E-mail Capture - Palo Verde 1 - Requests for Additional Information on Unit 1 21st Refueling Outage Steam Generator Tube Inspection Report
ML19234A32029 August 2019Redacted - Request for Additional Information for Amendment and Exemption Request to Support the Implementation of Framatome High Thermal Performance Fuel (EPID L-2018-LLA-0194; EPID L-2018-LLE-0010)Loop seal
Anticipated operational occurrence
Exemption Request
Earthquake
ML19155A18430 May 2019NRR E-mail Capture - Palo Verde Nuclear Generating Station, Unit 3 - Mvib Official RAIs for RR-63, Impractical Examinations for the Third 10-Year ISI Interval
ML19095A6554 April 2019NRR E-mail Capture - Palo Verde Nuclear Generating Station, Unit 3 - Mphb Official RAIs for RR-63, Impractical Examinations for the Third 10-Year ISI Interval
ML19044A73413 February 2019NRR E-mail Capture - Palo Verde1, 2, and 3 - Official Requests for Additional Information for RR 62, Third and Fourth 10-Year ISI Intervals, Proposed Alternative - Pressurizer Heat Sleeve Repairs
ML19008A3618 January 2019NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAIs for LAR Associated with Response Time Testing of Pressure Transmitters
ML18341A0253 December 2018Notification of NRC Design Bases Assurance Inspection (Teams)(05000528/2019011, 05000529/2019011, and 05000530/2019011) and Initial Request for InformationUltimate heat sink
Probabilistic Risk Assessment
Temporary Modification
Large early release frequency
ML18271A0392 October 2018Non Proprietary - Supplemental Information Needed for Acceptance of Requested License Amendments and Exemptions Implementation of Framatome High Thermal Performance Fuel (Epids L-2018-LLA-0194 and L-2018-LLE-0010)Exemption Request
ML18221A51023 August 2018Request for Additional Information License Amendment Request to Adopt Risk-Informed Completion Times (CAC Nos. MF6576, MF6577, and MF6578; EPID: L-2015-LLA-0001)
ML18229A31317 August 2018NRR E-mail Capture - Request for Additional Information Relief Request 58: Impractical Examinations for the Third 10-Year Inservice Inspection Interval Arizona Public Service Company Palo Verde Nuclear Generation Station, Unit 2 - Second Se
ML18227A86715 August 2018NRR E-mail Capture - Request for Additional Information Relief Request 58: Impractical Examinations for the Third 10-Year Inservice Inspection Interval Arizona Public Service Company Palo Verde Nuclear Generation Station, Unit 2
ML18124A0113 May 2018NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official Eeob RAIs for TSTF-505 (4b) LAR (CAC Nos. MF6576, MF6577, and MF6578; EPID L-2015-LLA-0001)Anticipated operational occurrence
Probabilistic Risk Assessment
ML18099A0076 April 2018NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAIs for 10 CFR 50.69 LAR (CAC Nos. MF9971, MF9972, and MF9973; EPID L-2017-LLA-0276)High winds
Internal Flooding
Probabilistic Risk Assessment
Tornado Missile Protection
Large early release frequency
Risk-Informed Steering Committee
Earthquake
ML18094B1124 April 2018NRR E-mail Capture - Palo Verde 1, 2, and 3 - Final RAIs for TSTF-505 (Initiative 4b) LAR (CAC Nos. MF6576, MF6577, and MF6578: EPID L-2015-LLA-0001)Safe Shutdown
Ultimate heat sink
Fire Barrier
Internal Flooding
Probabilistic Risk Assessment
ML18066A7037 March 2018Notification of Nrc Design Bases Assurance Inspection (Programs) 05000528/2018011, 05000529/2018011, and 05000530/2018011 Initial Request for InformationCommercial Grade Dedication
ML17248A01631 August 2017NRR E-mail Capture - Palo Verde 1, 2, and 3 - Final RAI for RRs PRR-03, PRR-04 and PRR-05, Pump Testing
ML17107A00514 April 2017NRR E-mail Capture - Palo Verde 1, 2, and 3 - Ngf LAR and Exemption RAIs (CAC Nos. MF8076 to MF8081)Boric Acid
ML17082A44628 March 2017PVNGS Units 1, 2, and 3 Transition to CE 16x16 Ngf - Draft RAIs Rev 3Boric Acid
ML17003A0182 January 2017NRR E-mail Capture - Palo Verde, Unit 3 - Draft RAIs for the Second Emergency LAR Associated with EDG 3B FailureProbabilistic Risk Assessment
Arc flash
FLEX
Job Performance Measure
Continuous fire watch
Fire Watch
ML16258A03114 September 2016PVNGS Units 1-3 - Notif of NRC Insp of the Implementation of Mitigation Strategies and Spent Fuel Pool Instr. Orders and Emer. Prep. Comm./Staffing/Multi-Unit Dose Assessment Plns(05000528/ 2016009;05000529/2016009;and 05000530/2016009) andSafe Shutdown
Safe Shutdown Earthquake
FLEX
Spent Fuel Pool Instrumentation
ML16111B33120 April 2016Notification of NRC Component Design Bases Inspection (05000528/2016007; 05000529/2016007; 05000530/2016007) and Initial Request for InformationProbabilistic Risk Assessment
Temporary Modification
ML16083A25023 March 2016NRR E-mail Capture - Palo Verde Nuclear Generating Station, Units 1, 2, and 3 - Official RAIs for EAL LARHigh winds
Reactor Vessel Water Level
Ultimate heat sink