Cy 2009 Baseline Inspection CompletionML100601032 |
Person / Time |
---|
Site: |
Palo Verde, Wolf Creek, Cooper, Arkansas Nuclear, Columbia, River Bend, Diablo Canyon, Waterford, South Texas, San Onofre, Comanche Peak, Fort Calhoun |
---|
Issue date: |
03/01/2010 |
---|
From: |
Chamberlain D D NRC/RGN-IV/DRP |
---|
To: |
Brown F D Division of Inspection and Regional Support |
---|
References |
---|
Download: ML100601032 (30) |
|
Similar Documents at Palo Verde, Wolf Creek, Cooper, Arkansas Nuclear, Columbia, River Bend, Diablo Canyon, Waterford, South Texas, San Onofre, Comanche Peak, Fort Calhoun |
---|
Category:Memoranda
MONTHYEARML24297A6392024-10-30030 October 2024 Reassignment of U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch IV ML24268A0722024-09-24024 September 2024 Summary of August 28, 2024, Public Meeting to Discuss Cyber Security Regulatory Issues Regarding Wolf Creeks Implementation of Advanced Remote Monitoring Using Wireless ML24157A0252024-07-0101 July 2024 Memo to Michelle Rome Summary of 4/4/2024 Meeting with CA SHPO ML24177A1892024-06-28028 June 2024 Summary of Information Meeting with Question and Answer Session to Discuss the 2023 Annual Assessment of Safety Performance at Columbia Generating Station ML24143A1202024-06-0303 June 2024 Memo to Michelle Rome Summary of 4/5/2024 Meeting with Ytt ML24128A2402024-05-0808 May 2024 Entergy Operations, Inc. - Entergy Fleet Project Manager Assignment ML24108A1482024-05-0707 May 2024 February 2024 Environmental Scoping Meetings Related to the Diablo Canyon LRA - Memo ML24122C6862024-05-0202 May 2024 Summary of the April 24, 2024 Information Meeting with Question and Answer Session to Discuss the 2023 Annual Assessment of Safety Performance at Cooper Nuclear Station ML24093A2502024-04-24024 April 2024 Management Directive 8.3 Evaluation for Waterford Steam Electric Station, Unit 3, Main Transformer Fire and Resulting Automatic Reactor Trip on March 21, 2024 ML24107B1272024-04-22022 April 2024 Ft. Calhoun Meeting Summary of March 27, 2024 Meeting with Omaha Public Power District on Submittal of Phase 1 Final Status Surveys ML24088A2672024-04-0808 April 2024 Management Directive 8.3 Evaluation for Waterford Steam Electric Station, Unit 3, Manual Trip on March 16, 2024 ML24088A2282024-04-0202 April 2024 License Renewal Application ML24067A1572024-03-0707 March 2024 Memorandum from the Secretary Referring Hearing Request to the Atomic Safety and Licensing Board Panel ML24019A0342024-01-30030 January 2024 Public Meeting Summary - 01-04-2024 - Comanche Peak LRA - Structures Monitoring Program ML24017A2432024-01-15015 January 2024 LTR-24-0008 Paul Blanch, E-mails Request for Formal Response to Requests for Meeting to Discuss Safety Issues with NRC Staff ML23279A1052023-10-0606 October 2023 Memorandum from the Secretary to the Board and Parties ML23265A1902023-09-26026 September 2023 Meeting Summary: September 13, 2023 Diablo Canyon, Units 1 and 2 License Renewal Application Pre-Application Meeting ML23179A2132023-07-0505 July 2023 Approval for Credit for the Wolf Creek Generating Station Operational Safety Review Team to the Baseline Inspection Samples/Hours ML23156A2822023-06-0505 June 2023 Summary of Meeting with Q & a Session to Discuss the 2022 Annual Assessment of Safety Performance at CGS ML23143A2262023-06-0101 June 2023 May 3, 2023, Summary of Public Meeting to Discuss the End of Cycle Assessment and Pre-Submittal License Renewal Process Overview for Diablo Canyon Power Plant, Units 1 and 2 ML23047A3822023-03-21021 March 2023 Summary of December 15, 2022 Periodic Advanced Reactor Stakeholder Public Meeting ML23046A0292023-02-23023 February 2023 Timely Renewal Exemption 5 Day Memorandum ML22349A5052023-02-0808 February 2023 Results of a Reactor Oversight Process Self Assessment Effectiveness Review of the Recommendations from IP 95003 at Arkansas Nuclear One ML22333B0922022-12-21021 December 2022 FY22 Nmss/Duwp Operating Experience Report ML22349A2002022-12-0101 December 2022 NRR E-mail Capture - (External_Sender) Energy Northwest Columbia Generating Station 2022 Priority Pollutant Discharge Monitoring Report ML22304A1912022-11-23023 November 2022 Aging Management Audit Plan Regarding the License Renewal Application Review ML22165A0882022-06-14014 June 2022 Information Request, Security IR 2022403 ML22147A0932022-06-0606 June 2022 2021 Annual Assessment Public Meeting Summary ML22131A1592022-05-11011 May 2022 Reply to the Nrc'S Response to the Office of the Inspector General'S (OIG) Event Inquiry Into the Nrc'S Oversight of the Auxiliary Feedwater System at Diablo Canyon Nuclear Power Plant, OIG Case No. 20-025 ML22109A1792022-05-0303 May 2022 Response OIG Special Inquiry Into Nrc'S Oversight AFW at Diablo Canyon (OIG Case No. 20-025) ML22108A1672022-05-0303 May 2022 Staff Assessment of OIG Event Inquiry Into the Nrc'S Oversight AFW at Diablo Canyon (OIG Case No. 20-025) ML22061A2152022-03-0808 March 2022 Summary of Teleconference with the National Marine Fisheries Services on Endangered Species Act Consultation for SONGS, Units 2 and 3 Decommissioning ML22034A3932022-02-16016 February 2022 Calendar Year 2021 Security Baseline Completion Memo ML21309A5482021-11-15015 November 2021 NSIR Staff Review of the Wolf Creek Generating Stations Security Plan Training & Qualification Plan & Safeguards Contingency Plan for the Verification of ASM EA 20 091 Incorporation ML21259A1492021-10-26026 October 2021 CPNPP, Unit Nos. 1 and 2 - Meeting Summary for Environmental Pre Submittal Meeting for Initial License Renewal Application on September 21, 2021 ML21295A0882021-10-21021 October 2021 Fiscal Year 2021 Research and Test Reactors Inspection Program Completion Status ML21288A0392021-10-18018 October 2021 September 14, 2021, Summary of Public Workshop on Scale/Melcor Source Term Demonstration Project - Pebble-Bed Molten-Salt-Cooled Reactor ML21259A1402021-10-0505 October 2021 Meeting Summary for Safety Pre Submittal Meeting for Initial License Renewal Application on September 21, 2021 ML21280A1082021-10-0505 October 2021 (SONGS) - Clarification to Request for Additional Information Response, Dated 10/05/2021 ML21273A1772021-10-0101 October 2021 Fiscal Year 2021 Research and Test Reactors Inspection Program Completion Status ML21243A4492021-09-0202 September 2021 ISFSI Technical Assistance Request - Review of Physical Security Plan ML21271A5992021-08-0303 August 2021 License Amendment Request (LAR) 21-01, Chapter 8, 12, Omaha Public Power District, FCS-SAF-103, FCS Deconstruction Health and Safety Plan CAC2 ML21209A0222021-07-29029 July 2021 Closed Predecisional Enforcement Conference with River Bend Station ML21202A3632021-07-20020 July 2021 Memorandum Disposition of Documents Discovered at Jensen Hughes ML21181A3352021-07-0101 July 2021 June 23, 2021, Summary of Public Meeting to Discuss Technology Inclusive Content of Application Project ML21146A1852021-06-28028 June 2021 DC RFI 2021401 ML21146A185 ML21176A1292021-06-25025 June 2021 CPNPP FFD Inspection Doc Request 2021 ML21174A0942021-06-23023 June 2021 Reactor Trip on June 7, 2021 - Management Directive 8.3 Screening ML21158A2232021-06-0808 June 2021 Meeting Summary for Ticap Workshop 3 ML21140A3892021-05-24024 May 2021 Riv Column 1 EOC 2020 Public Meeting Summary 2024-09-24
[Table view] |
Text
UNITED STATESNUCLEAR REGULATORY COMMISSIONREGION IV612 EAST LAMAR BLVD, SUITE 400ARLINGTON, TEXAS 76011-4125 March 1, 2010 MEMORANDUM TO: Frederick Brown, Director Division of Inspection and Regional Support Office of Nuclear Reactor Regulation
FROM: Dwight D. Chamberlain, Director
/RA AVegel for/
Division of Reactor Projects
SUBJECT:
CY 2009 BASELINE INSPECTION COMPLETION The purpose of this memorandum is to confirm that we completed 100 percent of the baseline
inspection program at all Region IV plants in calendar year 2009 for which we were responsible.
This does not include portions of the 2009 baseline inspection program for which other NRC
organizations are responsible. Attached is a table which provides the completion status of
baseline procedures for all Region IV sites (IR Report 8a).
If you have any questions, or desire additional details, please contact me at 817-860-8248.
Enclosure:
ROP Procedure Completion by Site (IR Report 8a)
Frederick Brown Electronic cc w/enclosure:
Elmo Collins, RIV
Dwight Chamberlain, RIV
David Lew, RI
Leonard Wert, RII
Steve West, RIII
Chuck Paulk, RIV
James Isom, NRR File located: S:/DRS/TSB/Baseline Completion/CY 2009 Completion Memo ML SUNSI Rev Compl. Yes No ADAMS Yes No Reviewer Initials CJP Publicly Avail Yes No Sensitive Yes No Sens. Type Initials CJP RIV:C:TSB D:DRS D:DRP MCHay RJCaniano DDChamberlain
/RA/ /RA/ /RA AVegel for/
02/26/2010 02/26/2010 02/26/2010 OFFICIAL RECORD COPY T=Telephone E=E-mail F=Fax